Sei sulla pagina 1di 41

Productivity Ratio

Concrete Factors
Manpower Rate
Preliminaries
Concreting Works
Concrete Admix
Rebars
Masonry Works
Elevator
Embankment
Home

PHILIPPINE PRODUCTIVITY RATIOS

DESCRIPTION MANHOUR/UNIT UNIT


1.STRUCTURAL EXCAVATION
Common excavation
Hand 6 MH/M3
Machine 0.5 MH/M3
Rock excavation 8 MH/M3
Hauling of spoils 1 MH/M3

2.STRUCTURAL BACKFILL
By hand 5 MH/M3
By machine 2 MH/M3

3.TRENCHING
By hand 6 MH/M3
By machine 0.5 MH/M3

EXCAVATION- MANUAL
Common earth 8 MH/M3
Loam of sand 1.31 MH/M3
Clay or heavy soil 1.64 MH/M3
Rock 2.63 MH/M3

EXCAVATION- MECHANICAL
Common earth 6.67 MH/M3
Rock with jack hammer 16.67 MH/M3
BACKFILLING
Common manual 0.82 MH/M3
Gravel fill manual 5 MH/M3

TRENCHING & BACFILLING OF UNDERGROUND PIPING USING EXCAVATION MATLS MANUAL FROM:
0 – 2m Depth 1.25 MH/LM
2 – 3m Depth 1.67 MH/LM
3 – 4m Depth 2.5 MH/LM
4 – 5m Depth 3.33 MH/LM
Placing binder gravel 0.11 MH/M3
Escombro backfilling 0.21 MH/M3
Spreading,tamping & grading 0.48 MH/M2
Mechanical compaction, plate compaction 0.06 MH/M3

MANUAL CLEARING & GRUBBING


Clearing under growth & trees – 12″ 0.05 MH/M2
Clearing under growth & shrubs 0.03 MH/M2
Disposal of soil 1.69 MH/M3
Hauling of soil 1 MH/M3
Gravel fill 2.07 MH/M3

EXCAVATION – CRANE & CLAMPSHELL


With 8 men & 2 carpenters 1.07 MH/M3

5.ROOFING AND SIDING


Roofing
Metallic 0.97 MH/m2
Non-Metallic 1.51 MH/m2
Siding
Metallic 1.29 MH/m2
Non-Metallic 1.51 MH/m2

CONCRETE WORKS
4.CONCRETE WORKS
Grade members
Formworks 2.54 MH/M2
Concreting 8.54 MH/M3
Rebar 0.07 MH/kg
Finishing 0.4 MH/M2
Suspended members
Formworks 3.28 MH/M2
Concreting 16.7 MH/M3
Rebar 0.08 MH/kg
Finishing 0.8 MH/M2
Embeded metal 0.27 MH/kg
Water proofing 1.82 MH/M2
Joint filler 0.3 MH/lLm

PLACING CONCRETE
Slab on Fill 5 MH/M3
Slip Form 25 MH/M3
Floor Finish Unhardened 1 MH/M3
Concrete finished hardened 1.43 MH/M3

REBAR WORKS
Ground floor installation 0.07 MH/M3
Upper floor installation 0.08 MH/M3
Fabrication 0.1 MH/M3
Mixing manual 16 MH/M3
Mixing machine 1.8 MH/M3
MORE THAN 1.8 M3 POUR
Chute from truck 7 MH/M3
Crane & bucket 14 MH/M3
Wheeling 27 MH/M3
Finishing 2.8 MH/M3
FORMWORKS & CARPENTRY WORKS
FORM WORKS INSTALLATION
Wall on ground 2 MH/M2
Wall above ground 2.35 MH/M2
Beams 3.08 MH/M2
Columns 2.35 MH/M2
Suspended slab
Suspended slab 0 – 18″ 1.67 MH/M2
Suspended slab 10 – 36″ up 3.33 MH/M2
Elevated & shored slab forming
Forming only 8.6 MH/M2
Forming & Shoring 11 MH/M2
Wood wall & Partition 0.5 MH/M2

FORM WORKS FABRICATION


Form works fabrication 1 MH/M2

STRIPPING OF FORMS
Wall on ground 0.25 MH/M2
Wall above 10″ 1.29 MH/M2
Beams 1.03 MH/M2
Columns 0.85 MH/M2
Suspended slab
Suspended slab 0 – 18″ 0.83 MH/M2
Suspended slab 10 – 36″ up 1.08 MH/M2
Elevated & shored slab forming – strip of f 3.5 MH/M2
Floor slab at grade – strip of forms 2.8 MH/M2

INSTALLATION OF CARPENTRY WORKS


Plywood partition 1 MH/PC
T & G Flooring and Siding 0.14 MH/B.F.
Ceiling & frame work 0.36 MH/B.F.
Siding frame work 0.27 MH/B.F.
Flooring framing 0.97 MH/B.F.
Wooden post errection 0.43 MH/B.F.
Truss Fabrication 0.35 MH/B.F.
Truss Installation 0.8 MH/B.F.
Girt Installation 0.21 MH/B.F.
Plates Installation 0.13 MH/B.F.
Purlins Installation 0.27 MH/B.F.
Fascia board Installation 0.46 MH/B.F.
1/4″ or 3/4″ thk. plywood
Cutting by manual 1 MH/PC
Assembly 0.42 MH/M2

ARCHITECTURAL SPECIALTIES
DOORS
Wooden 2.37 MH/M2
Steel 7.64 MH/M2
Aluminum 8.07 MH/M2
Cyclone wire 7.64 MH/M2

