LIGHTNING PROTECTION AND
Print dated : November 2019
GROUNDING INSTALLATION Page :
WORK METHOD
COMMENT SHEET
01 14-11-2019
SIGN
PT. HORAS
SINOHYDRO PLN-E PLN PERSERO
BANGUN
PERSADA Approved
Approved as note
Issued for
Not Approved
Approval
Catalog
1. Compilation basis -1-
1) Compilation basis
Indonesia pangkalan Susu power plant 3 & 4 (2 * 200 MW) coal-fired unit. Administration Building
installation engineering plant lightning protection grounding design and construction plans, electrical
equipment grounding installation drawings.
PANGKALAN SUSU COAL FIRED STEAM POWER PLANT PROJECT UNIT 3 & 4 (2*200MW)
page: - 1 -
Doc No. : 0603A/PLTU-HBP/XI/2019
LIGHTNING PROTECTION AND
Print dated : November 2019
GROUNDING INSTALLATION Page :
WORK METHOD
4) Construction progress
Because the entire plant lightning protection need to cooperate with other professional
construction managements, it especially be restrained by the schedule of civil engineering
company. So the scheduling of lightning protection should be on the basis of the schedule of civil
engineering company , and try to keep the continuation of project, and ensure the quality and
technology of project on the premise of safety.
PANGKALAN SUSU COAL FIRED STEAM POWER PLANT PROJECT UNIT 3 & 4 (2*200MW)
page: - 2 -
Doc No. : 0603A/PLTU-HBP/XI/2019
LIGHTNING PROTECTION AND
Print dated : November 2019
GROUNDING INSTALLATION Page :
WORK METHOD
Trench construction
Manufacturing and installation of lightning Connection of grounding facility Grounding of electric facility
device
PANGKALAN SUSU COAL FIRED STEAM POWER PLANT PROJECT UNIT 3 & 4 (2*200MW)
page: - 3 -
Doc No. : 0603A/PLTU-HBP/XI/2019
LIGHTNING PROTECTION AND
Print dated : November 2019
GROUNDING INSTALLATION Page :
WORK METHOD
PANGKALAN SUSU COAL FIRED STEAM POWER PLANT PROJECT UNIT 3 & 4 (2*200MW)
page: - 4 -
Doc No. : 0603A/PLTU-HBP/XI/2019
LIGHTNING PROTECTION AND
Print dated : November 2019
GROUNDING INSTALLATION Page :
WORK METHOD
-connecting those grounding lines and also for connecting the main line and earth pole, and
the connecting method applies for thermit welding (TW)
ii) Factory main connected to the level of net grounding is usually buried deep -0.8m and
ground lines from the building should not be less than 1.5m, the grounding grid should be
closed and aid edge angle should be made into a circular arc shape, arc radius is not less
than 5m. Main grounding grid design of vertical grounding electrodes and with horizontal
connected grid firm fireclay fusion connected, vertical grounding electrode spacing of not
less than 15m vertical grounding deep need to 6m.
iii) Ground wire must wear inside the pipe when they across the floor or wall.
iv) As to the grounding device under the ground, after the laying, it is a must to immediately
compact the soil. There must be sufficient length left about all grounding materials. The
laying of EL -0.8m main grounding screen shall be completed before soil backfilling, and the
grounding part of equipment shall be completed after the installation of equipment and
before terrace plastering,backfill should be pure soil without ballasts and sundry.
v) In the construction area to meet the grounding grid position, copper stranded wire should be
set aside 1 meters or so enough copper wire to expose the ground margin, ready to connect
with the late construction of the grounding grid.
vi) Should be set respectively grounding sign at the entrance of the grounding line into the
building and maintenance of temporary grounding terminals
vii) Grid should be installed at the walkway besides the edge of grounding grid where people
always pass by.
viii) The grounding conductors should be prevented from mechanical damnification and chemical
corrosion. Protection should be made to the grounding system at the place where it goes
across road, railway or chemical conduits and where mechanical damage might happen.
ix) The electrical installation team should cooperate with the structure team to the construction
of grounding grid.Confirmation and record for embedment should be made.
10.2. The equipment grounding of buried pipes are not allowed to use by cable.
The connection of equipment and conductor could use bolt and spring washer for shockproof. Joint of
bolt should be anti-rust.
1) The zero connection protection of single-phase 220V electrical equipment, should set up separate
protective zero line, not using the device's own work zero line doubles as a ground zero protection.
