Sei sulla pagina 1di 16

METHODOLOGY STATEMENT

NMRCL- Reach-2
AFCONS
Infrastructure Limited FORMAT NO. : QF 9949 10

DOCUMENT No: REV. No:


DATE: 01.11.2017 SHEET 1 OF 16
PM/3452/003 R0

METHOD STATEMENT FOR CONSTRUCTION OF BORED CAST IN-SITU PILE

NMRCL Reach 2 - PROJECT

Design and Construction of Elevated Viaduct of Length 2.607km from CH:3620.950 to


CH:3962.558, 4042.558 to 4330.490, CH:4411.490 to 5174.498 , 5255.498 to 5988.303 and
6131.017 to 6612.560 Between Gaddigodam to Sitabuldi (Excluding Stations) and Railway
Span Near Gaddigodam, Viaduct and Road Cum Rail Flyover (Double Decker) of Length
4.065km Including Approach Ramps from CH:-673.910 to 291.050, CH:-213.550 to 939.360,
CH:1016.860 to 2097.068, CH:2174.568 to 3125.370, Ch:3202.870 to 3620.950 and 3962.558 to
4042.558 on BOQ Basis (Excluding Stations) in Reach 2

CHECKED BY APPROVED BY
PREPARED
REV DATE SAFETY PROJECT NMRCL
BY QA MANAGER
MANAGER MANAGER REPRESENTATIVE
R0

Contents
1. Introduction..............................................................................................................................3
DETAIL SCHEMES / METHODS REV. : R0

PLANNING DEPARTMENT FORMAT NO. : QF 9949 10 DATE: 01.11.2017

Design and Construction of Elevated Viaduct of Length


2.607km from CH:3620.950 to CH:3962.558, 4042.558 to
4330.490, CH:4411.490 to 5174.498 , 5255.498 to 5988.303 and
6131.017 to 6612.560 Between Gaddigodam to Sitabuldi
(Excluding Stations) and Railway Span Near Gaddigodam,
PROJECT : Viaduct and Road Cum Rail Flyover (Double Decker) of
Length 4.065km Including Approach Ramps from CH:- REV :
R0 DATE
673.910 to 291.050, CH:-213.550 to 939.360, CH:1016.860 to
01.11.2017
2097.068, CH:2174.568 to 3125.370, Ch:3202.870 to 3620.950
and 3962.558 to 4042.558 on BOQ Basis (Excluding Stations)
in Reach 2
METHODS STATEMENT FOR BORED CAST IN-
DOC.TITLE: SITU PILE
DOCUMENT
PM/3452/003 SHEET : 2 of 16
NO.

2. SCOPE......................................................................................................................................3
3. REFERENCES.........................................................................................................................4
4. ORGANISATION CHART......................................................................................................5
5. RESPONSIBILITIES...............................................................................................................6
6. METHODOLOGY...................................................................................................................7
6.1 SETTING OUT:................................................................................................................7
6.2 DRIVING OF TEMPORARY CASING:.........................................................................8
6.3 BORING:..........................................................................................................................8
6.4 CHECKING BY GC/NMRCL:.......................................................................................10
6.5 Chiseling by Tripod Winch:............................................................................................10
6.6 REINFORCEMENT CAGE LOWERING:....................................................................10
6.7 COVER BLOCK:............................................................................................................11
6.8 CONCRETING:..............................................................................................................12
6.9 Material Used:.................................................................................................................13
6.10 EQUIPMENTS............................................................................................................14
7. HEALTH, SAFETY AND ENVIRONMENT........................................................................15
8. QUALITY ASSURANCE AND QUALITY CONTROL......................................................15
9. ENCLOSURES:.....................................................................................................................16