WINDOWS
Glass 3.23 MH/M2
Louver 4.63 MH/M2
Steel 32.29 MH/M2

PARTITIONS
single wall 2.48 MH/M2
Wooden wall 3.44 MH/M2
Wooden Louver 3.44 MH/M2
cyclone Louver 5.38 MH/M2

PAINTING ( 3 coats )
Equipment 0.24 MH/f2
Pipes 0.3 MH/f2
Miscillaneous 0.24 MH/f2

STRUCTURAL STEEL WORKS


7. STRUCTURAL STEEL
Fabrication
Light 110-130 MH/MT
Heavy 60-90 MH/MT
Errection
Light 70-100 MH/MT
Heavy 40-60 MH/MT

WELDING ( one pass only )


1- Welder and 1- Helper ( 16 total mh ) 40-50 Lf/day
G.1 STRUCTURAL STEEL
Fabrication
Heavy weight 50-90 MH/MT
Light weight 100-125 MH/MT
Grating 1 1/4″ x 3/16″ 3.0 – 3.5 MH/SF
Star threat grating 4.0 – 5.0 MH/SF
Errection
Heavy Structural teel 30 – 60 MH/MT
Light Structural steel 60- 90 MH/MT
Stacks ( Inc. full welding ) 250 – 300 MH/MT
Tanks ( Inc. full welding ) 200 – 275 MH/MT

FINISHING AND MASONRY WORKS


H. CHB
4” CHB
Laying 8.0 – 10 m2/day
Tooling 11 – 14 m2/day
Plastering 8.0 – 10 m2/day
6” CHB
Laying 7.0 – 9.0 m2/day
Tooling 11 – 14 m2/day
Plastering 8.0 – 10 m2/day
8” CHB
Laying 6.0 – 8.0 m2/day
Tooling 11 – 14 m2/day
Plastering 8.0 – 10 m2/day

These are average productivity ratios of an average worker.


Home
Guide to Cement and Aggregates Factors per Concrete Class Mixture

Handy guide on factors to multiply per cubic on different concrete class


mixtures. Just multiply each factor to the total volume (in cubic meter)
and you’ll get the needed amount of cement (40Kg/bag), sand (cu.m.) and
gravel (cu.m.).

Class C (2,000 psi)


Cement 5.634 Bags
Sand 0.4794 cu.m.
Gravel 0.898 cu.m.
Class B (2,500 psi)
Cement 7.399 Bags
Sand 0.486 cu.m.
Gravel 0.8856 cu.m.
Class A (3,500 psi)
Cement 8.799 Bags
Sand 0.5724 cu.m.
Gravel 0.856 cu.m.
Class AA (4,000 psi)
Cement 11.729 Bags
Sand 0.475 cu.m.
Gravel 0.8344 cu.m.

The following factors were already added an average wastage add-ons of


around 5% to 8%. This numbers should help average Filipinos to know
draft amount of materials needed for minor concreting works.
Home

This rate guide should help any Filipinos on how much should they rate construction laborers. Updated as of December 2018.

Construction Labor Rates


Description Unit Rate Unit Rate
Foreman hourly 87.36 daily 698.88
Electrician hourly 74.72 daily 597.76
Plumber hourly 74.72 daily 597.76
Leadman hourly 74.72 daily 597.76
Heavy Equipment Operator hourly 69.72 daily 557.76
Highly Skilled Worker hourly 69.72 daily 557.76
Light Equipment Operator hourly 65.81 daily 526.48
Driver hourly 58.63 daily 469.04
Skilled Worker hourly 58.63 daily 469.04
Semi-skilled Worker hourly 50.46 daily 403.68
Unskilled Worker hourly 42.33 daily 338.64

note:
as of December 2018.
Home

This is a bill of quantity price guide to complete installation,


testing and commissioning of elevator for a 6-Story building.
Disclaimer: Since this is a free website and we want to thrive, we
earn a small commission if you click through and purchase an
item on affiliate links.
GENERAL REQUIREMENTS / PRELIMINARIES
Description Qty Unit Amount (Php)
A. Mobilization (Temporary Office (including
construction/relocation of temporaryfacilities)
Contractor’s Office 1 lot 51,750.00
Warehouse 1 lot 51,750.00
B. Cleaning and Disposal of Garbage/Debris 1 lot 17,250.00
C. Premium for Insurance and Bonds (including Renewal Cost up
to Project Completion)
Surety Bond (Equivalent to 10% contract amount) 1 lot 21,968.65
Performance Bond (Equivalent to 10% contract amount) 1 lot 43,937.29
Guarantee Bond (Equivalent to 10% contract amount) 1 lot 109,814.06
D. Water and Electric Consumption 1 lot 23,000.00
E. Demobilization (Clearing, removal of temporary facilities,
Tools, Debris, Excess Materials, etc.) 1 lot 17,250.00
F. Other Requirements (Pls. specify)
Permits (Incl. Mayor’s City tax, & Other Misc. Permit charges) 1 lot 88,895.00
Cost of Local Procurement/ Material (Incl. Drawings/ Plotting,
PME Sign & Seal materials door safety nettings, barricades,
consumable materials, welding rods, wire, etc. 1 lot 492,200.00
Cable + Conduit (for WTB-Watch Tower Board or Supervisory
Panel 1 lot 34,500.00
Total 952,315.00
To see all the material prices we have posted click here.
Concreting Works – NCR
National Capital Region – (3rd Quarter of 2018)

Material Description Unit Ave. Price (Php)


