Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Abstract
In cities located in the subtropical regions, air-cooled chillers are commonly used to cool commercial buildings almost year-round,
which accounts for considerable electricity consumption in the long term. This paper explains how a chiller plant should be designed to
enable the chillers to operate frequently with maximum performance. Four design options with respect to the number and size of chillers
were studied for a chiller plant satisfying the year-round cooling demand of a hotel. For each design option, the annual electricity
consumption of chillers and pumps was assessed using a sophisticated chiller model. The assessment showed that an electricity saving of
10.1% can be achieved by installing a chiller plant with six chillers of three different sizes instead of four equally sized chillers. The results
of this paper will give engineers and researchers a better idea about how to select chillers of different sizes and how chiller part load
performance curves can be used to evaluate improvements in the energy performance of a chiller plant with alternative designs.
r 2006 Elsevier Ltd. All rights reserved.
0360-1323/$ - see front matter r 2006 Elsevier Ltd. All rights reserved.
doi:10.1016/j.buildenv.2006.09.004
ARTICLE IN PRESS
3738 F.W. Yu, K.T. Chan / Building and Environment 42 (2007) 3737–3746
The primary issue of a chiller plant design is to decide the chillers and pumps was assessed for each design option.
number and size of chillers based on the year-round Following that, there is a discussion on how to properly
cooling load demand of a building. For simplicity of stage multiple chillers and how to split the total cooling
operation and maintenance and the ease of installing capacity of a chiller plant into different proportions in order
chillers and pumps, most chiller plants are designed with to select chillers of different sizes.
equally sized chillers [8,10,12,14]. Installing chillers of
unequal size, in fact, is a possible means to enhance the 2. Evaluation of the year-round cooling load demand of a
flexibility of chillers in handling various part loads while hotel
meeting the changing building cooling load [13,24–26].
However, there is limited evidence to support this In the calculation of hourly building cooling loads,
arrangement and the potential electricity savings due to detailed features of an existing hotel in Hong Kong [7] were
this arrangement have not been fully realized. This is compiled into a building description file for the multi-zone
attributable to the lack of applicable data for the building model in TRNSYS [27]. As Table 1 illustrates, the
evaluation of chiller COP at part load and the absence of features include the envelope orientation, construction,
a clear picture of how the building cooling load varies ventilation and air-conditioning requirements, occupancy,
hourly with the outdoor temperature at various times of equipment power density, and operating schedules. The
the year due to the convention of peak load calculation. In hotel is a representative of the trade and has average
addition, very few investigations have been carried out on characteristics in terms of the number of guestrooms, total
the interaction between the chiller load and building- floor area and annual electricity consumption in kWh/unit
cooling load with respect to various chiller plant designs. floor area of the building in m2. It is expected that the hotel
This paper explains how a chiller plant should be designed has representative cooling requirement and energy perfor-
to enable the chillers to operate frequently with maximum mance for a large group of local hotels. The hourly local
performance. It first evaluates the year-round cooling weather data in 1989 were used because 1989 was the test
demand of a hotel by use of the simulation program reference year (TRY). TRY is considered representative of
TRNSYS [27]. Four design options with respect to the the prevailing weather conditions in Hong Kong in terms
number and size of chillers were studied for the hotel’s chiller of comparative energy analysis, which is appropriate for
plant. The schedule of staging chillers for each design option this particular study [28–30]. It should be noted that the
was discussed. This schedule, together with the cooling load cooling loads calculated from TRNSYS are simply the
demand of the hotel, was used to determine how the chiller idealised energy required to maintain indoor temperature
load varied at different building load ratios. Using the chiller set points and the results are not system-specific. In
part load performance curves developed from a sophisticated connection with this, it was assumed that every piece of
chiller model [6], the annual electricity consumption of the air-handling equipment is capable of delivering the cooling
Table 1
General information about the hotel and its HVAC systems
General
Total air-conditioned area (m2) 45540 (87.5% of gross floor area)
Orientation NW/NE/SE/SW
Window to wall ratio NW/SE: 0.6, SW/NE: 0.3
U-values of wall/window/roof (W/m2 1C) 1.9/5.4/0.7
Shading coefficient of glass 0.55
Area Guestrooms Shops and restaurants
Table 2
Frequency distribution of the hourly data of building load ratios for the hotel
Outdoor Building load ratio (building cooling load expressed as a ratio of its peak value) Subtotal
temperature (1C)
0–0.1 0.1–0.2 0.2–0.3 0.3–0.4 0.4–0.5 0.5–0.6 0.6–0.7 0.7–0.8 0.8–0.9 0.9–1
