1 Clearing and grubbing within the Site of all trees, bushes, etc. Ha 2,625.00
2 Cut down and clear away from site, trees exceeding 300mm and not exceeding
600mm girth measured at 1.00m above ground level including grubbing up roots
and filling up holes with approved earth. NO 94.50
3 Cut down and clear away from site, trees exceeding exceeding 600mm and not
exceeding 1200mm girth measured at 1.00m above ground level including
grubbing up roots and filling up holes with approved earth. NO 157.50
4 Cut down and clear away from site, trees exceeding 1200mm and not exceeding
1800mm girth measured at 1.00m above ground level including grubbing up roots
and filling up holes with approved earth. NO 252.00
5 Excavate oversite average 150mm deep to level off formation or reduce level and
2
dump away excess earth. M 1.60
9 Excavate for foundation, trenches, pier holes, manholes, septic tanks, filter
beds etc. not exceeding 1.50m deep, part backfill and remove surplus spoil
and deposit, spread and level on site as specified ( manually ). M3 16.80
10 Excavate for foundation, trenches, pier holes, manholes, septic tanks, filter
beds etc. exceeding 1.50m deep and not exceeding 3.00m deep, part backfill
and remove surplus spoil and deposit, spread and level on site as specified (
manually ). M3 18.90
11 Excavate for foundation, trenches, pier holes, manholes, septic tanks, filter
beds etc. exceeding 3.00m deep and not exceeding 4.50m deep, part backfill
and remove surplus spoil and deposit, spread and level on site as specified (
3
manually ). M 26.30
12 Excavate for foundation, trenches, pier holes, manholes, septic tanks, filter
beds etc. to irrespective of depth (by mechanical equipment). M3 10.50
3
(a) Open excavation (including use of explosive, etc). M 21.00
(b) Trench excavation (including for foundation, trenches, pier holes, manholes,
septic tanks, filter beds and etc.). M3 42.00
15 Imported approved earth from contractor's own source within 15 km from site
including unloading in filling areas. M3 24.20
16 Spread, level and compact excavated earth for filling in layers as specified in filling
3
areas. M 2.10
17 Spread, level and compact surplus excavated earth in areas away from site, within
3 km lead. M3 5.30