METHODOLOGY FOR BORED CAST IN-SITU PILE


DETAIL SCHEMES / METHODS REV. : R0

PLANNING DEPARTMENT FORMAT NO. : QF 9949 10 DATE: 01.11.2017

Design and Construction of Elevated Viaduct of Length


2.607km from CH:3620.950 to CH:3962.558, 4042.558 to
4330.490, CH:4411.490 to 5174.498 , 5255.498 to 5988.303 and
6131.017 to 6612.560 Between Gaddigodam to Sitabuldi
(Excluding Stations) and Railway Span Near Gaddigodam,
PROJECT : Viaduct and Road Cum Rail Flyover (Double Decker) of
Length 4.065km Including Approach Ramps from CH:- REV :
R0 DATE
673.910 to 291.050, CH:-213.550 to 939.360, CH:1016.860 to
01.11.2017
2097.068, CH:2174.568 to 3125.370, Ch:3202.870 to 3620.950
and 3962.558 to 4042.558 on BOQ Basis (Excluding Stations)
in Reach 2
METHODS STATEMENT FOR BORED CAST IN-
DOC.TITLE: SITU PILE
DOCUMENT
PM/3452/003 SHEET : 3 of 16
NO.

1. Introduction
This method statement covers the methodology of piling work for foundations works are coming
in between the stretch from CH:3620.950 to CH:3962.558, 4042.558 to 4330.490, CH:4411.490
to 5174.498 , 5255.498 to 5988.303 and 6131.017 to 6612.560 Between Gaddigodam to
Sitabuldi (Excluding Stations) and Railway Span Near Gaddigodam, Viaduct and Road Cum
Rail Flyover (Double Decker) of Length 4.065km Including Approach Ramps from CH:-673.910
to 291.050, CH:-213.550 to 939.360, CH:1016.860 to 2097.068, CH:2174.568 to 3125.370,
Ch:3202.870 to 3620.950 and 3962.558 to 4042.558 on BOQ Basis (Excluding Stations) in
Reach 2. The proposed type of pile is 1200mm dia. Bored cast-in-situ concrete pile. The boring
work for the pile will be done by Hydraulic Rotary Rig/Winch.

2. SCOPE
Method for Piling by using suitable capacity Hydraulic Rig in soil as well as Tripod Winch in rock
using partial depth casing and thereafter chiseling in hard rock. Concreting of pile as per
approved drawings including reinforcements, compaction etc. all complete.

3. REFERENCES
DETAIL SCHEMES / METHODS REV. : R0

PLANNING DEPARTMENT FORMAT NO. : QF 9949 10 DATE: 01.11.2017

Design and Construction of Elevated Viaduct of Length


2.607km from CH:3620.950 to CH:3962.558, 4042.558 to
4330.490, CH:4411.490 to 5174.498 , 5255.498 to 5988.303 and
6131.017 to 6612.560 Between Gaddigodam to Sitabuldi
(Excluding Stations) and Railway Span Near Gaddigodam,
PROJECT : Viaduct and Road Cum Rail Flyover (Double Decker) of
Length 4.065km Including Approach Ramps from CH:- REV :
R0 DATE
673.910 to 291.050, CH:-213.550 to 939.360, CH:1016.860 to
01.11.2017
2097.068, CH:2174.568 to 3125.370, Ch:3202.870 to 3620.950
and 3962.558 to 4042.558 on BOQ Basis (Excluding Stations)
in Reach 2
METHODS STATEMENT FOR BORED CAST IN-
DOC.TITLE: SITU PILE
DOCUMENT
PM/3452/003 SHEET : 4 of 16
NO.

1 Contract documents
2 Good for Construction drawing of pile
3 IS:2911 1979 Part 1 Section 2 and IRC 78
4 IS: 2911 1985 Part 4
5 Bar bending schedules as prepared by Contractor as per IS 2502
6 Quality assurance manual
7 Quality system manual
8 Health, Safety and Environment plan.

4. ORGANISATION CHART
DETAIL SCHEMES / METHODS REV. : R0

PLANNING DEPARTMENT FORMAT NO. : QF 9949 10 DATE: 01.11.2017

Design and Construction of Elevated Viaduct of Length


2.607km from CH:3620.950 to CH:3962.558, 4042.558 to
4330.490, CH:4411.490 to 5174.498 , 5255.498 to 5988.303 and
6131.017 to 6612.560 Between Gaddigodam to Sitabuldi
(Excluding Stations) and Railway Span Near Gaddigodam,
PROJECT : Viaduct and Road Cum Rail Flyover (Double Decker) of
Length 4.065km Including Approach Ramps from CH:- REV :
R0 DATE
673.910 to 291.050, CH:-213.550 to 939.360, CH:1016.860 to
01.11.2017
2097.068, CH:2174.568 to 3125.370, Ch:3202.870 to 3620.950
and 3962.558 to 4042.558 on BOQ Basis (Excluding Stations)
in Reach 2
METHODS STATEMENT FOR BORED CAST IN-
DOC.TITLE: SITU PILE
DOCUMENT
PM/3452/003 SHEET : 5 of 16
NO.

