Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Document No-TGPL/STEEL/18-19/001/R0-DEC-2018
Table of Contents
2. Execution of Temporary Cathodic Protection system for the Approved Work Completion
underground pipeline for the length of 03 KM Certificate and Copy of Work
Order
OR
Self-declaration on company
letterhead with Project details
with Work Order copy
4 List of Fit for use Equipment / Machinery and Measuring List of equipment / Instruments
Instruments available for inspection and Inspection Certificates issued
by competent authority
5. The bidder should have completed Station Piping/above Approved Work Completion
ground Piping works (including testing and hand over to Certificate
owner) for at least 2 station piping or 100 INCH DIA work OR
perform. Self-declaration on company
letterhead with Project details
with Work Order copy
6 HSE and Quality Policy Policy on company letterhead
7 Detail of HDD and NDT Sub contractor – If applicable Self-declaration on company
letterhead
TECHNICAL SPECIFICATION FOR LAYING, TESTING AND COMMISSIONING OF
CGD - STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
SCOPE OF WORK
Page 1 of 60
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYING, TESTING AND COMMISSIONING OF
CGD - STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
TABLE OF CONTENTS
1. OVERVIEW
1.1 DESCRIPTION
1.2 DEFINITIONS
2.1 SCOPE
3.1 GENERAL
Page 2 of 60
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYING, TESTING AND COMMISSIONING OF
CGD - STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
1. OVERVIEW
1.1. DESCRIPTION
Torrent Gas Pvt. Ltd. (“Torrent Gas” or “TGPL”) is part of the Ahmedabad based
Torrent Group, one of the fastest growing industrial groups of the country with
diverse interests in Pharma, Power and Gas sectors.
Torrent Power Limited, having a turnover of Rs. 11,500 crores, is one of the leading
players in the Indian power sector with a strong presence in the entire value chain of
the power sector; generation, transmission and distribution including strong
presence in renewable segment. The company has a generation capacity of 3,661
MW and distributes 16,000 million units of power to more than 3.2 million
customers in six cities.
Torrent Gas is currently implementing the City Gas Distribution project in the Pune
District through its associate company (TGPL). Further, in 9th CGD bidding Torrent
Gas has been authorized by the Petroleum and Natural Gas Regulatory Board
(PNGRB) for establishing City Gas Distribution system in following districts across
India:
Page 3 of 60
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYING, TESTING AND COMMISSIONING OF
CGD - STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
This document summarizes the Technical requirements and the specifications for
laying of steel pipeline, fabrication and installation of piping for extension and
reinforcement of gas network and associated civil work. The scope of this job
specification comprise of steel pipeline laying testing and commissioning, installation
of valve, above ground / underground pressure reduction station, construction of
valve chamber, station piping, fabrication and installation at CGS & CNG stations,
Cathodic protection system.
In addition to above, the scope of contract also includes end connection with
existing live gas network by shut down, Hot Tap support services.
All the operations of mentioned areas are performed from the City offices located in
Geographical area / City. The Pipeline used shall be API 5L, PSL-2, Grade X 52 / X 60,
Carbon Steel Pipe of 12 m approx. pipe length and of required Wall thickness.
Under this scope CONTRACTOR shall be required to start the mobilize of resources
within 15 days from the kick off meeting.
1.2. DEFINITIONS
In the Bid / Contract (as hereinafter defined) the following words and expressions shall
have the meanings hereby assigned to them except where the context otherwise
requires.
i) "TGPL" or "COMPANY" or “OWNER” shall mean M/s. Torrent Gas Pvt. Ltd.
iii) CONTRACT shall mean Purchase Order (PO) / Contract and all attached exhibits
and documents referred to therein and all terms and conditions thereof together
with any subsequent modifications thereto.
Page 4 of 60
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYING, TESTING AND COMMISSIONING OF
CGD - STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
iv) CONTRACT PRICE shall mean the price payable to the Contractor under the PO/
Contract for the full and proper performance of his contractual obligations.
v) COMPLETION DATE shall mean the date on which the goods are successfully
commissioned by the Contractor and handed over to the Owner.
vi) COMMERCIAL OPERATION shall mean the condition of the operation in which
the complete equipment covered under the Contract is officially declared by the
Owner to be available for continuous operation at different load up to and
including rated capacity.
vii) DRAWINGS shall mean and include Engineering drawings, sketches showing
plans, sections and elevations in relation to the PO/ Contract together with
modifications and/or revisions thereto.
viii) ENGINEER shall mean the Engineer or Executive-in-Charge of the Project SITE
nominated by OWNER at SITE.
ix) FINAL ACCEPTANCE shall mean the Owner’s written acceptance of the Works
performed under the PO / Contract after successful completion of performance
and guarantee tests.
x) GOODS shall mean articles materials, equipment, design and drawings, data and
other property to be supplied by Contractor to complete the contract.
xi) INSPECTOR shall mean any person or outside Agency nominated by OWNER to
inspect equipment, stage wise as well as final, before dispatch, at Contractor’s
works and on receipt at SITE as per terms of the PO / CONTRACT.
xii) INITIAL OPERATION shall mean the first integral operation of the complete
equipment covered under the Contract with sub-systems and supporting
equipment in service or available for service.
xiii) PERFORMANCE AND GUARANTEE TESTS shall mean all operational checks and
tests required to Determine and demonstrate capacity, efficiency and operating
characteristics as specified in the Contract Documents.
xiv) SELLER / BIDDER / CONTRACTOR shall mean the person, firm or company with
whom PURCHASE
ORDER/CONTRACT is placed / entered into by OWNER for supply of equipment,
materials and services. The term Contractor includes its successors and assigns.
Page 5 of 60
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYING, TESTING AND COMMISSIONING OF
CGD - STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
xv) SERVICE shall mean erection, installation and testing, commissioning, provision
of technical assistance, training and other such obligations of the Contractor
covered under the Contract.
xvi) SITE shall mean the Project or designated destination for which the Contract has
been issued and where the equipment / materials shall be erected.
xviii) SUB-CONTRACT shall mean order placed by the Contractor, for any portion of
the contracted work, after necessary consent and approval of OWNER.
xix) SUB-CONTRACTOR shall mean the person named in the CONTRACT for any part
of the work or any person to whom any part of the CONTRACT has been sub-let
by the SELLER with the consent in writing of the OWNER and will include the
legal representatives, successors, and permitted assigns of such person.
xx) START-UP shall mean the time period required to bring the equipment covered
under the Contract from an inactive condition, when construction is essentially
complete to the state of readiness for trial operation. The start-up period shall
include preliminary inspection and check out of equipment and supporting
subsystems, initial operation of the complete equipment covered under the
Contract to obtain necessary pre-trial operation data, perform calibration and
corrective action, shutdown inspection and adjustment prior to the trial
operation period.
xxi) TESTS shall mean such process or processes to be carried out by the Contractor
as are prescribed in the Contract or considered necessary by Owner or his
representative in order to ascertain quality, workmanship, performance and
efficiency of equipment or part thereof. TESTS ON COMPLETION shall mean such
tests as prescribed in the Contract to be performed by the Contractor before the
Works are taken over by the Owner.
xxii) CONSULTANT shall mean outside agency other than OWNER as authorized by
the OWNER. The term includes successors, assigns of CONSULTANT.
xxiii) The "BID" shall mean the Bid submitted by the CONTRACTOR for acceptance by
the TGPL.
Page 6 of 60
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYING, TESTING AND COMMISSIONING OF
CGD - STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
xxiv) "TGPL's REPERSENTATIVE" shall mean the person designated as such by the
Torrent Gas Pvt. Limited and shall include his authorized nominee or agent,
provided however that the TGPL's representative to be so designated by TGPL
may be one person for certain aspects of this agreement and another person for
other aspects of work covered by this Bid / Contract.
xxv) “THIRD PARTY INSPECTION AGENCY” (TPIA) shall mean outside inspection
agency other than TGPL authorized by the Company.
xxvii) “PERMANENT WORKS” or “WORKS” shall mean and include all works to be
executed in accordance with the Contract or part thereof as the case may be and
shall include all extras, additional, altered or substituted works as required for
the purpose of contract.
xxviii) “TEMPORARY WORKS” shall mean all temporary works of every kind required in
or about the execution, completion or modification of the works, which are not
permanent.
xxxii) “WORKING DAY” means any day, which is not declared to be holiday or rest day
by Owner.
xxxiii) “SPREAD” shall mean that combination of construction equipment including all
necessary tugs, supporting work, barges and personnel as defined in the Contract
and schedule of rates and prices, capable of performing specific portion of the
work.
xxxv) “COMMISSIONING” shall mean placing into service of the system including the
plant(s), equipment(s), vessel(s), pipeline, machinery (ies), or any other section
or sub-section of installation(s) pertaining to the work of the CONTRACTOR after
successful testing and trial runs of the same.
xxxvi) “GUARNTEE” means the period and other conditions governing the warranty /
guarantee in respect of the work as detailed in section hereunder.
xxxvii) “CP” means Cathodic Protection system designed and installed for corrosion
control of Steel Pipelines.
xxxviii) “TCP” means Temporary Cathodic Protection system designed and installed for
corrosion control of Steel Pipelines during construction.
xxxix) “PCP” means Permanent Cathodic Protection system designed and installed for
corrosion control of Steel Pipelines after completion of construction activity.