Common Nails Assorted Kg 68.00
Concrete Nails Assorted Kg 82.00
GI Sheet Plain Gauge 16 x 8′ (1.613mm thick) pc 1,860.00
GI Sheet Plain Gauge 20 x 8′ (1.006mm thick) pc 1,950.00
GI Sheet Plain Gauge 26 x 8′ (0.551mm thick) pc 540.00
Gravel G1 cu.m. 500.00
Gravel GI – 1/2″ cu.m. 425.00
Gravel G2 cu.m. 410.00
Gravel G2-1/2″ cu.m. 410.00
Gravel 3/4″ cu.m. 430.00
Fine Aggregate cu.m. 460.00
Lumber Coco bd.ft. 45.00
Lumber Good bd.ft. 55.00
Natural Gravel cu.m. 540.00
Formed Oil L 115.00
Plyboard 3/4″ x 4′ x 8′ pc 1,050.00
Plyboard 1″ x 4′ x 8′ pc 1,100.00
Plywood Marine 1/4″ x 4′ x 8′ pc 415.00
Plywood Marine 1/2″ x 4′ 8′ pc 765.00
Plywood Marine 3/4″ x 4′ x 8′ pc 1,340.00
Plywood Ordinary 1/4″ x 4′ x 8′ pc 382.00
Plywood Ordinary 1/2″ x 4′ x 8′ pc 690.00
Plywood Ordinary 3/4″ x 4′ x 8′ pc 1,165.00
Reinforcing Steel Bars Plain Grade 40 Kg 39.00
Reinforcing Steel Bars Plain Grade 60 Kg 40.00
Reinforcing Steel Bars Deformed Grade 40 Kg 39.00
Reinforcing Steel Bars Deformed Grade 60 Kg 40.00
Steel Deck SQ.M. 825.00
GI Tie Wire #12 Kg 75.00
GI Tie Wire #16 Kg 63.00

VAT exclusive. Hauling & Delivery should be considered

Luzon – Concrete and Road Formwork Prices

Material Description Unit Ave. Price (Php)


Hydaulic Cement bag 270.08
Portland Cement bag 252.36
Pozzolan Cement bag 211.30
Ready Mix Concrete 3000psi @ 3 days cu.m. 4,704.64
Ready Mix Concrete 3000psi @ 7 days cu.m. 4,512.36
Ready Mix Concrete 3000psi @ 14 days cu.m. 4,328.29
Ready Mix Concrete 3000psi @ 28 days cu.m. 4,037.04
Ready Mix Concrete 3500psi @ 3 days cu.m. 5,013.57
Ready Mix Concrete 3500psi @ 7 days cu.m. 4,799.01
Ready Mix Concrete 3500psi @ 14 days cu.m. 4,547.05
Ready Mix Concrete 3500psi @ 28 days cu.m. 4,295.22
Ready Mix Concrete 4000psi @ 14 days cu.m. 4,879.03
Ready Mix Concrete 4000psi @ 28 days cu.m. 4,575.05
Ready Mix Concrete 4500psi @ 28 days cu.m. 4,819.08
Ready Mix Concrete 5000psi @ 28 days cu.m. 5,040.72
Curing Compound L 61.73
Steel Forms 15cm Width ln.m. 45.02
Steel Forms 20cm Width ln.m. 53.13
Steel Forms 23cm Width ln.m. 60.06
Steel Forms 25cm Width ln.m. 64.15
Steel Forms 28cm Width ln.m. 70.15
Steel Forms 30cm Width ln.m. 72.77
Polyethylene Sheet (Plastic Cover) ln.m. 50.74

These prices are calculated using cost-averaging formula. Some locations’ costs may be more expensive compared to the other
Home
expensive compared to the other. We simplified it this way for easy price updating.
Concrete Admixtures and Curing Materials
National Capital Region – (3rd Quarter of 2018)

Material Description Unit Ave. Price (Php)


Concrete Accelerating Admixture L 98.00
Concrete Accelerating Admixture Bag 270.00
Concrete Retarding Admixture L 40.00
Concrete Retarding Admixture Bag 362.00
Concrete Water-Reducing Admixture L 60.00
Concrete Water-Reducing Admixture Bag 280.00
Concrete Water-Reducing and Accelerating Admixture L 105.00
Concrete Water-Reducing and Accelerating Admixture Bag 430.00
Concrete Water-Reducing High Range Admixture L 65.00
Concrete Water-Reducing High Range Admixture Bag 240.00
Concrete Water-Reducing and Retarding Admixture L 115.00
Concrete Water-Reducing and Retarding Admixture Bag 530.00
Concrete Water-Reducing, High Range and Retarding Admixture L 92.00
Concrete Water-Reducing, High Range and Retarding Admixture Bag 440.00
Water-Proofing Cement (SAHARA or Equivalent) Bag 43.00
Home
Deformed Reinforcing Bars Prices per Length Home

Deformed Reinforcing Bars Prices


Description Unit Amount (php)
REBAR, Gr 40, 12mm dia x 6m pc 187.13
REBAR, Gr 40, 12mm dia x 7.5m pc 233.92
REBAR, Gr 40, 12mm dia x 9m pc 280.69
REBAR, Gr 40, 12mm dia x 10.5m pc 327.47
REBAR, Gr 40, 12mm dia x 12m pc 374.26
REBAR, Gr 60, 16mm dia x 6m pc 334.42
REBAR, Gr 60, 16mm dia x 7.5m pc 418.02
REBAR, Gr 60, 16mm dia x 9m pc 501.62
REBAR, Gr 60, 16mm dia x 10.5m pc 585.23
REBAR, Gr 60, 16mm x 12m pc 668.83
REBAR, Gr 60, 20mm dia x 6.0m pc 522.60
REBAR, Gr 60, 20mm dia x 10.5m pc 914.56
REBAR, Gr 60, 25mm dia x 6.0m pc 816.55
REBAR, Gr 60, 25mm x 9.0m pc 1,224.82
REBAR, Gr 60, 25mm dia x 10.5m pc 1,428.97
REBAR, Gr 60, 25mm dia x 12m pc 1,633.10

VAT not included.


