Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
www.elsevier.com/locate/jcsr
Abstract
In steel–concrete composite beams, the longitudinal shear force is transferred across the steel flange/concrete slab interface by the mechanical
action of the shear connectors. The ability of the shear connectors to transfer these longitudinal shear forces depends on their strength, and also
on the resistance of the concrete slab against longitudinal cracking induced by the high concentration of shear force. Most of the research in
composite construction has concentrated on the more traditional reinforced concrete and metal deck construction, and little information is given
on shear capacity of the headed studs in precast hollowcore slabs. In this paper, a standard push test procedure for use with composite beams
with precast hollowcore slabs is proposed. Seven exploratory push tests were carried out on headed studs in solid RC slabs to validate the testing
procedures, and the results showed that the new test is compatible with the results specified in the codes of practice for solid RC slabs. Once a
standard procedure is established, 72 full-scale push tests on headed studs in hollowcore slabs were performed to determine the capacities of the
headed stud connectors in precast hollowcore slabs and the results of the experimental study are analysed and findings on the effect of all the
parameters on connectors’ strength and ductility are presented. Newly proposed design equations for calculating the shear connectors’ capacity
for this form of composite construction are also be given.
c 2006 Elsevier Ltd. All rights reserved.
Keywords: Precast; Steel; Hollowcore; Composite; Shear connection; Push test; Headed stud
1. Introduction
mechanical action of the shear connectors. The ability of the 460 mm long × 150 mm deep and reinforced with 10 mm mild
shear connector to transfer longitudinal shear forces therefore steel reinforcement. The specimen is bedded down onto the
depends on the strength of the shear connector, and also on platen of the compression machine. A vertical compressive load
the resistance of the concrete slab against longitudinal cracking is applied to the steel beam, and the slip between the steel beam
induced by the high concentration of shear force. Previous and the slabs are measured against the load. The code stated
research by Lam et al. [3] has attempted to determine the that the rate of loading should be uniform with the failure load
strength of shear connections in composite construction with is reached in not less than 10 minutes. With the introduction
precast hollowcore slabs, but no standard procedure for the of SI units, a metric version of the test was detailed in BS5400
testing has been developed. The objective of this paper is to [5] and later referred to in BS5950 [6]. Work by Johnson and
review the existing standard push test arrangement, and to Yuan [7] on shear connectors in troughs of profiled sheeting
propose a new push test procedure for use in composite beams suggested that the existing rules for shear connectors in troughs
with proprietary precast hollowcore slabs. of profiled sheeting were of limited scope and low accuracy,
especially for studs placed off-centre in the trough. The results
2. Standard push test of such push tests were also found to be widely scattered due
to differences in test specimens, methods of casting and testing
The push test was first devised in Switzerland in the 1930s
to determine the load transfer capacity of shear connectors. procedures.
Although the push test cannot exactly replicate the actual In Eurocode 4 [8], the standard push test was once again
conditions and the behaviour of the shear connectors in the modified from BS5400. Vertical push test specimens with
composite beam, it does enable the behaviour of different larger slabs, heavier reinforcement, wider steel sections and
types and sizes of shear connectors to be compared provided a connectors placed at two levels were introduced to allow
standardized test is used; therefore it is important that a standard for redistribution of forces. Fig. 3 shows the proposed push
test and procedure is adhered to. The two most important pieces test specimen in Eurocode 4. The changes were proposed
of information relevant to composite beam design are: (1) the because the specimen specified in BS5400 was criticized for its
ability of the shear connectors to transfer longitudinal shear very small slabs which were prone to splitting longitudinally,
force, and (2) the amount of slip at the steel–concrete interface. with light and poorly anchored mild steel reinforcement and
Most of the load–slip characteristics of the shear connectors with only one level of connectors, which in effect prevented
have been obtained from push tests. redistribution of load. Push tests with metal deck floorings have
In 1965, a standard push test was first published in CP117 previous been reviewed by Johnson and Yuan [7], and push tests
[4] in the UK. The test consisted of a short length of steel with solid slabs have recently been reviewed by Ernst et al. [9].