Page 8 of 60
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYING, TESTING AND COMMISSIONING OF
CGD - STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
2.1. SCOPE
2.1.1 This specification covers the minimum requirements for the various activities to be
carried out by CONTRACTOR for the Construction and Modification of the Steel
pipeline job.
The following is a broad description of activities, which shall be included as part of
this contract, as a minimum.
All the activities required for Pipeline Laying and Modification / Extension as per
the plan, including, but not limited to, the following:
o Issue & receipt of steel pipes and other free issue materials from TGPL
designated store or on site delivered directly from vendor as the case may
be.
o Supply of consumables such as Electrodes, coating sleeves, HDPE Warning
Mat (300 mm width + 5 mm X 300 micron thk.) etc. as per approved
vendor list of TGPL.
o Supply of Pipes and Valves of diameter less than 4” NB as per Approved
Vendor list of TGPL.
o Supply of all fittings such as Elbow, Tee, Flanges, Gaskets, Bolt & Nuts,
Plugs, Nipples, Socolets, Weldolets, Blinds etc., procured from approved
vendor list of TGPL is under scope of Contractor.
o Supply of O2 meter for working in confined areas, LEL meter for detecting
of any gas leakage prior to start of work. O2 meter and LEL meters shall
duly calibrated as per OEM schedule.
o Storage, Handling and Transportation of Pipes, Fittings, other project job
related material and equipment
o Stacking, Grading and Marker installation along the RoW
o Survey for utility identification.
o Procedure qualifications
o Pipe stringing and alignment along the RoW
o Excavation of trial pits / holes for utility identification and trenching.
Cable Locator for locating of any existing cable prior to start of
trenching. Local liasioning is in scope of contractor. TGPL will provide in
principal permission.
o Protection of trench using Shoring, Step cut and Shuttering
o Welding and NDT including Radiography
o Field Joint Coating
Page 9 of 60
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYING, TESTING AND COMMISSIONING OF
CGD - STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
o Provide Fabricated Caution Board and the Barricades as per the COMPANY
approved design.
o Preparation of detailed Risk register for Site Specific Risks along with
Mitigation plan for entire pipeline route.
o Conduct (Daily) site specific risk assessment with mitigation plan as per
COMPANY approved Formats.
o Entire mitigation plan shall be reviewed by TPI and approved by TGPL
o Site specific risk and Mitigation plan for entire pipeline route
o Preparation and approvals of HSE Plan
o Preparation and approvals of Project execution Plan as per time line
agreed while bidding
o Preparation and approval of resource deployment plan to complete the
project in time
o Preparation and get approval of HSE permit as per the COMPANY PTW
Matrix – Safe Working Practice.
o Conduct Tool Box talks with all involved man power at each location for
each activity and maintain record. `
o No Idle charges shall be payable to Contractor in any case.
The detail alignment, detailed route survey and soil investigation report for
proposed routes shall be provided to the CONTRACTOR by COMPANY for cross
country terrain or the pipeline in outskirts of city while for pipeline within the city
survey drawings will be made available. Also, the acquisition of Right of Use (RoW)
and statutory permission (in principal), shall be provided by Company.
The entire project shall be inspected and certified by a Third Party Inspection Agency
(TPIA), to be appointed by TGPL, from Material test certificates review, project
execution, commissioning to certification as per ASME B 31.8 “Gas Transmission and
Distribution Piping System” and PNGRB standards with any additional requirements
as demanded by the regulator for PNGRB during execution of work.
The total length of steel pipeline laying expected shall be as per the business plan
and size of the pipeline will vary from 4” NB to 16” NB depending upon the job
requirements.
2.1.2 This specification shall be read in conjunction with the conditions of all specifications
included in the BID.
2.1.3 CONTRACTOR shall, with due care and diligence, execute the work in compliance
with all laws, by-laws, ordinances, regulations, etc. and provide all services and
Page 11 of 60
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYING, TESTING AND COMMISSIONING OF
CGD - STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
2.1.4 CONTRACTOR shall take full responsibility for the stability and HSE of all operations
and methods involved in the work.
2.1.5 CONTRACTOR shall be deemed to have inspected and examined the work area and
its surroundings and to have satisfied himself so far as practicable as to the form and
nature thereof, including subsurface conditions, the extent and nature of work and
materials necessary for the completion of the work and the means of access to the
work area.
2.1.6 During the execution of work, CONTRACTOR should ensure that it should not
obstruct any or all other activities performed by other agencies.
2.1.9 Unless otherwise specified, all sections of this specification shall apply to all the
specification referred in this Contract.
Page 12 of 60
Contractor Sign & Stamp
Torrent Gas Pvt. Ltd. TECHNICAL SPECIFICATION FOR LAYING, TESTING AND COMMISSIONING OF
CGD - STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Page 13 of 60
Contractor Sign & Stamp
Torrent Gas Pvt. Ltd. TECHNICAL SPECIFICATION FOR LAYING, TESTING AND COMMISSIONING OF
CGD - STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Page 14 of 60
Contractor Sign & Stamp
Torrent Gas Pvt. Ltd. TECHNICAL SPECIFICATION FOR LAYING, TESTING AND COMMISSIONING OF
CGD - STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
CONTRACTOR shall repair at his own cost any damages caused to existing facilities.
CONTRACTOR shall execute the work in such a manner that the said structures,
utilities, pipelines etc. are not disturbed / damaged.
Despite all precaution should damage to those utilities/ structure whether or not
shown in the drawing,
• CONTRACTOR must make repair or bear the cost of making good the same
without delay to the satisfaction of the Engineer or Executive-in-charge and
authority having jurisdiction.
• If CONTRACTOR fails to repair the damage in reasonable time (agreed by
authority / TGPL) TGPL reserve the right to have it repaired at the cost of
CONTRACTOR.
• Claims / Penalties notice received from authority shall be forwarded to
CONTRACTOR by TGPL for payment and receipt or NOC from authority shall be
submitted to TGPL
• CONTRACTOR shall be liable for any damage occurring to, or resulting from
damage to other pipelines, underground structures/utilities.
In case the drawings are not available, CONTRACTOR shall dig out trial pits at no
extra cost as per direction/instruction of TGPL/TPIA to locate underground utilities.
Where the pipeline crosses other underground utilities/structures, the CONTRACTOR
shall manually excavate to a depth in such a manner that utilities/structures are
located and extra care to be taken that utilities/structures are not damaged.
Temporary under pinning or any other type of support or other protective devices
necessary to keep the interfering structure intact shall be provided by the
CONTRACTOR at his own cost and shall be of such design as to ensure against their
possible failure.
Page 16 of 60
Contractor Sign & Stamp
Torrent Gas Pvt. Ltd. TECHNICAL SPECIFICATION FOR LAYING, TESTING AND COMMISSIONING OF
CGD - STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
2.2.1.9 Crossings
For all crossings CONTRACTOR shall seek and obtain prior approval from TGPL to
lay the pipeline and shall carry out the crossing as per the instructions of the
concern owner/authorities.
Highways, Main roads, Main Gates of various industries roads and their verges
and banks of water are not allowed to be used for loading, unloading or stacking
of materials and /or equipment. For secondary roads such loading, unloading is
permitted only after prior approval from TGPL.
Owner reserves the right to demand from the CONTRACTOR for individual
crossings, a separate pre-test and /or a detailed report for approval, containing,
Time Period
Working method with equipment
Test procedure
Calculations of temporary works
The execution of the work may require working in deep trench requiring
extensive excavation ensuring all the required safety to maintain trench in
workable condition. The CONTRACTOR must plan, maintain minimum labour /
man power and necessary equipment as per the requirements of the job and
execute the pipeline construction according to prescribed schedule. No extra
costs shall be considered for such works. CONTRACTOR shall carry out
immediate restoration of crossing location and require to intimate concern
authority/owner for site visit.
Page 17 of 60
Contractor Sign & Stamp
Torrent Gas Pvt. Ltd. TECHNICAL SPECIFICATION FOR LAYING, TESTING AND COMMISSIONING OF
CGD - STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
The instrument shall be magnetic and accurate to survey the pilot hole during
drilling additionally, some deviation from the designed drilled path may be
experienced due to soil reaction. Therefore, anticipate a deviation in actual verses
designed pilot hole course of +/- 0.5% of the horizontal and vertical directions
drilled length. The error, when it is unacceptable, can be largely eliminated by re
drilling after "punch out" in the right of way limits. Best drilling standards shall be
followed to minimize the deflection as per the client’s requirements.