11–13 70 47 0 0 0 0 0 0 0 0 117
13–15 55 199 12 0 0 0 0 0 0 0 266
15–17 148 289 112 2 0 0 0 0 0 0 551
17–19 135 193 316 76 0 0 0 0 0 0 720
19–21 78 229 217 302 121 0 0 0 0 0 947
21–23 9 62 221 199 186 108 6 0 0 0 791
23–25 1 8 88 292 182 285 118 14 0 0 988
25–27 0 0 11 77 250 352 330 101 26 0 1147
27–29 0 0 3 6 78 553 242 412 126 56 1476
29–31 0 0 0 0 13 30 61 528 135 62 829
31–33 0 0 0 0 0 0 2 112 140 0 254
33–35 0 0 0 0 0 0 0 1 4 1 6
Subtotal 496 1027 980 954 830 1328 759 1168 431 119 8092
Table 3
Number and size of chillers and pumps for design options OP1–OP4
3.2. Schedules of staging chillers with design options chiller would be staged when the building cooling load
OP1–OP4 exceeded the total capacity of the staged chillers. Based on
this, the total cooling capacity of operating chillers
Given that air-cooled chillers with constant-speed increases in equal steps and the number of steps
compressors operate normally with maximum COP at full corresponds to the total number of chillers installed. The
load, chiller sequencing was implemented under which all minimum part load ratio of the operating chillers rises with
the chillers operate at the same part load, and no additional the step of their total cooling capacity. According to the
chillers in the chiller arrangement start to operate until principle of chiller sequencing, the minimum chiller part
each of the operating chillers is running at full load. load ratio for a given step of total cooling capacity is
Following this strategy for staging chillers, it is possible to calculated by the total capacity at its previous step over the
investigate how the chiller load changes in response to the total capacity at that step. The maximum part load ratio is
frequency distribution of building cooling loads shown in one when the chillers operate at full load. The minimum
Table 2 and the variations in the overall electricity and maximum part load ratios present the possible change
consumption due to this change. of chiller operating conditions for a given range of building
Tables 4–7 show how the chillers with the four design load ratios.
options were staged to implement chiller sequencing when More steps of total cooling capacity mean that the
the building load ratio reached a certain level. Under chillers are able to operate more frequently at full or near
options OP1 and OP2 with equally sized chillers, one more full load conditions to meet various building cooling loads.
Table 4
Schedule of staging chillers and ranges of chiller part load ratios with design option OP1
Building load ratio Number of operating chillers Total cooling capacity of Step Chiller part load ratio
(BLR) and their capacity (kW) operating chillers (kW)
Minimum Maximum
Table 5
Schedule of staging chillers and ranges of chiller part load ratios with design option OP2
Building load ratio Number of operating chillers Total cooling capacity of Step Chiller part load ratio
(BLR) and their capacity (kW) operating chillers (kW)
Minimum Maximum
Table 6
Schedule of staging chillers and ranges of chiller part load ratios with design option OP3
Building load ratio Number of operating chillers Total cooling capacity of Step Chiller part load ratio
(BLR) and their capacity (kW) operating chillers (kW)
Minimum Maximum
Table 7
Schedule of staging chillers and ranges of chiller part load ratios with design option OP4
Building load Number of operating chillers Total cooling capacity of Step Chiller part load ratio
ratio (BLR) and their capacity (kW) operating chillers (kW)
Minimum Maximum
Options OP3 and OP4 present the opportunity to use phenomena, including the capacity control of constant
unequally sized chillers in the chiller plant in order to allow speed reciprocating compressors and mechanistic relations
the chillers to operate more frequently with maximum COP between chiller components. In simulating the operation of
at full load. With regard to option OP3 where the chiller a chiller of any given size, the compressors and the
plant contains two large and two small chillers, there are condenser satisfy the mass balance of refrigerant and the
eight steps of total cooling capacity. The chillers would energy balance at the evaporator. An algorithm was
operate at a part load ratio of 0.8 or above for building introduced to compute the number of staged condenser
load ratios ranging widely from 0.51 to 1 which accounts fans based on a set point of condensing temperature. The
for about half of the total operating hours. When six model was experimentally verified by an error analysis,
chillers under option OP4 are split into three different which enabled all operating variables to be accurately
capacities, the number of steps of total cooling capacity predicted. Fig. 1 shows the part load performance curves
further increases to 26. Starting from a building load ratio developed from the chiller model. These curves are
of 0.22, the chillers under option OP4 would operate at a generally applicable to describing the steady-state beha-
minimum part load ratio of around 0.9. viour of the COP of air-cooled reciprocating chillers with a
nominal cooling capacity of 568–1450 kW. Using this set of
3.3. Calculation of the annual electricity consumption of curves can give a more accurate estimation of the annual
chillers and pumps chiller electricity consumption when compared with the
simplified chiller performance curve used generally in
The thermodynamic chiller model given in Ref. [6] was commercial software for chiller simulation.
