Sei sulla pagina 1di 6

Designation: D 7208 – 06

Standard Test Method for


Determination of Temporary Ditch Check Performance in
Protecting Earthen Channels from Stormwater-Induced
Erosion1
This standard is issued under the fixed designation D 7208; the number immediately following the designation indicates the year of
original adoption or, in the case of revision, the year of last revision. A number in parentheses indicates the year of last reapproval. A
superscript epsilon (e) indicates an editorial change since the last revision or reapproval.

1. Scope D 698 Test Methods for Laboratory Compaction Character-


1.1 This test method covers the guidelines, requirements, istics of Soil Using Standard Effort (12,400 ft-lbf/ft3(600
and procedures for evaluating the ability of temporary ditch kN-m/m3))
checks to protect earthen channels from stormwater-induced D 6460 Test Method for Determination of Erosion Control
erosion. Critical elements of this protection are the ability of (ECB) Performance in Protecting Earthen Channels from
the temporary ditch check to: Stormwater-Induced Erosion
1.1.1 Slow and/or pond runoff to encourage sedimentation, 3. Terminology
thereby reducing soil particle transport downstream;
1.1.2 Trap soil particles up stream of structure; and 3.1 Definition of Term Specific to This Standard:
1.1.3 Decrease soil erosion. 3.1.1 temporary ditch check (in erosion control), n—a
1.2 This test method utilizes full-scale testing procedures, non-permanent barrier consisting of rocks, straw bales, excel-
rather than reduced-scale (bench-scale) simulation, and is sior logs, wattles, lumber, rock bags, interlocking pre-cast
patterned after conditions typically found on construction sites concrete blocks, or other materials installed or constructed
at the conclusion of earthwork operations, but prior to the start across a drainage way, swale, or other ephemeral waterway to
of revegetation work. Therefore this test method considers only reduce flow velocity, decrease erosion, and promote soil
unvegetated conditions. retention.
1.3 This test method provides a comparative evaluation of a 4. Summary of Test Method
temporary ditch check to baseline bare soil conditions under
controlled and documented conditions. 4.1 The performance of a temporary ditch check in reducing
1.4 The values stated in SI units are to be regarded as stormwater-induced erosion is determined by subjecting the
standard. The inch-pound units given in parentheses are material to simulated stormwater flow in a controlled and
provided for information purposes only. documented environment.
1.5 This standard does not purport to address all of the 4.2 Key elements of the testing process include:
safety concerns, if any, associated with its use. It is the 4.2.1 Calibration of the stormwater simulation equipment;
responsibility of the user of this standard to establish appro- 4.2.2 Preparation of the test channel;
priate safety and health practices and determine the applica- 4.2.3 Documentation of the temporary ditch check(s) to be
bility of regulatory limitations prior to use. Also, the user must tested;
comply with prevalent regulatory codes, such as OSHA (Oc- 4.2.4 Installation of the temporary ditch check(s);
cupational Health and Safety Administration) guidelines, while 4.2.5 Performance of the test;
using the test method. 4.2.6 Collection of hydraulic, topographical, and associated
data;
2. Referenced Documents 4.2.7 Analysis of the resultant data; and
2.1 ASTM Standards: 2 4.2.8 Reporting.
5. Significance and Use
1
This test method is under the jurisdiction of ASTM Committee D18 on Soil and 5.1 This test method evaluates temporary ditch checks and
Rock and is the direct responsibility of Subcommittee D18.25.08 on Sediment their means of installation to:
Control.
Current edition approved May 15, 2006. Published July 2006.
5.1.1 Reduce soil loss and sediment concentrations in
2
For referenced ASTM standards, visit the ASTM website, www.astm.org, or stormwater runoff under conditions of varying channel condi-
contact ASTM Customer Service at service@astm.org. For Annual Book of ASTM tions and soil type; and
Standards volume information, refer to the standard’s Document Summary page on
the ASTM website.

Copyright © ASTM International, 100 Barr Harbor Drive, PO Box C700, West Conshohocken, PA 19428-2959, United States.