Chief Project Manager

QA/QC Manager
Section In-charge
Overall Execution

Site Engineer
QC Engineer
Ensuring quality as Safety Engineer
per Specification

Foreman Supervisor
Execution of work Execution of work

Safety Supervisor
Arrangement of safety
Lab Assistant measures at site
Testing of Materials
5. RESPONSIBILITIES
Following are the responsibilities and reporting structure of personnel involved in the scope of
the procedure:
DETAIL SCHEMES / METHODS REV. : R0

PLANNING DEPARTMENT FORMAT NO. : QF 9949 10 DATE: 01.11.2017

Design and Construction of Elevated Viaduct of Length


2.607km from CH:3620.950 to CH:3962.558, 4042.558 to
4330.490, CH:4411.490 to 5174.498 , 5255.498 to 5988.303 and
6131.017 to 6612.560 Between Gaddigodam to Sitabuldi
(Excluding Stations) and Railway Span Near Gaddigodam,
PROJECT : Viaduct and Road Cum Rail Flyover (Double Decker) of
Length 4.065km Including Approach Ramps from CH:- REV :
R0 DATE
673.910 to 291.050, CH:-213.550 to 939.360, CH:1016.860 to
01.11.2017
2097.068, CH:2174.568 to 3125.370, Ch:3202.870 to 3620.950
and 3962.558 to 4042.558 on BOQ Basis (Excluding Stations)
in Reach 2
METHODS STATEMENT FOR BORED CAST IN-
DOC.TITLE: SITU PILE
DOCUMENT
PM/3452/003 SHEET : 6 of 16
NO.

Sr Responsible Responsibilities
N. Person
1 Chief Project 1) Shall report to management
Manager
2 Deputy Project 1) Shall report to the Project Manager.
Manager / Section 2) Shall be responsible for control, supervision and direction for
implementation and execution of construction plans.
Incharge
3) Shall also be responsible for supervision of construction
activities and preparation of construction records, Develop
construction schedules, procedures and prepare progress
and accomplishment reports.
3 Piling / Site In charge 1) Shall report to Deputy Project Manager.
/ Engineers 2) Shall be responsible for day to day planning of site. Piling
activities and preparation of construction records.
4 Survey Engineer 1) Shall report to Project Manager
/Surveyor
5 QA/QC Engineer 1) Shall report to Project Manager.
2) Shall be responsible for overall control of QC activities and
sub-contractors QC activities, implementation of QAM and
Quality Plan
3) Shall be responsible for carrying out Inspection as per the I
& TP and/or this procedure
6 Site Supervisor 1) Site supervisor shall report to site engineer and shall be
responsible for supervision of all works as guided by site
engineer.
6. METHODOLOGY

6.1 SETTING OUT:


DETAIL SCHEMES / METHODS REV. : R0

PLANNING DEPARTMENT FORMAT NO. : QF 9949 10 DATE: 01.11.2017

Design and Construction of Elevated Viaduct of Length


2.607km from CH:3620.950 to CH:3962.558, 4042.558 to
4330.490, CH:4411.490 to 5174.498 , 5255.498 to 5988.303 and
6131.017 to 6612.560 Between Gaddigodam to Sitabuldi
(Excluding Stations) and Railway Span Near Gaddigodam,
PROJECT : Viaduct and Road Cum Rail Flyover (Double Decker) of
Length 4.065km Including Approach Ramps from CH:- REV :
R0 DATE
673.910 to 291.050, CH:-213.550 to 939.360, CH:1016.860 to
01.11.2017
2097.068, CH:2174.568 to 3125.370, Ch:3202.870 to 3620.950
and 3962.558 to 4042.558 on BOQ Basis (Excluding Stations)
in Reach 2
METHODS STATEMENT FOR BORED CAST IN-
DOC.TITLE: SITU PILE
DOCUMENT
PM/3452/003 SHEET : 7 of 16
NO.