used to compute the annual electricity consumption of Each design option involved a single-loop pumping
chillers for each design option, given the year-round system whereby the chillers and constant-speed pumps
cooling load demand of the hotel and the schedule of operated as pairs in order to deliver the required flow of
staging chillers at various building load ratios. The model chilled water. Given this situation, the electricity consump-
was developed using TRNSYS and able to determine tion of pumps varied step by step, depending on the
accurately how the electrical power of air-cooled chillers number of chillers staged. The overall annual electricity
changes hourly in response to various load and consumption of the chiller plant is the sum of chiller power
ambient conditions. The model considers the real process and pump power for all operating hours.
ARTICLE IN PRESS
3742 F.W. Yu, K.T. Chan / Building and Environment 42 (2007) 3737–3746
4 30°C
ratios
35°C
3
Based on the changes in the chiller loads in response to
the building cooling loads, it is possible to analyse how the
2 chiller COP varies across the entire range of building load
ratios for design options OP1–OP4. As Fig. 2 illustrates,
1 the COP data tend to be gathered together within the same
0.2 0.4 0.6 0.8 1.0
step of total cooling capacity with a given number and size
Chiller part load ratio
of operating chillers. The chiller COP fluctuates signifi-
Fig. 1. Chiller part load performance curves. cantly when the number or size of staged chillers varies.
When more numbers of chillers are staged, each of them
could operate at a higher part load, thereby resulting in less
4. Results fluctuation in their COP. With more numbers of steps of
total cooling capacity, the chiller COP tends to shift up
4.1. Frequency distribution of the hourly data of chiller part with less variation across the building load ratios. The
load ratios average COP rose from 2.91 for OP1, followed by 3.11 for
OP2, 3.12 for OP3 and 3.28 for OP4, with regard to a
Based on the frequency distribution of hourly building situation where the number of steps of total cooling
cooling loads in Table 2 and the relationship between the capacity increased from four for OP1, followed by six for
building load ratio and the possible range of chiller part load OP2, eight for OP3 and 26 for OP4. It is interesting to
ratios given in Tables 4–7, it is possible to analyse how the observe that the average COPs with options OP2–OP4 are
chiller part load ratios vary hourly in different ranges of higher than the nominal COP of 3.1 at full load specified by
outdoor temperatures. Tables 8–11 summarize the frequency chiller manufacturers. This is because the performance of
distribution of chiller part load ratios for design options air-cooled chillers can be improved from the COP of 3.1
OP1–OP4. The minimum part load ratio which the first lead when they operate at higher part loads with reduced
chiller handled depends on the nominal cooling capacity of outdoor temperatures (see Fig. 1).