beam connected to two concrete slabs by means of the shear The standard push test currently specified in Eurocode
connectors as shown in Fig. 2. The slabs are 300 mm wide × 4 is not suitable for use in precast hollowcore composite
1162 D. Lam / Journal of Constructional Steel Research 63 (2007) 1160–1174
construction for the following reasons: 3. New push test for hollowcore slabs
1. The dimensions specified for the slab are too narrow and too A new horizontal push test arrangement is proposed as
short for precast composite construction. shown in Fig. 4. The test specimens each consisted of four
2. The reinforcement specified in the standard test is not 600 mm wide × 800 mm long prestressed hollowcore units
suitable since only transverse reinforcement is used for connected to a 254 × 254 × 73 UC or HE206B with a single
the composite construction with precast hollowcore slabs. row of 6 pre-welded headed studs at 150 mm distances. The first
Unlike the solid RC slab and metal decking floor, no stud is located 200 mm from the end of the slabs as suggested
longitudinal reinforcement is used in this type of composite in the Eurocode 4. Cores 500 mm long were left open to allow
construction. for the placement of the transverse reinforcement. A 600 mm
3. For the current standard push-test, the steel section should slab width was chosen instead of the common 1200 mm width
be cut longitudinally along its length and two slabs should so that the effect of the transverse joint could be observed. The
be cast simultaneously before re-welding the steel section to position of the hollowcore slabs relative to the position of the
form the push off specimen. This method is unsuitable for studs is irrelevant, as their positions will be random in real life.
precast construction because of the need to avoid handling The in-situ concrete infill was cast horizontally and tested when
the assembly after the construction of the precast/in-situ the required design strength was reached. A horizontal load was
joints. applied to the specimen by two hydraulic jacks bracketed in
4. Recent work [10] has also suggested that the measured parallel onto the steel beam, and working against the slab via
connector strength determined from the typical push test spreader beams.
specimen can be strongly influenced by frictional forces Longitudinal slip is measured by LVDTs at the end of the
developing between the base of the test slabs and the slabs until the load has dropped to 20% below the maximum
reaction floor, in turn artificially increasing the measured load reached. This enables the load and slip capacity to
be determined. Because the slab is cast and loaded in the
shear strength.
horizontal position as it would be in practice, the construction
As the current standard push test is not suitable for difficulties using this standard push test for hollowcore slabs
composite precast hollowcore construction, a new standardised (HCS) and the inherent problems in the standard vertical push
push test is badly needed to fill the gap in the scope of BS5950 test where the weaker concrete slab fails first are eliminated.
and Eurocode 4. The test procedures for the horizontal push test for composite
D. Lam / Journal of Constructional Steel Research 63 (2007) 1160–1174 1163
beams with HCS are as follows: 9. If all three test results are within 10% of the mean result,
1. A minimum of three specimens are required for each test. then the lowest result should be used. If the test results are
Each push test specimen consists of four 600 mm wide × outside 10% of the mean result, the tests should be repeated.
800 mm long prestressed hollow core units. Fig. 5 shows a
specimen before casting. 4. Validation of the horizontal push test
2. The steel beams are wire brushed to remove loose scale and
rust before the hollowcore units are placed. For the purposes of consistency, 7 sets of horizontal push
3. Transverse reinforcement is placed in each opened core. tests with 19 and 22 mm diameter headed shear connectors in
4. The in-situ concrete infill is cast and cured horizontally in solid in-situ concrete slabs were carried out, and the results
the laboratory. were compared with the current codes of practice. This was
5. All three specimens should normally be cast and tested on to ensure that the results and procedures are consistent and
the same day when the required in-situ concrete strength is representative so that the test arrangement and procedures could
reached. be used to determine the shear and slip capacity of headed
6. Load is applied at 40 kN increments up to 60% of the stud in composite HCS. The test arrangement for the solid slab
expected failure load and reduced to 10 kN increments specimen is shown in Fig. 6 and the load–slip curve for the
thereafter. headed shear connectors in the solid slab is given in Fig. 7.
7. The loading is cycled 25 times between 5% and 40% of the The results compared well with the resistance strength specified
expected failure load. in BS5950, Eurocode 4 and the equation for static strength
8. The characteristic shear capacity of the headed stud prediction by Oehlers and Johnson [11]. Table 1 shows the test
connectors is the maximum load sustained by the studs. The results and the predicted resistance of the shear connector. It
slip capacity at which the maximum load is obtained is also showed that results from the horizontal push tests are consistent
recorded. and compatible with the predicted results, and therefore can be
1164 D. Lam / Journal of Constructional Steel Research 63 (2007) 1160–1174
Table 1
Headed shear stud in solid concrete slabs
Test Concrete strength Stud dia. Max. load per stud Slip at max. load BS5950 EC4a Oehlers
ref. (N/mm2 ) (mm) (kN) (mm) (kN) (kN) equ.b (kN)
RC1 15.3 19 71.7 3.7 95 60.4 79.3
RC2 29.1 19 102.6 6.2 100 88.9 112.9
RC3 28.5 19 101.6 6.9 100 87.8 111.7
RC4 28.0 19 100.1 6.3 100 86.8 110.6
RC5 50.1 19 133.2 9.0 109 113.5 152.3
RC6 24.0 22 120.8 5.2 119 106 136.2
RC7 44.6 22 124.3 6.2 139 152.1 191.5
a P 2 √ f E or P πd 2
R D = 0.29αd ck c R D = 0.8 f u 4 .
