No day date date required 1 MCC terrace slab (Slab suppose to be casted on 11 Nov .but it is postponed to 20Nov.becouse of space constraint to install constructional lift & safety constraint to work at 15 meter height at night) 2 DCS ROOM b) Internal Plaster (after de shuttering of window chajja) d) Quotation for aluminum internal partition e) IPS Flooring f) False ceiling ( Gypsum) g) Internal painting ( oil bond distemper) h) Anti-static False flooring( design approved by M/S Shroff on dated 08NOV. quotation to be submitted to Solvay for the same) i)Aluminum internal partition with door ( quotation to be submitted to Solvay) Formaldehyde Storage Tank installation schedule : 2 Plinth beam casting Afita 3 Dyke wall construction with plaster Afita Dismantling existing storage tank foundation 4 Foundation for 15 KL leg mounted SS Storage tank Afita 5 Floor finish ---- storage area Afita (parallel activity ) 6 Floor finish ---- Scrubber area Afita (parallel activity ) 7 Relocating of existing earthing pits from scrubber Afita,shroff & solvay Hard stand area. 7 Structure pre-fabrication for storage tank area Jobby 8 Structure pre-fabrication for Scrubber skid area Jobby 9 Structure erection at storage tank area Structure erection at scrubber skid area Piping – prefabrication for storage tank area Jobby Piping – prefabrication for scrubber skid area Jobby Piping – Installation at storage tank area Jobby Piping – Installation at scrubber skid area Formaldehyde Storage tank installation Scrubber, catch pot & pump Installation Mechanical work completion Arival of 15 KL SS Tank at site 3 Septic tank near EO scrubber ( with all sewage line Connectivity and ready for use) 4 Final septic tank at ETP area 5 Pavement of parking Area with concrete A) Area in between main road to ware house loading, B) Concreted civil work balance area 780 sqm (at some location parallel activity along with the work at mention above. 6 Road and storm water drain road from weigh bridge to MCC room a)Excavation b)WBM c)Tor laying During Shutdown Period road tor laying work will be carried out in one stretch from weight bridge to up to exiting boiler road 6,ii) Road in EO circle During Shutdown Work. 6,iii) Road at back side of unit 1 a) Excavation (M/S Solvay to hand over the area 18 Nov.) b) WBM c) Tor laying During Shutdown Period road tor laying work will be carried out in one stretch from weight bridge to up to exiting boiler road