Necessary survey is to be completed and pile points marked. The pile location is set out
with respect to the control points by suitable pin marked at location and checked by
Engineer’s representative. The permission to start boring will be obtained in writing as
per the checklist. The guide points (min. 2 nos.) as per enclosed sketch are fixed at
suitable location outside the casing for future reference and the reference points are
guarded. Recording of Ground levels shall be taken prior to starting of work jointly with
GC Engineer. The setting out of each pile shall be agreed with the Engineer prior to
commencement of work.
Prior to starting piling work, pile cap diagonal trenching shall be done at each pile
location to identify the underground utilities. If any utilities are found the same shall be
reported to GC/NMRCL immediately.

Procedure for Checking of Verticality:


Check the mast of Hydraulic Rig by Spirit level to ensure that Hydraulic Rig shaft is
vertical. For conventional winch verticality shall be checked by plumb bob from top of
pully of Tripod.

6.2 DRIVING OF TEMPORARY CASING:

Tripod Rig to be positioned at the pre marked pile point. After necessary checks for
verticality of the Tripod Rig, boring will be started by bailer and Chisel. On completion of
boring up to about 2m on top, temporary steel casing pipe will be installed in position
DETAIL SCHEMES / METHODS REV. : R0

PLANNING DEPARTMENT FORMAT NO. : QF 9949 10 DATE: 01.11.2017

Design and Construction of Elevated Viaduct of Length


2.607km from CH:3620.950 to CH:3962.558, 4042.558 to
4330.490, CH:4411.490 to 5174.498 , 5255.498 to 5988.303 and
6131.017 to 6612.560 Between Gaddigodam to Sitabuldi
(Excluding Stations) and Railway Span Near Gaddigodam,
PROJECT : Viaduct and Road Cum Rail Flyover (Double Decker) of
Length 4.065km Including Approach Ramps from CH:- REV :
R0 DATE
673.910 to 291.050, CH:-213.550 to 939.360, CH:1016.860 to
01.11.2017
2097.068, CH:2174.568 to 3125.370, Ch:3202.870 to 3620.950
and 3962.558 to 4042.558 on BOQ Basis (Excluding Stations)
in Reach 2
METHODS STATEMENT FOR BORED CAST IN-
DOC.TITLE: SITU PILE
DOCUMENT
PM/3452/003 SHEET : 8 of 16
NO.

using Tripod Rig. The casing pipe will be gradually pushed to the required depth &
simultaneously boring will be done; ensuring verticality. Casing shall be driven preferably
in one piece. The diameter of cutting tool shall in no case be less than the diameter of
the pile minus 75 mm. The working level should be 0.3m to 0.5 meter above ground
level. Top level of the casing shall be recorded along with GC Engineer. The centre line
of the casing pipe is then checked with respect to the reference points with total station.
Care shall be taken during driving to keep shift and verticality with in specified limits that
is for verticality 1.5% and 75mm for shift. After concreting the casing is extracted.

6.3 BORING:

Boring operation will be done by Hydraulic rotary rig with the help of Kelly and bucket.
The size of bucket shall not be less than 1125mm for 1200mm dia pipe. After completion
of boring, founding level will be checked with sounding chain. Immediately after
completion of boring the R/F cage fabricated as per the detailed drawing and approved
BBS is lowered. If, due to any reason starting of R/F cage lowering is delayed 2hrs, the
borehole will be clean by cleaning bucket and founding level is checked at 4 locations
inside circumference of pile with sounding chain again.

In case of end bearing piles founded in rock, minimum socketing length shall be followed
as per approved by designer.