b P = 5.0A f (E /E )0.40 ( f / f )0.35 , Table 5, BS5950 [6].
p u c s cu u
Table 2
Push test results
Test In-situ Rebar @ Studs φ × l HCS’s End profile Gap Max. load Slip at Load at Reduction
ref. concrete 300 mm c/c (mm) depth. (mm) per stud max. 6 mm slip (%)
strength and length (mm) (kN) load (kN)
(MPa) (mm) (mm)
PT1 23.38 T10/1000 19 × 100 150 Square end 65 63.4 1.43 54 14.8
PT2 23.38 T10/1000 19 × 100 150 Square end 65 57.8 0.78 50 13.5
PT3 34.20 T10/1000 19 × 100 150 Square end 80 73.5 2.38 68 7.5
PT4 34.20 T10/1000 19 × 100 150 Square end 100 82.1 2.43 76 7.4
PT5 52.27 T10/1000 19 × 100 150 Square end 80 91.7 2.1 83 9.5
PT6 38.80 T10/1000 19 × 100 150 Square end 120 83.2 1.75 73 12.3
PT7 38.80 T10/1000 19 × 100 150 Square end 140 82.1 2.41 76 7.4
PT8 53.30 T10/1000 19 × 100 150 Square end 120 89.1 1.67 77 13.6
PT9 26.15 T10/1000 19 × 100 150 Square end 80 84.8 3.34 83 2.1
PT10 40.17 2T10/1000 19 × 100 150 Square end 80 89 3.01 84 5.6
PT11 29.02 2T12/1000 19 × 100 200 Square end 80 101 3.98 99 2.0
PT12 40.33 T12/1000 19 × 100 150 Square end 80 81.3 2.27 76 6.5
PT13 26.15 T12/1000 19 × 100 150 Square end 80 112.8 4.13 111 1.6
PT14 24.87 T12/1000 19 × 100 150 Square end 80 85.3 4.6 83 2.7
PT15 19.91 T12/1000 19 × 100 300 Square end 100 90.9 2.22 83 8.7
PT16 26.41 T12/1000 19 × 100 300 Square end 100 99.7 3.4 91 8.7
PT17 46.60 T12/1000 19 × 100 300 Square end 100 113.3 2.66 90 20.6
PT18 24.71 T16/1000 19 × 100 200 Square end 80 99.7 5.63 99 0.7
PT19 24.71 T16/1000 19 × 100 200 Square end 80 105.7 8.1 104 1.6
PT20 28.49 T16/1000 19 × 100 200 Square end 60 91.8 3.46 88 4.1
PT21 28.49 T16/1000 19 × 100 200 Square end 100 100 4.74 97 3.0
PT22 28.49 T16/1000 19 × 100 200 Square end 40 87.8 3.96 86 2.1
PT23 23.43 T16/1000 19 × 100 150 Square end 80 114.3 6.75 111 2.9
PT24 23.43 T16/1000 19 × 100 150 Square end 80 95.3 6.27 95 0.3
PT25 23.43 T16/1000 19 × 100 150 Square end 80 101.9 4.26 101 0.9
PT26 26.09 T16/1000 19 × 100 250 Square end 80 105.1 5.76 104 1.0
PT27 26.09 T16/1000 19 × 100 250 Square end 80 97.6 6.16 97 0.6
PT28 42.10 T16/1000 19 × 100 150 Square end 80 127.8 6.06 127 0.6
PT29 42.10 T16/1000 19 × 100 150 Square end 80 128.1 5.58 127 0.9
PT30 51.70 T16/1000 19 × 100 150 Square end 80 112.8 8.48 112 0.7
PT31 26.15 T16/1000 19 × 100 150 Square end 80 117.7 7.84 115 2.3
PT32 26.15 T16/1000 19 × 100 150 Square end 80 114.3 8.72 112 2.0
PT33 35.72 T16/1000 19 × 100 200 Square end 80 110.6 6.81 110 0.5
PT34 44.13 T16/1000 19 × 100 200 Square end 80 130.1 9.2 126 3.2
PT35 26.15 T16/1000 19 × 100 150 Square end 80 82.5 5.3 82 0.6
PT36 29.17 T16/1000 19 × 125 200 Square end 80 102.7 4.71 102 0.7
PT37 29.17 T16/1000 19 × 125 200 Square end 80 102.7 4.71 102 0.7