that chiller and increases from 0.20 for OP1, followed by 0.26
for OP3, 0.29 for OP2 and 0.42 for OP4. Given that different 4.3. Annual electricity consumption of chillers and pumps
options provide different numbers of steps of total cooling
capacity, the chillers can operate more frequently at or near Having identified all hourly COP data and the schedules
full load for a given building load ratio when the number of of staging chillers for the hotel’s cooling load demand, it is
steps of total cooling capacity increases. When the number of possible to calculate how much electricity is consumed by
steps of total cooling capacity rises from 4 for OP1, followed chillers and pumps in the chiller plant with design options
by 6 for OP2, 8 for OP3 and 26 for OP4, the percentage of OP1–OP4. The annual electricity consumption of chillers
total operating hours in which the chillers operated at a part and pumps is normalized by the gross floor area of the
load ratio of 0.9–1 increases from 18.4% for OP1, followed hotel, in kWh/m2. As Table 12 illustrates, the annual
by 29.0% for OP2, 45.7% for OP3 and 78.7% for OP4. electricity consumption of the chillers reduced by 9.5%
Under multiple chiller arrangements, the individual when the number of steps of total cooling capacity
chiller loads are totally different from the building cooling increased from four with OP1 to 26 with OP4.
loads and have their own uniqueness with respect to each When the number of steps of total cooling capacity
chiller plant design. With regard to options OP1–OP4, the increased, the electricity saving of pumps rose along with
chillers could operate near full load at a wide range of that of chillers. Chillers and pumps normally operate as
outdoor temperatures of 11.0–33.7 1C. This operating pairs with regard to the single-loop pumping system for
condition is not covered in the rating condition given in chilled water circulation. Since the chilled water pumps are
the Air-conditioning and Refrigeration Institute (ARI) constant-speed devices and assuming pumping efficiency is
Standard 590 for the performance rating of air-cooled constant for each pump selection, the pumps’ electricity
chillers [32]. The ARI rating condition for part load consumption is constant when they are running—regard-
operation states that chiller part load ratios ranging from less of the chiller load. Therefore, operating the chillers at
0.33 to 1 are linearly related to outdoor temperatures or near full load helps minimizes the impact of the
ranging from 12.5 to 35 1C. The diverse combination of pumping energy. Fig. 3 shows how the hourly pump power
chiller loads and outdoor temperatures reported here varied across the building load ratios for design options
suggests that it is inaccurate to calculate the COP of OP1–OP4. The potential of saving pump power is high
ARTICLE IN PRESS
F.W. Yu, K.T. Chan / Building and Environment 42 (2007) 3737–3746 3743
Table 8
Frequency distribution of the hourly data of chiller part load ratios for design option OP1
11–13 0 0 6 67 40 3 1 0 0 0 117
13–15 0 2 34 25 88 48 39 21 5 4 266
15–17 0 8 116 25 83 117 74 51 38 39 551
17–19 0 3 74 62 64 194 101 65 82 75 720
19–21 0 1 37 45 74 209 207 200 123 51 947
21–23 0 0 3 7 5 167 153 192 130 134 791
23–25 0 0 0 1 1 69 235 352 206 124 988
25–27 0 0 0 0 0 7 122 351 381 286 1147
27–29 0 0 0 0 0 1 133 571 314 457 1476
29–31 0 0 0 0 0 0 1 432 107 289 829
31–33 0 0 0 0 0 0 0 133 90 31 254
33–35 0 0 0 0 0 0 0 1 5 0 6
Subtotal 0 14 270 232 355 815 1066 2369 1481 1490 8092
Table 9
Frequency distribution of the hourly data of chiller part load ratios for design option OP2
11–13 0 0 0 0 25 48 34 8 1 1 117
13–15 0 0 3 32 1 52 62 56 27 33 266
15–17 0 0 8 92 39 88 88 113 76 47 551
17–19 0 0 3 44 48 117 157 150 124 77 720
19–21 0 0 1 26 22 84 156 293 221 144 947
21–23 0 0 0 1 7 43 70 241 263 166 791
23–25 0 0 0 0 0 9 74 259 355 291 988