Excavated material from pile boring should be directly loaded to the trucks and
transported to dumping areas. It should not allow being stacked at site.
DETAIL SCHEMES / METHODS REV. : R0

PLANNING DEPARTMENT FORMAT NO. : QF 9949 10 DATE: 01.11.2017

Design and Construction of Elevated Viaduct of Length


2.607km from CH:3620.950 to CH:3962.558, 4042.558 to
4330.490, CH:4411.490 to 5174.498 , 5255.498 to 5988.303 and
6131.017 to 6612.560 Between Gaddigodam to Sitabuldi
(Excluding Stations) and Railway Span Near Gaddigodam,
PROJECT : Viaduct and Road Cum Rail Flyover (Double Decker) of
Length 4.065km Including Approach Ramps from CH:- REV :
R0 DATE
673.910 to 291.050, CH:-213.550 to 939.360, CH:1016.860 to
01.11.2017
2097.068, CH:2174.568 to 3125.370, Ch:3202.870 to 3620.950
and 3962.558 to 4042.558 on BOQ Basis (Excluding Stations)
in Reach 2
METHODS STATEMENT FOR BORED CAST IN-
DOC.TITLE: SITU PILE
DOCUMENT
PM/3452/003 SHEET : 9 of 16
NO.

Polymer
Use of polymer in stabilizing of pile borehole may also necessary together with
temporary or permanent casing wherever sub soil and ground water conditions are likely
to case instability of pile bore or sand boiling. However, this will be permitted only when
deemed necessary by Engineer. In such situations, the properties of polymer slurry used
& quality control shall be as per requirements given below. After installation of temporary
casing, the drilling operation will continuously proceed together with the application of
polymer slurry. The polymer shall be mixed with water in proportion according to
manufacturer in separate tank. The capacity of mixing tank shall be more than 1.5 times
of volume of the bore hole for which the polymer is to be used. For mixing and
application of polymer with water, agitator & pumping arrangement fixed with mixing tank
shall be used. Prior to preparation of mixture, care shall be given to cleanness of storage
tank and PH value of fresh water is to be between 7 to 9.

Properties of Polymer

REQUIRED
SL NO TYPE OF TEST EQUIPMENT TO BE USED
VALUE

1 Specific Gravity 1.00-1.05 g/cc Hydrometer

2 Marsh Funnel Value 60-70 seconds Marsh cone viscosity apparatus


DETAIL SCHEMES / METHODS REV. : R0

PLANNING DEPARTMENT FORMAT NO. : QF 9949 10 DATE: 01.11.2017

Design and Construction of Elevated Viaduct of Length


2.607km from CH:3620.950 to CH:3962.558, 4042.558 to
4330.490, CH:4411.490 to 5174.498 , 5255.498 to 5988.303 and
6131.017 to 6612.560 Between Gaddigodam to Sitabuldi
(Excluding Stations) and Railway Span Near Gaddigodam,
PROJECT : Viaduct and Road Cum Rail Flyover (Double Decker) of
Length 4.065km Including Approach Ramps from CH:- REV :
R0 DATE
673.910 to 291.050, CH:-213.550 to 939.360, CH:1016.860 to
01.11.2017
2097.068, CH:2174.568 to 3125.370, Ch:3202.870 to 3620.950
and 3962.558 to 4042.558 on BOQ Basis (Excluding Stations)
in Reach 2
METHODS STATEMENT FOR BORED CAST IN-
DOC.TITLE: SITU PILE
DOCUMENT
PM/3452/003 SHEET : 10 of 16
NO.

Viscosity

6.4 CHECKING BY GC/NMRCL:

After achieving initial rock level & quality of rock is checked by GC/NMRCL. After
approval further boring in rock is started by Tripod winch.

6.5 Chiseling by Tripod Winch:

Chiseling by using Tripod Winch is done upto desired depth in rock as per approved
drawings by using suitable capacity of chisel and Polymer Slurry. Cleaning will be done
by bailer at suitable intervals. One extra safety rope shall be used long with the Chisel.

