8 & 40 C No Comments Section 2,10.1 and 10.2 updated. Re-issued for Approval Closed
Date :
Signature:
Table of Contents
1. INTRODUCTION ........................................................................................................................ 6
1.1 PROJECT OVERVIEW ............................................................................................................ 6
1.2 SCOPE OF WORK .................................................................................................................. 6
1.3 DOCUMENT PURPOSE ........................................................................................................... 6
1.4 SCOPE OF PQMP ................................................................................................................... 6
1.5 CONTROL AND DISTRIBUTION .............................................................................................. 7
2. REFERENCE DOCUMENTS ......................................................................................................... 8
3. DEFINITIONS / ABBREVIATIONS ............................................................................................... 8
3.1 DEFINITIONS ......................................................................................................................... 8
3.2 ABBREVIATIONS.................................................................................................................... 9
4. PROJECT QUALITY MANAGEMENT ......................................................................................... 11
4.1 PROJECT QMS STRUCTURE ................................................................................................ 11
4.2 DOCUMENT CONTROL AND INFORMATION MANAGEMENT ................................................ 11
4.2.1 DOCUMENT CONTROLLER .............................................................................................. 12
4.3 CONTROL AND STORAGE OF RECORDS .............................................................................. 12
4.4 OUTSOURCED SCOPE OF WORK ......................................................................................... 13
5. MANGEMENT RESPONSIBILITIES ............................................................................................. 13
5.1 MANAGEMENT COMMITMENT ............................................................................................. 13
5.2 CUSTOMER FOCUS.............................................................................................................. 14
5.3 QUALITY POLICY ................................................................................................................ 14
5.4 PROJECT QUALITY OBJECTIVES ........................................................................................ 14
5.5 PROJECT QMS PLANNING ................................................................................................... 15
5.6 PERFORMANCE MANAGEMENT ........................................................................................... 15
5.7 QUALITY MANAGEMENT REPORTING ................................................................................. 15
5.8 RESPONSIBILITY, AUTHORITY AND COMMUNICATION ....................................................... 16
5.8.1 PROJECT ORGANIZATION ............................................................................................... 16
5.8.2 RESPONSIBILITY AND AUTHORITY ................................................................................. 16
5.8.3 INTERNAL COMMUNICATION .......................................................................................... 24
5.9 PROJECT MANAGEMENT REVIEW ....................................................................................... 25
6. RESOURCE MANGEMENT ........................................................................................................ 26
6.1 PROVISION OF RESOURCES ................................................................................................ 26
6.2 HUMAN RESOURCES (HR) ................................................................................................... 26
Salalah LPG Project, Oman Rev.D
Doc.No: SLPG-Q-000000-001-A1-4
Title: Project Quality Management Plan Page 4 of 44
1. INTRODUCTION
Salalah LPG SFZCO LLC, a subsidiary of Oman Gas COMPANY, intends to build an LPG
Extraction and Fractionation Plant at Salalah in Dhofar Governorate of Oman. Petrofac has
been appointed as an EPC CONTRACTOR to carry out Engineering, Procurement, Construction,
Commissioning and Start-up of the required facilities, on a lump sum turnkey basis.
The facilities will be designed to utilise the rich gas transported from Northern part of Oman
to the Southern part of the country through a cross country gas pipeline and extract Propane,
Butane and Heavy Hydrocarbons from the gas, liquefy & store them at low temperature before
exporting them through the tankers via a jetty located at Salalah Port. The lean gas is
compressed and delivered back into the gas pipe network for supply to local industries in and
around the Salalah region. The facilities also include blending of Propane and Butane to
produce commercial grade of LPG for domestic consumption. This LPG is then exported
through the road trucks.
Primary objective of the project is to build the state of the art facilities using the proven
technology, in an optimised and timely manner without compromising the Safety, Quality and
Technical Integrity.
The Scope of Work associated with the Salalah LPG Project involves Management, Engineering,
Procurement, Construction, Pre-commissioning, Commissioning, Initial start-up, Equipment
and Facility Performance testing and handover of facilities to the COMPANY. Detailed
CONTRACTOR’s Scope of Work shall be as stated in Appendix 1.2 of Contract document ref.
SLPG/08/2015.
The purpose of this Project Quality Management Plan is to describe how the quality is
managed and assured by EPC CONTRACTOR to carry out Engineering, Procurement,
Construction, Commissioning and Start-up activities for the project. This document has been
developed in line with CONTRACTOR’s QMS, COMPANY’s requirements ref. Appendix 6-Quality
Assurance and Quality Control (Contract Doc. no. SLPG/08/2015) and has been derived from
best practices established in ISO 9001: 2015 standard.
This PQMP has been aligned with the Project Execution Plan Doc No. SLPG-G-000000-008-A1-4
and Construction Execution Plan Doc No.SLPG-G-000000-011-A1-4.
This PQMP is applicable to all functional aspects of the Project, and scope as stated in section
1.2 of this PQMP. Application of this PQMP is mandatory for all work locations where the
project is executed.
Salalah LPG Project, Oman Rev.D
Doc.No: SLPG-Q-000000-001-A1-4
Title: Project Quality Management Plan Page 7 of 44
All SUBCONTRACTORs and SUPPLIERs/VENDORs associated with the Project will follow their
Quality Management Systems in accordance with the ISO 9001:2008 standard covering their
scope of work. Quality Management Systems in accordance with ISO 9001:2015 standard may
be considered. However, their Project Quality Plans which are applicable to the project scope
of work will be aligned to project requirements and submitted for COMPANY / CONTRACTOR’s
for review and approval.
This PQMP is a live document throughout the life cycle of the Project. Consequently, revisions
to this PQMP will be introduced as and when necessary. The revisions will be identified on the
front sheet and the latest revisions shall be marked up in the relevant sections through a
vertical line on the right hand side of page. For a complete revision, the revision marking will
be avoided. All revisions will be subjected to the same controls as applicable to the initial
development and issue of the plan.
The distribution of this PQMP shall be controlled throughout the Project. The Project Quality
Manager (PQM) will be responsible for controlling, updating, and communicating this PQMP to
all Project team members. The latest revision approved by the COMPANY will be available in
CONTRACTOR’s web based QMS for implementation.
2. REFERENCE DOCUMENTS
SLPG-M-000000-002-A1-4 Pre-commissioning/Commissioning
Strategy & Execution Plan
3. DEFINITIONS / ABBREVIATIONS
3.1 DEFINITIONS
3.2 ABBREVIATIONS
CONTRACTOR’s Quality Management System (QMS) includes the policies, objectives, processes,
procedures and tools necessary to facilitate the management of EPC projects. The QMS is
delivered to users through the web-based QMS and as necessary by distribution of hard copies
of QMS documents.
A project specific view is created in QMS Web Page and QMS database will be updated as and
when key documents are updated and new key documents developed.