1
D 7208 – 06
5.1.2 Improve water quality exiting the area disturbed by 6.2 Water Source—Any water source shall be suitable for
earthwork activity by reducing suspended solids. this use provided that it is not sediment laden or contains
5.2 This test method models and examines conditions typi- deleterious materials that could impair the operation of the
cally found on construction sites involving earthwork activi- pumps.
ties, including: highways and roads; airports; residential, com- 6.3 Total Station System—The total station system is a
mercial and industrial developments; pipelines, mines, and standard surveying instrument that is capable of measuring
landfills; golf courses; etc. vertical and horizontal angles, and distance, simultaneously to
determine measurement point coordinates (that is, X, Y and Z
5.3 This test method is a performance test. It is a compara-
axis) and that uses an internal data logger to store this
tive tool for evaluating the erosion control characteristics of
information for future use. In lieu of a total station system,
different temporary ditch checks and can be used for quality manual surveying equipment may be used provided that
control to determine product conformance to project specifi- equivalent accuracy is achievable. Periodic calibration and
cations. Take caution when comparing results from different certification of this equipment shall be performed.
laboratories because information about between-laboratory 6.4 Velocity Probe—A velocity probe capable of measuring
precision is incomplete and slight differences in soil and other point velocities to an accuracy of 6 0.03 m/s (0.1 ft/s) shall be
environmental and geotechnical conditions may affect tempo- used to identify flow conditions during test operation. Accept-
rary ditch check performance. Unique project-specific condi- able types of probes include electromagnetic, spinning cup,
tions should be taken into consideration. propeller, and static tube devices. Periodic calibration and
certification of this equipment shall be performed.
6. Apparatus 6.5 Miscellaneous—Other miscellaneous equipment in-
6.1 Water Delivery System—The water delivery system cludes: meteorological equipment (wind speed, temperature,
shall include pump(s), piping, channels, and water control precipitation), and cameras or video recorders.
structures, as necessary, to achieve the desired hydraulic
conditions. The water control structures shall regulate the flow 7. Procedure
and to direct it into the desired test channel. The water delivery 7.1 Test Channel Preparation:
system shall be constructed such that turbulence at the entrance 7.1.1 Construct earthen test channels using conventional
to the test channel is minimized. Use of flow straighteners (for earthwork placement techniques similar to procedures outlined
example, tube racks or vanes) are recommended to reduce in Test Method D 6460. Perform compaction of channel bed
turbulence and achieve uniform flow conditions. A direct flow material to create a stable subgrade.
system (that is, controlled flow diverted from a natural water- 7.1.2 Plate the channel surface with a minimum 45 cm (18
way) may also be employed for this purpose. The water in) thick veneer of soil. General soil types to be used for testing
delivery system in Fig. 1 shows an example of a closed-loop shall be loam, clay, and sand. Target grain sizes and plasticity
water delivery system. indices are included in Table 1. Place the veneer in 15 cm (6 in)