25–27 0 0 0 0 0 0 21 159 512 455 1147
27–29 0 0 0 0 0 0 3 176 893 404 1476
29–31 0 0 0 0 0 0 0 3 310 516 829
31–33 0 0 0 0 0 0 0 0 48 206 254
33–35 0 0 0 0 0 0 0 0 2 4 6
Subtotal 0 0 15 195 142 441 665 1458 2832 2344 8092
Table 10
Frequency distribution of the hourly data of chiller part load ratios for design option OP3
11–13 0 0 0 8 55 43 9 1 1 0 117
13–15 0 0 27 9 11 61 66 39 35 18 266
15–17 0 0 54 74 20 29 119 116 88 51 551
17–19 0 0 22 60 49 54 84 136 184 131 720
19–21 0 0 10 31 29 63 73 145 353 243 947
21–23 0 0 0 4 5 3 29 96 343 311 791
23–25 0 0 0 0 1 1 5 71 436 474 988
25–27 0 0 0 0 0 0 2 16 437 692 1147
27–29 0 0 0 0 0 0 0 4 492 980 1476
29–31 0 0 0 0 0 0 0 0 151 678 829
31–33 0 0 0 0 0 0 0 0 134 120 254
33–35 0 0 0 0 0 0 0 0 4 2 6
Subtotal 0 0 113 186 170 254 387 624 2658 3700 8092
ARTICLE IN PRESS
3744 F.W. Yu, K.T. Chan / Building and Environment 42 (2007) 3737–3746
Table 11
Frequency distribution of the hourly data of chiller part load ratios for design option OP4
11–13 0 0 0 0 0 1 17 45 37 17 117
13–15 0 0 0 0 28 7 1 60 80 90 266
15–17 0 0 0 0 64 54 19 101 151 162 551
17–19 0 0 0 0 24 34 33 70 219 340 720
19–21 0 0 0 0 10 24 13 78 231 591 947
21–23 0 0 0 0 0 3 4 12 146 626 791
23–25 0 0 0 0 0 0 0 1 103 884 988
25–27 0 0 0 0 0 0 0 0 16 1131 1147
27–29 0 0 0 0 0 0 0 0 30 1446 1476
29–31 0 0 0 0 0 0 0 0 6 823 829
31–33 0 0 0 0 0 0 0 0 0 254 254
33–35 0 0 0 0 0 0 0 0 1 5 6
Subtotal 0 0 0 0 126 123 87 367 1020 6369 8092
Fig. 2. Chiller coefficient of performance at different building load ratios for design options (a) OP1, (b) OP2, (c) OP3 and (d) OP4.
the chillers to operate frequently with maximum perfor- [6] Chan KT, Yu FW. Optimum set point of condensing temperature for
mance. The year-round cooling load demand of a hotel air-cooled chillers. International Journal of HVAC&R Research
2004;10(2):113–27.
was determined using TRNSYS. Four design options
[7] Chan KT, Yu FW. Part-load efficiency of air-cooled multiple-chiller
with respect to the number and size of chillers were studied plant. Building Services Engineering Research and Technology 2002;
for the hotel’s chiller plant. The unique frequency 23(1):31–41.
distribution of chiller loads was described for each design [8] Landman W. ‘‘Off-design’’ chiller performance. Trane Engineers
option. It is possible to use the number of steps of total Newsletter 1996;25(5):1–5.
cooling capacity to analyse the frequency of chillers [9] Piper J. 5 threats to chiller efficiency. Maintenance Solutions 2003;
11(4):13–4.
operating at or near full load. Using a set of chiller part [10] Braun JE, Klein SA, Mitchell JW, Beckman WA. Applications of
load performance curves, the variation in chiller COP and optimal control to chilled water systems without storage. ASHRAE
the annual electricity consumption of chillers and pumps Transactions 1989;95(1):663–75.
were assessed for each design option. This assessment [11] Gidwani BN. Optimization of chilled water systems. Energy
shows that unequally sized chillers should be installed in a Engineering 1987;84(5):30–50.
[12] Kaya A. Improving efficiency in existing chillers with optimization
chiller plant to enhance the number of steps of total cooling technology. ASHRAE Journal 1991;33(10):30–8.
capacity, thereby enabling the chillers to operate more [13] Beyene A. Performance evaluation of conventional chiller systems.
frequently near full load with improved performance. The ASHRAE Journal 1995;37(6):36–44.
annual electricity consumption of chillers and pumps could [14] Austin SB. Optimum chiller loading. ASHRAE Journal 1991;33(7):
40–3.
be saved by 10.1% when the chiller plant was designed with
[15] Chang YC, Lin JK, Chuang MH. Optimal chiller loading by genetic
six chillers of three different sizes instead of four equally algorithm for reducing energy consumption. Energy and Buildings
sized chillers. 2005;37(2):147–55.