Documents and Data pertaining to this Project are controlled in accordance with Document
Control and Numbering Procedure Doc. No. SLPG-G-000000-005-A1-4. Complete list of project
deliverables are defined in Technical Document Register (TDR), similarly the complete list of
SUPPLIER/VENDOR documents is defined in SUPPLIER/VENDOR Document Register (VDR).
Transmittals will be used to exchange engineering documents and technical data between the
Salalah LPG Project, Oman Rev.D
Doc.No: SLPG-Q-000000-001-A1-4
Title: Project Quality Management Plan Page 12 of 44
organisations involved. The main elements of the Document Control Plan are given in below
Figure1.
Project specific documents are prepared, checked and approved before release by personnel
authorised. Changes to documents shall be reviewed and approved by the same functions that
performed the original review and approval.
Only Key Controlling documents applicable for this Project will be included in QMS - Salalah
LPG ‘Project View’. Documents relevant to the projects such as Plans and Procedures, the
relevant CONTRACTOR Standards, Lessons Learnt spread sheets etc. will be available via
CONTRACTOR’s QMS Database.
Dedicated Document Controllers are assigned for the project; act as the single focal point for
implementation of CONTRACTOR’s Document Control System. The main responsibilities of
Document Controllers are managing the central documents, SUBCONTRACTOR documents,
VENDOR/SUPPLIER document or documents generated at Value Engineering Centre.
The objective for establishing and maintaining quality records is to provide evidence of the
Salalah LPG Project, Oman Rev.D
Doc.No: SLPG-Q-000000-001-A1-4
Title: Project Quality Management Plan Page 13 of 44
The Process Owners are required to ensure the collection and maintenance of the quality
records within the scope of their respective work.
All quality records pertaining to the Quality Management System and the Project, as
applicable, generated by CONTRACTOR, SUBCONTRACTORs and SUPPLIERs/VENDORs are stored
as computer database under defined system names and/or as hard copy.
Project records (i.e. engineering records, SUPPLIER/VENDORs MDRs, Construction Dossier, site
Quality Records etc.) that provide evidence of conformance to COMPANY requirements shall
be identified, stored, protected, and retained as per Contract guidelines.
On completion of the scope of work, CONTRACTOR will hand over to the Project approved
project records in accordance with Contract requirements and agreed procedures.
Records are retained for a minimum of five years. Quality records are identified, filed and
archived in accordance with the Control of Records procedure Doc No. PEC-QU-PRO-X-2799.
Wherever the scope of work is outsourced, the product conformity to project specific
requirements shall be maintained by the CONTRACTOR to ensure project goals are met.
5. MANGEMENT RESPONSIBILITIES
the Project Quality Management System on annual basis to assure the continuing, suitability,
adequacy and effectiveness of the project quality management system.
CONTRACTOR’s management shall ensure that competent and qualified personnel are
available to perform their relevant functions.
CONTRACTOR conducts regular meetings with COMPANY to understand the perceptions during
project execution phase.
COMPANY comments regarding Project activities will be analysed and relevant improvement
actions will be taken. Feedback will be gathered during various meetings, reviews,
correspondences, joint inspections and day-to-day interactions. Feedbacks/concerns raised by
COMPANY requiring resolution will be reported to the Project Director for initiating
satisfactory close out actions by concerned process owners.
The Project Director is responsible for handling COMPANY feedback according to QMS
Internal/External Customer Feedback Procedure Doc No. PEC-QU-PRO-X-1086. Customer
Feedback will be obtained once a year in July.
CONTRACTOR is committed to working with COMPANY as a team to ensure that all Project
objectives are met. These include:
• Drive the concept of Health, Safety, Security and Environment (HSSE) management
throughout all phases of the Project and ensure that all targets, measured by key
performance indicators are fully met;
• Facilities will be designed, procured, constructed, Installed and Commissioned such
that the design intent and Contract requirements for performance, quality, safety,
environmental, constructability, operability, maintenance are fully met;
• Constructability, Operability & Maintainability built into the design;
• Cooperate with COMPANY, appreciate COMPANY requirements and be responsive to
their needs;
• The facilities will be designed to ensure safe and efficient plant construction,
operation and maintenance;
Salalah LPG Project, Oman Rev.D
Doc.No: SLPG-Q-000000-001-A1-4
Title: Project Quality Management Plan Page 15 of 44
Planning starts with setting of Project Objectives and establishing the system to achieve these
objectives. Project Director is responsible to set Project Quality objectives. Refer Project
Execution Plan Doc No. SLPG-G-000000-008-A1-4 for Project Objectives.
Quality planning for the Contract shall be under taken by Project Quality Manager considering
the Quality Objectives, scope of work and Contract specifications as follows:
A set of Quality Key Performance Indicators (KPIs) and metrics shall be established for the
project for monitoring quality performance and shall be reported in the Monthly Report. The
KPIs are dynamic in nature and may change during the course of the Project and revisions shall
be communicated independently.
The CONTRACTOR’s key positions and their reporting structures are included in Project
Organisation Chart Doc No. SLPG-G-000000-013-A1-4 and Project Execution Plan Doc. No.
SLPG-G-000000-008-A1-4. Since the organisation chart is dynamic in nature and will change
during the Project development, the revisions will be communicated independently. The
project QA/QC organization chart indicating the positions and their reporting structures is as
per Doc No. SLPG-Q-000000-006-A1-4. (Refer Attachment -5)
The Project Director will assign the Project Quality Manager as the Management
Representative for quality on the project. Project Quality Manager will ensure the quality
system is established, maintained and implemented.
Project specific roles and responsibilities of all Key positions are as stated in Project Execution
Plan Doc. No. SLPG-G-000000-008-A1-4. Job descriptions for the Project quality personnel are
established and are available in the Corporate QMS Webpage.
PROJECT DIRECTOR
• Liaise with the client senior management and troubleshooting any areas of conflict
between the project management team and the client to ensure a smooth and
continuing working relationship;
• Anticipate and resolve any problems, bottlenecks/scheduling conflicts to achieve on
time or earlier deliveries to keep the project on schedule;
• Ensure high safety standards are maintained across projects, the client’s feedback is
positive and that project management is proactive;
• Ensure project QMS are regularly reviewed considering the Internal and external issues
and the requirements of interested parties (where relevant);
• Ensure the Quality Management System achieves its intended results;
• Be accountable for the effectiveness of Project QMS.
The Deputy Project Director reports to the Project Director and is responsible during PD’s
absence. The Project Director may delegate his responsibilities to DPD.
• Carry out any other related quality activities as requested by the Project Quality
Manager.