CONTRACTOR have to prepare and get approval of proposed bore profile
indicating depth, existing utility and pulling calculation prior to start HDD
operation.
On acceptance of drilling hole, a string on line pipe is pullback in the drilled hole
utilizing the cranes/side booms and pipe rollers to assure proper alignment and
entry angle into the hole. The entry angle is calculated and included as part of this
engineering and design package. Once the pipeline has been successfully pulled
into the drilled hole, the pull head is removed from the pipe string. The drill rig
will be demobilized and the job site secured. These activities are also a part of the
Quality Assurance responsibilities of the Driller.
Specification of HDD machine / equipment, manpower, equipment calibration as
well as HDD work is to be done as per the approved TGPL Guidelines
No extra costs shall be considered for such works.
Page 18 of 60
Contractor Sign & Stamp
Torrent Gas Pvt. Ltd. TECHNICAL SPECIFICATION FOR LAYING, TESTING AND COMMISSIONING OF
CGD - STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
installation of all electrical equipment’s, and fixtures, piping, valves and fittings;
mount all instruments and make all piping and electronic connections, etc.
The CONTRACTOR at the locations as directed by the TGPL shall install fittings,
Valves and Insulating joints. CONTRACTOR shall obtain prior approval for
procedure of joints from the OWNER before installation.
Handling and installation of the insulating joints and valves shall be carried out
with all required precautions for avoiding damage and excessive stresses and that
the original pup length is not reduced.
The insulating joints and the welded joints shall be protected by external coating.
Insulating joints shall be electrically tested before welding into the pipeline. The
electrical conductance test shall be carried out using a Megger in presence of
TGPL/TPIA. The tests shall be repeated after installation and welding of the joint
into the pipeline to verify that the assembly is undamaged.
Page 19 of 60
Contractor Sign & Stamp
Torrent Gas Pvt. Ltd. TECHNICAL SPECIFICATION FOR LAYING, TESTING AND COMMISSIONING OF
CGD - STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
qualified welder shall be used for golden joints. Golden joints shall be double NDT
tested (RT & UT) and other NDE as certified by TPIA. Golden joints shall be
identified / highlighted in pipe book. The CONTRACTOR shall propose the method
for installation / hook up of underground valves stations depending on the
methodology of carrier pipe installation (HDD or open cut methodology). The
same shall be approved by TGPL /TPIA prior to installation / hook up of
underground valves stations.
The work of prefabrication and testing shall be carried out at workshop or made
up site camp which is approved by Engineer or Executive in charge.
Page 20 of 60
Contractor Sign & Stamp
Torrent Gas Pvt. Ltd. TECHNICAL SPECIFICATION FOR LAYING, TESTING AND COMMISSIONING OF
CGD - STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
gases and all types of electrodes, filler wire, solder wire, brazing rods, flux
etc. for welding/cutting and soldering purpose.
v) All materials, equipment and instruments required for all types of tests
such as radiography, Ultrasonic testing, magnetic particle and dye
penetrate examination and any other tests as per requirement of
Owner/Owner’s Representative.
vi) All materials, equipment, instruments and consumables including primer
calibrated pump required for external corrosion coating and concrete
coating (where required) of field weld Joints.
vii) All materials, equipment, instruments and consumables required for
repair of damaged Coating of line pipe.
viii) Casing pipes, insulators and end seals and materials for casing vents and
drains as per Drawings, if applicable.
ix) All materials, equipment, instruments and consumables required for
continuous concrete Coating / Concrete slabs for providing anti buoyancy
to the pipeline, wherever required.
x) All materials, equipment, instruments, temporary vehicles required for
sand/soft soil padding around pipeline, Warning MAT, select approved
quality backfill, bank stabilization of water crossings, etc.
xi) All materials, consumables and equipment related to blasting of rock for
excavating trench or grading the Right-of-Way.
xii) All equipment and material for excavation.
xiii) Corrosion inhibitor for water used for hydrostatic testing, including water
for testing.
xiv) All equipment, pumps, instruments, pipes, fittings and equipment,
metallic blinds, temporary gaskets as required for filling, pressurizing and
dewatering for hydrostatic testing, including pipe headers for air and
hydro testing.
xv) All pigs for cleaning, gauging, filling, dewatering and swabbing of the
pipeline.
xvi) All consumables, equipment (air compressors/air dryers of suitable
capacity), instruments for drying of pipeline includes pigs as required.
xvii) All primer and paints for painting above ground piping.
xviii) All materials, equipment, instruments for lowering and back filling
and tie-in of pipeline sections.
xix) All materials, equipment required for repair/restoration of pavements,
roads, bunds, other structures affected/damaged by Contractor’s
construction activities. Materials shall be equivalent/superior to those used
for original construction of the facility.
xx) Bolts, nuts, washers, U bolts, clamps, clips, and gaskets for supports.
xxi) Shims, wedges and packing plates (machined wherever required).
Page 22 of 60
Contractor Sign & Stamp
Torrent Gas Pvt. Ltd. TECHNICAL SPECIFICATION FOR LAYING, TESTING AND COMMISSIONING OF
CGD - STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
xxii) All materials, equipment for civil and structural works, grouting etc.
xxiii) All safety tools/tackles/devices/apparatus/ equipment, etc. including
ladders and scaffolding as required.
xxiv) All materials for corrosion protection of buried piping, pipe-fittings,
valves, casing pipes, etc.
xxv) HDPE Warning mat & Protection of pipeline for HT Line crossing,
foreign pipeline crossing with PVC mat or RCC.
xxvi) All materials, equipment for all types of pipeline markers.
xxvii) Nitrogen gas if required, for filling in the pipeline system for
preservation.
xxviii) All other materials not specifically listed herein, but required for the
execution of the WORK.
Page 23 of 60
Contractor Sign & Stamp
Torrent Gas Pvt. Ltd. TECHNICAL SPECIFICATION FOR LAYING, TESTING AND COMMISSIONING OF
CGD - STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
except the materials which will be issued by the TGPL and shall take his own
arrangement for procuring such materials and transport thereof.
Completeness of the EQUIPMENT shall be the responsibility of the CONTRACTOR.
Any equipment, fittings and accessories which may not be specifically mentioned in
the specifications or drawings, but which are usual or necessary for the satisfactory
functioning of the equipment (successful operation and functioning of the
EQUIPMENT being CONTRACTOR’s responsibility) shall be provided by CONTRACTOR
without any extra cost.
The CONTRACTOR shall perform the necessary loading, unloading, hauling to points
designated by the owner and storing if necessary of the material furnished by
CONTRACTOR. The CONTRACTOR shall exercise care in handling, hauling, storing and
distribution of such materials in order to avoid damage or deterioration of these
materials.
Materials excluding line pipe shall be stored in the sheltered storage. Such materials
shall not be strung on the Right-of-way but shall be transported in conveyances for
use only at the time of installation.
CONTRACTOR shall ensure that all Pipes & valves and whenever applicable, other
materials are fitted with suitable end covers.
• CONTRACTOR shall return all the balance material at TGPL designated store
along with the necessary documents. Any discrepancies, if found in material
Page 24 of 60
Contractor Sign & Stamp
Torrent Gas Pvt. Ltd. TECHNICAL SPECIFICATION FOR LAYING, TESTING AND COMMISSIONING OF
CGD - STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Page 25 of 60
Contractor Sign & Stamp
Torrent Gas Pvt. Ltd. TECHNICAL SPECIFICATION FOR LAYING, TESTING AND COMMISSIONING OF
CGD - STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
The location of work site shall be provided in detail job order issued from time to
time.
Page 27 of 60
Contractor Sign & Stamp
Torrent Gas Pvt. Ltd. TECHNICAL SPECIFICATION FOR LAYING, TESTING AND COMMISSIONING OF
CGD - STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
The CONTRACTOR shall without prejudice to his overall responsibility to execute and
complete the work as per specifications, time agreed in Job order, progressively
deploy at site adequate equipment, tools and tackles and augment the same as
decided by the TGPL/TPIA depending on the exigencies of work so as to suit the
construction schedule. All equipment shall be “FIT FOR USE”. Audit / Inspection of all
equipment shall be carried out by TGPL/TPIA at CONTRACTOR place / site prior to
mobilize equipment for TGPL.
Site Organization
The CONTRACTOR shall not recruit personnel of any category from among those who
are already employed by other agencies working at the various sites of TGPL.
However, CONTRACTOR shall give priority and make maximum use of local workers
available. If in any case CONTRACTOR wants to recruit personal of any category from
among those who are already employed by other agencies working at the various
sites of TGPL than CONTRACTOR have to get No Objection Certificate from other
agencies.