Home

Masonry Works
Concrete Hollow Blocks (CHB) 4″ pc 10.00
Concrete Hollow Blocks (CHB) 6″ pc 16.00
Portland Cement, 40 kg. bag 265.95
Washed sand cu.m. 1,165.00
10 mm. Dia. x 6.0 M. DSB pc. 156.20
Tie Wire #16 kg. 65.00
Stone Masonry
Cement bag 260
Sand cu.m. 1,232.05
Gravel Fill cu.m. 1,207.05
Weep Holes (PVC) Lm. 228.33
Filter Cloth sq.m. 280
Boulders cu.m. 1,282.05
Screened Sand cu.m. 1,521.00
Screened Gravel cu.m. 1,581.00
ELEVATOR WORKS, TESTING & COMMISSIONING
Description Qty Unit Amount (Php)
Installation of Scaffolding 1 lot 17,503.00
Hoisting 1 lot 26,254.50
Template Setting 1 lot 43,757.50
Marking and Boring of Holes 1 lot 26,254.50
Bracket Setting 1 lot 35,006.00
Rail Setting 1 lot 43,757.50
Sill/Jamb Installation 1 lot 52,509.00
Floor Indicator/Call buttons 1 lot 8,751.50
Machine Room Equipment Setting 1 lot 43,757.50
Machine Room Piping 1 lot 17,503.00
Hoist-way Piping 1 lot 43,757.50
Landing Door Assembly 1 lot 35,006.00
Car Assembly 1 lot 61,260.50
Travelling Cable Lay-out 1 lot 21,878.75
CWT Assembly 1 lot 21,878.75
Lay-out of Ropes 1 lot 26,254.50
Wiring (Machine Room/Hoist-way) 1 lot 70,012.00
Initial Test 1 lot 52,509.00
Slow Speed test (Start up) 1 lot 26,254.50
Load Test 1 lot 13,127.25
Drop Test 1 lot 13,127.25
Buffer Test 1 lot 8,751.50
Plate Setting/Slow Switch Installation 1 lot 43,757.50
Rubber Block Setting 1 lot 17,503.00
High Speed Testing 1 lot 61,260.50
Standard/Special Feature Test 1 lot 26,254.50
Others 1 lot 17,503.00
Total 875,150.00
Embankment (per cubic meter)
Common Borrow 384.40
Selected Borrow 392.40
Mixed Sand & Gravel 585.11
Rock 602.56
Aggregate Subbase Course
Aggregate Subbase Course Material 818.13
Aggregate Base Course 934.89
Crushed Grading A 839.13
Uncrushed Grading A 926.00
Crushed Grading B 831.63
Uncrushed Grading B 837.00
Blended Weathered Limestone and Crush Stone 818.22
Filler Materials 401.00
Crushed Aggregate Base (per cubic meter)
Crushed Grading A 921.63
Crushed Grading B 875.43
Lime Stabilized Road Mx Base Course (per cubic meter)
Lime Stabilized Mixed Soil Aggregate Base Course Cru 693.75
Lime Stabilized Mixed Soil Aggregate Base Course Cru 662.78
Lime Stabilized Mixed Soil Aggregate Base Course Unc 670.00
Lime Stabilized Mixed Soil Aggregate Base Course Unc 641.11
Aggregate Surface Course (per cubic meter)
Crushed Grading A 878.22
Crushed Grading B 864.33
Crushed Grading C 884.75
Crushed Grading D 856.38
Uncrushed Grading A 826.13
Uncrushed Grading B 817.38
Uncrushed Grading C 812.63
Uncrushed Grading D 793.25

Note: Prices are for pick-up


VAT excluded
Luzon – Flooring Tile Prices
Description Unit Amount (Php)

Ceramic Glazed Tiles sq.m. 749.03


Ceramic Unglazed Tile sq.m. 708.31
Narra Wood Tile sq.m. 1,567.70
Tanguile Wood Tile sq.m. 818.13
1/16″ thk – Vinyl Tiles sq.m. 304.82
1/14″ thk – Vinyl Tiles sq.m. 388.53
1/12″ thk – Vinyl Tiles sq.m. 435.11

Visayas – Flooring Tile Prices


Description Unit Amount (Php)

Ceramic Glazed Tiles sq.m. 659.75


Ceramic Unglazed Tile sq.m. 747.32
Narra Wood Tile sq.m. 1,116.17
Tanguile Wood Tile sq.m. 838.39
1/16″ thk – Vinyl Tiles sq.m. 266.94
1/14″ thk – Vinyl Tiles sq.m. 312.32
1/12″ thk – Vinyl Tiles sq.m. 349.51

Mindanao – Flooring Tile Prices


Description Unit Amount (Php)

Ceramic Glazed Tiles sq.m. 682.68


Ceramic Unglazed Tile sq.m. 771.27
Narra Wood Tile sq.m. 1,271.70
Tanguile Wood Tile sq.m. 825.78
1/16″ thk – Vinyl Tiles sq.m. 323.67
1/14″ thk – Vinyl Tiles sq.m. 355.49
1/12″ thk – Vinyl Tiles sq.m. 357.96
Average glazing works prices in the Philippines.
Curtain Walls and Glazing Works Prices

Material Description Unit Price


8mm thk Reflective Tempered Glass Door sq.m. 33,600.00
12mm thk Frameless Glass Door sq.m. 33,000.00
12mm thk Reflective Tempered Glass Door sq.m. 37,000.00
12mm thk Clear Tempered Glass Wall sq.m. 6,700.00
Light Blue Light Reflective Tempered Glass Curtain Wall sq.m. 7,400.00
Aluminum Wall Cladding sq.m. 4,200.00
Aluminum Canopy sq.m. 4,400.00
Railing with 12mm thk Clear Tempered Glass x 0.8m H l.m. 1,008.50

All amount in Php. Accessories included and material price alone.