6.6 REINFORCEMENT CAGE LOWERING:

Before cutting and bending of reinforcement, protective coating of reinforcement rods


against corrosion shall be done according to Contract document. The bar bending
schedule based on approved drawing is prepared and got approved from GC/NMRCL.
Reinforcement is cut and bent to required size and shape. Reinforcement cage shall be
fabricated at fabrication yard and transported to location and not at site/near pile
location. Specified cover blocks shall be provided to reinforcement cage for the pile.
Reinforcement cage shall be lowered in 1 piece or more depending on the available
length of steel bars & length of pile. Bottom cage is lowered inside the borehole and
temporarily supported on the casing pipe top, keeping the dowel length projecting above
and second cage is lifted and lapped as per approved drawings or construction
DETAIL SCHEMES / METHODS REV. : R0

PLANNING DEPARTMENT FORMAT NO. : QF 9949 10 DATE: 01.11.2017

Design and Construction of Elevated Viaduct of Length


2.607km from CH:3620.950 to CH:3962.558, 4042.558 to
4330.490, CH:4411.490 to 5174.498 , 5255.498 to 5988.303 and
6131.017 to 6612.560 Between Gaddigodam to Sitabuldi
(Excluding Stations) and Railway Span Near Gaddigodam,
PROJECT : Viaduct and Road Cum Rail Flyover (Double Decker) of
Length 4.065km Including Approach Ramps from CH:- REV :
R0 DATE
673.910 to 291.050, CH:-213.550 to 939.360, CH:1016.860 to
01.11.2017
2097.068, CH:2174.568 to 3125.370, Ch:3202.870 to 3620.950
and 3962.558 to 4042.558 on BOQ Basis (Excluding Stations)
in Reach 2
METHODS STATEMENT FOR BORED CAST IN-
DOC.TITLE: SITU PILE
DOCUMENT
PM/3452/003 SHEET : 11 of 16
NO.

drawings. Helicals / rings are tied as per approved drawing and main reinforcement laps
are properly welded to provide more rigidity to the cage. The cage is further lowered in
the borehole. MS Pipe of 2.9 mm thick 50 mm outer dia shall be installed according to
drawing for Cross hole sonic test. Also earthing rod shall be provided as per approved
drawing.

6.7 COVER BLOCK:

Circular Cover Block of 150mm dia shall be made with the same grade of concrete as
that of pile concrete and fixed to either the main bar or to helical as mentioned in
drawings. The cover block shall be provided at approximately 1.2 to 1.5 meters intervals
and suitably staggered. The strength of concrete cover blocks will be same as that of
concrete in pile.

6.8 CONCRETING:

Funnel shall be attached on top of the tremie pipe for pouring of concrete. The concrete
shall be placed in the bore through the tremie. The bottom of the Tremie shall be 300
mm (approx) above the bottom of the bore. Before the first charge of concrete is placed
in the funnel, a floating plug will be inserted in to the tremie pipe and a suitable plate will
close the mouth of the tremie at top. During concreting care has to be taken to see that
the tremie pipe is always embedded in concrete by 1.0 to 1.5 m.
DETAIL SCHEMES / METHODS REV. : R0

PLANNING DEPARTMENT FORMAT NO. : QF 9949 10 DATE: 01.11.2017

Design and Construction of Elevated Viaduct of Length


2.607km from CH:3620.950 to CH:3962.558, 4042.558 to
4330.490, CH:4411.490 to 5174.498 , 5255.498 to 5988.303 and
6131.017 to 6612.560 Between Gaddigodam to Sitabuldi
(Excluding Stations) and Railway Span Near Gaddigodam,
PROJECT : Viaduct and Road Cum Rail Flyover (Double Decker) of
Length 4.065km Including Approach Ramps from CH:- REV :
R0 DATE
673.910 to 291.050, CH:-213.550 to 939.360, CH:1016.860 to
01.11.2017
2097.068, CH:2174.568 to 3125.370, Ch:3202.870 to 3620.950
and 3962.558 to 4042.558 on BOQ Basis (Excluding Stations)
in Reach 2
METHODS STATEMENT FOR BORED CAST IN-
DOC.TITLE: SITU PILE
DOCUMENT
PM/3452/003 SHEET : 12 of 16
NO.

If Cut off level (COL) is less than 1.0 m below the ground level, concrete shall be cast at
top of the piling platform level and overflow the concrete. In case COL of Pile is more
than 1.0m below working level then concrete shall be cast to a minimum of one meter
above COL.

On completion of concreting to the required elevation, temporary casing will be


withdrawn by tripod rig. Lowering Reinforcement Cage, lowering Tremie pipe, pouring
concrete & extraction of tremie will be done Tripod or suitable crane. Tripod rig then will
be shifted to next pile location.