QA/QC ENGINEER
Responsibilities include:
• Reviews contract documents to ensure identification and comprehension of quality
requirements;
• Identifies specific requirements in the Contract, which require to be addressed and
need to be controlled through specific procedures;
• Where necessary, organizes/participates in assessing the SUPPLIER/VENDOR for their
capability in meeting. Identify areas requiring reinforcements and rectification before
placing a purchase order;
• Reviews SUPPLIER/VENDOR document. Also identify interventions required by
CONTRACTOR and COMPANY inspectors based on the criticality level;
• Participates in KOM, schedule and conduct PIM and resolves the issues related to
quality /inspections with SUPPLIERs/VENDORs;
• Ensures ITP and applicable documents are approved prior to schedule the inspections.
• Liaises with Resident Inspector, TPI and COMPANY representatives in all
SUPPLIER/VENDOR inspections;
• Ensures all relevant documents like PO, PR, Data sheets, drawings, procedures; ITP,
WPS/PQR, etc. are issued to the visiting Inspector;
• Coordinates all inspection requirements for TPI inspectors.
• Surveillance inspection visits to the SUPPLIER/SUB-SUPPLIER premises as and when
required;
• Provides technical inputs for SUPPLIER/VENDOR queries and non-conformance reports.
Review SUPPLIER/VENDOR queries, CR (Conformance Reports), NCR (Non Conformance
Reports) for possible resolutions and analyze fitness to purpose. Provide necessary
recommendations for COMPANY approval;
• Reviews SUPPLIER/VENDOR/SUBCONTRACTOR quality plans, procedures and project
material certification;
• Ensures all reviewed inspection reports and material test certificates are compiled and
uploaded in the respective project folders;
• Integrates with and work along- side the quality team and perform all related tasks as
and when requested by the supervisor;
• Ensures the inspections are carried out as per the approved ITP and all hold/witness
and review points are honored;
• Issue and close out NCRs for any deficiency that impact the design;
• Issues Surveillance reports;
• Reviews MRB documents.
Salalah LPG Project, Oman Rev.D
Doc.No: SLPG-Q-000000-001-A1-4
Title: Project Quality Management Plan Page 20 of 44
He is responsible for managing all Site related quality activities. The responsibilities include,
WELDING ENGINEER
His responsibilities include:
• Liaison with the Site Welding Engineer and providing feedback on all welding activities
on the site;
• Coordinating the resolution of welding related issues;
• Monitoring compliance with approved welding procedures and best practices;
• Analysis of weld rejections to establish the correct welder skill profile and appropriate
welder allocation;
• Providing advice and guidance to welders and supervisors related to the welding of
special/exotic materials;
• Monitoring the onsite control of welding consumables;
• Monitoring the validity of welder qualifications.
NDT ENGINEER
His responsibilities include:
• Providing advice and guidance as appropriate, to avoid deviation from the drawing and
specification requirements;
• Monitoring and reviewing defect levels, and providing advice on appropriate remedial
and corrective actions;
• Providing input for the satisfactory closure of any reported non-conformances;
• Performing all types of inspection and testing according to the qualified discipline,
including material receipt, in-process and final inspection, as per the requirements of
the approved ITPs and associated reference drawings, specifications and standards.
• Ensuring that all QC inspection and testing records are completed correctly and
accurately;
• Monitoring the compilation of inspection and testing records and reviewing test packs
prior to submission to COMPANY;
• Maintaining comprehensive records of all inspection and testing carried out to ensure
that all sections of the work have been covered;
• Witnessing the qualification testing of special processes and personnel e.g. concrete
mixes, welding, painting etc.;
• Verifying the calibration status of all instruments and equipment used for the
measurement of process parameters;
• Ensuring that only COMPANY approved materials are used for the construction of the
permanent works and that material traceability is maintained;
• Highlighting any errors or omissions that may be discovered in the QC documentation;
• Monitoring the construction activities and highlighting any non-conformities that may
occur;
• Witnessing the application of remedial and corrective actions, as appropriate.
• The Site Manager is the senior CONTRACTOR position at the Project site;
• He is responsible for all construction activities as required by the Contract;
• The Site Manager discharges those duties in accordance with the Construction
Execution Plan and implementing related procedures and work processes as provided
by the hierarchy of instructions;
Salalah LPG Project, Oman Rev.D
Doc.No: SLPG-Q-000000-001-A1-4
Title: Project Quality Management Plan Page 23 of 44
• The Site Manager is CONTRACTOR single point of contact on the project site for
COMPANY;
• All correspondence to COMPANY and offsite entities shall receive the approval of the
Site Manager or Designee.
• The Area Construction Superintendents (CS) has the responsibility for leading direct
Work and SUBCONTRACTORs in delivering the construction targets;
• The CMs & CSs discharge these duties aligning to the Construction Execution Plan.
COMMISSIONING MANAGER
The Commissioning Manager reports to the Project Director. His responsibilities include:
PRE-COMMISSSIONING COORDINATOR
The Pre-commissioning/Commissioning Coordinator reports to the Commissioning Manager. His
responsibilities include:
Common network drive and Document system CAPITAL Projects will be available to Project
team for availability of documents required for execution of the projects.
The Project Quality Manager shall ensure the processes of the Project Quality Management
System and their effectiveness are communicated throughout the organization by distribution
of audit reports, management review results, work instruction and surveillance reports etc.
Salalah LPG Project, Oman Rev.D
Doc.No: SLPG-Q-000000-001-A1-4
Title: Project Quality Management Plan Page 25 of 44
Project Quality induction will be provided to the project team which shall ensure the
awareness of Project Quality Management system. Project specific view on web based QMS
will provide only key Project Specific Quality Management system documents.
Project Execution Plan (PEP)-details the communication flow with SUBCONTRACTORs and
SUPPLIERs/VENDORs.
Project management review shall be conducted to review Project performance and Project
QMS the adequacy and effectiveness. It will also include assessing opportunities for
improvement, changes to the Project QMS, quality policy and quality objectives.
CONTRACTOR's Project Director along with Project Sponsor will review the project specific
Quality System once in a year to ensure that the system is suitable, adequate and effective.
Project Quality Manager shall present the Management review input to Project Director in
order to review the Project QMS and document the output.
Review Input:
Review Output:
The output from the Project quality management review meeting will be recorded and
implemented to an agreed timetable.
Any changes to the Project Quality System that result from CONTRACTOR’s Project
Management Reviews shall be incorporated in the PQMP, with the approval of COMPANY
Representative. Proposed changes to the Project QMS will be approved by the Project
Director.
Salalah LPG Project, Oman Rev.D
Doc.No: SLPG-Q-000000-001-A1-4
Title: Project Quality Management Plan Page 26 of 44
6. RESOURCE MANGEMENT
CONTRACTOR will provide adequate and suitably qualified resources to facilitate the
Construction, Pre-commissioning, Commissioning and Start-up activities as may be required by
the COMPANY.
Quality personnel employed by CONTRACTOR and its SUBCONTRACTORs to perform the WORK
described in this Contract will meet, as a minimum, the qualification and experience
requirements in line with Appendix 6.3 of the Contract.
