Title : MEDIUM VOLTAGE CABLES

Type : FIELD TEST REPORT

Contract :

Contract specific number Site

by
on
C by Andus M Pasti Malau
on 12.10.2010 12.10.2010
B by Jefferson M Pasti Malau Dian I 4
on 14.01.2008 14.01.2008 14.01.2008
A by Sudung Malau Sudung Malau GONCALVES ORIGINAL ISSUE 4
on 05.09.2001 05.09.2001 05.09.2001
Ind Rev Prepared Checked Approved Modification Sheets

PT. ALSTOM GRID


FA - SECTION

J K T T I 1 0 H B B C 0 0 0 0
Place of issue File number

This document is the property of Alstom Grid - SBU ITS and cannot be used, reproduced or transmitted to thirds without prior written permission.
PT. ALSTOM GRID MEDIUM VOLTAGE Ref.
FA - SECTION CABLES Chapt.
Sheet : 2
A T : I.08.H.BBC.0000 Rev. C

SUMMARY SHEET REVISION

1 LIST OF TEST EQUIPMENT USED 2 C

2 CHARACTERISTICS 3 C

3 TEST CONDITIONS 3 C

4 PRELIMINARY CHECKS 3 C

5 INSULATION RESISTANCE TEST 4 C

6 DIELECTRIC TEST 4 C

1 LIST OF TEST EQUIPMENT USED

Test corresponding to paragr.


Identification
Designation
Number
1 2 3 4 …… ……

H …………… …………………………………………………… …… …… …… …… …… ……

H …………… …………………………………………………… …… …… …… …… …… ……

H …………… …………………………………………………… …… …… …… …… …… ……

H …………… …………………………………………………… …… …… …… …… …… ……

H …………… …………………………………………………… …… …… …… …… …… ……

H …………… …………………………………………………… …… …… …… …… …… ……

H …………… …………………………………………………… …… …… …… …… …… ……

This document is the property of Alstom Grid - SBU ITS and cannot be used, reproduced or transmitted to thirds without prior written permission.
PT. ALSTOM GRID MEDIUM VOLTAGE Ref.
FA - SECTION CABLES Chapt.

Sheet : 3
A T : I.08.H.BBC.0000 Rev. C

2 CHARACTERISTICS

- Manufacturer : - Cell No :

- Type : - Rated Voltage : KV

- Length : - Service Voltage : KV

3 TEST CONDITIONS

- Temperature : o
C - Humidity : %

4 PRELIMINARY CHECKS

- Equipment conformity with schematic diagram

- Earthing circuit & connections

- Marking, continuity, order of phases

- Cleanliness & tightening of Bus Bar connections

- Isolators conditions

This document is the property of Alstom Grid - SBU ITS and cannot be used, reproduced or transmitted to thirds without prior written permission.
PT. ALSTOM GRID MEDIUM VOLTAGE Ref.
FA - SECTION CABLES Chapt.

Sheet : 4

A T : I.08.H.BBC.0000 Rev. C

5 INSULATION RESISTANCE TEST

Circuit Test voltage Duration Requirement Test result

Phase R

Phase S

Phase T

6 DIELECTRIC TEST

Cable rated voltage: : KV

Type of test : DC AC

Test voltage : KV

Test duration : minute

TIME 1 mn 5 mn 10 mn 15 mn - No breakdown of insulation


shall occur

PHASE Leakage current (mA)


- There shall be no disruptive
discharge during the test
R

Tested by : Witnessed by : Date :