PROJECT STATUS:

Accomplishment to Date : 61.63


Required as per PERT CPM : 100.00
Period Accomplishment : 2.46

ITEM NO. ACTIVITY DESCRIPTION

PART B: Other General Requirements


B.5 Project Billboard /Signboard
B.7(1) Occupational Safety and Health Program
B.7(1) Traffic Management
B.9 Mobilization and Demobilization
B.4(1) Construction Survey & Staking
PART C: Earthworks
101(1) Removal of Structures and Obstructions
102(1) (including
UnsuitableRestorations-wooden
Excavation house)
103(1)a Structure Excavation
103(3) Foundation Fill
103(6)a Pipe Culvert and Drain Excavation
104(2)a Embankment (from Borrow)
PART D: Subbase and Base Course
200(1) Aggregate Subbase Course
PART G: Drainage and Slope Protection Structures
404(1)a Reinforcing Steel Grade 40
405(1)a3 Structural Concrete Class A
500(1)b1 Pipe Culvert, 610mm dia. (24" dia.)
505(1)b7 Pipe Culverts, 1830mm dia. (72" dia.)
502(1)g Manhole (1830mm dia. RCPC)
510(1) Bed Course Granular Material
510(2) Concrete (Slope Protection)
EXTRA WORK
401(1)a1 Metal Railing
101(3)b3 Removal of Existing Concrete Pavement
101(2)f Removal of RCPC(60" diam.) - 1520mm
101(2) Removal of Existing Headwall
502(1)g PCC Pavement (Unreinforced) 0.28 m. thk.
Total

Prepared by:
Renzo Ray M. Olivar
Project / Resident Engineer
Km.7 Tigatto Road, Buhangin, Davao City

PROJECT ACCOMPLISHMENT REPORT

Period
Project ID No. :
Project Code Name :

CUMULATIVE PROGRESS
SCHEDULED
UNIT NET WT.
QUANTITY (PERT-CPM)
%

each 4.00 0.040


mo 4.00 0.144
mo 4.00 0.103
ls 1.00 0.031
km 2.04 0.081

ls 1.00 0.207
cu.m. 15,130.70 8.800
cu.m. 3,345.00 1.979
cu.m. 9.60 0.020
cu.m. 10.25 0.005
cu.m. 9,616.03 12.048
cu.m. 821.50 1.070

kg 64,676.60 9.033
cu.m. 698.79 9.457
ln.m. 20.00 0.156
ln.m. 333.00 12.257
each 20.00 6.448
cu.m. 1,510.06 2.930
cu.m. 1,984.62 30.811

Ln.m. 484.00 4.233


sq.m. 28.50 0.011
ln.m. 13.00 0.036
each 6.00 0.053
sq.m. 11.40 0.043
100
Page No.:

PORT

: Sep. 1-30, 2019 PROJECT COST:


18LC-0104 Budget to Date :
Code Name : La Filipina Actual Budget : 46,7

CUMULATIVE PROGRESS
CUMMULATIVE ACCOMPLISHMENT THIS
ACCOMPLISHMENT MONTH
NET WT. NET WT. REMARKS
QUANTITY QUANTITY
% %

4.00 0.040 - - Completed


4.00 0.144 - - Completed
4.00 0.103 - - Completed
0.50 0.016 - -
2.04 0.081 - - Completed

0.85 0.176 -
12,276.97 7.140 - On going
3,345.00 1.979 - - Completed
9.60 0.020 - - Completed
10.25 0.005 - - Completed
2,076.29 2.601 122.59 0.154 On going
- - - -

61,658.50 8.611 2,800.43 0.39


611.67 8.278 43.00 0.582 21 ln.m. lef
1.000 0.008 - 19 pcs lef
320.00 11.778 -
20.00 6.448 - Completed
633.62 1.229 59.80 0.116 On going
832.22 12.920 78.59 1.22 On going

0.00 - no plan/design
14.25 0.006 - half of existing R
6 0.017 - demolished
3 0.027 -
0.00 - Afer Box Culv
61.627 2.46

Project Inspector / Assistant Chief Engineer

Chief Engineer
JECT COST:

46,763,373.61

REMARKS

Completed
Completed
Completed

Completed

On going
Completed
Completed
Completed
On going
21 ln.m. lef
19 pcs lef

Completed
On going
On going

no plan/design yet
alf of existing RCPC
demolished

Afer Box Culvert


Km.7 Tigatto Road, Buhangin, Davao City

PROJECT TARGET REPORT


PROJECT STATUS:
Accomplishment to Date : 53.94 Period : July 1-31, 2019 PROJECT COST:
Required as per PERT CPM : 100.00 Project ID No. : 18LC-0104 Budget to Date :
Period Accomplishment : 0.00 Project Code Name : La Filipina Drainage Canal Actual Budget : 47,530,183.04

CUMULATIVE PROGRESS
CUMMULATIVE ACCOMPLISHMENT TO
SCHEDULED TARGET Month of JULY
ACCOMPLISHMENT DATE
ITEM NO. ACTIVITY DESCRIPTION UNIT REMARKS
QUANTITY NET WT. QUANTITY NET WT. QUANTITY NET WT. QUANTITY NET WT.
(PERT-CPM) Week 1 Week 2 Week 3 Week 4
% % % %
PART B: Other General Requirements 1 2 3 4 5 6 8 9 10 11 12 13 15 16 17 18 19 20 22 23 24 25 26 27
B.5 Project Billboard /Signboard each 4.00 0.040 4.00 0.040 - - Completed
B.7(1) Occupational Safety and Health Program mo 4.00 0.144 4.00 0.144 - - Completed
B.7(1) Traffic Management mo 4.00 0.103 4.00 0.103 - - Completed
B.9 Mobilization and Demobilization ls 1.00 0.031 0.50 0.016 - -
B.4(1) Construction Survey & Staking km 2.04 0.082 2.04 0.082 - - Completed
PART C: Earthworks
Removal of Structures and Obstructions
101(1) (including Restorations-wooden house) ls 1.00 0.207 0.85 0.176 With Revisions

102(1) Unsuitable Excavation cu.m. 16,518.00 9.608 12,276.97 7.141 On going


103(1)a Structure Excavation cu.m. 3,406.00 2.015 3,405.65 2.015 Completed
103(3) Foundation Fill cu.m. 10.00 0.021 9.04 0.020
103(6)a Pipe Culvert and Drain Excavation cu.m. 11.36 0.006 11.36 0.006 Completed
104(2)a Embankment (from Borrow) cu.m. 9,851.00 12.342 3,845.23 4.818
PART D: Subbase and Base Course
200(1) Aggregate Subbase Course cu.m. 944.00 1.229 - -
PART G: Drainage and Slope Protection Structures
404(1)a Reinforcing Steel Grade 40 kg 54,913.00 7.669 52,611.25 7.348 328.82 0.046 328.820 0.046 On going 0.046
405(1)a3 Structural Concrete Class A cu.m. 589.87 7.983 568.67 7.696 21.19 0.287 On going 0.287
500(1)b1 Pipe Culvert, 610mm dia. (24" dia.) ln.m. 21.00 0.164 1.000 0.008 20.00 0.156 On going 0.156
505(1)b7 Pipe Culverts, 1830mm dia(72" dia.) ln.m. 348.00 12.809 320.00 11.778 -
502(1)g Manhole (1830mm dia. RCPC) each 21.00 6.770 20.00 6.448 - considered completed

510(1) Bed Course Granular Material cu.m. 1,736.04 3.369 361.35 0.701 319.16 0.619 52.610 0.102 On going 0.155 0.155 0.155 0.155

510(2) Concrete (Slope Protection) cu.m. 2,280.68 35.407 347.86 5.400 419.28 6.509 69.090 On going 1.627 1.627 1.627 1.627
1.070

TOTAL 100.00 53.940 7.62 1.22 Total 1.828 1.782 1.782 2.225
Cummulative 7.62

Prepared by:
Renzo Ray M. Olivar
Office Engineer
Verified Correct by:
Project Inspector / Assistant Chief Engineer

Approved by:
Chief Engineer