This paper will give designers and researchers a better [16] Hartman T. All-variable speed centrifugal chiller plants. ASHRAE
idea about how chiller part load performance curves can be Journal 2001;43(9):43–53.
used to evaluate improvements in the energy performance [17] Koury RNN, Machado L, Ismail KAR. Numerical simulation of a
variable speed refrigeration system. International Journal of Refrig-
of a chiller plant with alternative designs. Designers and eration 2001;24:192–200.
researchers will better understand how to properly stage [18] Shelton SV, Weber ED. Modelling and optimization of commercial
multiple chillers and how to split the total cooling capacity building chiller/cooling tower systems. ASHRAE Transaction 1991;
of a chiller plant into different chiller sizes. It is hoped that 97(2):1209–16.
[19] Tassou SA, Quereshi TQ. Comparative performance evaluation of
unequally sized chillers can be widely implemented and
positive displacement compressors in variable-speed refrigeration
integrated with other energy efficient technologies so they applications. International Journal of Refrigeration 1998;21(1):29–41.
can operate highly efficiently with a considerable decrease [20] Wong AK, James RW. Capacity control of a refrigeration system
in the overall electricity consumption. It remains to be seen using a variable speed compressor. Building Services Engineering
how overall engineering economics (i.e., life-cycle-cost Research and Technology 1988;9(2):63–8.
analysis) can help determine if the electricity savings are [21] Mazurkiewicz G. Better cooling via improved chillers. Air Con-
ditioning, Heating and Refrigeration News 2002;215(15):37–8.
worth the increased capital and maintenance costs for [22] Dubov I. Chilled water plant efficiency. ASHRAE Journal 2003;
multiple chillers of different sizes. 45(6):37–40.
[23] Celuch J. Hybrid chilled water plant. ASHRAE Journal 2001;43(7):
34–5.
Acknowledgement [24] Deng SM. Sizing replacement chiller plants. ASHRAE Journal 2002;
44(6):47–9.
The work described in this paper was supported by a [25] Chan KT, Yu FW. How chillers react to building loads. ASHRAE
Journal 2004;46(8):52–8.
grant from the Research Grants Council of the Hong Kong
[26] Environmental Energy Technologies Division of Lawrence Berkeley
SAR, China (Project no. PolyU 5112/05E). National Laboratory. Cleanroom energy efficiency workshop pro-
ceedings section F. California: Author; 1999.
[27] Solar Energy Laboratory. TRNSYS: a transient system simulation
References program (reference manual). Madison, WI: University of Wisconsin-
Madison Press; 2000.
[1] Yu FW, Chan KT. Electricity end-use characteristics of air-cooled [28] Hui SCM, Lam JC. Test reference year for comparative energy study.
chillers in hotels in Hong Kong. Building and Environment Hong Kong Engineer 1992;20(2):13–6.
2005;40(1):143–51. [29] Lam JC, Hui SCM. Outdoor design conditions for HVAC system
[2] Lam JC. Energy analysis of commercial buildings in subtropical design and energy simulation for buildings in Hong Kong. Energy
climates. Building and Environment 2000;35:19–26. and Buildings 1995;22(1):25–43.
[3] Chan KT, Yu FW. Applying condensing-temperature control in air- [30] Lam JC, Hui SCM, Chan ALS. A statistical approach to the
cooled reciprocating water chillers for energy efficiency. Applied development of a typical meteorological year for Hong Kong.
Energy 2002;72:565–81. Architectural Science Review 1996;39(4):201–9.
[4] Yik FWH, Burnett J, Prescott I. Predicting air-conditioning energy [31] American Society of Heating, Refrigeration, and Air-conditioning
consumption of a group of buildings using different heat rejection Engineers. ASHRAE handbook: fundamentals (SI ed.). Atlanta, GA:
methods. Energy and Buildings 2001;33:151–66. Author; 2001.
[5] Chan KT, Yu FW. Analysis of the component characteristics [32] Air-conditioning and Refrigeration Institute. Standard 550/590:
of air-cooled chillers for modelling floating condensing temperature performance rating of water chilling packages using the vapor
control. Energy Conversion and Management 2005;46(6):927–39. compression cycle. Arlington, Virginia: Author; 2003.