PT38 29.17 T16/1000 19 × 125 150 Square end 80 82.6 2.91 78 5.6
PT39 26.15 T16/1000 19 × 125 150 Square end 80 89.2 3.67 86 3.6
PT40 25.09 T16/1000 19 × 125 250 Square end 80 86.5 5.7 85 1.7
PT41 25.09 T16/1000 19 × 125 250 Square end 80 97.4 2.77 85 12.7
PT42 24.44 T16/1000 22 × 100 150 Square end 80 117.5 4.61 116 1.3
PT43 24.44 T16/1000 22 × 100 150 Square end 80 114.6 4.64 110 4.0
PT44 24.44 T20/1400 22 × 100 150 Square end 80 114.5 4.08 102 10.9
PT45 26.79 T20/1400 22 × 100 150 Square end 80 116.2 2.7 108 7.1
PT46 26.06 T20/1400 19 × 100 150 Square end 80 108.8 6.37 108 0.7
PT47 26.06 T20/1400 22 × 100 150 Square end 80 131.7 4.31 126 4.3
PT48 26.06 T20/1400 22 × 100 150 Square end 80 129.8 5.15 128 1.4
PT49 26.72 T20/1400 22 × 100 200 Square end 80 121.2 4.62 111 8.4
PT50 28.80 T20/1400 22 × 100 250 Square end 80 131.6 2.64 110 16.4
PT51 28.80 T20/1400 22 × 100 250 Square end 80 125.3 3.95 124 1.0
PT52 27.85 T20/1400 22 × 125 250 Square end 80 118.5 4.26 115 3.0
PT53 27.85 T20/1400 22 × 125 250 Square end 80 128.3 3.49 123 4.1
PT54 27.85 T20/1400 22 × 125 200 Square end 80 124.6 5.09 123 1.3
PT55 24.27 T20/1400 22 × 125 200 Square end 80 117.3 3.95 116 1.1
PT56 26.62 T12/1000 19 × 100 150 Chamfered end 65 69.9 2.05 65 7.0
PT57 26.09 T16/1000 19 × 100 150 Chamfered end 65 93.3 3.54 89 4.6
PT58 26.62 T16/1000 19 × 100 150 Chamfered end 65 81.1 6.69 81 0.1
PT59 39.67 T16/1000 19 × 100 150 Chamfered end 65 118.0 5.35 118 0.0
PT60 24.87 T16/1000 19 × 100 200 Chamfered end 65 92.1 3.2 87 5.5
(continued on next page)
1166 D. Lam / Journal of Constructional Steel Research 63 (2007) 1160–1174
Table 2 (continued)
Test In-situ Rebar @ Studs φ × l HCS’s End profile Gap Max. load Slip at Load at Reduction
ref. concrete 300 mm c/c (mm) depth. (mm) per stud max. 6 mm slip (%)
strength and length (mm) (kN) load (kN)
(MPa) (mm) (mm)
PT61 22.03 T16/1000 19 × 125 200 Chamfered end 65 104.5 6.28 104 0.5
PT62 22.03 T16/1000 19 × 125 200 Chamfered end 65 90.6 4.48 90 0.7
PT63 26.79 T16/1000 22 × 100 150 Chamfered end 65 104.5 4.04 100 4.3
PT64 26.79 T16/1000 22 × 100 150 Chamfered end 65 102.9 4.2 101 1.8
PT65 26.62 T16/1000 22 × 100 150 Chamfered end 65 98.2 5.68 96 2.2
PT66 24.74 T20/1400 19 × 100 250 Chamfered end 65 103.4 8.0 102 1.4
PT67 24.74 T20/1400 19 × 100 250 Chamfered end 65 92.4 3.25 89 3.7
PT68 24.27 T20/1400 22 × 100 250 Chamfered end 65 98.8 5.9 98 0.8
PT69 24.27 T20/1400 22 × 100 250 Chamfered end 65 97.3 2.83 90 7.5
PT70 24.74 T20/1400 22 × 100 200 Chamfered end 65 91.7 4.14 89 2.9
PT71 26.30 T20/1400 22 × 100 200 Chamfered end 65 128.9 5.91 128 0.7
PT72 26.30 T20/1400 22 × 125 200 Chamfered end 65 116.9 3.34 116 0.8
Fig. 7. Load vs. slip curves for push tests with solid RC slabs.
