Concrete Factors
Manpower Rate
Preliminaries
Concreting Works
Concrete Admix
Rebars
Masonry Works
Elevator
Embankment
Home
2.STRUCTURAL BACKFILL
By hand 5 MH/M3
By machine 2 MH/M3
3.TRENCHING
By hand 6 MH/M3
By machine 0.5 MH/M3
EXCAVATION- MANUAL
Common earth 8 MH/M3
Loam of sand 1.31 MH/M3
Clay or heavy soil 1.64 MH/M3
Rock 2.63 MH/M3
EXCAVATION- MECHANICAL
Common earth 6.67 MH/M3
Rock with jack hammer 16.67 MH/M3
BACKFILLING
Common manual 0.82 MH/M3
Gravel fill manual 5 MH/M3
TRENCHING & BACFILLING OF UNDERGROUND PIPING USING EXCAVATION MATLS MANUAL FROM:
0 – 2m Depth 1.25 MH/LM
2 – 3m Depth 1.67 MH/LM
3 – 4m Depth 2.5 MH/LM
4 – 5m Depth 3.33 MH/LM
Placing binder gravel 0.11 MH/M3
Escombro backfilling 0.21 MH/M3
Spreading,tamping & grading 0.48 MH/M2
Mechanical compaction, plate compaction 0.06 MH/M3
CONCRETE WORKS
4.CONCRETE WORKS
Grade members
Formworks 2.54 MH/M2
Concreting 8.54 MH/M3
Rebar 0.07 MH/kg
Finishing 0.4 MH/M2
Suspended members
Formworks 3.28 MH/M2
Concreting 16.7 MH/M3
Rebar 0.08 MH/kg
Finishing 0.8 MH/M2
Embeded metal 0.27 MH/kg
Water proofing 1.82 MH/M2
Joint filler 0.3 MH/lLm
PLACING CONCRETE
Slab on Fill 5 MH/M3
Slip Form 25 MH/M3
Floor Finish Unhardened 1 MH/M3
Concrete finished hardened 1.43 MH/M3
REBAR WORKS
Ground floor installation 0.07 MH/M3
Upper floor installation 0.08 MH/M3
Fabrication 0.1 MH/M3
Mixing manual 16 MH/M3
Mixing machine 1.8 MH/M3
MORE THAN 1.8 M3 POUR
Chute from truck 7 MH/M3
Crane & bucket 14 MH/M3
Wheeling 27 MH/M3
Finishing 2.8 MH/M3
FORMWORKS & CARPENTRY WORKS
FORM WORKS INSTALLATION
Wall on ground 2 MH/M2
Wall above ground 2.35 MH/M2
Beams 3.08 MH/M2
Columns 2.35 MH/M2
Suspended slab
Suspended slab 0 – 18″ 1.67 MH/M2
Suspended slab 10 – 36″ up 3.33 MH/M2
Elevated & shored slab forming
Forming only 8.6 MH/M2
Forming & Shoring 11 MH/M2
Wood wall & Partition 0.5 MH/M2
STRIPPING OF FORMS
Wall on ground 0.25 MH/M2
Wall above 10″ 1.29 MH/M2
Beams 1.03 MH/M2
Columns 0.85 MH/M2
Suspended slab
Suspended slab 0 – 18″ 0.83 MH/M2
Suspended slab 10 – 36″ up 1.08 MH/M2
Elevated & shored slab forming – strip of f 3.5 MH/M2
Floor slab at grade – strip of forms 2.8 MH/M2
ARCHITECTURAL SPECIALTIES
DOORS
Wooden 2.37 MH/M2
Steel 7.64 MH/M2
Aluminum 8.07 MH/M2
Cyclone wire 7.64 MH/M2
WINDOWS
Glass 3.23 MH/M2
Louver 4.63 MH/M2
Steel 32.29 MH/M2
PARTITIONS
single wall 2.48 MH/M2
Wooden wall 3.44 MH/M2
Wooden Louver 3.44 MH/M2
cyclone Louver 5.38 MH/M2
PAINTING ( 3 coats )
Equipment 0.24 MH/f2
Pipes 0.3 MH/f2
Miscillaneous 0.24 MH/f2
This rate guide should help any Filipinos on how much should they rate construction laborers. Updated as of December 2018.
note:
as of December 2018.