FIG. 1 Typical Closed Looped Water Delivery System

2
D 7208 – 06
TABLE 1 Target Grain Sizes and Plasticity Indices 7.3.1 Maintain a test folder for each test cycle, including
Sand Loam Clay information on:
D100 (mm) D100 < 40 D100 < 25 D100 < 10 7.3.1.1 Site conditions;
D85 (mm) 1.0 < D85 < 10.0 0.5 < D85 < 5.0 0.01 < D85 < 1.0
D50 (mm) 0.08 < D50 < 2.0 0.01 < D50 < 1.0 0.001 < D50 < 0.1
7.3.1.2 Geotechnical and soil conditions;
D15 (mm) 0.001 < D15 0.0005 < D15 D15 < 0.0005 7.3.1.3 Meteorological data;
Plasticity Index nonplastic 1 < PI < 8 14 < PI
7.3.1.4 Temporary ditch check product type, description,
and installation procedure; and
7.3.1.5 Photo documentation.
lifts and compact to 90 6 3 % of standard Proctor density in 7.3.2 Include the following subjective site information:
accordance with Test Method D 698. general visual conditions of the channel to be tested; general
7.1.3 Excavate the channels to a trapezoidal cross-section meteorological information; channel treatment; photographs
with a 0.61 m (2 ft) bottom width and 2H:1V side slopes. The and/or videotape, and any supplemental information that is not
test channels shall be a minimum of 18.3 m (60 ft) in length to included in the following sections, but is thought to be of
allow sufficient distance between temporary ditch check struc- significance to the test.
tures during testing. Bed slope shall be approximately 5 %. Fig. 7.3.3 Include the following geotechnical and soils informa-
2 shows a typical channel profile and Fig. 3 shows a typical tion: soil classification [Unified Soil Classification System
channel cross-section. (USCS) and USDA classification system.]; standard proctor
7.1.4 Begin the test reach far enough below the inlet to the moisture-density relationship; “K” factor; and; gradation (in-
channel to ensure flow is uniform and extend 12.2 m (40 ft) cluding hydrometer test for the P200 fraction).
downstream from that point. Establish benchmarks on either 7.3.4 Include the following meteorological information: all
side of the channel at each end of the test reach and at 1.5 m data from the on-site weather station at the time of the test (that
(5 ft) intermediate intervals (nine cross-sections total). is, ambient air temperature, wind speed and precipitation).
7.1.5 Loosen the soil veneer in the test reach and 1.5 m (5
7.3.5 Include the following product type and description
ft) upstream and downstream of the test reach to a depth of
information: manufacturer name; product name; description;
approximately 10 cm (4 in.) using a tiller or other appropriate
specifications; size, and; a sample of the material, if practical.
tools. Rake the tilled channel smooth with a steel hand rake and
compact. Repair depressions, voids, soft or uncompacted areas 7.4 Test Set-Up:
before testing can commence. Also, free the channel from 7.4.1 Install the temporary ditch check(s) in the channel
obstruction or protrusions, such as roots, large stones or other after calibration has been completed and the test channel has
foreign material. been prepared. Document the installation methodology for the
7.1.6 If the channel has been used previously for a test temporary ditch check(s) including: orientation on the bed and
series, discard the soil carried out of the channel, and obliterate side slopes (longitudinal or lateral); placement (which side
any rills and gullies. Spread new soil of the same type across faces up); termination details; joint details; spacing between
the channel and blend (rake or tilled) into the surface. temporary ditch checks if more than one is to be tested, and;
7.2 Calibration: anchor type and installation pattern. Place the temporary ditch
7.2.1 Perform determination of the water delivery system check(s) across the channel bottom perpendicular to the flow
discharge (Q). Begin calibration of the water delivery system direction and extend it up the side slopes far enough so ponded
when a steady-state flow is achieved. water cannot erode around the temporary ditch check. If more
7.2.2 For open-channel water delivery systems, measure the than one temporary ditch check is to be tested, spacing shall
depth of water flowing into the test channel. Measure the follow manufacturer recommendations or ditch check spacing
velocity in the supply channel using the velocity probe in the equation (see Section 8).
three-point measurement pattern shown in Fig. 3. 7.4.2 Measure the elevation of the channel surface with the
7.3 Pre-Test Documentation: total station equipment using the reference benchmarks and a