(a) Single reinforcing bar per open core with square HCS.
(b) Dual reinforcing bars per open core with square end HCS. (c) Single reinforcing bar per open core with
chamfered end HCS.
Table 3
Strength of transverse reinforcement
Table 4
Main parameters
Table 6
Effect of in-situ infill gap
Test In-situ concrete Rebar @ 300 mm c/c Slabs thkn. Gap Max. load per Slip at max. load Load at 6 mm Reduction (%)
ref. strength (MPa) and length (mm) (mm) (mm) stud (kN) (mm) slip (kN)
PT1 23.38 T10/1000 150 65 63.4 1.43 54 14.8
PT2 23.38 T10/1000 150 65 57.8 0.78 50 13.5
PT3 34.20 T10/1000 150 80 73.5 2.38 68 7.5
PT4 34.20 T10/1000 150 100 82.1 2.43 76 7.4
PT6 38.80 T10/1000 150 120 83.2 1.75 73 12.3
PT7 38.80 T10/1000 150 140 82.1 2.41 76 7.4
RC2 29.1 T10@200c/c 150 ∞ 102.6 6.2 102.6 0.0
RC3 28.5 T10@200c/c 150 ∞ 101.6 6.9 100 0.01
RC4 28.0 T10@200c/c 150 ∞ 100.1 6.3 100 0.01
PT22 28.49 T16/1000 200 40 87.8 3.96 86 2.1
PT20 28.49 T16/1000 200 60 91.8 3.46 88 4.1
PT18 24.71 T16/1000 200 80 99.7 5.63 99 0.7
PT19 24.71 T16/1000 200 80 105.7 8.1 104 1.6
PT33 35.72 T16/1000 200 80 110.6 6.81 110 0.5
PT21 28.49 T16/1000 200 100 100 4.74 97 3.0
1168 D. Lam / Journal of Constructional Steel Research 63 (2007) 1160–1174
Table 7
Effect of in-situ concrete strength
Test ref. In-situ concrete Rebar @ 300 mm c/c and HCS’s depth End profile Max. load per stud Load at
strength (MPa) length (mm) (mm) (kN) 6 mm slip
(kN)
RC1 15.3 T10@200c/c 150 RC 71.7 70.5
RC4 28.0 T10@200c/c 150 RC 100.1 100
RC3 28.5 T10@200c/c 150 RC 101.6 100
RC2 29.1 T10@200c/c 150 RC 102.6 102.6
RC5 50.1 T10@200c/c 150 RC 133.2 130.3
PT2 23.38 T10/1000 150 Square end 57.8 50
PT3 34.20 T10/1000 150 Square end 73.5 68
PT10 40.17 2T10/1000 150 Square end 89 84
PT5 52.27 T10/1000 150 Square end 91.7 83
PT15 19.91 T12/1000 300 Square end 90.9 83
PT16 26.41 T12/1000 300 Square end 99.7 91
PT17 46.60 T12/1000 300 Square end 113.3 90
PT18 24.71 T16/1000 200 Square end 99.7 99
PT19 24.71 T16/1000 200 Square end 105.7 104
PT36 29.17 T16/1000 200 Square end 102.7 102
PT37 29.17 T16/1000 200 Square end 102.7 102
PT33 35.72 T16/1000 200 Square end 110.6 110
PT34 44.13 T16/1000 200 Square end 130.1 126
PT23 23.43 T16/1000 150 Square end 114.3 111
PT24 23.43 T16/1000 150 Square end 95.3 95
PT25 23.43 T16/1000 150 Square end 101.9 101
PT31 26.15 T16/1000 150 Square end 117.7 115
PT32 26.15 T16/1000 150 Square end 114.3 112
PT28 42.10 T16/1000 150 Square end 127.8 127
PT29 42.10 T16/1000 150 Square end 128.1 127
PT30 51.70 T16/1000 150 Square end 112.8 112
PT58 26.62 T16/1000 150 Chamfered end 81.1 81
PT59 39.67 T16/1000 150 Chamfered end 118.0 118
Table 8
Effect of hollowcore slabs’ thickness
Test ref. Studs φ × l (mm) HCS’s depth (mm) End profile Max. load per stud (kN) Slip at max. load (mm) Load at
6 mm
slip (kN)
PT23 19 × 100 150 Square end 114.3 6.75 111
PT24 19 × 100 150 Square end 95.3 6.27 95
PT25 19 × 100 150 Square end 101.9 4.26 101
PT32 19 × 100 150 Square end 114.3 8.72 112
PT31 19 × 100 150 Square end 117.7 7.84 115
PT18 19 × 100 200 Square end 99.7 5.63 99
PT19 19 × 100 200 Square end 105.7 8.1 104
PT21 19 × 100 200 Square end 100 4.74 97
