Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
80 % Uptime
60 % 3’part down time (downhole)
WoW + W logistic
40 %
Planned maintenance
20 % Rig Equipment down time
0%
Rig 1 Rig 2 Rig 3 Rig 4 Rig 5 Rig 6 Rig 7 Rig 8 Rig 9
ARCTIC DESIGN designed for -25°C minimum design tem- • Working environment, including noise
perature (standby mode). exposure and sheltering of working
The design temperatures in the Barents
areas.
Sea area vary, with the lowest tempera- • Redundant Automatic Truster Assist
tures northeast with the Russian border. (ATA) positioning system in order to • Late introduction of arctic design
The water depths vary from 150 m to 400 fulfil Statoil’s requirements for shallow issues.
m, with some areas with low satellite water depths and low satellite coverage
coverage. in the Barents Sea area. Further, it is considered important with
an early establishment of an extensive
In order to fulfil Statoil’s ambitions with and realistic operational QA/QC- and
regards to arctic operation, focus should STATOIL NEW MODUS commissioning program including the
be on the following design factors: EXPERIENCE following:
• The rig’s exposed areas, such as the Statoil is generally concerned for some • Selection of a construction yard with
derrick, drill floor, muster stations, of the new rig construction projects with good QA/QC systems, dry dock capacity
pipe and riser deck, etc, should be fully regards to lack of operational personnel and top side drilling equipment assembly
sheltered or enclosed in order to ful- involved in the early project planning experience.
fil Statoil’s ambitions for the working phase. Focus on early involvement of
environment while operating under cold operational personnel in the project can • Change management to focus on
conditions. reduce the number of variation orders weight control and associated prioritiz-
at a later stage in the project phase. The ing of VDL capacity against motion char-
• All critical equipment, escape ways following operational issues should be acteristic).
and muster stations should be heat addressed at an early stage of a new rig
traced. building project: • Commissioning of electrical systems,
PLS, IT, ESD and fire and gas detection
• Utility systems should be placed • Safe and efficient logistic design (inter- systems.
in enclosed heated voids under deck nal on the rig and external to supply
in order to avoid environmental and boats). • Integrated sea trail testing of complex
mechanical damage. mooring ATA and DP3 positioning sys-
• Third-party equipment such as logging tems, all motion compensating systems.
• Safety systems such as well control unit, cement unit, test plant, workover/
equipment, positioning systems, fire- This article is based on a presentation made
completion equipment. at IADC World Drilling 2006, 21-22 June,
fighting and escape systems should be Prague, Czech Republic.
Diana/Hoover platform rig G10,000 drillship Pride Africa DSS20 semi Maersk Explorer CJ70 jack-up Maersk Innovator Ensco 7500 semi-submersible
GustoMSC
FORESIGHT IN OFFSHORE www.GustoMSC.com