COMPANY approval shall be obtained for Project Quality Manager, Site Quality Manager, and
Site QC personnel. All QC personnel CV’s and qualifications shall be submitted to COMPANY for
review.
6.2.1 TRAINING
CONTRACTOR recruits employees capable of meeting the minimum technical skill, experience
and educational requirements for the defined job function activities stated in Job
Descriptions.
All staff and senior employees are responsible for recommending the training needs of
personnel to ensure that all employees allocated for specific tasks are suitably qualified and
experienced to execute those tasks. Additional training needs may be either requested or
identified during annual assessments by the Supervisor/Manager.
6.3 INFRASTRUCTURE
Infrastructure for efficient execution of the project will be implemented under control of the
Project Director. This may include:
• Workspace, offices; warehouse, storage yards, workshops, industrial area, and
associated facilities;
• Equipment, hardware and software;
• Suitable maintenance of construction and test materials and equipment etc.;
• Mobilization and Demobilization of personnel.
The work environment necessary to achieve conformity of project activities will be identified
and managed by the Project Director. These measures will include:
7. PROJECT EXECUTION
The planning program is established at the beginning of the project, monitored and controlled
by Project Controls Manager as per Project Controls Procedure Doc No. SLPG-G-000000-007-A1-
4.
The implementation, monitoring and verification of these processes will be carried out under
control of the Project Controls Manager.
Setting and monitoring of CONTRACTOR’s interface management system will be as per the
project specific Interface Management Execution Plan Doc. No. SLPG-G-000000-018-A1-4.
Procedure details the management of interfaces between different engineering offices,
SUBCONTRACTOR yards, site works, shop surveillance etc. Also include interface with
Salalah LPG Project, Oman Rev.D
Doc.No: SLPG-Q-000000-001-A1-4
Title: Project Quality Management Plan Page 28 of 44
COMPANY, technology Licensors (if any), regulatory agencies, and third party consultants etc.
as per project requirements.
All changes will be handled in accordance with section General Conditions 36.0 of Contract
Agreement and with Change Management Procedure Doc.no SLPG-G-000000-048-A1-4 which is
also be applicable to all SUPPLIERs/VENDORs and SUBCONTRACTORs, Consultants or any other
entity involved in the delivery of a part of Project. Procedure will identify specific type of
changes that may influence quality.
CONTRACTOR shall perform Project Risk Management review as per COMPANY requirements.
Project Risk Management activities include any risks to the project objectives, mainly in terms
of cost, schedule, reputation, HSSE etc.
A Risk Register shall be established for the project and is controlled by the Project Controls
Manager. The Project risk register shall be based on an advanced excel sheet, including the
risk details, the assessment and the action details. On completion of the project a full debrief
will be conducted to ensure lessons learnt are captured in the overall project duration.
The effectiveness of the Risk Management process shall be verified through periodic audit.
CONTRACTOR’s LL database will be utilized to review lessons learned from previous projects
of similar nature. This LL review shall be organized at early phase of the project so that
outcome of LL review can be made input to all phases of the project. A project specific
Lessons Learned Procedure Doc No. SLG-G-000000-017-A1-4 will be implemented on the
project.
COMPANY’s learning points (i.e. potential flaws) will be incorporated into project specific LL
database and will be regularly monitored for implementation of action.
CONTRACTOR shall develop a project specific Right First Time (NAM) Procedure Doc No.
No.SLG-G-000000-016-A1-4 for implementation of NAM process to ensure that the most minor
of issues are identified and addressed prior to the commissioning and start-up activities
thereby providing the platform for attaining a First Class commissioning, start-up, and
operational performance for the project.
NAM addresses the Management of Risks by facilitating controlled mitigations to the known
issues. These design, engineering, procurement, construction, commissioning and start-up
Salalah LPG Project, Oman Rev.D
Doc.No: SLPG-Q-000000-001-A1-4
Title: Project Quality Management Plan Page 29 of 44
risks to project success are recorded within the CONTRACTOR Lessons Learned Database.
Objective areas that have been critical to the success of the NAM process will be identified.
Risks to these objectives will be pro-actively identified, assessed, and addressed during
engineering, procurement, and site implementation.
The approach will be to add value using best practices, apply the CONTRACTOR and COMPANY
lessons learned, and cooperate in the application of flaw mitigation, risk management, and
the resulting improvement of normal work processes.
CONTRACTOR’s Project Management shall conduct a Contract Review in accordance with the
QMS Contract Review Procedure Doc No.SHJ-CC-PRO-F-1096 to ensure that the Project team
clearly understands contract requirements. After review of the Contract documents, the
amendments or variations (if any) will be prepared and followed up by Project Director, as
necessary, during execution phase.
All formal Project correspondence between the CONTRACTOR and the COMPANY shall be as
per Project Coordination/Communication Procedure Doc No. SLPG-G-000000-009-A1-4.
Information and documents received from or issued to COMPANY will be handled, distributed,
filed, reviewed and followed-up by the project management. For all formal correspondence, a
controlled number will be obtained from software - CAPITAL Projects for easy traceability.
Design and Engineering activities will be carried out in CONTRACTOR’s home office and their
Technical Services locations in India as per Engineering Execution Plan Doc No. SLPG-G-
000000-021-A1-4, QMS Design Control Procedure Doc No.PEC-EN-PRO-X-1097 and Contract
requirements under the control of Project Engineering Manager.
Engineering Manager will identify the work scope and responsibilities of the design engineers,
identify the applicable design control procedures and COMPANY requirements. Engineering
deliverables are monitored in CAPITAL Projects (Document control system).
Technical Queries
The process for the management and control of Technical Queries for the Project will be in
accordance with corporate Technical Query and Deviations Procedure PEC-EN-PRO-X-0030. The
Project Engineering Manager is the owner of this process.
CONTRACTOR reviews the Critically Rating of the equipment and materials and determines the
use of resources for inspection, including deployment of Resident Inspectors at manufacturing
facilities.
Where applicable, CONTRACTOR will review the criticality of Equipment and bulk material in
accordance to CONTRACTOR QMS Criticality assessment procedure for Engineering Equipment
Doc No.PEC-EN-PRO-X-0035 and Criticality Rating for Bulk Items Doc No.PEC-EN-PRO-X-10982
respectively.
The design input information received by each discipline will be reviewed and evaluated to
ensure its correctness and the details are adequate to proceed with the designing process.
Transfer of Information within the disciplines is based on QMS Inter Discipline Information
Transfer Procedure Doc No.PEC-EN-PRO-X-0669.
Any clarifications or ambiguous requirements will be resolved through technical queries in line
Salalah LPG Project, Oman Rev.D
Doc.No: SLPG-Q-000000-001-A1-4
Title: Project Quality Management Plan Page 31 of 44
The outputs of the design and development process will be recorded in drawings and
documents suitable for verification. These are reviewed and approved according to QMS
Procedure for Documents Review and Approval Requirements Doc No. PEC-EN-PRO-X-1098 and
submitted to COMPANY as required. All deliverables will be numbered as per the project
Document Control and Numbering Procedure Doc No. SLPG-G-000000-005-A1-4.
