Sei sulla pagina 1di 3

DRILLING RIGS

Rig design philosophy key for harsh-environment


drilling in Barents Sea, Haltenbanken area
By Geir Ove Eikill, Bjorn Cristoffer Oftedal, a substantial amount of advanced and • Large deck area and storage capaci-
Statoil ASA challenging production drilling, comple- ties to ensure efficient logistics.
tion and workover operations on the
HIGHER RIG RATES have led Haltenbanken and in the Barents Sea • High air gap in operation condition
to an impressive newbuild program of area. Statoil hopes that some of the new and in survival.
semisubmersible drilling units. Will multi-purpose 6th-generation semisub- • Arctic design.
these new rigs be built for operational
safety and efficiency in a harsh envi- • Environmental care.
ronment? Year-around offshore drilling Statoil is generally A medium-capacity drilling facility, 4,500
operations in the north of Norway on the
Haltenbanken and the Barents Sea area
concerned for some of the to 5,000 tonnes variable deck load, with
a large deck area, should be sufficient
is a challenge against forces of nature new rig construction proj- because the majority of offshore drilling
in an extremely harsh environment with
the following special environmental
ects with regards to lack operations north on the Norwegian con-
tinental shelf will be performed in water
characteristics: of operational personnel
depths varying from 150 m to 450 m.
Barents Sea involved in the early project
Drilling-related expenditure is a main
• Polar low pressures. planning phase. contributor to overall field development
costs in a harsh environment. Indirect
• Low temperatures. operational drilling cost is affected by
• Ice and snow. concept design factors such as:
mersible drilling units will be built with
• Drifting ice. the objective to improve the unit perfor- • Waiting on weather.
mance considerably and fully meet the
Haltenbanken challenging present and future opera- • Back-loading and requirements for
tions and area conditions. temporary boat storage.
• Atlantic Ocean hurricanes.
• Weather window required for position-
• Strong current. RIG DESIGN FACTORS ing the rig over the well location.
Rig design philosophy is key for opera- • Uptime/reliability of equipment/rig in
• Long wave periods.
tional safety while performing opera- cold weather conditions.
A rig design philosophy with the main tions in a harsh environment on the
focus on the required operations is key Haltenbanken and the Barents Sea area. • Working environment.
to success in these waters.
The following rig design factors should • Environmental care.
The majority of the 4th-generation rigs be established as basis for a rig design
operating on the Norwegian continental made for these conditions: MOTION CHARACTERISTICS
shelf today were built in the ’80s and
• Rig motion characteristic. The wave conditions experienced on
hence designed for exploration drilling
Haltenbanken are special. Very long
operations. Today Statoil is performing • Natural heave period.

KPI operation factors


100 %

80 % Uptime
60 % 3’part down time (downhole)
WoW + W logistic
40 %
Planned maintenance
20 % Rig Equipment down time

0%
Rig 1 Rig 2 Rig 3 Rig 4 Rig 5 Rig 6 Rig 7 Rig 8 Rig 9

Rigs on contract for Statoil 2005


Figure 1 shows that statistical uptime for the rigs on contract for Statoil in 2005 was improved along with improved rig motion
characteristic and good logistic facilities.

84 March/April 2007 D R I L L I N G CONTRACTOR


DRILLING RIGS

optimal motion characteristics. The


optimization relative to variable deck
load capacity, equipment capacities, unit
geometry and motion characteristics
have to be considered from the unit con-
cept phase.

Additional cost issues are:

• Additional column height to fulfil air


gap requirements.

• Additional spacing between columns in


order to gain restoring stability moment.

• Breadth and depth under the water


table of the pontoons in order to get
damping effect to fulfil natural heave
period and motion characteristic
requirements.