Page 28 of 60
Contractor Sign & Stamp
Torrent Gas Pvt. Ltd. TECHNICAL SPECIFICATION FOR LAYING, TESTING AND COMMISSIONING OF
CGD - STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
2.2.3.7 Land for CONTRACTOR’s Field Office, Godown, Store, Camp and Workshop
The CONTRACTOR shall at his own cost hire the facilities or provide land to construct
all these temporary facilities including camp site for technical staff and for
excavation workers, line pipe stockyard and provide suitable water supply and
sanitary arrangements. TGPL as a part of mobilization would audit the facilities with
respect to HSE requirements.
a) Camp Site / Land for
• Suitable water supply and sanitary arrangements
• Health and Hygienic conditions
• First Aid facilities
• Fence and security
b) Pipe yard / Godown with
• Secured Boundaries
• Elevated or prevented against logging of water
• Stable ground for stocking of line pipes and the vehicular movements
• Stable approach for Movements of pipe loaded tailor
• Support to avoid rolling over of pipe from pipe stack
• Covering protection against Rain
• Covering of end of pipe by night cap
• Free from passing over head electrical wire
• First Aid facilities
The contractors need to clearly separate out the camp yard and pipe yard for risk
reduction purpose.
the correctness of the details given in the Bid Document to help the CONTRACTOR to
take up the Bid is not guaranteed.
CONTRACTOR shall be deemed to have inspected and examined the work area and
its surroundings and to have satisfied himself so far as practicable as to the form and
nature thereof, including subsurface conditions, the extent and nature of work and
materials necessary for the completion of the work and the means of access to the
work area.
CONTRACTOR shall be deemed to have obtained all necessary information on subject
as mentioned above as to risks, contingencies and all other circumstances, which
may influence the work.
Page 30 of 60
Contractor Sign & Stamp
Torrent Gas Pvt. Ltd. TECHNICAL SPECIFICATION FOR LAYING, TESTING AND COMMISSIONING OF
CGD - STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Page 31 of 60
Contractor Sign & Stamp
Torrent Gas Pvt. Ltd. TECHNICAL SPECIFICATION FOR LAYING, TESTING AND COMMISSIONING OF
CGD - STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
authorized representatives present who have free access to the work at all time. If
TGPL/TPIA’s representative notifies the CONTRACTOR’s authorized representative
not lower than a foreman of any deficiency, or recommends action regarding
compliance with the specifications, and the HSE, the CONTRACTOR shall make every
effort to carry out such instructions to complete the work conforming to the
specifications. HSE requirements and approved drawings in the fullest degree
consistent with best engineering practice.
2.2.4.5 Documentation
“AS BUILT” DRAWINGS”
Notwithstanding the provisions contained in standard specifications, upon
completion of WORK, the CONTRACTOR shall complete all of the related drawings to
the “AS BUILT” stage (including all vendor / sub vendor drawings for bought out
items) and provide the owner, the following.
Two complete set of full size (Alignment Sheets) reproducible drawings (Soft
Copies - Digital format, in latest available version / informed by TGPL of
AutoCAD, in CDs – 3 sets)
One complete set of original size prints (Hard Prints) and Two Xerox copy of
the same.
Soft copies / scan copies of all project documents in CDs or USB – 3 Sets
“Hand Over Take Over Document”
CONTRACTOR shall prepare and submit Hand over Take over Documents (3 Set)
along with as built drawing one day before the commissioning as part of
documentation.
Page 32 of 60
Contractor Sign & Stamp
Torrent Gas Pvt. Ltd. TECHNICAL SPECIFICATION FOR LAYING, TESTING AND COMMISSIONING OF
CGD - STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
HSE activities
OHSAS:18001 & ISO:14001 Compliance documents
Training / HSE briefing records
HSE Plan and Review Documents
Records of SSRA & Tool Box talk
Records of Closing of Non Conformities
Site photos
Final Closeout report
Waste Disposal records
This shall as a minimum include but not limited to the following: -
Page 33 of 60
Contractor Sign & Stamp
Torrent Gas Pvt. Ltd. TECHNICAL SPECIFICATION FOR LAYING, TESTING AND COMMISSIONING OF
CGD - STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Daily:
a) Progress Report
Page 34 of 60
Contractor Sign & Stamp
Torrent Gas Pvt. Ltd. TECHNICAL SPECIFICATION FOR LAYING, TESTING AND COMMISSIONING OF
CGD - STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Page 35 of 60
Contractor Sign & Stamp
Torrent Gas Pvt. Ltd. TECHNICAL SPECIFICATION FOR LAYING, TESTING AND COMMISSIONING OF
CGD - STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Page 36 of 60
Contractor Sign & Stamp
Torrent Gas Pvt. Ltd. TECHNICAL SPECIFICATION FOR LAYING, TESTING AND COMMISSIONING OF
CGD - STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Page 37 of 60
Contractor Sign & Stamp
Torrent Gas Pvt. Ltd. TECHNICAL SPECIFICATION FOR LAYING, TESTING AND COMMISSIONING OF
CGD - STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
j. Risk Mitigation plan for each risk is decided as per the OSHAS Risk register
communicated by TGPL.
k. First aid facilities are maintained at each site, office, store, vehicles with
trained first aid provider
l. A Toolbox talk is conducted at each site / activities with all the involved to
updates them on each risk with required Mitigation action.
3. CONTRACTOR shall erect and maintain barricade required in connection with
this operation to guard the work site as directed by TGPL (Specification of
Barricade provided TGPL).
4. “CONTRACTOR” shall ensure proper disposal of solid / liquid waste and shall
ensure to follow the legal requirements associated with waste handling and
shall maintain waste disposal record. If found appropriate, these requirements
shall form part of the HSE orientation discussions held before commencement
of the job.
5. “CONTRACTOR” must ensure that tools, appliances, machines, vehicles or other
equipment which are going to be used for the job are periodically inspected and
maintained. The “CONTRACTOR” shall maintain records of these inspections and
modification activities. TGPL reserves the rights to verify these records and
prohibit use of items not found fit for use.
6. “CONTRACTOR”'s personnel shall not smoke or resort to misuse of drugs,
medicines or alcohol while on duty. “CONTRACTOR” shall also ensure that in no
case the ability of his employees to carry out their assigned duty is impaired by
use of the substances mentioned herein.
7. “CONTRACTOR” shall comply with all applicable statutory requirements.
8. No child labour below 18 years of age shall be employed by the “CONTRACTOR”
during the execution of job.
9. Qualified employee, if behave unsafely at site shall be disqualified for working at
site
10. The safe working practice Guideline for specific pipeline construction related
activities is implemented during execution of projects.
11. CONTRACTOR shall ensure that as a minimum, but not limited to, these
guidelines shall be followed and ensured by its personnel / sub-CONTRACTOR at
work site / office at all the times.
Page 38 of 60
Contractor Sign & Stamp
Torrent Gas Pvt. Ltd. TECHNICAL SPECIFICATION FOR LAYING, TESTING AND COMMISSIONING OF
CGD - STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
2.2.5.6 Lighting
Proper lighting shall be arranged at work site in case the day lighting is insufficient.
Recommended illumination level shall be as follows
Hand lamp shall be used with protective cover/guard and double insulated
wire
2.2.5.7 Equipment
All the equipment present on the site, regardless of its purpose, must be kept in
faultless condition and be suited to the work (Fit for Purpose) to be carried out.
Activity wise critical equipment shall be identified and list will be prepared. Identified
equipment will be checked through government approved and recorded.
The equipment must be regularly checked by an authorized person and any defect in
the equipment must immediately be repaired and action taken report is filled Safety
devices which were originally part of the equipment must never be removed or
adapted without the express approval of the owner and/or the engineer and after
the submission of a clear written justification for the adjustment concerned.
The instruction for use and safety and health instruction must be made available
upon simple request by the owner.
Page 40 of 60
Contractor Sign & Stamp
Torrent Gas Pvt. Ltd. TECHNICAL SPECIFICATION FOR LAYING, TESTING AND COMMISSIONING OF
CGD - STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
fall prevention systems viz. Scaffoldings, platforms etc. apart from the above all
personnel shall be provided with safety harnesses as line of defence.
All scaffolds and ladders shall be inspected by Designated Competent person
before allowing personnel to work at heights.
It is ensured that the persons trained in working with safety belt, fall arrestor,
scaffolding are allowed to work at height.
A warning tape just below the work at height is provided and warning boards are
displayed to restrict entry into that protected area. This is ensured to protect the
injury to the person due to fall of object or person from height.
2.2.5.9 Electrical Safety on Site
Inspection
every electrical installation at site, including generators, distribution cabinets, etc
will be inspected on site by a Recognized inspection agency before it is brought in
to service; any defect must be reported immediately.