Workability of concrete; Concrete cubes will be casted as per specification requirements


and test cubes for 7 days and 28 days strength on a regular basis

Preparation of concrete graph indicating the theoretical and actual quantity of concrete
used at various depths to determine the extent at location of over break. Incase of
chocking of tremie the additional set of tremie to be used so that the same can be
inserted in the concrete by more than one meter.

6.9 Material Used:

Prior to utilization of materials needed tests has to be done in the laboratories in the
presence of GC/NMRCL.

(A) Concrete
 Grade of Concrete As per drawing
 Slump of concrete 150 to 175 mm
 The maximum size of Coarse aggregate shall not exceed 20mm
DETAIL SCHEMES / METHODS REV. : R0

PLANNING DEPARTMENT FORMAT NO. : QF 9949 10 DATE: 01.11.2017

Design and Construction of Elevated Viaduct of Length


2.607km from CH:3620.950 to CH:3962.558, 4042.558 to
4330.490, CH:4411.490 to 5174.498 , 5255.498 to 5988.303 and
6131.017 to 6612.560 Between Gaddigodam to Sitabuldi
(Excluding Stations) and Railway Span Near Gaddigodam,
PROJECT : Viaduct and Road Cum Rail Flyover (Double Decker) of
Length 4.065km Including Approach Ramps from CH:- REV :
R0 DATE
673.910 to 291.050, CH:-213.550 to 939.360, CH:1016.860 to
01.11.2017
2097.068, CH:2174.568 to 3125.370, Ch:3202.870 to 3620.950
and 3962.558 to 4042.558 on BOQ Basis (Excluding Stations)
in Reach 2
METHODS STATEMENT FOR BORED CAST IN-
DOC.TITLE: SITU PILE
DOCUMENT
PM/3452/003 SHEET : 13 of 16
NO.

 The cement used for piling work as per IS:455 specification for Portland Slag
Cement and IS 269 Ordinary Portland cement or any other cement as per
technical specification and directions of Engineer.
 Minimum cement content for design Mix shall not be less than 400kg/m3
 For Piling, quantity of cement shall be as per the Design Mix or the min. cement
content whichever is greater.
 Concrete cube shall be tested as per specifications.

(B) Reinforcement steel:


 Fe 500D bars shall be used
 18 gauge G.I. wire shall be used for binding reinforcement
 Bending of reinforcement shall be as per IS:2502
 The reinforcement shall extend as specified in the drawing
 Only circular cover blocks threaded on the helix of the pile cage.

6.10 EQUIPMENTS

S. No. DESCRIPTION TYPE CAPACITY NO.


1. Hydraulic Rig - - 1
2. Vertical Pump with __ Suitable 1
Tripod
3 Service Crane __ Suitable 1 (if required)
4 Excavator JCB 0.25 cum 1
5 Dumpers Tata / AL 4 cum 1
6 Batching Plant Automatic 30 & 60 cum/hr 1 each
DETAIL SCHEMES / METHODS REV. : R0

PLANNING DEPARTMENT FORMAT NO. : QF 9949 10 DATE: 01.11.2017

Design and Construction of Elevated Viaduct of Length


2.607km from CH:3620.950 to CH:3962.558, 4042.558 to
4330.490, CH:4411.490 to 5174.498 , 5255.498 to 5988.303 and
6131.017 to 6612.560 Between Gaddigodam to Sitabuldi
(Excluding Stations) and Railway Span Near Gaddigodam,
PROJECT : Viaduct and Road Cum Rail Flyover (Double Decker) of
Length 4.065km Including Approach Ramps from CH:- REV :
R0 DATE
673.910 to 291.050, CH:-213.550 to 939.360, CH:1016.860 to
01.11.2017
2097.068, CH:2174.568 to 3125.370, Ch:3202.870 to 3620.950
and 3962.558 to 4042.558 on BOQ Basis (Excluding Stations)
in Reach 2
METHODS STATEMENT FOR BORED CAST IN-
DOC.TITLE: SITU PILE
DOCUMENT
PM/3452/003 SHEET : 14 of 16
NO.