2) Electric facilities within the same system are prohibited for partial grounding and partial neutral
connection
3) The grounding for AC power equipment of Turbine Hall shall apply for 40*3 copper bar as the
PANGKALAN SUSU COAL FIRED STEAM POWER PLANT PROJECT UNIT 3 & 4 (2*200MW)
page: - 5 -
Doc No. : 0603A/PLTU-HBP/XI/2019
LIGHTNING PROTECTION AND
Print dated : November 2019
GROUNDING INSTALLATION Page :
WORK METHOD
grounding line, for generator macro-axis grounding carbon brush and 400V and below equipments,
the grounding conductor shall apply for copper stranded wire (16 mm2), and for medium pressure
equipment grounding conductor applies for copper stranded wire (35 mm2). Each grounding part of
electric facility shall connect with grounding main line through independent grounding wire, and it is
prohibited for cascading several grounding parts on one grounding line
4) Boiler equipment and boiler proper casing connect with steel column which needs to conduct
grounding lead-down wire at EL +0.3m, applying for bolt connection to connect with the closest main
grounding screen; The grounding system should form a loop, part is not isolated in the system
when a point off.
Grounding electrode and measurement well
1 The location of grounding electrode shall be base don the design drawing and the main
grounding line shall be connected with grounding electrode or main grounding screen by thermit
weld.
2 Grounding measurement well is used to check the grounding resistance of each area; the
connecting sheet of the groundling wire shall be installed within the well that can be seen on the
ground, and the grounding connecting sheet within the grounding measurement well shall be bolt
fastening.
3 Lightning protection and grounding and relevant requirements
4 As to all frames with lightning rod and lightning wire, microwave tower shall be equipped with
centralized grounding device.
5 Lightning rod shall be equipped with centralized grounding and its grounding wire shall be
connected with earth screen in the shortest distance.
6 Independent lightning rod (line) should be set up independent centralized grounding device,
grounding resistance should not be more than 10Ω.
7 Independent lightning rod (wire) should not be located in the local people often pass. Lightning
rod (line) and its connection device and roads or entrance with a distance not less than 3m.
Otherwise, it shall be take all measures, the laying of move stone or asphalt surface.
PANGKALAN SUSU COAL FIRED STEAM POWER PLANT PROJECT UNIT 3 & 4 (2*200MW)
page: - 6 -
Doc No. : 0603A/PLTU-HBP/XI/2019
LIGHTNING PROTECTION AND
Print dated : November 2019
GROUNDING INSTALLATION Page :
WORK METHOD
PANGKALAN SUSU COAL FIRED STEAM POWER PLANT PROJECT UNIT 3 & 4 (2*200MW)
page: - 7 -
Doc No. : 0603A/PLTU-HBP/XI/2019
LIGHTNING PROTECTION AND
Print dated : November 2019
GROUNDING INSTALLATION Page :
WORK METHOD
8) Safety Measures
The do’s and don’ts
1. Construction workers must seriously study < electric power construction safety production work
procedures >, must grasp the construction procedures with electrical and instrumentation;
2. When enter into site, it is a must to carefully check the construction environment, thus to avoid any
accident such as strike or falling and so on;
3. It is a must to master each construction gist when conducting every work activity;
4. When using any specific tool or machine, it is a must to master the use method of those tools or
machines;
5. Before conducting the thermit welding (TW), it is a must to carefully check whether the mould and
welding powder is moisture or not; clean and dry the mould and check the specification of the mould
and gun powder before use it;
6. Before welding, it is necessary to clean all flammable articles around to avoid any fire disaster; after
the welding, keep and store the mould and cool off the welded junction to avoid any heat injury.
Meanwhile, clean up the welded junction so as to ensure the welding quality;
7. After finish the construction, take protective measures to prevent any stolen or damage to those
materials and equipments.For example: let the security guard; backfill immediately after construction
completion
8. Keep civilized construction and clean up the construction site after finish the relevant construction;
9. Conduct supervision and inspection during the construction: absolutely stop those violation activities
and as to those construction with potential danger, first relieve the potential danger and take
precautious measures to avoid any further accident;
10. Must be unified dress and wearing a safety helmet before into the construction site,the height of the
work must be correctly hoisted safety belt, is strictly prohibited to wear slippers, sandals, high heels,
PANGKALAN SUSU COAL FIRED STEAM POWER PLANT PROJECT UNIT 3 & 4 (2*200MW)
page: - 8 -
Doc No. : 0603A/PLTU-HBP/XI/2019
LIGHTNING PROTECTION AND
Print dated : November 2019
GROUNDING INSTALLATION Page :
WORK METHOD
- All welding moulds shall be stored in the appointed container with anti-moisture
and anti-breakage measures. Welding mould shall be lightly both lifted and lay
down and the welding and cleaning shall meet the requirements of welding
procedure;
- Bear copper stranded wire shall be in collection storage and make records about
the claim; take protective measures for those installed ground screens without
backfilling and give notice to security department about security guide.
PANGKALAN SUSU COAL FIRED STEAM POWER PLANT PROJECT UNIT 3 & 4 (2*200MW)
page: - 9 -
Doc No. : 0603A/PLTU-HBP/XI/2019
LIGHTNING PROTECTION AND
Print dated : November 2019
GROUNDING INSTALLATION Page :
WORK METHOD
PANGKALAN SUSU COAL FIRED STEAM POWER PLANT PROJECT UNIT 3 & 4 (2*200MW)
page: - 10 -