Noroff Instituttet Stavanger


ENVIRONMENTAL CARE
This illustration shows the seamless product line for drilling waste minimization and the
The Barents Sea area in particular is
safe, efficient transport of drill cuttings onto the deck of a service vessel. The environ-
an important breeding area for fish vul-
ment must be considered in rig design for the Barents Sea area in particular. nerable to potential pollution from any
drilling operation. Environmental issues
period waves (over 21-sec period and 6 2005 was improved along with improved
in the Barents Sea area has gained an
-7 m high) are experienced at a yearly rig motion characteristic and good logis-
increasingly political focus in Norway,
basis during periods with relatively tic facilities.
requiring drilling operations to go hand
moderate weather conditions when the
Other factors affecting the rig’s KPI per- in hand with the fishing industry.
rigs can be in full operation. The special
conditions are a result of past distant formance typically are:
In order to fulfil Statoil’s ambitions with
Atlantic storms adding to the local condi- • Location and season of the year. regards to environmental care, focus
tions. This type of wave occurs as one should be on the following design factors
among normal period waves, and drilling • Type of operation and third-party for the new rig projects:
units with lower natural heave response downhole equipment used.
period will suddenly heave 6-7 m. • 2nd barrier philosophy with dedicated
slope tanks and drain water cleaning
Safety: Natural heave period exceeding 6TH-GEN RIG CONCERNS system designed to clean emulsified oil
21 seconds is an important design crite- There is a possible conflict between in water, in order to minimize transport
ria for a drilling rig performing efficient increased drilling facility capacity for of slope to shore. As a minimum, the fol-
conventional completion or workover ultra-deepwater and the rigs motion lowing drain/tanks should be included:
operations in the Haltenbanken area, in characteristic required for comple-
order to avoid a possible compensator tion and workover operations in the 1. Drain from non-hazardous clean
stroke out, or a surface flow tree collid- Haltenbanken area. There is a consider- areas.
ing into the drill floor when the comple- able cost impact for the substructure to
2. Drain from non-hazardous polluted
tion riser is attached to the well head. maintain the rig’s motion characteristic
areas.
required for the Haltenbanken area as
Cost: The magnitude of nonproductive the top side drilling capacities are scaled 3. Drain from hazardous polluted
time is affected by the rig’s motion char- up to meet the requirement for ultra- areas.
acteristic while operating in relatively deep drilling.
moderate sea state conditions. • Low NOX-emission from diesel genera-
The hull structure made for a typical tors.
Efficient rigs with low wait-on-weather ultra-deep drilling rig planned to be
score is usually achieved with rigs hav- operating in relatively moderate sea • Transport of all water-based cuttings
ing good rigs motion characteristic in conditions will typically focus on gain- to shore after installing the BOP.
low amplitude sea state conditions. ing high variable deck load (VDL) at the
• Primary cutting transport system
An efficient rig for a harsh environment lowest possible cost. The most cost-effi-
should be based on allocate tanks, pneu-
is usually achieved by large displace- cient way of increased VDL is usually
matic cuttings transport, and offloading
ment, large spacing between columns achieved by increasing the column diam-
system for cuttings treatment equipment
having relatively small total water plan eter or to add blisters on the column in
and logistic to boat.
area, and wide pontoons with the top of order to gain higher stability restoring
the pontoons positioned relatively deep moment, and hence increase the variable • Secondary cutting transport sys-
under the water table. deck load capacity of the rig. tem should be based on pneumatic or
vacuum cuttings transport and logistic
Figure 1 shows that statistical uptime A unit designed for both the ultra-deep
to boat by using skips handled by the rig
for the rigs on contract for Statoil in and harsh environment drilling needs
cranes.
to have both the large capacities and

86 March/April 2007 D R I L L I N G CONTRACTOR


DRILLING RIGS

ARCTIC DESIGN designed for -25°C minimum design tem- • Working environment, including noise
perature (standby mode). exposure and sheltering of working
The design temperatures in the Barents
areas.
Sea area vary, with the lowest tempera- • Redundant Automatic Truster Assist
tures northeast with the Russian border. (ATA) positioning system in order to • Late introduction of arctic design
The water depths vary from 150 m to 400 fulfil Statoil’s requirements for shallow issues.
m, with some areas with low satellite water depths and low satellite coverage
coverage. in the Barents Sea area. Further, it is considered important with
an early establishment of an extensive
In order to fulfil Statoil’s ambitions with and realistic operational QA/QC- and
regards to arctic operation, focus should STATOIL NEW MODUS commissioning program including the
be on the following design factors: EXPERIENCE following:
• The rig’s exposed areas, such as the Statoil is generally concerned for some • Selection of a construction yard with
derrick, drill floor, muster stations, of the new rig construction projects with good QA/QC systems, dry dock capacity
pipe and riser deck, etc, should be fully regards to lack of operational personnel and top side drilling equipment assembly
sheltered or enclosed in order to ful- involved in the early project planning experience.
fil Statoil’s ambitions for the working phase. Focus on early involvement of
environment while operating under cold operational personnel in the project can • Change management to focus on
conditions. reduce the number of variation orders weight control and associated prioritiz-
at a later stage in the project phase. The ing of VDL capacity against motion char-
• All critical equipment, escape ways following operational issues should be acteristic).
and muster stations should be heat addressed at an early stage of a new rig
traced. building project: • Commissioning of electrical systems,
PLS, IT, ESD and fire and gas detection
• Utility systems should be placed • Safe and efficient logistic design (inter- systems.
in enclosed heated voids under deck nal on the rig and external to supply
in order to avoid environmental and boats). • Integrated sea trail testing of complex
mechanical damage. mooring ATA and DP3 positioning sys-
• Third-party equipment such as logging tems, all motion compensating systems.
• Safety systems such as well control unit, cement unit, test plant, workover/
equipment, positioning systems, fire- This article is based on a presentation made
completion equipment. at IADC World Drilling 2006, 21-22 June,
fighting and escape systems should be Prague, Czech Republic.

Diana/Hoover platform rig G10,000 drillship Pride Africa DSS20 semi Maersk Explorer CJ70 jack-up Maersk Innovator Ensco 7500 semi-submersible

GustoMSC FOR BOTH NEW BUILD AND CONVERSION/UPGRADE OF MODU’s.


GustoMSC provides complete, innovative, A total of 55 MODU’s have been built to our
field-proven and cost-effective designs: designs (7 units are arctic class). A total of
• jack-ups (CJ40, CJ46, CJ50, CJ54, CJ62, CJ70) 18 MODU’s are currently under construction.
• semi-submersibles (DSS20, DSS40, DSS50, DSS60) The MODU designs are complemented with our
• drillships (Pelican, G10,000, P10,000 and PRD12,000 engineered products supply, such as:
class) • rack & pinion and positive engagement jacking systems
• tender(-assist) drilling barges and semi-submersibles • X-Y cantilever systems
• platform drilling rigs • rack fixation systems
• thruster retrieval systems

GustoMSC
FORESIGHT IN OFFSHORE www.GustoMSC.com

D R I L L I N G CONTRACTOR March/April 2007 87

Potrebbero piacerti anche