Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
DETERMINATION OF OPEN
ACCESS CHARGES
FOR THE FY 2017-18
W.E.F-Dt.01.04.2017
BEFORE THE ODISHA ELECTRICITY REGULATORY COMMISSION
B H U B A N E S W A R.
Filing No.
Case No.
AND
…... .Applicant
Cont’d……P/2.
-2-
PRAYER
Filing No.
Case No.
AND
…... .Applicant
I Sri Prasanna Kumar Dash,, S/o Late Sri B.N. Dash, aged about
58 years residing at Bhubaneswar do here by solemnly affirm and say
as follows:
1. The Open Access charges are applicable to both long-term and short-term
customers.
2. Open Access applicants requiring load more than 1MW are only envisaged in this
application. Load below 1 MW is not considered as this does not appear in
Section 11 “Phasing of Open Access” in OERC (Terms & Condition of Open
Access) regulations 2005.
3. Wheeling charge is payable to avail Open Access to HT network only. (33KV or
11KV)
Page - 4
5. For surcharge calculation Avoided Cost method is adopted as per
recommendations of Forum of Indian Regulators.
6. Bulk tariff, transmission & SLDC charges are as approved for FY 2016-2017.
7. Approved loss level in EHT and HT for FY 2016-17.
8. Power factor at normative level of 90%.
9. Open Access for LT customers not envisaged as load above 1 MW need to be
availed in HT as per section 76 (3) of OERC (Distribution Conditions of Supply)
Code 2004.
1: Wheeling charge for Open Acess:
The Licensee estimated following bulk power purchase and Sales to
customers at different voltage level for FY 2017-18.
o Bulk Power Purchase – 9094.05 Million Units.
o Sale to EHT customers— 872.626 Million Units.
o Sale to HT customers—1354.24 Million Units.
o Sale to LT customers—4062.59 Million Units
Total unit to be wheeled in the distribution network of CESU is equal
to 8221.424 MU i.e. total power purchase minus the EHT sales.
Total Wheeling cost for the Financial Year 2017-18 is tabulated below:-
Particulars (Rs.in crores)
Employee cost 356.14
Repair & Maintenance
115.71
cost
Administrative &
19.13
General Expenses
Interest & Finance cost 240.12
Bad debt provision 25.34
Reasonable Return 10.47
Depreciation 106.16
Total 847.74
Wheeling charge per unit = [Rs.847.74Crs ] / [8221.424 MU] = Rs 103.12 paise
per unit.
So, CESU proposes wheeling charge of Rs 103.12 paise per unit for Open
Access HT customers for the FY 2017-18.
Page - 5
2: Cross subsidy surcharge:
Page - 6
C is the per unit weighted average cost of power purchase by the
Licensee, including meeting the Renewable Purchase Obligation. (270p)
D is the aggregate of transmission, distribution and wheeling charge
applicable to the relevant voltage level . (25 paise)
L is the aggregate of transmission, distribution and commercial
losses, expressed as a percentage applicable to the relevant voltage level
(8%).
R is the per unit cost of carrying regulatory assets.
Applying the above formula rate of cross subsidy surcharge is calculated as
203Paisa/ unit.
The above rate is applicable to following category of consumers.
General Purpose >70KVA
Specified Public Purpose
Public Water Works sewerage pumping
Large Industry
Power Intensive Industry
Mini Steel Plant
Railway Traction
Further, for Emergency Supply to CGP/ IPP category of consumers the
surcharge is calculated to 402p/unit for HT consumers based on the similar
principle.
For irrigation, Allied agriculture activities and Allied Agro Industrial activities
categories, open access surcharges are not envisaged since, the RST rates are
highly subsidized and Open Access is not a viable proposal.
2.2: For EHT Open Access Consumers:
Page - 7
Mini Steel Plant.
Sales rate per unit is computed at 100% load factor and which is tabulated
below:
Normal Normal
Demand
Energy Energy
Charge
charges. charges. Power factor
(Rs./
<=60% >60%
KVA)
(P/KWH) (P/KWH)
Tariff
250 520 415 0.9
rate
Surcharge(S) =T-(C+D+E)
Where T- sales rate per unit (516p)
C-BST rate for CESU / per unit (270p)
D-Transmission Charge / unit (25p)
R- The per unit cost of carrying regulatory assets.
• The fixed asset cost for the FY.2015-16 as approved by the commission in
RST order for the FY.2016-17 i.e Rs. 1619.15 Crores.
Page - 8
• The life cycle of the asset is taken as 20years.
• Total unit to be wheeled in the distribution network of CESU excluding the
EHT sales is equal to 8221.424 MU i.e. total power purchase minus the
EHT sales.
Additional Surcharge = (Approved asset cost as on 01.04.2016/ life
cycle of asset considered)/ Total unit to be wheeled in the
distribution network of CESU excluding the EHT sales =
(1619.15Cr/20year)/8221.42MU = 9.85 Paisa.
The additional surcharge is payable by all the open access consumers in
addition to other charges on the open access consumption.
From current financial year two EHT consumers are migrated to Eastern
Regional Power Grid from the Licensee’s area. The Licensee is yet to be compensated
on loss of EHT sales. The Licensee need to recover minimum fixed cost from all
Open Access Customers whether they avail power from owns CGP or any other
Utility. Hence additional surcharge of 9.85 paisa per unit may be allowed to be levied
on all open access customers.
4: Scheduling & System operation charges:
Intra state ABT regulations are applicable to all HT & EHT consumers
availing supply with load of 5 MVA and above. Such consumers when apply for
long or short term open access are liable to pay scheduling and operation charges
for effecting each change in scheduling.
CESU proposes that a sum of Rs.2000/ day or part thereof may be paid by
all open access customers.
5: Reactive Energy charges:
Reactive energy charges when applicable will be levied on all Open Access
consumers.
6: Miscellaneous charges:
Meter rent & customer charges applicable to EHT & HT consumers shall be
borne by all Open Access consumers.
Page - 9