Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
2 BITUMEN 700 KG
8 GAS 8 NOS
9 LABOUR 65 NOS
10 Aluminium Paint 4 20 L
12 OTHER ACCESSORIES
TOTAL
PER SFT FOR 9684 SFT
Considering 2 times
65 45500 application as per specs
given, 300 KG's /
application (9600 SFT)
1350 10800
Considering
20000 20000 Rs.1000/worker for 6 days
for 2.5 weeks
512900
53
Specs To Consider
Providing and laying Membrane Waterproofing as mentioned below or as directed by Engineer- in- charge etc complete.
2 BITUMEN 1000 KG
8 GAS 12 NOS
10 Aluminium Paint 4 20 L
12 OTHER ACCESSORIES
TOTAL
PER SFT FOR 9684 SFT
Considering 2 times
65 65000 application as per specs
given, 300 KG's /
application (9600 SFT)
1350 16200
Considering
20000 20000 Rs.1000/worker for 6 days
for 2.5 weeks
853800
88
Specs To Consider
Providing and laying Membrane Waterproofing as mentioned below or as directed by Engineer- in- charge etc complete.