Home
These prices are calculated using cost-averaging formula. Some locations’ costs may be more expensive compared to the other
Home
expensive compared to the other. We simplified it this way for easy price updating.
Concrete Admixtures and Curing Materials
National Capital Region – (3rd Quarter of 2018)
Masonry Works
Concrete Hollow Blocks (CHB) 4″ pc 10.00
Concrete Hollow Blocks (CHB) 6″ pc 16.00
Portland Cement, 40 kg. bag 265.95
Washed sand cu.m. 1,165.00
10 mm. Dia. x 6.0 M. DSB pc. 156.20
Tie Wire #16 kg. 65.00
Stone Masonry
Cement bag 260
Sand cu.m. 1,232.05
Gravel Fill cu.m. 1,207.05
Weep Holes (PVC) Lm. 228.33
Filter Cloth sq.m. 280
Boulders cu.m. 1,282.05
Screened Sand cu.m. 1,521.00
Screened Gravel cu.m. 1,581.00
ELEVATOR WORKS, TESTING & COMMISSIONING
Description Qty Unit Amount (Php)
Installation of Scaffolding 1 lot 17,503.00
Hoisting 1 lot 26,254.50
Template Setting 1 lot 43,757.50
Marking and Boring of Holes 1 lot 26,254.50
Bracket Setting 1 lot 35,006.00
Rail Setting 1 lot 43,757.50
Sill/Jamb Installation 1 lot 52,509.00
Floor Indicator/Call buttons 1 lot 8,751.50
Machine Room Equipment Setting 1 lot 43,757.50
Machine Room Piping 1 lot 17,503.00
Hoist-way Piping 1 lot 43,757.50
Landing Door Assembly 1 lot 35,006.00
Car Assembly 1 lot 61,260.50
Travelling Cable Lay-out 1 lot 21,878.75
CWT Assembly 1 lot 21,878.75
Lay-out of Ropes 1 lot 26,254.50
Wiring (Machine Room/Hoist-way) 1 lot 70,012.00
Initial Test 1 lot 52,509.00
Slow Speed test (Start up) 1 lot 26,254.50
Load Test 1 lot 13,127.25
Drop Test 1 lot 13,127.25
Buffer Test 1 lot 8,751.50
Plate Setting/Slow Switch Installation 1 lot 43,757.50
Rubber Block Setting 1 lot 17,503.00
High Speed Testing 1 lot 61,260.50
Standard/Special Feature Test 1 lot 26,254.50
Others 1 lot 17,503.00
Total 875,150.00
Embankment (per cubic meter)
Common Borrow 384.40
Selected Borrow 392.40
Mixed Sand & Gravel 585.11
Rock 602.56
Aggregate Subbase Course
Aggregate Subbase Course Material 818.13
Aggregate Base Course 934.89
Crushed Grading A 839.13
Uncrushed Grading A 926.00
Crushed Grading B 831.63
Uncrushed Grading B 837.00
Blended Weathered Limestone and Crush Stone 818.22
Filler Materials 401.00
Crushed Aggregate Base (per cubic meter)
Crushed Grading A 921.63
Crushed Grading B 875.43
Lime Stabilized Road Mx Base Course (per cubic meter)
Lime Stabilized Mixed Soil Aggregate Base Course Cru 693.75
Lime Stabilized Mixed Soil Aggregate Base Course Cru 662.78
Lime Stabilized Mixed Soil Aggregate Base Course Unc 670.00
Lime Stabilized Mixed Soil Aggregate Base Course Unc 641.11
Aggregate Surface Course (per cubic meter)
Crushed Grading A 878.22
Crushed Grading B 864.33
Crushed Grading C 884.75
Crushed Grading D 856.38
Uncrushed Grading A 826.13
Uncrushed Grading B 817.38
Uncrushed Grading C 812.63
Uncrushed Grading D 793.25