7 Transit Mixers __ 6/4 cum 3


8 Welding Rectifier __ 400 Amps 1
9 Tremie Pipe __ Min 200 Dia 20 – 25 rm
10 Hopper __ __ 1 nos.
11 Trailor __ __ 1 nos.
12 Water Tanker __ __ 1 nos.
13 Compressor __ __ 1 nos.
14 WILDEN Pump __ __ 1 nos.
15 NW2E Pump __ __ 1 nos.

As per actual site condition the number of equipment mentioned above may increase or
decrease. Any other equipments, machinery, tools and plants etc. whenever required to
complete the work successfully shall be deployed.

7. HEALTH, SAFETY AND ENVIRONMENT

Barricade having suitable width and length shall be erected at construction work location.
Suitable reflectors, blinkers, diversion board, proper illumination, painting of barricade etc. shall
be provided to caution the road users and their safety.
All site personnel shall be provided with PPE’s.
Proper precautions and safety devices shall be used for activities like excavation, fabrication,
handling of electrically operated equipments etc.
All site personnel shall follow the health and safety policy of the company and environment
policy and plan of NMRCL.
Traffic shall be diverted as per approved scheme wherever and whenever required.
DETAIL SCHEMES / METHODS REV. : R0

PLANNING DEPARTMENT FORMAT NO. : QF 9949 10 DATE: 01.11.2017

Design and Construction of Elevated Viaduct of Length


2.607km from CH:3620.950 to CH:3962.558, 4042.558 to
4330.490, CH:4411.490 to 5174.498 , 5255.498 to 5988.303 and
6131.017 to 6612.560 Between Gaddigodam to Sitabuldi
(Excluding Stations) and Railway Span Near Gaddigodam,
PROJECT : Viaduct and Road Cum Rail Flyover (Double Decker) of
Length 4.065km Including Approach Ramps from CH:- REV :
R0 DATE
673.910 to 291.050, CH:-213.550 to 939.360, CH:1016.860 to
01.11.2017
2097.068, CH:2174.568 to 3125.370, Ch:3202.870 to 3620.950
and 3962.558 to 4042.558 on BOQ Basis (Excluding Stations)
in Reach 2
METHODS STATEMENT FOR BORED CAST IN-
DOC.TITLE: SITU PILE
DOCUMENT
PM/3452/003 SHEET : 15 of 16
NO.

8. QUALITY ASSURANCE AND QUALITY CONTROL

Quality control and assurance shall be strictly followed as per proforma attached.

9. ENCLOSURES:
A. INSPECTION AND TEST PLAN
B. PERMANENT CASING CHECKLIST
C. REINFORCEMENT CHECKLIST
D. BORING PERMISSION SHEET
E. PRE POUR CHECKLIST
F. PERMISSION OF CAGE LOWERING
G. TREMIE CHECK LIST
H. CONCRETE POUR CARD
I. POLYMER SLURRY TEST
J. SETTING OUT PILE LOCATION
K. SAFETY CHECKLIST
L. HIRAC FOR PILING ACTIVITY
DETAIL SCHEMES / METHODS REV. : R0

PLANNING DEPARTMENT FORMAT NO. : QF 9949 10 DATE: 01.11.2017

Design and Construction of Elevated Viaduct of Length


2.607km from CH:3620.950 to CH:3962.558, 4042.558 to
4330.490, CH:4411.490 to 5174.498 , 5255.498 to 5988.303 and
6131.017 to 6612.560 Between Gaddigodam to Sitabuldi
(Excluding Stations) and Railway Span Near Gaddigodam,
PROJECT : Viaduct and Road Cum Rail Flyover (Double Decker) of
Length 4.065km Including Approach Ramps from CH:- REV :
R0 DATE
673.910 to 291.050, CH:-213.550 to 939.360, CH:1016.860 to
01.11.2017
2097.068, CH:2174.568 to 3125.370, Ch:3202.870 to 3620.950
and 3962.558 to 4042.558 on BOQ Basis (Excluding Stations)
in Reach 2
METHODS STATEMENT FOR BORED CAST IN-
DOC.TITLE: SITU PILE
DOCUMENT
PM/3452/003 SHEET : 16 of 16
NO.

M BORE LOG SHEET

Potrebbero piacerti anche