PROGRES PEKERJAAN PANEL M SYSTEM

Proyek : UNIVERSITAS MANDIRI 2 Desember 2019


Lokasi : JAKARTA BARAT
VOLUME BOBOT bobot marial bobot aktual terpasang bobot aktual terpasang Finising sisa
bobot marial
Material terpasang thd MOS thd KONTRAK
NO. DESCRIPTION terpasang
terpasang terhadap
QTY. QTY. terhadap MOS
UNIT UNIT KONTRAK nilai bobot (78.33%) nilai bobot (78.33%) nilai bobot (21.67%)
a b c=(b/a x 100%) d=c x 78.33%
1 Dinding M System sisi dalam 3,763 m2 76.73
delivery 1 50 lbr 300 m2 6.12
delivery 2 6 lbr 36 m2 0.73
delivery 3 63 lbr 378 m2 7.71
delivery 4 63 lbr 378 m2 7.71
delivery 5 63 lbr 378 m2 7.71
delivery 6 53 lbr 318 m2 6.48
delivery 7 63 lbr 378 m2 7.71
delivery 8 63 lbr 378 m2 7.71
delivery 9 48 lbr 288 m2 5.87
jumlah 472 2,832 1,758.00 62.08 57.74 48.62 45.23 1,074.00
2 Dinding M System R. Meeting 1,087 m2 23.27

ACUAN
300,000.00
install 235,000.00 78.33%
fin 65,000.00 21.67%
100.00%
Jakarta, 2 Des 2019

Yoga Hantoro
Project Manager