Ceiling Works

Description Unit Unit Price


4′ x 8′ x 4.50mm Fiber Cement (ceiling board) sht 425.00
4′ x 8′ x 9mm Gypsum Board (ceiling board) sht 410.00
4′ x 8′ x 9mm Gypsum Board (ceiling board, Moisture Resistant) sht 520.00
Ficem Screw 20mm pc 0.70

Ceiling Vent:
1″x1″x10′ s4s Tanguile or its equivalent pc 65.00
1″x3″x8′ s4s Tanguile or its equivalent pc 65.00
Insect Sreen sht 140.00
0.8mm thk. -12mm x 38mm x 5.00m Double Furring pcs 112.56
0.8mm thk. -12mm x 38mm x 5.00m Single Furring pcs 102.56
0.2mm thk-20mm x 20mm x 2.44m Wall Angle pcs. 36.50
Rod suspension hanger w/adjustment spring set 65.00
Pre-formed wire clip set 3.03
Toks Srew pcs. 0.70
Truss Works

Item Name Unit


6mm thk.x 65mm x 65mm x 6.0 Angle bar(T & B Chord) pc
6mm thk. x 50mm x 50mm x 6.0 Angle bar(Web Member) pc
10mm thk. Gusset plate welded to truss sq.m.
150mm x 65mm x 20mm x 2mm LC-Purlins pcs.
255mm x 90mm x 25mm x 5mm thk. LC- Channel beam pcs.
300mmx12mm dia. Plain Bar w/ standard nuts & washers @ both ends: Sagrod pcs.
350mmx12mm dia. Plain Bar w/ standard nuts & washers @ both ends: Sagrod pcs.
380mmx12mm dia. Plain Bar w/ standard nuts & washers @ both ends: Sagrod pcs.
465mmx12mm dia. Plain Bar w/ standard nuts & washers @ both ends: Sagrod pcs.
550mmx12mm dia. Plain Bar w/ standard nuts & washers @ both ends: Sagrod pcs.
12mm. Thk. Buckle Plate sq.m.
16mm dia. Plain Bar cross bracing pc.
16 mm dia. Turn buckle pc.
12mm x 250mm x 300mm Base Plate sq.m.
100 x 100 x 6mm thk. Angular base plate pc.
50 x 50 x 5mm Angular Bar pc.
75 x 75 x 6mm x 130mm Clip Angle to Purlins pc.
Welding Rod (Fuji) box
Oxygen(content only) tank
Acetylene(content only) tank
Hacksaw Blade pc.
Paint brush # 4 pc.
Paint brush # 2 pc.
Red Lead Primer gal.
Paint Thiner gal.
Price
2,248.70
1,704.66
4,245.52
1,089.00
4,057.57
74.12
76.74
78.31
82.76
87.22
5,100.44
419.10
137.50
5,100.44
1,880.00
1,392.12
2,611.40
2,330.00
1,575.00 450.00
2,000.00 600.00
65.00
65.00
35.00
429.45
551.25
Occupational Supplies Prices
Boots – Waterproof Pair 1,370.00
LED Flashlight Set 520.00
Heavy Duty Leather Gloves Pair 650.00
Safety Goggles pc 470.00
Heavy Duty Construction Hard Hat pc 1,260.00
Safety Harness set 1,210.00
Rain Coat pc 800.00
Twisted Rope: (Strength = 44.3kN) set 420.00
Heavy Duty Steel Toe Shoes Pair 2,650.00
Steel Toe Shoes Pair 500.00
Dome Type Tent: Two full door and vestibules,
breathable, lightweight fabrics, water-resistant set 2,820.00
Reflectorized Vest pc 88.00
Duct Tape, 4″ pc 225.00
Duct Tape, 1″ pc 145.00
Fire Protection Materials Price Guide