Cables and connections
Distribution panels must remain closed at all times during use. The connection to
distribution panels may only be made using approved and waterproof plugs.
The electrical cables for connection to the various users of site electricity shall be in
impeccable condition and shall be protected in a sufficient manner. In places where
traffic must run over the connecting cables, they must be buried with a protective
sleeve. The same rules are applicable for the connections of the cables.
Furthermore, they must be watertight.
Page 41 of 60
Contractor Sign & Stamp
Torrent Gas Pvt. Ltd. TECHNICAL SPECIFICATION FOR LAYING, TESTING AND COMMISSIONING OF
CGD - STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Electrical tools
Electrical hand-tools must confirm to the stipulations of the regulations of the
Country concerned, be in impeccable condition and be suitable for the work to be
carried out. They must be properly earthed or double-insulated.
Welding transformer and generators must be equipped with a power limiter that
will guarantee the prescribed safety current.
In closed area, tunnels, deep construction pit and damp crawling spaces, only tools
with safety current may be use.
Page 42 of 60
Contractor Sign & Stamp
Torrent Gas Pvt. Ltd. TECHNICAL SPECIFICATION FOR LAYING, TESTING AND COMMISSIONING OF
CGD - STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Page 43 of 60
Contractor Sign & Stamp
Torrent Gas Pvt. Ltd. TECHNICAL SPECIFICATION FOR LAYING, TESTING AND COMMISSIONING OF
CGD - STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Page 44 of 60
Contractor Sign & Stamp
Torrent Gas Pvt. Ltd. TECHNICAL SPECIFICATION FOR LAYING, TESTING AND COMMISSIONING OF
CGD - STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
r. While lifting/lowering pipes by crane, one end of pipe should be tied with a
rope with other end of the rope (Tag Line) held by competent rigger to avoid
dancing of hanged pipes.
s. Adequate lighting arrangement and warning signals to be provided while under
taking operations in night.
t. Ensure that the operator must properly secure the crane and boom in safe way
before going off duty or when operations are shut down.
Page 45 of 60
Contractor Sign & Stamp
Torrent Gas Pvt. Ltd. TECHNICAL SPECIFICATION FOR LAYING, TESTING AND COMMISSIONING OF
CGD - STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Page 46 of 60
Contractor Sign & Stamp
Torrent Gas Pvt. Ltd. TECHNICAL SPECIFICATION FOR LAYING, TESTING AND COMMISSIONING OF
CGD - STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
d. While using two or more lifting equipment to lift/lower the pipe section,
proper balancing is must. Approved lifting plan shall be available at site.
e. Signals to the operators shall be given by only one authorized person to avoid
any confusion. However, STOP signal given by any one will be obeyed for
emergency.
f. Overhead electric lines, poles, trees etc. must be watched during operation.
g. Unsafe poles in the trench must be tied with ropes before lifting pipe section.
k. Load should be lifted within the safe working load capacity of lifting equipment
and tackles.
l. Instead of shifting lifted load by cranes, load should be lowered and change the
suitable location of the cranes accordingly.
Page 47 of 60
Contractor Sign & Stamp
Torrent Gas Pvt. Ltd. TECHNICAL SPECIFICATION FOR LAYING, TESTING AND COMMISSIONING OF
CGD - STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
m. Lifting and lowering operation should be done slowly, without sudden jerks.
Page 48 of 60
Contractor Sign & Stamp
Torrent Gas Pvt. Ltd. TECHNICAL SPECIFICATION FOR LAYING, TESTING AND COMMISSIONING OF
CGD - STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
A. Electric Welding:
Page 49 of 60
Contractor Sign & Stamp
Torrent Gas Pvt. Ltd. TECHNICAL SPECIFICATION FOR LAYING, TESTING AND COMMISSIONING OF
CGD - STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Page 50 of 60
Contractor Sign & Stamp
Torrent Gas Pvt. Ltd. TECHNICAL SPECIFICATION FOR LAYING, TESTING AND COMMISSIONING OF
CGD - STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
l. Electrode holder when not in use shall be placed on insulated hook. Live
electrode shall not be left on welding shield, gloves or cables and should not be
left unattended.
m. Arc weld rod size and amperage of the machine shall be left to the desecration
of experienced, qualified welder and shall be within the limits of a required
procedure.
n. The welding operation shall be adequately sheltered from wind. Work should
be avoided on wet location/rain.
o. After a welding job completed, the material/work piece should be chalk
marked ‘HOT’ to warn other workers.
p. Whenever welding is discontinued, machine shall be isolated by operating both
switches on the machine and on the power supply line.
q. Ensure adequate fire extinguishers are available at site with trained personals
in fire-fighting.
B. GAS CUTTING & HEATING OPERATION
a. Gas cutting/heating work shall be done by skilled/experienced person.
b. Before starting work, all hoses, blow pipe, torch, pressure regulators, gauges
and all connections shall be checked thoroughly for any defects, leakage, by
experienced person. Greasy or oil soaked hoses shall not be used.
c. No cutting/heating job shall be carried out unless suitable regulator and
pressure gauges are provided.
d. Only standard keys or spanners shall be used to open or close cylinder valves.
During work leave key in position on the cylinders for use in emergency.
e. Oxygen cylinder valves and fittings shall never be handled with oily or greasy
hands. Acetylene cylinder and accessories, hoses, torches etc. shall never be
fitted with parts of copper or copper alloys to avoid forming of explosive
compounds.
f. Hoses should be examined before use. Defective hoses shall never be used and
replaced immediately.
g. Oxygen and fuel gas hoses shall not be interchanged. (Black or green hose for
oxygen, while red or maroon hose for fuel gas).
Page 51 of 60
Contractor Sign & Stamp
Torrent Gas Pvt. Ltd. TECHNICAL SPECIFICATION FOR LAYING, TESTING AND COMMISSIONING OF
CGD - STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
h. Hoses should not rout over the shoulder or between the legs of persons
engaged in works. Hoses shall be protected from falling sparks, flames or slag
and damaging by sharp objects.
i. Hoses in use should be replaced when a flash back occurs as it may sustain
unseen internal damage. While lighting torch, care shall be taken that flame
should not affect any part of the body of self or fellow workers. Torch shall not
be dropped during operation.
j. During work breaks torches must be extinguished and lighted torch shall never
be left unattended.
k. In case of leakage developing in cylinder, same shall be removed immediately
from the work to open & safe space.
l. Cylinders should never be allowed to come in contact with live electric wires
and shall be protected from sparks, flames, arc or slag falling from welding and
cutting operations.
m. After completion of job, cylinder valve should be tightly closed, re-place the cap
and store at the proper place.
n. Ensure flame arrestors / NRVs on Oxygen & Acetylene cylinders.
o. Ensure adequate fire extinguishers are available at site with trained personals
in fire-fighting.
Page 52 of 60
Contractor Sign & Stamp
Torrent Gas Pvt. Ltd. TECHNICAL SPECIFICATION FOR LAYING, TESTING AND COMMISSIONING OF
CGD - STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
e. The user should wear appropriate dress & safety equipment like, safety
goggles, face shields, safety shoes etc., for protection against flying metal chips.
f. Earthing / grounding must be provided for electric tools.
g. Never start machine when its rotating component is in contact with work piece
or any object. Ensure that the moving parts have come to a complete stop,
before placing it on the floor.
h. Excess force during its use may break the disc /tool resulting in accident.
i. Special care must be taken while using it in overhead position.
j. Power supply should be disconnected after completion of the job and tool
should be stored in proper safe place.
k. Use double insulated portable power tools.
l. Use of grinding disc with correct speed rating. Never use disc whose validity is
expired.
Page 53 of 60
Contractor Sign & Stamp
Torrent Gas Pvt. Ltd. TECHNICAL SPECIFICATION FOR LAYING, TESTING AND COMMISSIONING OF
CGD - STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Work site should be always kept clean to the entire satisfactions of the TGPL/TPIA.
Before handing over any work to TGPL, the CONTRACTOR in addition to other
formalities to be observed as detailed in the document shall clear the site to the
entire satisfaction of TGPL/TPIA.
The CONTRACTOR shall carryout restoration as per permission authority
requirements mentioned in Permit and also as per the satisfaction of the
nominated person of the authority at no extra cost to TGPL.
Page 54 of 60
Contractor Sign & Stamp
Torrent Gas Pvt. Ltd. TECHNICAL SPECIFICATION FOR LAYING, TESTING AND COMMISSIONING OF
CGD - STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
familiarity with the site conditions will not be considered a reason either for
extra claims or for not carrying out work in strict conformity with drawings and
specifications and TGPL HSE requirements.
f) In case of contradiction between referred Standard, General Conditions of
Contract, Special Conditions of Contract, Specifications, Drawings, Schedule of
Rates, the following shall prevail in order of precedence.
