ID Task Name Start Finish

Workshop and Garage


1 Brick work
Grid 1 to 3 (First floor) Balance work 2019.11.09 2019.11.30
Grid 1 to 3 (Ground floor) Balance work 2019.11.21 2019.11.30
Grid 3 to 15 2019.11.01 2019.12.10
2 Staircase
Formwork 2019.11.22 2019.11.26
Rebar 2019.11.25 2019.11.26
Concrete 2019.11.27 2019.11.27
3 Washroom and toilet
Plumping work 2019.12.11 2019.12.17
Plastering 2019.12.02 2019.12.10
Tiling & fittings 2019.12.20 2020.01.05
4 Electrical conduit work 2019.11.15 2019.12.08
5 Roof work
Grid 1 to 8 2019.11.09 2019.11.26
Grid 8 to 15 2019.11.12 2019.11.26
6 Plastering work 2019.11.20 2019.12.25
7 Hoist beam
Febrication 2019.11.09 2019.11.30
Installation & painting 2019.12.02 2019.12.20
8 Floor Finishing work 2020.02.15 2020.02.28
9 Painting 2020.01.15 2020.02.15
10 Windows and Doors fixing 2019.12.10 2019.12.31

Garage Extension
11 RCC columns
1st lift 2019.11.04 2019.11.08
2nd lift 2019.11.09 2019.11.13
3rd lift 2019.11.14 2019.11.22
4th lift 2019.11.23 2019.11.26
12 Floor concrete
Grid 1 to 5 2019.11.07 2019.11.09
Grid 5 to 10 2019.12.05 2019.12.12
13 Brickwork 2019.11.20 2019.12.10
14 Roof beam 2019.12.10 2019.12.20
15 Steel structure with roof
Febrication 2019.11.11 2019.11.25
Installation & painting 2019.12.20 2019.12.30
16 Plastering 2019.12.10 2019.12.30
17 Windows fixing 2020.01.05 2020.01.15
18 Painting 2020.01.20 2020.02.28