Automatic Fire Sprinkler System


BSP 25mm diameter lm 266.49
BSP 32mm diameter lm 353.43
BSP 40mm diameter lm 421.92
BSP 50mm diameter lm 531.54
BSP 65mm diameter lm 666.18
BSP 80mm diameter lm 861.48
BSP 100mm diameter lm 1,314.18
BSP 150mm diameter lm 2,153.88
BSP 200mm diameter lm 3,285.63
Valves and Accessories including necessary consumables
OS & Y Gate valve,150mm diameter pc 32,717.43
OS & Y Gate valve,200mm diameter pc 55,468.17
Gate Valve, 25mm diameter pc 2,287.26
Gate Valve, 65mm diameter pc 17,340.84
Check valve, 50mm diameter pc 9,402.57
Check valve,65mm diameter pc 12,536.82
Check valve,100mm diameter pc 23,245.29
Check valve,150mm diameter pc 42,050.43
Floor Control Valve, 100mm diameter pc 21,410.01
Flexible connector,65mm diameter pc 17,750.88
Fire Department Connection, 150x65x6 pc 24,957.45
Supervisory switch pc 4,530.87
Water flow switch pc 6,590.34
Pressure Reducing Valve, 150mm diamet pc 180,646.20
ITC Drain Valve, 25mm diameter pc 4,387.41
Roof Manifold,150x65x65mm diameter pc 38,742.12
Sight glass pc 1,233.36
Fire hose valve, 65mm diameter pc 10,157.13
Alarm check valve, 150mm diameter pc 81,396.09
Butterfly Valve, 150mm diameter pc 25,278.57
SSP 200mm diameter lm 23,636.70
SSP 250mm diameter lm 29,690.01
Gate Valve, 100mm diameter pc 21,176.55
Gate Valve, 80mm diameter pc 18,564.75
Check valve,200mm diameter pc 71,389.98
Wye Strainer 65mm diameter pc 6,355.44
Wye Strainer 200mm diameter pc 44,314.02
Flexible connector,200mm diameter pc 41,418.72
Float Valve, 100 mm diameter pc 120,301.29
Pressure relief valve, 65mm diameter pc 118,838.25
Pump Test Connection, 150x65x65mm di pc 24,957.45
Sprinklers to include fixing with necessary consumables
Upright sprinkler head pc 488.07
Pendent sprinkler head pc 521.10
Equipment
Fire Pump unit 114,651.54
Jockey Pump unit 30,412.80
Fire Protection Specialties
Fire Hose Cabinets, Recessed Type set 20,900.00
Portable fire extinguisher, 10 lbs pc 3,570.57
Portable fire extinguisher, 15 lbs pc 24,797.16
Portable fire extinguisher, 125 lbs Dry Ch pc 61,957.35
Portable fire extinguisher, 11 lbs pc 16,543.53
Portable fire extinguisher, 9.46L pc 8,812.44

VAT not included.


Electrical Conduit Prices per Commercial Length

Electrical Pipe Prices per Commercial Length

Description Unit Amount (Php)


IMC PIPE 1/2″ (15mm) x 3M w/ COUPLING pc 227.70
IMC PIPE 3/4″ (20mm) x 3M w/ COUPLING pc 294.19
IMC PIPE 1″ (25mm) x 3M w/ COUPLING pc 515.53
IMC PIPE 1-1/4″ (32mm) x 3M w/ COUPLING pc 613.88
IMC PIPE 1-1/2″ (40mm) x 3M w/ COUPLING pc 777.52
IMC PIPE 2″ (50mm) x 3M w/ COUPLING pc 992.70
IMC PIPE 2-1/2″ (65mm) x 3M w/ COUPLING pc 1,685.50
IMC PIPE 3″ (80mm) x 3M w/ COUPLING pc 2,060.26
IMC PIPE 3-1/2″ (90mm) x 3M w/ COUPLING pc 3,091.29
IMC PIPE 4″ (100mm) x 3M w/ COUPLING pc 3,583.05
FMC ORDINARY 1/2″ (15mm) pc 21.59
FMC LT 4″ (100mm) pc 1,841.44
FMC LT 30″ (80mm) pc 1,095.94
FMC LT 2-1/2″ (65mm) pc 924.46
PVC CONDUIT 20MM (1/2″) x 3m pc 58.14
PVC CONDUIT 25MM (3/4″) x 3m pc 76.04
PVC CONDUIT 32MM (1″) x 3m pc 108.09
PVC CONDUIT 40MM (1-1/4″) x 3m pc 137.92
PVC CONDUIT 63MM (2″) x 3m pc 222.17
PVC CONDUIT 110MM (4″) x 3m pc 673.96

VAT not included.

ELECTRICAL WORKS
Pipe and Fitting
20mmdia UPVC pipe pcs 85.00
20mmdia RSC conduit pcs 216.00
20mmdia RSC coupling pcs 20.00
20mmdia UPVC coupling pcs 5.00
20mmdia UPVC adoptor pcs 7.50
20mm dia. Locknut& bushing pcs 8.00
20mm dia. RSC Locknut& bushing pcs 14.30
Boxes and Gutter
Junction box depth type,metal gauge 16 w/ cover pcs 25.00
Utility box depth type, metal gauge 16 w/cover pcs 25.00
4×4 square box depth, metal gauge 16 w/cover pcs 50.00
Miscellaneous and Consumables
Electrical tape big pcs. 40.00
Rubber tape big pcs. 90.00
Solvent cement 100cc pcs. 240.00
G.I. Wire No. 12 kls. 70.00
Concrete nail no.3 kls. 120.00
CWN no.3 kls. 70.00
Entrance cap pcs. 35.00
Terminal Lugs lot 600.00
Red Led Paint pcs. 429.00
Cable Tie pc 1.00
Secondary Rack pc 540.00
Black Paint gal 610.00
Wires
8.0mm2 THHN m 43.33
5.5mm2 THHN m 36.59
3.5mm2 THHN m 25.00
2.0mm2 THHN m 23.33
Wiring Devices
1-gang Switch, 10A, 240V set 110.00
2-gang switch, 10A, 240V set 140.00
2-gang 3 way switch, 10A, 240V set 240.00
1-gang Convenince Outlet, 10A, 240V set 250.00
2-gang Convenience Outlet, 3 prong 10A, 240V set 351.00
Lighting Fixtures
24 Watts light bulb set 285.00
1-18watts Compact flourescent lighting fixtures set 680.00
keyless type,porcelain receptacle
2-36 watts ,220v,Flourescent (box type) set 1,200.00
1 x 18, 230V, Compact Flourescent (Keyless Type set 680.00
Power Load Center Switch Gear and Panel Board
Main :40AT/50AF,1PCB,240V,18KAIC, BOLT-ON set 12,500.00
Branches
2-15AT/50AF,1PCB,240V,10KAIC,,BOLT-ON PC 315.70
3-20AT/50AF,1PCB,240V,10KAIC,,BOLT-ON PC 315.70
Plumbing and Sanitary Works