Key Reviews
Key Design reviews shall be performed as required in accordance with the procedures referred
therein. Some examples of Key design reviews are HAZOP, 3D Model review, 3D Model HSE
review, HAZID, SIL etc.
Design verification will be carried out on all design deliverables to ensure it:
• Meets the design input requirements specified in the contractual documents;
• Contain or make reference to acceptance criteria, for the relevant products;
• Contain references to applicable COMPANY specifications;
• Define the characteristics of products that are essential to their safe and proper use;
• Provide information for purchasing, testing and construction activities.
Documents having interface or impact on other engineering deliverables will be routed for
inter-discipline checks (IDC) in line with QMS IDC procedure Doc No.PEC-EN-PRO-X-1099. The
Lead Discipline Engineers decide the need for independent design verification including IDC for
a revised engineering deliverable based on the evaluation of the extent of technical changes
and their impact on the overall design.
Software and Spreadsheet Validation in the Engineering is carried out in compliance with QMS
Software and Spread Sheet Validation Procedure Doc No.PEC-EN-PRO-X-0032 to ensure that:
• Accuracy and reliability of software and spreadsheets;
• Reliability of results for the intended purpose.
Design changes or modifications shall be identified by the Discipline Engineer and approved by
the Project Director/Project Engineering Manager in accordance with the QMS Design Change
Notice Procedure Doc No.PEC-EN-PRO-X-06729. The only exception will be “Changes due to two
or more entirely different items that can be captured in single P&IDs DCN if different items are
defined in the Front sheet and the DCN mark-ups within the DCN P&IDS are clearly labelled in
reference to each categorized item”.
The Design Change Notices will be logged in ‘CAPITAL Projects’ and will be monitored in
accordance with the procedure. Revisions to project design documents shall be controlled.
The sourcing of goods and services from SUPPLIERs will be carried out in accordance with
Procurement Execution Plan Doc No. SLPG-G-000000-022-A1-4.
Procurement from stockists may be done based on the type of product and Criticality,
provided sourcing is from Project Approved SUPPLIER/VENDOR List. This will be subjected to
MTC review and additional tests wherever required to meet Project requirements.
Salalah LPG Project, Oman Rev.D
Doc.No: SLPG-Q-000000-001-A1-4
Title: Project Quality Management Plan Page 33 of 44
Requisition is carried out as per Procurement Execution Plan Doc No. SLPG-G-000000-022-A1-4
by Discipline Engineer, reviewed by Discipline Lead Engineer, Buyer/Procurement Engineer
ensures that RFQ’s are adequately defined and contain applicable project and COMPANY
specifications as listed in Appendix 6.10 of the Contract. The SQRF’s which details the Quality
requirements are included in the RFQ.
The Project Procurement Manager will ensure that the purchase packages adequately define
the relevant project requirements and will establish a close working relationship and feedback
system with each SUPPLIER/VENDOR.
Prior to release of the PO/PR, all purchasing data and documents are reviewed by respective
disciplines. The PO/PR will include the Inspection Levels and SUPPLIER/VENDOR Quality
Salalah LPG Project, Oman Rev.D
Doc.No: SLPG-Q-000000-001-A1-4
Title: Project Quality Management Plan Page 34 of 44
The Pre-Production/Pre-Inspection Meeting will be conducted for all Criticality Rating 1 and
CR 2 equipment and materials as per the agenda stated in SQRF.
Expediting activities (Desk & Field) are performed by the Delivery Team after issuance of
LOA/PO to SUPPLIER for delivery of Goods / Services as per Expediting Procedure Doc no. PEC-
PR-PRO-X-0142.
The Project Manager - Delivery and his Team will ensure goods and services are procured from
SUPPLIERs/VENDORs in accordance with the Purchase Order requirements and delivered in
accordance with agreed schedules.
The team will closely monitor on close-out of Purchase Orders in a systematic manner,
ensuring SUPPLIERs/VENDORs have complied with their obligations regarding quality,
verification, cost and delivery, no outstanding work remains, all required documentation has
been prepared, compiled and received as per PO and project specifications.
Shipping Coordinator will perform shipping activities in accordance with the Project
Procurement Execution Plan and the related QMS Logistics Procedure Doc. No. PEC-PR-PRO-X-
0476.
Packing and marking will be in accordance with Packing & Transportation procedures.
Preservation requirements shall be in line with Appendix 6.4 of the Contract.
Verification and inspection activities of purchased products shall be carried out as per
Coordination Procedure for Inspection at SUBCONTRACTOR, VENDPR/SUPPLIER Workshop
Procedure Doc No. SLPG-Q-000000-003-A1-4. SUPPLIER Quality Control procedures shall be
reviewed against project specifications and COMPANY’s requirements. ITPs from SUPPLIERs
will be reviewed based on the Inspection Level and Criticality Rating of each item and
approved by CONTRACTOR and COMPANY.
The following actions will ensure compliance with the purchasing documents:
• Review of VENDOR/SUPPLIER documents by Quality Engineers;
• Pre-inspection meetings (PIM) at SUPPLIER’s/VENDOR’s location;
• Planned inspection and surveillance at SUPPLIER’s/VENDOR’s premises based on the
criticality and inspection level of the equipment and as per agreed ITPs;
• Ensure that no material or equipment shall be released from Sub-SUPPLIER premises to
SUPPLIER’s/VENDOR’s place without inspection;
Salalah LPG Project, Oman Rev.D
Doc.No: SLPG-Q-000000-001-A1-4
Title: Project Quality Management Plan Page 35 of 44
The Inspection Coordination and release process is based on Coordination Procedure for
Inspection at SUBCONTRACTOR, VENODR/SUPPLIER workshops Procedure Doc No. SLPG-Q-
000000-003-A1-4.
Prior to final inspection, all relevant documents will be approved and all Technical Queries,
non-conformances and concessions will be agreed and closed. FAT tests of equipment and
packages will be performed at the SUPPLIER’s/VENDOR’s works prior to final inspection and
release. COMPANY will be notified in advance as per ITP requirements. Once satisfactory
Inspection is completed by assigned Inspector, EPC CONTRACTOR shall issue an Inspection
Release Notice (IRN). COMPANY approval on IRN will be sought before release of equipment for
CR 1 items. If any non-conformance is identified during final Inspection, the IRN will not be
issued unless approved by COMPANY.
CONTRACTOR will monitor the quality of procured items directly using their QC personnel. For
inspection activities at SUPPLIER/VENDOR location, based on geographical area and depending
on the availability of Inspectors, CONTRACTOR will engage the services of external inspection
agency personnel. CV’s of agency personnel will be reviewed before assigning for inspection
and their activities will be monitored by QC Engineers.