FIG. 2 Typical Channel Profile

3
D 7208 – 06

FIG. 3 Typical Channel Cross-Section

stringline between opposing benchmarks. Take elevation mea- condition of the test channel. Markers may be used to identify
surements for each test cross-section (nine total) at the loca- any scour patterns for the pictorial documentation.
tions shown in Fig. 3. Elevation measurements for additional 7.5.8 Include a minimum of three tests for each type of
cross-sections directly in front and behind each temporary temporary ditch check to be evaluated.
ditch check shall also be taken to measure deposition and/or
scour directly adjacent to ditch check structure. To allow 8. Calculation
measurement of the channel surface, a 0.6 cm (0.25 in.) 8.1 Calibration Data:
diameter steel tip extension (“stinger”) may need to be attached 8.1.1 Discharge—Calculate discharge for each flow and
to the base of the surveyor’s rod. Perform rod placement from report measurement method and the associated accuracy.
an above channel platform, so that the rodman does not walk 8.2 Temporary Ditch Check Spacing:
on the test channel. The rodman must use care in positioning 8.2.1 Ditch Check Spacing Equation—The necessary spac-
the rod so measurements are indicative of the channel surface. ing required between temporary ditch checks that place the
7.4.3 Take photographs and/or videotape of the test channel bottom of the upstream temporary ditch check and the top of
prior to testing. the downstream temporary ditch check at the same elevation is
7.5 Test Operation and Data Collection: computed as:
7.5.1 Include the following test data: operator name and
D 5 ~H / S! 3 100 (1)
title; time flow began; time flow stopped; time runoff stopped;
flow depths, and; measured velocities. where:
7.5.2 Take water surface elevation measurements at the D = spacing distance, ft,
centerline point of each test cross-section and directly in front H = distance between channel bed and top of installed
and behind each temporary ditch check using the total station temporary ditch check, ft, and
equipment as soon as the flow reaches a steady-state, uniform S = slope of channel bed, %,
condition. Take velocity measurements at the centerline point
NOTE 1—The ditch check spacing equation is not available in SI units.
of each test cross-section using the velocity probe (see Fig. 3).
If the depth of flow is less than 20 cm (8 in.), take only the 8.3 Test Data:
six-tenths depth reading. Take photographs and/or videotape 8.3.1 Analysis of the test data involves the following
during the test. variables: total discharge, velocity, flow depth, and energy
7.5.3 Perform testing at a target flow of 0.085 m3/s (3 cfs). slope.
7.5.4 Test duration shall be 30 minutes or until a temporary 8.3.2 Determine total discharge by the calibration activity
ditch check becomes dislodged. and also compute at each of the nine measurement cross-
7.5.5 At the conclusion of the test, take channel surface sections by the continuity equation, as follows:
elevation measurements again at the same locations as the Q 5 Vavg A (2)
pre-test measurements. As with the previous test data collec-
tion, take the rodman elevation measurements from above and where:
do not walk on the test channel surface. Q = discharge, m3/s,
7.5.6 Record general observations regarding the condition Vavg = average of the three centerline velocity measure-
of the tested temporary ditch check(s) at the conclusion of the ments, m/s, and
A = cross-sectional area of flow, m2.
data collection.
7.5.7 Carefully remove the temporary ditch check(s) from 8.3.3 Determine the energy slope, Sf, by fitting a regression
the channel, with as little disturbance of the soil as possible. line through the energy grade line elevation determined at each
Note general observations regarding the condition and scour of the nine measurement cross-sections, as follows:
patterns. Take photographs and or videotape to record the Sf 5 WSE 1 Vavg2 / 2 g (3)

4
D 7208 – 06

where: 9.1.4 Materials documentation including temporary ditch


Sf = energy slope, check material and anchor description,
WSE = water surface elevation, 9.1.5 Test set-up activities including trenching (if appli-
Vavg = average velocity, m/s, and cable), anchor pattern, and average anchor density (anchor per
g = gravitational constant, 9.8 m/s2. unit area),
8.3.4 Calculate the Clopper Soil Loss Index (CSLI) from 9.1.6 Test operation and data collection (including “raw”
the topographic data gathered before and after test flows using data such as measured discharge for each test flow), and
the total station equipment. Use the change in channel topog- 9.1.7 Analysis (including hydraulic conditions, CSLI, and
raphy to define the performance of the temporary ditch check. SAI compared to a bare soil data set containing a minimum of
Quantify areas of degradation (soil loss) as “cut” and quantify three replications).
areas of aggradation (sediment deposition) as “fill.” Use 9.2 Reporting of Significant Digits:
commercially-available earthworks software to evaluate the 9.2.1 Round off values from computation to the number of
channel topographies and determine areas of cut and fill. decimal places justified by the data. All calculations and
Calculate the CSLI as follows: reporting of experimental results shall adhere to the procedures
CSLI 5 ~CT / AT! 3 100 (4) described in “Experimental Methods for Engineers” (Holman
1984).3
where: 9.2.2 Examples of Significant Digits:
CSLI = Clopper Soil Loss Index, cm, Number as Number of
CT = total cut, m3, and Written Significant Digits
Implied Range

AT = wetted channel area, m2.


