Zubair New Degassing Project Task Method Statement

Company MSK Ref:


Work Main Site Start Date:23/9/2016
location Start Time: 06:00am
Description Installation Roof Plate - Mobilization of welding car & End Date: 30/9/2016
of the task Shelter & Scaffold & Generator & Shell Plate & Roof End Time: 17:00hrs
Plate
Personnel Name Position Tel
SECL Mohammed Abid Mech. Supervisor 0782-121-4108
Issuing Authority
SUBCON Hamza A, Site Engineer
Performing Authority
Tools & Crane & Chain Sling / web sling, shackles, man basket
Equipment:

Sequence of
Operations 1. All the equipment is to be inspected prior to Mobilization by a Heavy Equipment Inspector
(Specifying and signed off fit for purpose.
methods of
working, tools, 2. Equipment Mobilization to the working area by proper movement, signal man escorting to
materials and the work location
equipment
utilised)
3. Prior to start activity, traffic management plan, barricade for safe distance and competent
and trained personal will be identified and Tool box talk will be arranged for pre task check
& verification.
4. Inspection the land area, should be compacted well abs should be safe for lifting, loading &
unloading operations.
5. Installing of 50 ton mobile crane in proper position for the work site.
6. Proper certified lifting accessories will be used by colour coded from Samsung inspections.
7. Setting out of crane by extending outrigger by providing proper padding.
8. Preparation and selection of load to be lift by providing proper lifting connections.
9. Providing tagline. Communication means & safe distance for transferring material.
10. Centre of gravity to be clearly marked on the Items to be lifted.
11. If required to keep material in work area, it will be provided proper arrangement.
12. If loaf will be transfer, it will be properly tie up.
13. If required working at height. Full body harness, life line or other means for fall protection
will be used
14. Simultaneous work will be avoided unless it is approved by authority of Samsung.
15. Wind speed limit will be observed
16. House Keeping before and after job for any combustible material or any inflammable
material.
17. Man basket will be use for emergency evacuation case, when any expected case happen
at inside the hot oil pit.
18. In case of any emergency, it will be reported to safety & construction department.
19. Job supervisor (performing authority) will be remaining responsible to ensure safe lifting
work procedure to be followed and implemented.
20.
21.
22.
23.
24.

First Aid (e.g. first aid box or clinic) First Aider: (24 x 7) – 078.0648.7625
Facilities Tel No:
All work will be undertaken by qualified competent persons with experience of the type of work described above, and in all cases in
full accordance with safety procedures specified in the SECL Health and Safety Policy.

(Subcontractor) (Samsung):
Prepared by: Hamza A. Reviewed by: Mohammed Abd
Position: site engineer Position: Mech. Supervisor
Signature: Signature:
Date Date: 23-09-2016