Independent verification of the goods and or services being provided will be carried out when
specified in the Contract, or by any applicable regulatory or legislative requirement. This will
provide objective documentary evidence of compliance with Statutory and Regulatory
requirements.
The Delivery Team will ensure all quality records are legible, correctly identified, readily
retrievable and protected to prevent damage, loss or deterioration. Documents will be
retained for a period defined by COMPANY or within legislative and or regulatory
requirements. Where there is a conflict between any of these requirements, the longest
retention time for a particular record will be applied.
The format, content, compilation and methods for MDR documentation deliverables are stated
in SQRF which is attached to RFQs. All MDRs shall be reviewed by CONTRACTOR before
submission to COMPANY.
Salalah LPG Project, Oman Rev.D
Doc.No: SLPG-Q-000000-001-A1-4
Title: Project Quality Management Plan Page 36 of 44
COMPANY's intellectual property and personnel data shall be identified, verified, stored,
protected, controlled and maintained adequately by the CONTRACTOR, while under the
CONTRACTOR’s responsibility.
COMPANY supplied documents will be treated as COMPANY property and applicable controls
shall be exercised as per Document Control Procedure and security is enforced through
CONTRACTOR’s “Code of Conduct” & Ethical, Social and Regulatory Risk Policy.
8. SUBCONTRACTOR MANAGEMENT
Subcontracting activities will be conducted in accordance with the Subcontracting
Management procedure Doc No. SLPG-G-000000-010-A1-4. Construction Manager, Contracts
Manager in conjunction with the Project Director will be responsible for following activities:
• Identifying activities to be subcontracted;
• Pre-qualifying potential SUBCONTRACTORs;
• Conducting a pre-assessment or qualification audit on proposed SUBCONTRACTOR
premises if needed;
• Review of all quality and other requirements prior to issue of enquiries;
• Issuing enquiries;
• Carrying out technical and commercial evaluations;
• Proposing the selected SUBCONTRACTOR for COMPANY approval;
• Preparing subcontract agreements and obtaining signatures;
• Maintaining Subcontract Schedule, monitoring and controlling these activities.
The Construction Manager will monitor the scope of supply of subcontracted works at site. The
Site Quality Manager will ensure implementation of all quality requirements, identified
through review of SUBCONTRACTOR quality submissions, audits, surveillance and inspections as
per approved Inspection and Test Plans.
9. CONSTRUCTION
CONTRACTOR will be responsible to carry out the construction activities in accordance with
the Construction Execution Plan Doc No. SLPG-G-000000-011-A1-4. The Site Quality Manager
will monitor implementation of all quality requirements at site.
CONTRACTOR will use own inspectors or agency personnel for inspection activities during
construction. All QC Inspection personnel CV’s and qualifications shall be submitted to
COMPANY for review and approval. Effectiveness of inspection and surveillance will be
enhanced by assigning qualified and specialized QC Inspectors.
Salalah LPG Project, Oman Rev.D
Doc.No: SLPG-Q-000000-001-A1-4
Title: Project Quality Management Plan Page 37 of 44
The Site Quality Manager shall be delegated the clear power and immediate access to
Contractor’s senior management to stop any works that are nonconforming. Weekly Quality
Team Meetings shall be held at site, COMPANY Quality Representatives shall be invited, in
order COMPANY and CONTRACTOR personnel are updated about all QC matters and non-
conformances.
Inspection and surveillance during the Construction phase shall be enhanced by assigning
qualified and specialised QC Inspectors in different disciplines and by taking the following
measures:
• The inspection and testing requirements shall be detailed in the Inspection and Test
Plans for each process, indicating which record/verification document is produced for
each stage;
• CONTRACTOR’s intervention points shall be marked against each activity/stage in the
Inspection and Test Plans during the document approval stage to establish the QC
involvement;
• Detailed QC procedures shall be developed for all critical processes, also considering
the Lessons Learned from previous projects;
• SUBCONTRACTOR staff shall be provided with training and/or awareness on handling
special material and processes involved in the Project;
• All QC activities and their history/records shall be compiled on a database referencing
the ITP/QC Procedure/Certification so that the status can be generated at any time.
Primary control of this function will be Petro-PCS;
• All critical processes shall be continuously monitored until the process performance is
satisfactory to achieve project quality objectives;
• Site Surveillance.
CONTRACTOR’s Construction Engineer shall be responsible for the overall execution of the
work and ensuring that all installation to an acceptable standard of workmanship and in
accordance with latest revision of the applicable drawings and specifications as well as making
request for inspection (RFI) to Quality Department at each stage of work as per the applicable
ITP requirements. He shall ensure the work/ activity is ready for inspection before raising the
RFI.
CONTRACTOR’s Construction Site QC Engineer/QC Inspector shall be responsible for ensuring
that all inspections and tests are witnessed based on approved ITP, recorded on applicable ITR
and uploaded into Petro PCS system in a timely manner.
CONTRACTOR shall provide a complete set of Petro-PCS Inspection and Test Report (ITR)
formats on a discipline and system basis for review and approval by COMPANY prior to
commencing construction activities. (Prior to commissioning and testing completed ITRs will
Salalah LPG Project, Oman Rev.D
Doc.No: SLPG-Q-000000-001-A1-4
Title: Project Quality Management Plan Page 38 of 44
be submitted in the Test Packs). These ITR forms shall be referenced on SUBCONTRACTORs
ITPs against the relevant work activities. All completed ITRs shall be cross-referenced to the
applicable Project System.
QCPs shall be developed by CONTRACTOR and SUBCONTRACTORs to identify the activities that
need to be monitored and controlled for each discipline based on the scope of work. QCPs of
SUBCONTRACTORs will be reviewed and approved by CONTRACTOR/COMPANY before
implementation.
ITPs shall be prepared for all construction work on a discipline basis and a list of anticipated
ITPs will be included as an addendum to each of the SUBCONTRACTOR’s Project Quality Plans.
ITP format shall be as per Appendix 6.2 of Contract document. Inspection Test Plans of
SUBCONTRACTOR will be reviewed and approved by CONTRACTOR/COMPANY before
implementation.
The site quality procedures shall include the strategy for controlling the dimensions of pipe
spools/ structures, as well as all field installations. These requirements may be incorporated
into CONTRACTOR/SUBCONTRACTOR’s ITPs as applicable.
All Procedures and Personnel Qualification of special processes as indicated in Appendix 6.3
shall be submitted for review and/or approval prior to the start of WORK.
The identification and traceability system will be applied for the following:
• Pipes, valves, fittings, welding consumables;
• Welded joints and welders;
• Other permanent items / equipment incorporated in the construction;
• Inspection, test and quality verification status;
Salalah LPG Project, Oman Rev.D
Doc.No: SLPG-Q-000000-001-A1-4
Title: Project Quality Management Plan Page 39 of 44
Products and construction activities will be identified during all phases of product realisation
by means of legible and durable markings maintained from initial receipt to final destination
and/or by using relevant follow-up documentation.