341 3 340.5 to 341.5
8.3.5 Calculate the Soil Aggradation Index (SAI) from the 34.1 3 34.05 to 34.15
topographic data gathered before and after test flows using the 0.00341 3 0.003405 to 0.003415
total station equipment. Use the change in channel topography 3410.0 4 3409.5 to 3410.5
341 EE7 3 340.5 EE7 to 341.5 EE7
to define the performance of the temporary ditch check. 3.41 EE-2 3 3.405 EE-2 to 3.415 EE-2
Quantify areas of aggradation (sediment deposition) as “fill”
and quantify areas of degradation (soil loss) as “cut”. Use 10. Precision and Bias
commercially-available earthworks software to evaluate the 10.1 Precision—The precision of this test method is being
channel topographies and determine areas of cut and fill. established.
Calculate the SAI as follows: 10.2 Bias—The true value of erosion control performance
SAI 5 ~FT / AT! 3 100 (5) of temporary ditch checks can be defined only in terms of a test
method. Within this limitation, the procedure described herein
where: has no known bias and, since there is not an accepted referee
SAI = Soil Aggradation Index, cm, test method, the procedures of this test method have no
FT = total fill, m3, and inherent bias.
AT = wetted channel area, m2.
11. Keywords
9. Report
11.1 erosion control; scour; sediment; soil loss; temporary
9.1 Report at a minimum the following information: ditch check
9.1.1 General information, including test facility location,
date, time and operator(s),
9.1.2 Test channel preparation, 3
Holman, J. P., Experimental Methods for Engineers, McGraw-Hill Book
9.1.3 Calibration data and analysis, Company, Fourth Edition, 1984.

ADDITIONAL REFERENCES

(1) Ayres Associates. “A Quantitative Assessment of Erosion and Sedi- (3) Linsley, Kohler and Paulhus, Hydrology for Engineers, McGraw-Hill
ment Control Best Management Practices—Channel Erodibility Stud- Book Company, 1972.
ies: Straw Bale Check Structures,” Ayres Associates, Fort Collins, CO, (4) McWhorter, J. C., Carpenter, T. G., and Clark, R. N., “Erosion Control
2001. Criteria for Drainage Channels,” Conducted for the Mississippi State
(2) Cabalka, D. A., Clopper, P. E., and Johnson, A., “Research, Develop- Highway Department in cooperation with the U.S. Federal Highway
ment and Implementation of Test Protocols for Channel Erosion
Administration by the Agricultural and Biological Engineering Depart-
Research Facilities (CERFs),” Proceedings of the International Ero-
ment, Mississippi State University, State College, Mississippi, 1968.
sion Control Association, Vol 29, 1998, pp. 237–248.

5
D 7208 – 06
ASTM International takes no position respecting the validity of any patent rights asserted in connection with any item mentioned
in this standard. Users of this standard are expressly advised that determination of the validity of any such patent rights, and the risk
of infringement of such rights, are entirely their own responsibility.

This standard is subject to revision at any time by the responsible technical committee and must be reviewed every five years and
if not revised, either reapproved or withdrawn. Your comments are invited either for revision of this standard or for additional standards
and should be addressed to ASTM International Headquarters. Your comments will receive careful consideration at a meeting of the
responsible technical committee, which you may attend. If you feel that your comments have not received a fair hearing you should
make your views known to the ASTM Committee on Standards, at the address shown below.

This standard is copyrighted by ASTM International, 100 Barr Harbor Drive, PO Box C700, West Conshohocken, PA 19428-2959,
United States. Individual reprints (single or multiple copies) of this standard may be obtained by contacting ASTM at the above
address or at 610-832-9585 (phone), 610-832-9555 (fax), or service@astm.org (e-mail); or through the ASTM website
(www.astm.org).

Potrebbero piacerti anche