A. K. CONSTRUCTIONS
AND BUILDING MATERIAL SUPPLIERS
At/Post- Chincholi Morachi, Taluka- Shirur, District- Pune- 412218

Ref.: Date: 05-12-2019.

To,
Project Manager,
B.G. Shirke Construction Technology Pvt. Ltd.

1st R.A. Bill. (Site – PS10-PS17 / Pimpale Saudagar).

Sr. Description Of Item. Quantity Unit Rate Amount.


No.
1. Excavation of Road (Trial Pit) 59.81 Cum. 115.00 6878.15
2. Carting 12km. 59.81 Cum. 168.00 10048.08
3. Excavation for chamber. 112.00 Cum. 115.00 12880.00
4. Carting Up to 12km. 112.00 Cum. 168.00 18816.00
5. Excavation for Pit. 147.00 Cum. 115.00 16905.00
6. Carting up to 12km. 147.00 Cum. 168.00 24696.00
7. Excavation for Trench. 2450.70 Cum. 115.00 281830.15
8. Carting 0-3 km. 1021.12 Cum. 100.00 102112.00
9. Carting Up to 12 km. 1429.57 Cum. 168.00 2040167.76
10. Hume Pipe Fixing (1400 Dia) 220.50 R.M. 810.00 178605.00
11. Backfilling 1021.12 Cum. 55.00 56161.60
12. Excavation of Chamber. 770.00 Cum. 115.00 88550.00
13. Carting up to 12 km. 770.00 Cum. 168.00 129360.00
14. Rubble Soiling 280.60 Cum. 200.00 56120.00
15. Removing Hume Pipe. (900 Dia) 220.50 R.M. 190.00 41895.00
16. Concrete Breaking. 58.26 Cum. 500.00 29130.00
17. R.C.C. Chamber Casting. (1400 Dia) 4.00 Nos. 20000.00 80000.00
18. Excavation for Road. 1293.60 Cum. 115.00 148764.00
19. Carting up to 12 Km. 1293.60 Cum. 168.00 217324.80
20. Old Sever Line Repairing. 2.00 Nos. 2000.00 4000.00
Total. 1744241.00