CONTRACTOR shall strictly adhere to the Quality Assurance Plan agreed with the
TGPL.
During the execution of work, entire / part activity shall be carried out under the
"Third Party Inspection". The brief scope of TPIA shall be as follows:
SR.
ACTIVITY DESCRIPTION PROPOSED SCOPE FREQUENCY
NO.
[A] – Pipeline
Page 55 of 60
Contractor Sign & Stamp
Torrent Gas Pvt. Ltd. TECHNICAL SPECIFICATION FOR LAYING, TESTING AND COMMISSIONING OF
CGD - STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
1 Review of Documents;
1.1 Material Test certificate (CONTRACTOR bought Review
out material)
1.2 Material Test certificate for consumables Review
1.3 Instrument calibration Review / Witness
1.4 Instrument Test certificate Review
1.5 WPS / PQR, Drawings: Alignment sheet & cross Witness & Review
sections
1.6 Verification of Measurement Sheet for Bill Review
2 Pipeline Construction;
2.1 Trenching & Backfilling Random Inspection Daily
2.2 Welding & Laying Random Inspection Daily
2.3 Stringing & Hauling Random Inspection Daily
2.4 Field Joint Coating & Coating repair Random Inspection Daily
2.5 Lowering Witness Daily
2.6 Review of construction reports Random Inspection Daily
2.7 Canal crossings Witness, Check, Review Daily
Page 56 of 60
Contractor Sign & Stamp
Torrent Gas Pvt. Ltd. TECHNICAL SPECIFICATION FOR LAYING, TESTING AND COMMISSIONING OF
CGD - STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
4 Testing;
4.1 Approval of Pipe book Review
4.2 Hydro testing including pigging, final cleaning & Witness
drying
4.3 Pneumatic Testing Witness
5 Pre-commissioning Witness
6 Commissioning Witness
7 HSE Compliances
7.1 Site Specific Risk Assessment and Witness Daily
ensuring risk mitigation plan in place
7.2 Tool Box Talk Participation / Briefing Daily
7.3 Lesson Learnt Sharing Briefing As when
required
7.4 Un Safe actions Interventions Daily
7.5 HSE Documentation / Data Verifications Daily
[B] – Cathodic Protection
1 Approval of Documents;
1.1 TCP design basis document and detail design Approval
document
1.2 Material and Equipment Specification and Data Approval
sheet
1.3 Detail Bill of Material Approval
1.4 QA/QC Plan Approval
SR.
ACTIVITY DESCRIPTION PROPOSED SCOPE FREQUENCY
NO.
Page 57 of 60
Contractor Sign & Stamp
Torrent Gas Pvt. Ltd. TECHNICAL SPECIFICATION FOR LAYING, TESTING AND COMMISSIONING OF
CGD - STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
2 Review of Documents;
2.1 Material Test certificate (CONTRACTOR issue Review
material)
Instrument calibration
3 Installation
3.1 TLP Unit Random Inspection Daily
4 Testing and Commissioning of TCP System Witness
5 Final Document Handover Review and Handover
During the execution of work, entire / part activity shall be carried out under the
"Third Party Inspection". The brief scope of TPIA shall be as follows:
“Prepared” shall means collect information and documents, and reporting to the
concern persons.
“Perform” shall means deliver / execute actions to deliver the required level of
performance
“Certification” shall mean ensures and confirm the quality parameter confirming to
code, standards and the specifications
The work referred in this bid is for laying of gas pipeline ranging from 4” dia to 16”
dia underground and above ground installations.
The work requires a special skill and attention as majority work will be on gas
network. The contractor is required to understand the full scope of work detailed in
the bid. The contractor is also required to keep sufficient equipment, skilled
manpower to act on an emergency work that may arise while executing the hook up
on live pipeline without any additional cost to TGPL.
Page 59 of 60
Contractor Sign & Stamp
Torrent Gas Pvt. Ltd. TECHNICAL SPECIFICATION FOR LAYING, TESTING AND COMMISSIONING OF
CGD - STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
case, CONTRACTOR shall submit relevant “Job Execution Statement” along with
resource allocation and planning before starting the contract. The same shall be
properly supported with proposed manpower and equipment deployment chart.
In case of any injury or an accident at the site, the CONTRACTOR shall immediately
inform the TGPL Engineer of the incident and further take immediate steps to take
the injured person(s) to any of the TGPL nominated hospitals.
The following critical parameter describes the system performance and service level
expectations and requirements during the Implementation phase of contract. The
service level includes target performance measures, unacceptable measures and the
related penalties for not meeting required service levels.
Page 60 of 60
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
(Technical specification)
PIPELINES
Page 1 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Index
Page 2 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Page 3 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
TABLE OF CONTENTS
1. SCOPE
2. REFERENCE CODE AND STANDARD
3. SUBMITTAL BY CONTRACTOR
4. REQUIREMENTS OF RIGHT OF WAY ACCESS THERETO
5. RIGHT- OF- WAY
6. HANDLING, HAULING, STRINGING AND STORING OF MATERIALS
7. TRENCHING
8. BENDING
9. LINING UP
10. LOWERING IN TRENCH
11. BACKFILLING
12. SPECIAL INSTALLATION ON THE PIPELINE
13. WORKING SPREAD LIMITATIONS
14. CLEAN-UP AND RESTORATION OF RIGHT OF WAY
15. DOCUMENTATION
Page 4 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
1. SCOPE
1.1 This specification covers the minimum requirements for the various activities to be
carried out by CONTRACTOR for the construction of Natural gas pipeline in CGD
Networks.
1.2 The various activities covered in this specification include the following work of
pipeline construction:
Establishing and Preparation of Right of Way for Construction of pipeline with
reference to the route maps.
Handling, Hauling, Storage and Stringing of pipeline and Materials.
Trenching for laying of Pipeline.
Forming of vertical and horizontal Cold Field Bends.
Laying of pipe section in the Trench
Pipe Laying through HDD
Tie-ins of pipeline section
Connectivity of newly laid network with existing charged network
Hydro and Pneumatic testing
Drying of Pipeline
Commissioning of Pipe Line Network
Backfilling of Trench.
Restoration of ROW.
Special Installation on the Pipeline
1.3 It is intended that all the work performed in accordance with this specification shall
meet or exceed the requirement of governing and reference standards & codes
1.4 This specification shall be read in conjunction with the conditions of all specification
and documents included in the CONTRACT between TGPL/TPIA and CONTRACTOR.
1.5 CONTRACTOR shall, with due care and diligence, execute the WORK in compliance
with all laws, by-laws, ordinances, regulations, etc., and provide all service and
labour, inclusive of supervision and all materials, excluding the material indicated as
TGPL supplied materials in the CONTRACT, equipment appliances or other things of
whatsoever nature required in or about the execution of the work, whether of a
temporary or permanent nature.
1.6 CONTRACTOR shall take full responsibility for the stability and safety of all operations
and methods involved in the work.
1.7 CONTRACTOR shall be deemed to have inspected and examined the work area(s) and
its surrounding and to have satisfied himself as far as practicable as to the form and
nature thereof, including sub-surface conditions, hydrological and climatic
Page 5 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
conditions, the extent and nature of the work and materials necessary for the
completion of the work and the means of access to the work area (s). Extra care shall
be taken as and when work area is adjacent to Canal and crop.
1.8 CONTRACTOR shall be deemed to have obtained all necessary information on all
subjects as above mentioned as to risks, contingencies and all other circumstances,
which may influence the work.
1.9 CONTRACTOR shall, in connection with the work, provide and maintain at his own
costs, all lights, guard, fencing, watching etc., when and where necessary or required
by TGPL/TPIA or by any duly constituted authority and / or by the authorities having
jurisdiction thereof for the protection of the work and properties or for the safety
and the convenience of public and / or others.
1.10 Unless otherwise specified, all sections of this specification shall apply to all activities
referred in this specification.
Page 6 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
3. SUBMITTAL BY CONTRACTOR
3.1 The CONTRACTOR shall submit the Procedures for EQT, WPS, Right of way, stringing,
Handling & Storage of Line Pipes, Trenching, Cold Field Bending, Lowering, Backfilling,
Crossing by open cut and HDD, Installation of SV and Restoration along with quality
records (Activity format, Inspection test plan), etc. at least one week prior to
commencement of the work for approval of TGPL/TPIA.
3.2 The CONTRACTOR shall submit Inspection test plans for all the activities compatible
to this specification at least one week prior to commencement of the work for
approval of TGPL/TPIA.