PT36 19 × 125 200 Square end 102.7 4.71 102
PT37 19 × 125 200 Square end 102.7 4.71 102
PT40 19 × 125 250 Square end 86.5 5.7 85
PT41 19 × 125 250 Square end 97.4 2.77 85
PT27 19 × 100 250 Square end 97.6 6.16 97
PT26 19 × 100 250 Square end 105.1 5.76 104
PT16 19 × 100 300 Square end 99.7 3.4 91
PT44 22 × 100 150 Square end 114.5 4.08 102
PT45 22 × 100 150 Square end 116.2 2.7 108
PT47 22 × 100 150 Square end 131.7 4.31 126
PT48 22 × 100 150 Square end 129.8 5.15 128
PT49 22 × 100 200 Square end 121.2 4.62 111
PT54 22 × 125 200 Square end 124.6 5.09 123
PT55 22 × 125 200 Square end 117.3 3.95 116
PT50 22 × 100 250 Square end 131.6 2.64 110
PT51 22 × 100 250 Square end 125.3 3.95 124
PT52 22 × 125 250 Square end 118.5 4.26 115
PT53 22 × 125 250 Square end 128.3 3.49 123
PT57 19 × 100 150 Chamfered end 93.3 3.54 89
PT58 19 × 100 150 Chamfered end 81.1 6.69 81
PT59 19 × 100 150 Chamfered end 118.0 5.35 118
PT60 19 × 100 200 Chamfered end 92.1 3.2 87
PT61 19 × 125 200 Chamfered end 104.5 6.28 104
PT62 19 × 125 200 Chamfered end 90.6 4.48 90
PT63 22 × 100 150 Chamfered end 104.5 4.04 100
PT64 22 × 100 150 Chamfered end 102.9 4.2 101
PT65 22 × 100 150 Chamfered end 98.2 5.68 96
PT70 22 × 100 200 Chamfered end 91.7 4.14 89
PT71 22 × 100 200 Chamfered end 128.9 5.91 128
PT72 22 × 125 200 Chamfered end 116.9 3.34 116
PT68 22 × 100 250 Chamfered end 98.8 5.9 98
PT69 22 × 100 250 Chamfered end 97.3 2.83 90
core wall collapse. The two main functions of the transverse phenomenon was observed in all the push-off tests when the
reinforcement are: (a) to transfer the shear force from the steel mode of failure was concrete failure or combined stud shearing
beam to the slabs, and (b) to provide confinement against and concrete failure; all specimens with a low reinforcement
concrete splitting. Transverse reinforcement enhances the in- ratio achieved their maximum load with slip less than 4 mm,
plane shear resistance of the composite slab in the same way and a significant reduction in capacity was observed when
that stirrups strengthen a concrete beam in vertical shear. 6 mm of slip was reached. An idealised load–slip relationship
It is also required for control, and limits the longitudinal for shear connectors with high and low reinforcement ratios is
splitting of the slab caused by local forces from individual shown in Fig. 12.
shear connectors. Table 5 shows the summary of our test Resistance against concrete splitting is provided by the
results with the main variable being the amount of transverse tensile strength of the concrete, Fct , and after cracking, by the
reinforcement and all the other variables being kept constant. A tensile strength of the transverse reinforcement, Ft . For the push
dual reinforcing bars arrangement, as shown in Fig. 8, was also test specimens with low reinforcement ratios, i.e. Ft < Fct , the
compared to investigate the effectiveness of this arrangement. shear capacity drops immediately after the concrete is cracked,
From the results shown in Table 5 and Fig. 11, specimens as the transverse reinforcement is immediately yielded.
