Action plan for pre shutdown Works

Sr. Description No of Start Finish Remarks


No day date date
required
1 MCC terrace slab
(Slab suppose to be casted on 11 Nov .but it is
postponed to 20Nov.becouse of space constraint to
install constructional lift & safety constraint to work
at 15 meter height at night)
2 DCS ROOM
b) Internal Plaster (after de shuttering of window
chajja)
d) Quotation for aluminum internal partition
e) IPS Flooring
f) False ceiling ( Gypsum)
g) Internal painting ( oil bond distemper)
h) Anti-static False flooring( design approved by M/S
Shroff on dated 08NOV. quotation to be submitted
to Solvay for the same)
i)Aluminum internal partition with door ( quotation to
be submitted to Solvay)
Formaldehyde Storage Tank installation schedule :
2 Plinth beam casting Afita
3 Dyke wall construction with plaster Afita
Dismantling existing storage tank foundation
4 Foundation for 15 KL leg mounted SS Storage tank Afita
5 Floor finish ---- storage area Afita (parallel activity )
6 Floor finish ---- Scrubber area Afita (parallel activity )
7 Relocating of existing earthing pits from scrubber Afita,shroff & solvay
Hard stand area.
7 Structure pre-fabrication for storage tank area Jobby
8 Structure pre-fabrication for Scrubber skid area Jobby
9 Structure erection at storage tank area
Structure erection at scrubber skid area
Piping – prefabrication for storage tank area Jobby
Piping – prefabrication for scrubber skid area Jobby
Piping – Installation at storage tank area Jobby
Piping – Installation at scrubber skid area
Formaldehyde Storage tank installation
Scrubber, catch pot & pump Installation
Mechanical work completion
Arival of 15 KL SS Tank at site
3 Septic tank near EO scrubber ( with all sewage line
Connectivity and ready for use)
4 Final septic tank at ETP area
5 Pavement of parking Area with concrete
A) Area in between main road to ware house loading,
B) Concreted civil work balance area 780 sqm (at
some location parallel activity along with the work at
mention above.
6 Road and storm water drain road from weigh bridge
to MCC room
a)Excavation
b)WBM
c)Tor laying During Shutdown Period road tor laying work will be carried out in one stretch from weight bridge to up to
exiting boiler road
6,ii) Road in EO circle During Shutdown Work.
6,iii) Road at back side of unit 1
a) Excavation (M/S Solvay to hand over the area 18
Nov.)
b) WBM
c) Tor laying During Shutdown Period road tor laying work will be carried out in one stretch from weight bridge to up to
exiting boiler road