CG POWER AND INDUSTRIAL SOLUTIONS LIMITED

Standard Delivery Time for Order Booking with immediate effect


We would like to confirm Standard Delivery Lead Times for LT AC Motors as below (Subject to T&C as
mentioned),

MTO
MTS MTS SR Brake
Frames/Weeks Motors &
IE3 IE2 Motors Motor
MTS 8pole
63 – 132 Frame Alu
4 4 6 NA 8
(GD)Motors
63- 132 Frame FLP 6 6 8 NA NA
63- 132 Frame SMOKE 6 6 12 NA NA
63 – 132 Frame CI Motors 4 4 12 12 8
160 – 180 frame NFLP &
8 8 12 16 16
Smoke
160 – 180 frame FLP 12 12 16 16 NA
200-250 frame NFLP 12 12 16 14 16

200-250 frame FLP 12 12 16 NA NA


280 ,315M/L Frame 12 12 16 18 20
355, 400, 450 & 500 Frame 16 16 20 20 NA

MTO – Made to Order (Indent Motors) i.e. Non-Standard motors and / or Motors with Inspection and / or
Motors for which Cat_ref is not available.

MTS – Made to Stock (DDI Motors) i.e. Standard Cat_ref motors without inspection and clear for dispatch.

Terms & Conditions:-


1. Above mentioned SDT is applicable from the date of clearance for execution.
2. For MTO & Inspection Motors – SDT is applicable after receipt of Techno-Commercial Sales Orders
(as per CG Policy) plus Code-1 approval of all documents (Datasheet, GA, Curves etc) including
approved QAP.
3. For Inspection orders – SDT is to be considered as ready for Inspection (RFI) date.
4. In case of orders having combination of frames with One Lot delivery condition, SDT of highest lead
time frame should be considered.
5. For delivery of Ratings not listed above like IE4, UL certified, FLP Brake & FLP IIC, please take
specific confirmation from CG marketing team.
6. Above SDT is not applicable for orders having abnormal quantities and orders having customer
delivery schedule which is accepted by CG separately.
7. Above SDT is not applicable, if the business account is in Credit Lock.

Note :- Above SDT is subject to change without any prior notice.