with a high reinforcement ratio showed a significant increase in Whereas, the specimens with high transverse reinforcement
ductility over specimens with a low reinforcement ratio. This ratios, i.e. Ft > Fct , the shear connectors are able to maintain
1170 D. Lam / Journal of Constructional Steel Research 63 (2007) 1160–1174
Table 9
Effect of hollowcore slabs’ end profile and stud height
Test ref. Studs φ × l (mm) HCS’s depth (mm) End profile Max. load per stud (kN) Load at 6 mm slip (kN)
PT23 19 × 100 150 Square end 114.3 111
PT24 19 × 100 150 Square end 95.3 95
PT25 19 × 100 150 Square end 101.9 101
PT57 19 × 100 150 Chamfered end 93.3 89
PT58 19 × 100 150 Chamfered end 81.1 81
PT18 19 × 100 200 Square end 99.7 99
PT19 19 × 100 200 Square end 105.7 104
PT20 19 × 100 200 Square end 91.8 88
PT21 19 × 100 200 Square end 100 97
PT60 19 × 100 200 Chamfered end 92.1 87
PT61 19 × 125 200 Chamfered end 104.5 104
PT62 19 × 125 200 Chamfered end 90.6 90
PT50 22 × 100 250 Square end 131.6 110
PT51 22 × 100 250 Square end 125.3 124
PT53 22 × 125 250 Square end 128.3 123
PT52 22 × 125 250 Square end 118.5 115
PT68 22 × 100 250 Chamfered end 98.8 98
PT69 22 × 100 250 Chamfered end 97.3 90
PT42 22 × 100 150 Square end 117.5 116
PT43 22 × 100 150 Square end 114.6 110
PT63 22 × 100 150 Chamfered end 104.5 100
PT64 22 × 100 150 Chamfered end 102.9 101
PT65 22 × 100 150 Chamfered end 98.2 96
PT49 22 × 100 200 Square end 121.2 111
PT54 22 × 125 200 Square end 124.6 123
PT55 22 × 125 200 Square end 117.3 116
PT70 22 × 100 200 Chamfered end 91.7 89
PT71 22 × 100 200 Chamfered end 128.9 128
Fig. 11. Load–slip curves for specimens with high and low transverse reinforcement ratios.
the load as redistribution of stresses takes place between the After the slab has split, the load is transferred from the
concrete and transverse reinforcement, with a failure slip of at slab to the stud through the cone of concrete by transverse
least 6 mm. These specimens only failed when the ultimate reinforcement. Failure occurs when either the stud shears
strength of the transverse reinforcement was reached. This off or the transverse reinforcement yields. If the transverse
effect is particularly important when a partial shear connection reinforcement is not yielded immediately after the concrete
design is adopted when the ductility of the shear connectors splitting occurs, the load is transferred through the transverse
becomes an important issue. reinforcement; therefore no sudden drop of load capacity of the
D. Lam / Journal of Constructional Steel Research 63 (2007) 1160–1174 1171
7.5. The effect of hollowcore slabs’ end profile and stud height
8. Design equations
shows the summary of the test results with the main variable π d2
PR D = 0.8 f u (2)
being the hollowcore slab’s thickness, with all the other 4γv
variables being kept constant. The results showed that the effect where
of slab thickness to the capacity of the shear studs was not
significant. For practical purposes, it is recommended to use the f ck is the average cylinder strength of the in-situ and
125 mm long headed studs for the hollowcore slabs thickness precast concrete.
over 300 mm, so that the transverse reinforcement can be placed Ec is the average modulus of elasticity of the in-situ and
below the head of the studs. precast concrete (N/mm2 ).
D. Lam / Journal of Constructional Steel Research 63 (2007) 1160–1174 1173
Fig. 16. Comparison of the test results/predicted shear capacity of the headed studs.
fu is the ultimate tensile strength of the headed stud premature failure of the slabs. The optimum in-situ gap width
(450 N/mm2 ). of 80 mm should be used for square-end hollow core slabs.