3.3 The CONTRACTOR shall submit the Procedure for mitigation of risks related to each
activities and the site for Right of way, Material loading, unloading and
transportation, stringing, Storage of Line Pipes, Trenching, Cold Field Bending,
Lowering, Backfilling, tie-ins, Installation of SV and Restoration along with HSE
records
4. REQUIREMENTS OF RIGHT OF WAY ACCESS THERETO
4.1 General
4.1.1 CONTRACTOR shall, before starting any clearing operations, familiarize himself with
all the requirements of the Applicable Authorities having jurisdiction over the Right
of way (ROW) for work along the pipeline routes or in connection with the use of
other lands or roads for construction purposes.
Page 7 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
4.1.2 CONTRACTOR shall notify TGPL/TPIA well in advance during work progress, the
method of construction for crossing road, pipeline, cable, railway, river, canal and
other existing obstacles. The risks associated with proposed pipeline, mains and
service routes shall be assessed to ensure that all reasonably practicable steps have
been taken to minimize the risks to people & property in the event of an unplanned
release of Gas.
4.1.3 CONTRACTOR shall commence work on such crossing after getting approval from the
authorities and landowners concerned to the satisfaction of TGPL/TPIA. The crossings
shall be installed to meet at all times the requirements and specification. In the
absence of any specific requirements by authorities, CONTRACTOR shall comply with
TGPL’s instructions.
4.1.4 The right of ingress and Egress to the ROW shall be limited to points where such
ROW intersects public roads. Arrangements for other access required by the
CONTRACTOR shall be made by him at his own cost and responsibility and for such
access the conditions of this specification shall also apply.
4.1.5 Where the ROW comes within 1.0 Meter of an existing line or facility, CONTRACTOR
shall propose and provide methods to safe-guard the existing line or facility (e.g. a
demarcation fence). No work is allowed in such area without TGPL/TPIA prior
approval.
4.1.6 Pipeline, which is constructed inside the area of high voltage lines, may be electrically
influenced by this high voltage line. The voltage caused by the influence may at times
be so high as to pose a danger to personnel working on the pipeline. It is imperative
therefore, that the instructions given in section 4.2 shall be strictly observed.
4.2 Instructions concerning HIGH VOLTAGE INFLUENCED SAFETY measures during
construction of pipelines inside the area influenced by high voltage lines
4.2.1 It is a prerequisite that all personnel working on the pipeline which is being laid in the
area influenced by the high voltage system, be given clear instructions on measures
to be taken.
4.2.2 Vehicle and equipment shall be earth-connected. This may be effected by attaching
an un-insulated cable or chain (which touches the ground) of adequate length to the
underside of the vehicle.
4.2.3 If it is not possible for plant and / or materials to come beyond 50m of the centre of
the high voltage system, special measures must be taken to prevent any approach
beyond that distance, unless section 4.3 is complied with.
4.2.4 During thunderstorms or when discharges are observed on insulators all personnel
shall leave the area of the high voltage line and pipeline
Page 8 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
4.2.5 To prevent electrical voltages in a non-buried section of the pipeline from rising to
dangerous values, the length of the pipeline section which has been welded together
before burial shall not exceed the length at which the max. admissible voltage may
be induced. This length may on calculated using an approved calculation method.
4.2.6 Before a pipeline section is lowered into the trench, the structure's earth electrodes
indicated in the drawings or determined with calculation method must have been
installed and connected both to the pipeline section already buried and to the
section which is about to be buried. The electrical connections, which serve the
purpose of preventing dangerous voltages, shall have a min. area of 35 mm2.
Side connections shall not be interrupted until after the permanent safety earth
connections have been installed and connected to the entire uninterrupted pipeline.
Personnel doing work inside the area influenced by the high voltage systems must
wear electrically insulating footwear (e.g. rubber knee boots) and wear insulating
rubber or plastic gloves.
4.3 Additional measures for work at less than 50m from the centre of the high voltage
system.
If work is done at less than 50m from the centre of the high voltage system, the
regulations below shall be complied with in addition to the rules specified in section
4.2
4.3.1 The work shall not be started until agreement has been reached with the authorities
who control the high voltage system, about the implementation of the safety
measures specified in this section (Lock-out & Tag out done & signed off)
4.3.2 Measures shall be taken to prevent excavating and hoisting equipment’s from
approaching high voltage lines to within any of the following distances. Adherence to
latest addition of The Indian Electricity Rules, 1956 is to be strictly maintained.
This distance depends on the voltage carried for individual connections the
distance must be:
0 to 50Kv - 3m
40 to 200Kv - 5m
200 to 380Kv - 8m
Page 9 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Page 11 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
5.3.7 In the case of natural or artificial deposits of loose soil, sand heaps of earth or
other fill materials, these shall be removed till stable natural ground level is
reached so as to ensure the construction of the pipeline ditch in stable ground.
5.3.8 In the case of RoW clearing and grading on the hillside or in steep slope areas,
proper barriers or other structures shall be provided to prevent the removed
materials from rolling downhill. The RoW cross fall shall not exceed 10%.
5.3.9 Wherever the pipeline RoW runs across, through or alongside farmyards, built-
up areas, groups of trees, groves, horticultural spreads, gardens, grass-fields,
ditches, dikes, roads, paths, railways or any other area with restrictions of some
kind, CONTRACTOR shall grade only the width of the RoW necessary for digging
the pipeline trench and constructing the pipeline. In the said place CONTRACTOR
shall carry out the work in such a way that damage resulting from the pipeline
construction is kept to a minimum.
5.4 PROVISION OF DETOURS
5.4.1 CONTRACTOR shall do all necessary grading and bridging at road, water and
other crossings and at other locations where needed, to permit the access for
men and equipment. It is understood that the CONTRACTOR has recognized such
restrictive features of the RoW and shall provide the necessary detours and
execute the works without any extra cost to TGPL. Public travel shall not be
inconvenienced nor shall it be wholly obstructed at any point.
5.4.2 CONTRACTOR, at his own cost, shall furnish and maintain at detour watchman,
lanterns traffic lights, barricades, signs, wherever necessary to fully protect the
public.
5.4.3 CONTRACTOR shall be responsible for moving its equipment and machineries on
or around watercourses. This may require the construction of temporary bridges
or culverts. Temporary bridging or access to fording required for RoW crossing
watercourse shall be constructed. CONTRACTOR shall ensure that such
temporary works shall not interfere with normal water flow, avoid overflows,
keep the existing morphology unchanged and shall not unduly damage the banks
of water course. No public ditches or drains shall be filled or bridged for passage
of equipment until CONTRACTOR has secured written approval of the Authorities
having Jurisdiction over the same. CONTRACTOR shall furnish TGPL/TPIA a copy
of such approval.
5.5 RIGHT–OF-WAY DAMAGES
5.5.1 CONTRACTOR shall confine all its operation within limits of the RoW. Any damages
to property inside or outside ROW shall be restored or settled to the
CONTRACTOR’s account.
Page 12 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
5.5.2 CONTRACTOR shall promptly settle all off RoW damage claims. If CONTRACTOR is
fails to do so, TGPL/TPIA shall give written notice to CONTRACTOR. If CONTRACTOR
does not settle such claims within seven days after such notice, TGPL’s shall have
the authority to settle claims from the account of CONTRACTOR.
In case of damage of the branch canal, CONTRACTOR shall get it repaired on his
own cost and as per farmer satisfaction. In no case, CONTRACTOR shall dump the
soil in farms or on the bank of the canal.
CONTRACTOR shall be fully responsible for the damage of the vegetation and crop
compensation.
CONTRACTOR shall ensure proper disposal of Bentonite as per vendor
recommendation.
Correctness of road level if damaged (due to poor quality of work) after raining or
water seepage shall also be addressed by CONTRACTOR on his own cost
immediately.
Page 13 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Damaged pipe shall be reported to TGPL immediately on receipt and same shall be
recorded.
CONTRACTOR shall notify TGPL/TPIA well in minimum one week in advance for
issue of line pipe from TGPL. In case of delays in takeover of TGPL supplied
materials due to non-availability of resources, CONTRACTOR shall be fully
responsible for the delay and rearranging means of transportation at no extra
cost to TGPL. Any claim by the transporter for undue delay in taking over of the
material shall be settled to contractor’s account.
Unloading, stacking of line pipe (at CONTRACTOR’s decided site stacking yard) on
proper sandbags, fencing and safe guarding of storage yard shall be the
responsibility of the CONTRACTOR. Material receipt register shall be maintained
at storage yard and daily receipt shall be intimated to TGPL/TPIA.
6.3 HANDLING OF LINE PIPE
6.3.1 To avoid damages to the pipe and Coating the CONTRACTOR shall
Load, unload, transport and stockpile the coated pipes using approved
suitable means and manner.
Use vacuum lifting equipment (suitable handling equipment’s with proper
length of booms). Hooks may also be used for handling the pipes provided
they are covered with soft material like rubber, Teflon or equivalent.