The identification of items / equipment, material certificates, ITP and all test records will be
maintained by the project. Material certificates, construction welding book and inspection
reports will be the supporting elements for identification and traceability of products.
The Construction Manager will ensure that appropriate facilities are made available for
handling, packaging, storage and preservation of products. The Material Control Manager will
be responsible for carrying out handling and storage activities. Any non-conforming conditions
shall be documented.
The Construction Superintendents shall ensure that appropriate measuring instruments are
procured, and they are calibrated as per the requirement. The Site Quality Manager shall
ensure implementation of the calibration and control processes is in accordance with QMS
Control of Measuring and Test Equipment Procedure Doc No. PEC-QU-PRO-X-11152. The Site
Quality Manager ensures that measuring and test equipment log maintained and monitor their
calibration status. The Test equipment user shall ensure that appropriate test equipment is
selected and used correctly.
Mechanical Completion Certificate will be produced subsystem wise and at end before
commissioning a single certificate will be issued.
The Method Statements and Procedures for Pre-commissioning will include those for individual
elements of the systems, which will be progressively incorporated into subsystems /systems.
ITR’s will be completed and punch lists prepared and agreed by Construction and
Commissioning. A Project specific procedure for Punch Listing and Handover Doc No. SLPG-G-
000000-031-A1-4 will be developed. As-built drawings by sub-system/system will be marked to
reflect the As-built condition at time of Mechanical Completion.
PetroPCS, Petrofac’ s Project Completion System, a project tool will be used for tracking and
controlling documentation/testing/inspection from Construction, Mechanical Completion, Pre-
commissioning to Commissioning including Punch listing, Preservation etc., till handover of the
project
Preservation logs will be maintained for all activities performed up to Mechanical Completion.
10.2 COMMISSIONING
CONTRACTOR will develop Start-Up and Systems Turnover Sequence Plan Doc No. SLPG-M-
000000-008-A1-4 based on Contract requirement and accordingly executes the scope
throughout Commissioning and Start-Up, which may include the support of
SUPPLIER’s/VENDOR’s as applicable.
The Project team will manage the verification/testing scope of work from construction
through commissioning, handover and start-up. Systems/sub-systems will be verified for
functional performance using PetroPCS and documentation required for handover and
acceptance certification will be generated.
The final documentation from Commissioning will be the Ready for Start-Up (RFSU) Dossiers.
CONTRACTOR will complete the documentation pertaining to commissioning activities in a
RFSU dossier arranged by System/Subsystem.
Salalah LPG Project, Oman Rev.D
Doc.No: SLPG-Q-000000-001-A1-4
Title: Project Quality Management Plan Page 41 of 44
The Project Director will ensure that the Process Owners will establish Performance
Indicators, monitor their performance, and take appropriate actions for improvement.
The Project Key performance indicators are included in Project Execution Plan Doc No. SLPG-
G-000000-008-A1-4.
11.2.1 AUDITS
The Project Quality Manager/ Senior QA Engineer shall develop overall Audit schedule covering
EPCC activities and implement internal and external (SUPPLIER/VENDOR/SUBCONTRACTOR)
audits using trained and certified auditors. Audits will be performed in accordance with the
Project Quality Internal and External Audit Procedure Doc No. SLPG-Q-000000-004-A1-4.
Internally approved Audit report will be forwarded to the COMPANY within 10 working days
after the conclusion of the audit.
Any Non-Conformances shall be resolved to the satisfaction of CONTRACTOR & COMPANY and
records shall be maintained by the Project Quality Manager/Sr.QA Engineer. Sr.QA Engineer
shall carry out follow-up actions, distribute records and track all relevant actions till their
Salalah LPG Project, Oman Rev.D
Doc.No: SLPG-Q-000000-001-A1-4
Title: Project Quality Management Plan Page 42 of 44
close out.
All processes and relevant procedures will be monitored and/or measured by the Process
Owners. The results of monitoring will be recorded in the relevant reports.
Depending on the nature of the product, monitoring and measurement will be carried out:
Test Procedures shall be developed and implemented by the SUBCONTRACTOR for their scope
of work. The Quality Inspectors and Construction Superintendents will carry out the required
in-process inspections and surveillances as per agreed ITPs. Products will only be released
when the appropriate inspections and tests, are completed.
The final inspection and testing includes hydrostatic testing, commissioning and start-up
testing as required by the Contract.
CONTRACTOR shall raise NCR for any non-conformance identified. Identification, recording and
segregation of non-conforming product shall be exercised in accordance with contractual
requirements and CONTRACTOR Project specific Non Conformance Control Procedure (Doc No.
Non-Conformance Control Procedure Doc No. SLPG-Q-000000-008-A1-4.
COMPANY will be notified of all NCRs including SUPPLIER NCRs and closeout will be verified by
the COMPANY.
When non-conformity is detected after delivery, the consequences will be reviewed and the
necessary actions carried out by the Project Quality Manager and Project Director.
The rejected products shall be removed from construction site utilisation points. All the
repaired and reworked products shall be re-inspected.
COMPANY may operate their own non-conformance control system. When a COMPANY non-
conformance report is received, CONTRACTOR will acknowledge receipt by signature on the
original non-conformance report form and prepare a corrective action plan as per the contract
requirements.
The following data generated by the Project Management, Engineering, Procurement and
Construction Departments shall be subject to analysis as part of Management review.
The results will be presented during the Project Management review for determination of the
suitability, effectiveness and adequacy of the Project QMS.
11.5 IMPROVEMENT
The Project Quality Manager shall review and analyse the following elements for improvement
of the effectiveness of the Project QMS:
a) Non-conformance Control;
b) Key performance indicators;
c) Internal and external audit results;
Salalah LPG Project, Oman Rev.D
Doc.No: SLPG-Q-000000-001-A1-4
Title: Project Quality Management Plan Page 44 of 44
d) Analysis of data;
e) Corrective Actions;
f) Project Management review reports;
g) Lessons Learned.
CONTRACTOR will share to the COMPANY the result of the analysis of the above.
Lessons Learned (LL) from previous projects will be analysed and those considered relevant to
the project shall be captured and highlighted to the relevant discipline engineers to help
prevent a recurrence. LLs from previous Projects are logged in Quality Management system in
accordance with the Project QMS Lessons Learned Procedure Doc No. PEC-QU-PRO-X-0065. A
Project specific LL Procedure Doc. No. SLPG-G-000000-017-A1-4 has been developed.
Corrective actions will be implemented to reduce or eliminate the causes of identified non-
conformities. In order to prevent its recurrence, below steps will be followed by the process
owners.
• Review non-conformities and COMPANY complaints(if any) for the processes executed;
• Determine the causes of non-conformities and the appropriate corrective actions;
• Implement the corrective actions needed and recording of the results.
