Sei sulla pagina 1di 4

AMITY SCHOOL OF ENGINEERING AND TECHNOLOGY

DEPARTMENT OF COMPUTER SCIENCE AND ENGINEERING


SOFTWARE PROJECT MANAGEMENT

Assignment# 1

1. “Software projects are similar to other projects but have done attributes that present
particular difficulties”, Justify and explain.
2. How does Software project differentiate from other engineering projects?
3. What is the meaning of Business case in software project management?
4. Compare software product and software project. List the different types of software
project plan.

5. Discuss dimensions of project monitoring and control.


AMITY SCHOOL OF ENGINEERING AND TECHNOLOGY
DEPARTMENT OF COMPUTER SCIENCE AND ENGINEERING
SOFTWARE PROJECT MANAGEMENT

Assignment# 2

1 . Based on the following table of activities


a) Draw a network diagram.
b) Find the critical path
c) Estimate the duration of project.

Activity Required Predecessors Duration


A None 5 Month
B None 1 Month
C A 2 Month
D A 3 Month
E A 2 Month
F C 3 Month
G D 4 Month
H B,E 2 Month
I H 1 Month
J F,G,I 1 Month

2. Based on the following table of activities


a) Draw a network diagram.
b) Find the critical path
c) Estimate the duration of project.
Activity Required Predecessors Duration
A H/w Selection None 6 Month
B S/w Design None 4 Month
C Install H/w A 3 Month
D Code and Test S/w B 4 Month
E File take on B 3 Month
F Write User manuals None 10 Month
G User Training E,F 3 Month
H Install and test C,D 2 Month
system
AMITY SCHOOL OF ENGINEERING AND TECHNOLOGY
DEPARTMENT OF COMPUTER SCIENCE AND ENGINEERING

SOFTWARE PROJECT MANAGEMENT

Assignment #3

1. Discuss the Monitoring and Control process.


2. What do you mean by Software Configuration Management?
3. What are fundamental source of change?
4. What are baselines of change control?
5. Discuss software configuration items.

Potrebbero piacerti anche