γv is the partial safety factor, and is taken as 1.25 at the Transverse reinforcement is the dominant factor affecting both
ultimate limit state. shear capacity and slip ductility. 16 mm diameter high tensile
α is the factor which takes into account the height of stud bars are recommended to be used as transverse reinforcement to
and is given by 0.2(h/d + 1) ≤ 1.0. ensure that a slip ductility of 6 mm minimum is maintained at
β is the factor that takes into account the in-situ infill gap the maximum load. The design equations proposed for ultimate
between the HCS, gi , and is given by 0.5(gi /71+1) ≤ shear capacity compare well with the experimental results, and
1.0 and gi ≥ 30. can be used to estimate the shear capacity of headed shear
ε is the factor that takes into account the transverse connectors in precast hollowcore slabs.
reinforcement, and is given by 0.5(φ/20 + 1) ≤ 1.0,
where φ is the diameter of transverse reinforcement. Acknowledgements
Fig. 16 shows the comparison of the predicted shear capacity
of the headed studs against the push test results, which include The author would like to acknowledge a research grant
both chamfered-end and square-end HCS, and good agreement provided by the Engineering and Physical Sciences Research
is obtained between the two. Hence, the proposed equations can Council, the support provided by Severfield—Revee Structures
be used to predict the shear capacity of headed shear studs in Ltd. in supplying the steel specimens and Bison Concrete
hollowcore slabs. Products Ltd. for supplying the precast hollowcore slabs used
in this study. The author would also like to thank Dr. Ivan
9. Conclusions Nip for his help in carrying out the tests, and the skilled
assistance provided by the technical staff in the School of Civil
A standard push test procedure is developed for use with Engineering at University of Leeds.
composite beams with precast hollowcore slabs to determine
the shear capacity of the headed shear connectors. Push tests References
were first carried out on headed studs in solid RC slabs to
validate the testing procedures to show that the new test is [1] Lam D, Elliott KS, Nethercot DA. Designing composite steel beams with
compatible with the results specified in the current codes precast concrete hollow core slabs. Proceedings of the Institution of Civil
Engineers, Structures and Buildings 2000;140:139–49.
of practice. Once a standard procedure is established, push
[2] Lam D, Elliott KS, Nethercot DA. Experiments on composite steel
tests on headed studs in hollowcore slabs are performed to beams with precast concrete hollow core floor slabs. Proceedings of the
determine the capacities of the headed stud connectors in Institution of Civil Engineers, Structures and Buildings 2000;140:127–38.
precast hollowcore slabs. 72 full-scale push tests were carried [3] Lam D, Elliott KS, Nethercot DA. Push off tests on shear studs with
out, and their load–slip characteristic curves were produced. hollow-cored floor slabs. The Structural Engineer 1998;76(9):167–74.
The results showed that 100 mm long-headed studs with [4] CP117. Part 1: Composite construction in structural steel and concrete.
London: British Standards Institution; 1965.
square-end hollow core slabs performed as well as 125 mm
[5] BS5400. Part 5: Steel, concrete, and composite bridges. London: British
long-headed studs with tapered-end slabs. For the tapered-end Standards Institution; 1979.
slabs, the top of the headed stud should be at least 35 mm [6] BS5950. Part 3.1: Structural use of steelwork in building. London: British
above the chamfered-end of the hollowcore slabs to avoid Standards Institution; 1990.
1174 D. Lam / Journal of Constructional Steel Research 63 (2007) 1160–1174
[7] Johnson RP, Yuan H. Existing rules and new tests for stud shear [11] Oehlers DJ, Johnson RP. The strength of stud shear connec-
connectors in troughs of profiled sheeting. Proceedings of The Institution tions in composite beams. The Structural Engineer 1987;65B(2):
of Civil Engineers, Structures and Buildings 1998;128:244–51. 44–48.
[8] BS EN1994-1-1. Eurocode 4: Design of composite steel and concrete [12] BS4449. Specification for carbon steel bars for the reinforcement of
structures: Part 1.1: General rules and rules for buildings. London: British concrete. London: British Standards Institution; 1997.
Standards Institution; 2004. [13] Johnson RP, Molenstra N. Partial shear connection in composite beams
[9] Ernst S, Bridge RQ, Wheeler A. Strength of headed stud shear connection for buildings. Proceeding of the Institution of Civil Engineers, Part 2 1991;
in composite beams. In: Australian structural engineering conference. 91:679–704.
Newcastle (Australia); 2005. [14] Moy SSJ, Tayler C. The effect of precast concrete planks on shear
[10] Hicks SJ, Couchman G. The shear resistance and ductility requirements connector strength. Journal of Constructional Steel Research 1996;36(3):
of headed studs used with profiled steel sheeting. In: United engineering 201–13.
foundation conference, composite construction in steel and concrete. vol. [15] Menzies JB. CP117 and shear connectors in steel–concrete composite
V; 2004. beam. The Structural Engineer 1971;49(3):137–54.