The impact or importance of the problem encountered will be considered during the
evaluation of the corrective actions as per Non-Conformance Control Procedure Doc No. SLPG-
Q-000000-008-A1-4.
12. ATTACHMENTS
Attachment – 1: PROJECT QUALITY POLICY
Attachment – 2: LIST OF DOCUMENTS REFERRED IN PROJECT QUALITY MANAGEMENT PLAN
Attachment – 3: PROJECT AUDIT SCHEDULE (Sample)
Attachment - 4: GAP ANALAYSIS OF ISO 29001:2011 and PQMP
Attachment - 5: PROJECT SPECIFIC QUALITY ORGANIZATION CHART
1.0 LIST OF PROCEDURES REFERRED IN THE PQMP Formatted: Font: (Default) Trebuchet MS, 12 pt, Bold, All
caps, Not Highlight
IDC procedure
29 7.3.5 PEC-EN-PRO-X-1099
Software and Spread sheet Validation
30 7.3.6.1 PEC-EN-PRO-X-0032
Design Change Notice
31 7.3.7 PEC-EN-PRO-X-06729
Procurement Execution Plan
32 7.4 SLPG-G-000000-022-A1-4
Project Procurement plan
33 7.4.1 SLPG-G-000000-022-A1-4
Supplier Quality Management System
34 7.4.1 Manual PEC-QU-PLM-X-12419
Logistics Procedure
36 7.4.6 PEC-PR-PRO-X-0476
7.4.7 and SLPG-Q-000000-003-A1-4
37 Inspection Coordination Procedure
7.4.7.1
SLPG-G-000000-010-A1-4
38 8.0 Subcontracting Management Procedure
Construction Execution Plan
39 9.1 SLPG-G-000000-011-A1-4
Material identification and Traceability
40 9.6 procedure SLPG-Q-000000-011-A1-4
Pre-commissioning/Commissioning
44 10.1 SLPG-M-000000-002-A1-4
Strategy & Execution Plan
Procedure for Punch listing and
45 10.1 SLPG-G-000000-031-A1-4
Handover
Start-Up and Systems Turnover SLPG-M-000000-008-A1-4
46 10.2
Sequence Plan
PEC-QU-PRO-X-1086
47 11.2.1 Internal/External Customer Feedback
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Project Management
PROJECT MANAGEMENT (INCLUDING
PROJECT CONTROLS, QUALITY,
CONTRACTS, INTERFACE ETC)
Interface Management
Project control
Quality Management
Engineering Disciplines
Integrity Assurance
e.g. -DELHI)
Requisitions/TBE
Deviations
Interface Control
Design Reviews
Procurement Management
Expediting Process
Logistics
& LOGISTIC)
Local Purchasing
INTERFACE ETC)
Project Controls
Quality Management
(HO)
PetroPCS
COMPANY
Legends: P O R
1 This schedule shall be monitored, updated and submitted to COMPANY along with Quality Report on monthly basis . Planned Audits Completed Audits Rescheduled Audits U Unplanned Audits
2 All applicable elements of QMS and Project Procedures will be audited for each core process.
C
3 The audits will be conducted in accordance with the Project Specific Auditing Procedure. X Cancelled Audits TBA Schedule to be advised Closed Audits
13 Clause 7.4.3.1 Verification of Purchased product Clause 7.4.7 Project Specific Inspection
Coordination Procedure Doc
CONTRACTOR verifies all purchased product as per Inspection and Testing
No. SLPG-Q-000000-003-A1-
Management Procedure (Procurement) and Control of SUPPLIER outstanding
4 refers.
punch list procedures.
14 Clause 7.5.1.1 Control of Production and Service Provision Clause 7.4.7.1
The organization shall establish control features that describe the control of
production and service activities performed.
15 Clause 7.5.1.2 Process Controls Clause 9.4
Process controls shall be documented in Inspection Test Plans, Checklists and
shall include requirements for verifying compliance with Quality Plans, control
features, and reference standards/codes. The inspection and test plan or
equivalent shall include or reference instructions, acceptance criteria for
processes, tests, inspections, and CONTRACTOR/ COMPANY inspection hold,
surveillance or witness points.
16 Clause 7.5.2.1 Validation of Processes for Production and Service Provision Clause 9.6
In case of welding, the Welder/Operator and Welding Procedure Specification
may be simultaneously qualified. Special validation requests made by the
COMPANY shall be taken into consideration. Procedures for special processes like
welding, painting / coating, PWHT, NDT, concreting, cable joining, CRA welding,
Dimensional Control etc., shall be qualified as required.
17 Clause 7.5.3.1 Identification and Traceability Clause 9.7 Project Specific Material
Identification and
The organization shall establish control features (see 3.1.4) for identification and
Traceability Procedure Doc
traceability of the product by
No. SLPG-Q-000000-011-A1-
suitable means from receipt and during all stages of production, delivery and
24 Clause 8.2.4.1 Monitoring and Measurement of Product Clause 7.4.7.1 Project Specific Inspection
Coordination Procedure Doc
The Organization shall establish control features (see 3.1.4) to monitor and
No. SLPG-Q-000000-003-A1-
measure the characteristics of the product.
4 refers.
25 Clause 8.2.4.2 Acceptance Inspection Clause 7.4.7.1 Project Specific Inspection
Coordination Procedure Doc
Personnel other than the persons who performed or directly supervised the
No. SLPG-Q-000000-003-A1-
production of the materials or products shall perform final acceptance and
4 refers.
product release.
26 Clause 8.3.1 Release or Acceptance of Nonconforming Product Clause 11.3 Project Specific Non-
Conformance Control
The process of evaluation, release and acceptance of nonconforming product is
Procedure Doc No. SLPG-Q-
addressed in Project Non-conformance procedure.
000000-008-A1-4 refers.
27 8.3.2 Field Nonconformity Analysis Clause 11.3 Project Specific Non-
Conformance Control
The documented procedure for nonconforming product shall include
Procedure Doc No, SLPG-Q-
requirements for identifying, documenting and reporting incidents of field
000000-008-A1-4 refers.
nonconformities (see 3.1.9) or product failures. The documented procedure shall
ensure the analysis of field nonconformities, provided the product or
documented evidence supporting the nonconformity is available to facilitate the
determination of the cause.
28 Clause 7.1.3 Field Nonconformity Analysis Clause 11.3 Project Specific Non-
Conformance Control
The CONTRACTOR’s Project NCR procedure address field nonconformities and
Procedure Doc No.SLPG-Q-
root cause analysis of the NC.
000000-008-A1-4 refers.
Krishna Katkam
Location Mob 18.04.2017
HO Demob TBA
Agency Inspectors
Site Quality Team
-
Refer to Site Quality
Location Mob NA
Organogram
HO Demob NA Location Mob NA
HO Demob NA