Ceiling Vent:
1″x1″x10′ s4s Tanguile or its equivalent pc 65.00
1″x3″x8′ s4s Tanguile or its equivalent pc 65.00
Insect Sreen sht 140.00
0.8mm thk. -12mm x 38mm x 5.00m Double Furring pcs 112.56
0.8mm thk. -12mm x 38mm x 5.00m Single Furring pcs 102.56
0.2mm thk-20mm x 20mm x 2.44m Wall Angle pcs. 36.50
Rod suspension hanger w/adjustment spring set 65.00
Pre-formed wire clip set 3.03
Toks Srew pcs. 0.70
Truss Works
ELECTRICAL WORKS
Pipe and Fitting
20mmdia UPVC pipe pcs 85.00
20mmdia RSC conduit pcs 216.00
20mmdia RSC coupling pcs 20.00
20mmdia UPVC coupling pcs 5.00
20mmdia UPVC adoptor pcs 7.50
20mm dia. Locknut& bushing pcs 8.00
20mm dia. RSC Locknut& bushing pcs 14.30
Boxes and Gutter
Junction box depth type,metal gauge 16 w/ cover pcs 25.00
Utility box depth type, metal gauge 16 w/cover pcs 25.00
4×4 square box depth, metal gauge 16 w/cover pcs 50.00
Miscellaneous and Consumables
Electrical tape big pcs. 40.00
Rubber tape big pcs. 90.00
Solvent cement 100cc pcs. 240.00
G.I. Wire No. 12 kls. 70.00
Concrete nail no.3 kls. 120.00
CWN no.3 kls. 70.00
Entrance cap pcs. 35.00
Terminal Lugs lot 600.00
Red Led Paint pcs. 429.00
Cable Tie pc 1.00
Secondary Rack pc 540.00
Black Paint gal 610.00
Wires
8.0mm2 THHN m 43.33
5.5mm2 THHN m 36.59
3.5mm2 THHN m 25.00
2.0mm2 THHN m 23.33
Wiring Devices
1-gang Switch, 10A, 240V set 110.00
2-gang switch, 10A, 240V set 140.00
2-gang 3 way switch, 10A, 240V set 240.00
1-gang Convenince Outlet, 10A, 240V set 250.00
2-gang Convenience Outlet, 3 prong 10A, 240V set 351.00
Lighting Fixtures
24 Watts light bulb set 285.00
1-18watts Compact flourescent lighting fixtures set 680.00
keyless type,porcelain receptacle
2-36 watts ,220v,Flourescent (box type) set 1,200.00
1 x 18, 230V, Compact Flourescent (Keyless Type set 680.00
Power Load Center Switch Gear and Panel Board
Main :40AT/50AF,1PCB,240V,18KAIC, BOLT-ON set 12,500.00
Branches
2-15AT/50AF,1PCB,240V,10KAIC,,BOLT-ON PC 315.70
3-20AT/50AF,1PCB,240V,10KAIC,,BOLT-ON PC 315.70
Plumbing and Sanitary Works
For reference, 20 sq.m normally consumes a gallon of paint. All amount in Php.
Concreting Works 2018
Concrete
Soil Poisoning – Termicide Liter 325.00
Gravel cu.m 1,310.00
Wash Sand cu.m 1,435.00
Portland Cement, 40kg Bag 259.00
Pozzolan Cement, 40kg Bag 261.00
Steel Bars
10mm Diameter Deformed Bars pc 156.00
12mm Diameter Deformed Bars pc 221.00
16mm Diameter Deformed Bars pc 392.00
20mm Diameter Deformed Bars pc 642.00
#16 G.I. Tie Wire kg 16.00
Formworks
2 x 3 x 10′ Coco lumber pc 270.00
2 x 4 x 10 Coco lumber pc 270.00
1/2″ x 4′ x 8′ Plywood pc 656.00
6mm thk. Lawanit board pc 201.00
6mm thk. Ordinary Plywood pc 323.00
1″x2″x8′ Wood pc 75.00
2″x2″x8′ Wood pc 95.00
2″x3″x8′ Wood pc 105.00
2″x4″x8′ Wood pc 125.00
Construction Heavy Equipment and Engineering Survey Equipment Price List
4th Quarter of 2018