Sanitary Lines Unit Price


100mm dia. PVC pc 753.50
75mm dia. PVC pc 485.00
50mm dia PVC (vp & wp) pc 330.00
PVC Clean Out w/ plug & sealing ring 100mm pc 95.00
PVC Clean Out w/ plug & sealing ring 150mm pc 114.00
PVC P-Trap w/ plug & sealing ring 50mm pc 66.00
PVC Te (150mm) pc 95.00
PVC Tee (100mm) pc 95.00
PVC WYE (100mm) pc 95.00
PVC WYE REDUCER (100mmX50mm) pc 85.00
PVC WYE REDUCER (100mmX75mm) pc 95.00
PVC ELBOW 90° (100mm) pc 95.00
PVC ELBOW 90° (75mm) pc 85.00
PVC Elbow 90° (50mm) pc 66.00
PVC Elbow 45° (100mm) pc 95.00
PVC Elbow 45° (75mm) pc 85.00
PVC Elbow 45° (50mm) pc 66.00
PVC Coupling (100mm) pc 95.00
Vulca Seal pc 440.00

Cold Water Lines Unit Price


20mmØ Polypropylene, Type 3, PN20 pc. 250.00
20mmØ Coupling pc. 95.00
20mmØ Tee pc. 95.00
20mmØ Elbow pc. 95.00
Teflon Tape roll 27.50
Painting Works

Description / Item Unit Ave. Price


Paint Tinting Color Ltr 182.22
Paint Aluminum gal 661.27
Paint Enamel gal 666.82
Paint Latex Gloss gal 642.20
Paint Latex Semi-Gloss gal 652.00
Paint Red Lead gal 597.09
Thinner Paint gal 317.89
Thinner Lacquer gal 481.40
Paint Metal Epoxy gal 776.00
Paint Primer Solvent gal 735.60
Brush Paint (101mm) pc 77.50
Brush Roller (152mm) pc 94.45
Brush Steel (101mm) pc 36.20
Oil Paint Ltr 108.09
Spar Varnish Ltr 1,286.91
Lacquer Putty Kg 655.70
Concrete neutralizer gal 429.45
Putty Knife pc 25.00
Roller paint # 9 w/ tray pc 150.00
2″paint brush pc 35.00
Putty Knife pc 25.00
Paint thinner gal 280.00
Sand paper #120 dozen 120.00

For reference, 20 sq.m normally consumes a gallon of paint. All amount in Php.
Concreting Works 2018
Concrete
Soil Poisoning – Termicide Liter 325.00
Gravel cu.m 1,310.00
Wash Sand cu.m 1,435.00
Portland Cement, 40kg Bag 259.00
Pozzolan Cement, 40kg Bag 261.00
Steel Bars
10mm Diameter Deformed Bars pc 156.00
12mm Diameter Deformed Bars pc 221.00
16mm Diameter Deformed Bars pc 392.00
20mm Diameter Deformed Bars pc 642.00
#16 G.I. Tie Wire kg 16.00
Formworks
2 x 3 x 10′ Coco lumber pc 270.00
2 x 4 x 10 Coco lumber pc 270.00
1/2″ x 4′ x 8′ Plywood pc 656.00
6mm thk. Lawanit board pc 201.00
6mm thk. Ordinary Plywood pc 323.00
1″x2″x8′ Wood pc 75.00
2″x2″x8′ Wood pc 95.00
2″x3″x8′ Wood pc 105.00
2″x4″x8′ Wood pc 125.00
Construction Heavy Equipment and Engineering Survey Equipment Price List
4th Quarter of 2018

Description Unit Price

Amphibious Excavator Unit 15,800,000.00


Backhoe Payloader Unit 4,800,000.00
Crack Sealing Applicator, Walk Behind Unit 390,000.00
Cutter Suction Dredge and Support Vessel Unit 300,000,000.00
Dump Truck, 210 Hp, 5.5 cu.m Unit 3,450,000.00
Dump Truck, 150 Ps, 3 cu.m Unit 2,700,000.00
High side Pick-Up with Roof (HSPUR) Unit 920,000.00
Hydraulic Excavator Unit 5,900,000.00
Kneading Machine Unit 960,000.00
Multi-Purpose Amphibious Dredge Unit 37,500,000.00
Multi-Purpose Amphibious Dredge, 10 Unit 41,500,000.00
Multi-purpose Cutter Suction Dredge Unit 54,700,000.00
Pavement Marking Remover Unit 1,180,000.00
Prime Mover, 400 Hp Unit 4,750,000.00
Road Patcher Unit 4,300,000.00
Stake Truck, 210 Hp Unit 3,100,000.00
Vibratory Roller, 15 Hp, 1500 Kgs Unit 1,400,000.00
Wheel Loader, 110 Hp, 1.7 cu.m Unit 2,500,000.00
Digital Level Unit 110,000.00
Handheld Global Positioning System (GPS) Unit 44,000.00
Total Station Unit 460,000.00
Site Office Supply Materials Prices

Description Unit Amount (Php)

