Sei sulla pagina 1di 5

St.

Xavier’s Catholic College of Engineering, Chunkankadai


Department of Management Studies
BA5028 - Project Management
Unit Test – I
Date: 15.07.2019 Max. Marks: 20

1.Which of the following is not a characteristic of a project?


It is unique
It is infinite
It is heterogeneous
It is non-repetitive

2.What does ‘R’ represents in a SMART project?


Risk
Relevant
Realistic
Resource

3.Which of the following statement is false?


Projects are one time processes
Projects are not limited by budget and resources
Projects have a clear set of goals
Projects are customer focused

4.What does term ‘KSTT’ stands for with respect to project management?
Knowledge, Skills, Tools and Technology
Knowledge, Skills, Techniques and Technology
Knowledge, Skills, Tools and Techniques
Knowledge, Skills, Tools and Time

5.What are the determinants of project success as per Iron Triangle?


Resources, Cost, Performance
Knowledge, Time, Resources
Cost, Skills, Performance
Cost, Performance, Time

6.What does ‘PMMM’ stands for?


Project Management Measurement Model
Project Management Maturity Model
Project Management Mixed Model
Project Management Mass Model

7.Which of these is not a key element of Organization Structure?


Formal reporting relationship
Grouping together of individuals
Design of system to ensure effective communication
Training of individuals for effective management
St. Xavier’s Catholic College of Engineering, Chunkankadai
Department of Management Studies
BA5028 - Project Management
Unit Test – I
Date: 15.07.2019 Max. Marks: 20
8.Which of the following is not a form of organizational structure?
Functional
Project
Grouped
Matrix

9.Which of these is not a characteristics of a Program Manager?


Program managers handles a group of related projects
Program manager works with project sponsors
Program manager oversees all the projects
Program manager act as bosses for project managers

10.Which of these statements is not true for sub projects?


Sub-projects are manageable components of a project
Subprojects involve the use of special technology
Sub-projects are handled by internal enterprise only
Sub-projects consist of series of smaller sub-projects for a large project.

11. Which of the following is not a classification of Brownfield projects?


Expansion
Diversification
Modernization
Vertical Integration

12. Steel industry manufacturing steel pipes is an example of _____________?


Backward integration
Upstream expansion
Forward integration
None of the above

13. Which of the following is not a type of diversification project?


Concentric
Retrenchment
Conglomerate
None of the above

14. Project Life Cycle generally do not define which of the following?
Technical work
Deliverables
Control and approval
Training
15. Which of the following is longest phase of a Project life cycle in terms of time?
St. Xavier’s Catholic College of Engineering, Chunkankadai
Department of Management Studies
BA5028 - Project Management
Unit Test – I
Date: 15.07.2019 Max. Marks: 20
Concept phase
Implementation phase
Planning phase
Termination phase

16. Which of the following activity is not part of development phase?


Schematics
Resources
Cash flowing
Procurement

17. What is the correct sequence of Project Life Cycle phases?


Initiation, Implementation, Planning and Project Clean-up
Initiation, Project Clean-up, Planning and Implementation
Initiation, Project Clean-up, Implementation and Planning
Initiation, Planning, Implementation and Project Clean-up

18. Brainstorming is a part of which of the following phase of Project Life Cycle?
Initiation
Implementation
Planning
Project Clean-up

19. Which of the following is not a brainstorming activity?


Vision for future growth
Long term objectives
Testing
SWOT analysis

20. Which of the following is not a part of technical project appraisal?


Engineering aspects
Location
Process
Pricing options

Answer All Questions


1.Which of the following is not a characteristic of a project?
St. Xavier’s Catholic College of Engineering, Chunkankadai
Department of Management Studies
BA5028 - Project Management
Unit Test – I
Date: 15.07.2019 Max. Marks: 20
1. It is unique 2. It is infinite 3. It is heterogeneous 4. It is non-repetitive
2.What does ‘R’ represents in a SMART project?
1. Risk 3. Relevant 3. Realistic 4. Resource
3.Which of the following statement is false?
1. Projects are one time processes 2. Projects are not limited by budget and resources
3. Projects have a clear set of goals 4. Projects are customer focused
4.What does term ‘KSTT’ stands for with respect to project management?
1. Knowledge, Skills, Tools and Technology 2. Knowledge, Skills, Techniques and
Technology 3. Knowledge, Skills, Tools and Techniques 4. Knowledge, Skills,
Tools and Time
5.What are the determinants of project success as per Iron Triangle?
1.Resources, Cost, Performance 2.Knowledge, Time, Resources
3.Cost, Skills, Performance 4.Cost, Performance, Time
6.What does ‘PMMM’ stands for?
1.Project Management Measurement Model 2.Project Management Maturity Model
3.Project Management Mixed Model 4.Project Management Mass Model
7.Which of these is not a key element of Organization Structure?
1.Formal reporting relationship 2.Grouping together of individuals 3.Design of
system to ensure effective communication 4.Training of individuals for effective
management
8.Which of the following is not a form of organizational structure?
1.Functional 2.Project 3.Grouped 4.Matrix
9.Which of these is not a characteristics of a Program Manager?
1.Program managers handles a group of related projects 2.Program manager works
with project sponsors 3.Program manager oversees all the projects 4.Program
manager act as bosses for project managers
10.Which of these statements is not true for sub projects?
1.Sub-projects are manageable components of a project 2.Subprojects involve the use
of special technology 3.Sub-projects are handled by internal enterprise only
4.Sub-projects consist of series of smaller sub-projects for a large project.

11. Which of the following is not a classification of Brownfield projects?


St. Xavier’s Catholic College of Engineering, Chunkankadai
Department of Management Studies
BA5028 - Project Management
Unit Test – I
Date: 15.07.2019 Max. Marks: 20
1.Expansion 2.Diversification 3.Modernization 4.Vertical Integration
12. Steel industry manufacturing steel pipes is an example of _____________?
1.Backward integration 2.Upstream expansion 3.Forward integration 4.None of the above
13. Which of the following is not a type of diversification project?
1.Concentric 2.Retrenchment 3.Conglomerate 4.None of the above
14. Project Life Cycle generally do not define which of the following?
1.Technical work 2.Deliverables 3.Control and approval 4.Training
15. Which of the following is longest phase of a Project life cycle in terms of time?
1.Concept phase 2.Implementation phase 3.Planning phase 4.Termination phase
16. Which of the following activity is not part of development phase?
1.Schematics 2.Resources 3.Cash flowing 4.Procurement
17. What is the correct sequence of Project Life Cycle phases?
1.Initiation, Implementation, Planning and Project Clean-up
2.Initiation, Project Clean-up, Planning and Implementation
3.Initiation, Project Clean-up, Implementation and Planning
4.Initiation, Planning, Implementation and Project Clean-up
18. Brainstorming is a part of which of the following phase of Project Life Cycle?
1.Initiation 2.Implementation 3.Planning Project 4.Clean-up
19. Which of the following is not a brainstorming activity?
1.Vision for future growth 2.Long term objectives 3.Testing 4.SWOT analysis
20. Which of the following is not a part of technical project appraisal?
1.Engineering aspects 2.Location 3.Process 4.Pricing options

*****

Potrebbero piacerti anche