Sei sulla pagina 1di 3

METHOD STATEMENT FOR DRAINAGE WORK

PROJECT: PROPOSED HIGH-RISE CONDIMINIUMS (WITH SUBSIDIARY (STRATA) TITLES TO BE APPLIED FOR) ON CL.015029731
OFF BUNDUSAN, KOTA KINABALU, SABAH (A JOINT VENTURE DEVELOPMENT PROJECT)

CONTENT PAGE NO

1.0 WORK PROCEDURE FOR PRECAST RC-DRAIN 2

2.0 WORK PROCEDURE FOR CASCADE DRAIN 3

3.0 WORK PROCEDURE FOR PRECAST CONCRETE 3


BOX CULVERT

VINASI HASIL SDN. BHD Page 1


METHOD STATEMENT FOR DRAINAGE WORK

PROJECT: PROPOSED HIGH-RISE CONDIMINIUMS (WITH SUBSIDIARY (STRATA) TITLES TO BE APPLIED FOR) ON CL.015029731
OFF BUNDUSAN, KOTA KINABALU, SABAH (A JOINT VENTURE DEVELOPMENT PROJECT)

1.0 WORK PROCEDURE FOR PRECAST RC-DRAIN (300MM-1800MM


WIDE

1. Site Survey
Surveyor to set out of points and establish of Temporary Bench Mark
(TBM) level. Positioning of point will carry on based on construction
detail drawing from the engineer.

2. Site clearance
Site need to remove all of the vegetation and stumps that will disturb
the construction process.

3. Excavation
Excavation of drainage according to drawing specification need to be
carried out accordance to the drain positioning in the road reserve.

4. Setting out for drain


After excavation has been done. Setting out for the drainage need to be
carried out.

5. Formwork installation
Need to be done before concreting work are carried out. Fully support
for formwork structure are need to make sure formwork are not
collapse.

6. Sand blinding
This compacted sand act as a cover for the drainage follow the
specification

7. Reinforcement installation.
Reinforcement steel bar according to the drawing need to be install
before of concreting work

8. Concreting work

9. Lay the RC-Drain Based on the drawing

VINASI HASIL SDN. BHD Page 2


METHOD STATEMENT FOR DRAINAGE WORK

PROJECT: PROPOSED HIGH-RISE CONDIMINIUMS (WITH SUBSIDIARY (STRATA) TITLES TO BE APPLIED FOR) ON CL.015029731
OFF BUNDUSAN, KOTA KINABALU, SABAH (A JOINT VENTURE DEVELOPMENT PROJECT)

2.0 WORK PROCEDURE FOR CASCADE DRAIN (400MM – 1800MM) WIDE

1. Excavation for cascading drain shall be carried out to the dimensions


as shown in the drawing.

2. To compact base and lay reinforcement as shown in the drawing.

3. To concrete base to a thickness according to size cascade drain and


lay mass concrete (G35) 150mm max. height steps.

3.0 WORK PROCEDURE FOR PRECAST CONCRETE BOX CULVERT

1. Excavation for box culvert shall be in accordance to a depth and size as


shown in the drawing.

2. Box culvert shall be laid as close as possible.

3. The gap shall be filled with cement mortar and finished smooth.

4. To construct wing wall, compact base with hardcore lay lean concrete,
concrete base with reinforcement steel bar, starter bar to wall, formwork,
install 50mm dia. pvc pipe for weep hole and place in vibrated concrete
mix for wall.

5. Backfill with suitable earth stockpiled and compact the sides.

VINASI HASIL SDN. BHD Page 3

Potrebbero piacerti anche