A4 Folder, 50 pieces per bundle bundle 233.86


Legal Size Folder, 50 pieces per bundle bundle 292.33
L-type, A4 Size Folder, 50 pieces per pack pack 169.95
L-type, Legal Size Folder, 50 pieces per pack pack 179.65
Pressboard Folder, size: 240mm x 370mm, 100 pieces per box box 763.23
Tagboard Folder (A4), 100 pieces per pack pack 184.30
Tagboard Folder (Legal), 100 pieces per pack pack 204.80
All-Purpose Glue (200ml) jars 45.16
Heavy Duty Paper Puncher piece 116.80
300 Leaves Record Book, size: 214mm x 278mm book 60.33
500 Leaves Record Book, size: 214mm x 278mm min book 86.63
#18 Rubber Band box 95.37
Plastic Ruler piece 15.82
Scissors pair 14.03
Scouring Pad, 5 pieces per pack pack 121.05
Liquid/Gel-inked Sign Pen (Blue, Black Red) 0.5mm Point piece 38.94
Stamped Pad Ink, 50ml (min.) bottle 25.17
Stamp Pad (60mm x 100mm) piece 31.76
Plier Type Staple Remover piece 18.58
Heavy Duty Staple Wire box 23.92
Standard Staple Wire box 19.34
Standard Type Stapler piece 90.23
Table Top Tape Dispenser piece 48.77
Electrical Tape roll 18.60
Masking Tape, width: 24mm roll 56.21
Masking Tape width: 48mm roll 105.02
Packaging Tape, width: 48mm roll 31.31
Standard Tape, width: 24mm roll 17.75
Standard Tape, width: 48mm roll 27.11
Standard Mongol Pencil, 12 dozens per box box 74.43
Sharpener for Pencil piece 191.34
Ruled Pad Paper pad 18.39
32mm Paper Clip, 100 pieces per box box 6.91
48mm Paper Clip, 100 pieces per box box 13.82
Paper Shredder unit 5,612.64
A4 Paper, 80gsm, size: 210mm x 297mm ream 91.95
Legal Paper, 80gsm, size: 216mm x 330mm ream 105.24
Metal Fastener, 50 sets per box box 56.15
Legal Sized File Organizer piece 72.23
Permanent Marker (Red, Blue, Black) piece 9.55
Whiteboard Marker (Red, Blue, Black) piece 10.50
Blackboard/Whiteboard Eraser piece 11.35
Scientific Calculator unit 770.68
A4 Sized Envelope, 500 pieces per box box 384.72
Legal Sized Envelope 500 pieces per box box 497.20
Mailing Envelope, 500 pieces per box box 134.87
Mailing Envelope w/ Window, 500 pieces per box box 172.72

VAT not included.


Slope Stabilization Mesh System

Description Unit Price (Php)


3mm Ø High Tensile Wire mesh (3.5x30mm) sq.m 6,992.00
10mm Ø Tensile Rope Anchor ln.m 1,012.00
4mm Ø High Tensile Wire Clips pc 138.00
10mm Ø Tensile Wire Rope Anchor pc 4,600.00
Anchor Bolt (32mmØ x 2.5m) pc 966.00
Threading of Bolts w/ nuts pc 1,288.00
Non-Shrink Grout bags 552.00
Centralizer pc 230.00
Drill Bit pc 18,400.00
Centrosema Seeds kgs. 294.40
Enzyme ltrs. 13.80
3D Geonet sq.m 598.00
Average prices for National Capital Region’s doors and windows.
DOORS AND WINDOWS
National Capital Region – (3rd Quarter of 2018)

Material Description Unit Ave. Price (Php)

Aluminum Glass Door SQ.M. 6,700.00


Accordion Type Door SQ.M. 2,050.00
Flush Hollow Core Door SQ.M. 850.00
Flush Type Solid Core Door SQ.M. 1,660.00
Glass Transom on Wood SQ.M. 2,000.00
Narra Type Solid Core Door SQ.M. 5,300.00
Tanguile Paneled Door SQ.M. 4,600.00
Varifold Type Door SQ.M. 2,980.00
Awning Type Steel Casement Windows SQ.M. 1,870.00
Glass Jalousie Window SQ.M. 660.00
Fixed Glass Window on Metal Frame SQ.M. 440.00
Fixed Louvered Steel Window SQ.M. 530.00
Aluminum Casement Window SQ.M. 4,600.00
Sliding Aluminum Window SQ.M. 5,350.00
Swing Type Steel Casement Windows SQ.M. 1,800.00
Gabions and Mattresses
National Capital Region – (3rd Quarter of 2018)

Description Unit Php


Gabions Metallic Coated, 0.5m x 1m x 3m PC 1,600.00
Gabions Metallic Coated, 0.5m x 1m x 4m PC 2,050.00
Gabions Metallic Coated, 1m x 1m x 2m PC 2,250.00
Gabions Metallic Coated, 1m x 1m x 3m PC 2,700.00
Gabions Metallic Coated, 1m x 1m x 4m PC 3,100.00
Gabions PVC Coated, 0.5m x 1m x 3m PC 1,900.00
Gabions PVC Coated, 0.5m x 1m x 4m PC 2,200.00
Gabions PVC Coated, 1m x 1m x 2m PC 2,200.00
Gabions PVC Coated, 1m x 1m x 3m PC 2,800.00
Gabions PVC Coated, 1m x 1m x 4m PC 3,250.00
Mattresses Metallic Coated 0.3m x 2m x 6m PC 3,600.00
Mattresses PVC Coated 0.3m x 2m x 6m PC 4,050.00
Filter Cloth PC 160.00
FENCING WORKS
National Capital Region – (3rd Quarter of 2018)

Material Description Unit Ave. Price (Php)


Gauge 10 – Galvanized Cyclone Wire 3′ ln.m 981.00
Gauge 10 – Galvanized Cyclone Wire 4′ ln.m 1,315.00
Gauge 10 – GalvanizedCyclone Wire 5′ ln.m 1,642.00
Gauge 10 – Galvanized Cyclone Wire 6′ ln.m 1,972.00
Gauge 12.5 Galvanized Barbed Wire – 2 Strands ln.m 11.00
Gauge 12.5 Galvanized Barbed Wire – 3 Strands ln.m 14.00
Chain Link Fence Fabric ln.m 96.00

Potrebbero piacerti anche