BASEMENT
GROUND FLOOR
01 Outdoor lights Wiring done , not clear detail provided for light fittings
03 Lights inside two display areas Wiring done , not clear detail provided for light fittings
05 Roller door to the main entrance, Back entrance 2 doors completed and the Basement door is remaining
and to the basement (3 nos)
11 Wash room to be completed (with exhaust) Bath ware fittings need to be fixed, other works
completed
12 Rear entrance door Sliding door not fixed but wooden door frame fixed
FIRST FLOOR
03 Washroom at the fire escape side & washroom Partially done. Tiles work is remaining
inside to be completed
04 Dining area at the fire escape side Plumbing line need to be fixed
SECOND FLOOR
02 Entrance door and other doors Roller door fixed but not working properly. Wood door
frame fixed.
THIRD FLOOR
02 Entrance door, server room door and other Roller door is fixed and other door frames fixed.
doors
FOURTH FLOOR
01 Entrance door and other doors Glass door not fixed. Other doors frame done and
material at site.
07 Electrical works (switches, plugs, light fittings Light fixing completed and switch need to be fixed
etc)
03 Do pond test for waterproofing in between CJS building and makeen bookshop Not done
05 Fix ground floor bathroom threshold Shall we finished when granite fixing
06 Ground floor bathroom column plastering should be done up to ceiling level completed
08 Send shop drawing of SO1 ground floor sliding door Need to submit by subcontractor
09 Wall construction near landing ara in ground floor to 1 st floor stair case completed
12 Remove 1st floor curtain box and redo plastering with cement mortar completed
16 Fix sliding aluminium window on the above of fire hose reel box Not done
19 Discuss with exel holding about granite fixing on stair case tread completed
20 Arrange water supply for 4th floor kitchen area Not done
21 Remove unwanted water lines and close the ceiling in 6 th floor Not done
22 Fix tile insulation gulley for every floor bathroom Not done
23 Demolish concrete and re plaster of 5th floor fin in fire exit area completed
26 Arrange power supply and necessary lights to 4 th floor lift motor room Not done
Date 11/01/2019
Based on above site instruction, the following table illustrate the status of those instruction.
1 Done
2 On progress
3 On progress
4 Done
5 Done
6 On progress
7 Not done
8 Not done
9 Not done
10 Done
11 Not done
28/01/2019
Based on above site instruction, the following table illustrate the status of that instruction.
1 In progress
2 Done
3 In progress
4 Done
5 Done
6 Done
7 Not done
8 Not done
9 Not done