Ensure Hoisting crane / wire ropes have sufficient inclination compared to
pipe axis so that they do not come into contact with external coating.
Handle the pipes by means of belts of proper width made of non-
metallic/non-abrasive materials and pipes to be stacked separated row by
row.
Not bump coated pipes against any other pipe or any other objects. Rolling,
skidding or dragging shall be strictly forbidden.
Stack the pipe, completely clear from the ground so that the bottom row of
pipes remains free from any surface water. The pipe shall be stacked at a
slope so that driving rain does not collect inside the pipe. The line pipes shall
be stored so that there is no fouling with each other.
Stack the coated pipes by placing them on ridges of sand / sand bags, free
from stones and covered with a plastic film. The supports shall be spaced in
such a manner as to avoid permanent bending of the pipes.
Stack limited number of pipe layers so that the pressure exerted by the
pipe's own weight does not cause damages to the coating. Stack shall be
suitably secured against falling down and shall consist of pipe section having
the same diameter and wall thickness.
Page 14 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
6.3.2 Coated pipes stacked in open storage yards/dump yards shall be suitably
covered on top to avoid direct exposure to sunlight. The ends of the pipes
during handling and stacking shall always be protected with bevel protectors.
6.3.3 The trailer shall be equipped with adequate pipe supports having as many
round hollow beds as the number of pipe to be paved on the bottom of the
lorry bed. Supports shall be provided for at least 20% of the pipe length, using
suitable means and in a manner to avoid damages to the pipe and coating.
CONTRACTOR shall submit to Company a complete procedure indicating the
manner and arrangement used for handling and staking of coating pipes for
company approval prior to commencement of handling operation. All
stanchions of Lorries / Trailer used for transportation shall be covered by non-
abrasive material like rubber belts or equivalent. Care shall be exercised to
properly cover the top of the stanchions and convex portions to prevent the
damage to the coated surface. Line pipes shall be entirely within the Lorries /
trailer so as to prevent case hardening / mechanical stresses due to cantilever
loading of the pipes.
6.3.4 Pipes which are damaged at the time of delivery or "taking-over" (when line
pipe is supplied by TGPL), particularly those which are dented, buckled, or
otherwise permanently deformed, must be stacked separately and may be
transported to the sites only when these defects have been repaired or
eliminated.
6.4 STRINGING OF PIPE
6.4.1 The CONTRACTOR shall exercise utmost care in stringing the line pipe to avoid
the damages. The CONTRACTOR shall adhere to the following as a minimum-
Use side boom, Hydra or swinging crane or other suitable equipment
appropriate to site condition and available RoW. Dragging or sliding of
pipe shall not be permitted.
Stringing of pipe shall only be carried out after clearing and grading.
Pipe shall not be strung on the RoW in rocky areas where blasting may
be required, until all blasting is complete and the area cleared of all
debris.
Pipes shall be strung on loose soft soil / sand filled gunny bags / straw
stacks / soft padded wooden skids, in such a way so as to match the
grade profile and trench profile.
The stringing of the pipe on the RoW shall be done in such a manner as
to cause the least interference with the normal use of the land crossed
The pipe length must be properly spaced in order to make easier the
handling during the welding phase.
Page 15 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Page 17 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
7.2.2 In steep slope areas or on the hillside, before commencing the works, proper
barriers or other protection shall be provided to prevent the removed materials
from rolling downhill.
7.2.3 On slopes wherever there is danger of landslide, the pipeline trench shall be
maintained open only for the time strictly necessary. Moreover, TGPL may
require excavation of trench manually, local route detouring and limiting the
period of execution of the work.
7.2.4 In certain sloppy sections, before the trench cuts through the water table, proper
drainage shall be ensured both near the ditch and the Right-of -way in order to
guarantee soil stability.
7.2.5 All sewers drain ditches and other natural waterways involved in the execution
of the work shall be maintained open and functional. The same applies to canals,
irrigation canals. Pipelines and buried facilities crossed by the ditch for which
temporary pipelines shall be laid, if required and proper temporary installations
provided.
7.3 NORMAL COVER AND TRENCH DIMENSIONS
7.3.1 The trench shall be excavated to a minimum width so as to provide, on both
sides of the installed pipeline, a clearance as indicated in the job
standards/drawings and to a depth sufficient to provide the minimum cover as
indicated below. The dimensions in the table below shall govern except as noted
herein or as shown on the job standards or detailed construction drawings or as
required by authorities having jurisdiction, whichever is greatest. Minimum
depth of cover shall be measured from the top of pipe corrosion/concrete
weight coating (as applicable) to the top of undisturbed surface of the soil or top
of graded working strip or top of road or top of rail whichever is lower. Fill
material in working strip shall not be considered to add to the depth of cover.
However, surface of full material placed to fill hollows may be used to determine
the depth of cover subject to prior approval by TGPL/TPIA.
Page 18 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
7.3.2 Wherever the Depth of Excavation required, for any Pipeline related activity
exceeds 1.2 Mtrs, the Trench will fall under ‘Confined Space’ as per TGPL HSE
requirements, and the following clauses shall apply:
Page 19 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Page 20 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
(b) When laid parallel to any existing underground cable, drain or other
utilities, the pipeline or main shall be laid with a clear distance of at least 500
mm from existing utility.
Where the pipeline crosses areas, whose easements specifically require greater
than normal depths of cover, the trench shall be excavated to extra depth in
accordance with right of way agreement.
CONTRACTOR shall excavate all such additional depths as may be necessary at no
extra cost to the TGPL.
7.6 GRADES, BENDS AND FINISH OF TRENCH
The trench is to be cut to a grade that will provide a firm uniform and continuous
support for the pipe. Bends shall be made in the pipe at significant changes in
grade of the trench. TGPL reserves the right to set the grade of the trench and
locate the bends if so desired, in which case CONTRACTOR shall excavate, at no
extra cost, the trench and bend the pipe to such a grade. TGPL/ TPIA may desire
to reduce to a minimum the required number of cold field bends to lay the pipe
to conform to the general contour of the ground and maintain normal cover.
OWNER intends that there will be a minimum of hand grading of the trench
bottom. However, to achieve this, CONTRACTOR will have to dig as square a
bottom of the trench as possible with his equipment. This in part can be
obtained by adjusting and adopting the crumbling shoe and digging teeth of the
trenching machines and by use of a drag behind the trenching machines or
manually dressing-up the same. CONTRACTOR shall do such handwork in the
trench as is necessary to free the bottom of the trench from loose rock and hard
clods and to trim protruding roots from the bottom and side walls of the trench.
7.7 PADDING
In all cases where rock or gravel or hard soil is encountered in the bottom of the
trench, requirement of bedding & padding will be decided by TGPL Site
engineer/TPIA. TGPL/TPIA will decide the exact extent of required trench
padding. The thickness of the padding at bottom shall not be less than 150 mm.
Acceptable padding shall be placed under the pipeline before its installation and
around after installation to establish at both sides and on top of the pipe a
permanent layer of padding. The thickness of the padding on the top shall be
minimum 300 mm. CONTRACTOR shall execute all such padding including supply
of suitable padding material. Padding shall be done by soft soil/sand.
7.8 PROTECTION OF THE TRENCH
CONTRACTOR shall keep the trench in good condition until the pipe is laid and no
claim is to be made to the TGPL by reason of its cave in either before or after
pipe is laid. CONTRACTOR shall de-water, if necessary, using well point system or
Page 21 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
other suitable systems, to excavate the trench and install the pipe, and backfill
the trench in accordance with the specifications.
7.9 PROTECTION OF UNDERGROUND UTILITIES AND SPECIAL METHODS
CONTRACTOR shall obtain plans and full details of all existing and planned
underground services from the relevant local authorities and shall follow the
relevant plans closely at all times during the performance of work. CONTRACTOR
shall be responsible for location and protection of all underground utilities &
structures and any damage to them shall be restored at his own cost. In special
locations the use of trenching machine may result in damage to property and
sub-surface structures likely to be encountered during excavation. At such places,
CONTRACTOR shall excavate the trench manually to same specification at no
extra cost.
Where the pipeline crosses other underground utilities/structures, the
CONTRACTOR shall first manually excavate to a depth and in such a manner that
utilities/structures are located.
Temporary under pinning or any other type of supports and other protective
devices necessary to keep the interfering structure intact shall be provided by
the CONTRACTOR at his own cost and shall be of such design as to ensure against
their possible failure.
Despite all precautions, should any damage to any structure/utility, etc. occurs,
the OWNER/AUTHORITY concerned shall be contacted by the CONTRACTOR and
at his expense under the direction and to the satisfaction of OWNER and the
concerned authority. If CONTRACTOR fails to repair in reasonable time, OWNER
reserves the right to have the repair executed at the cost of the CONTRACTOR.
7.10 ENCROACHMENT AND WORKING NEAR OTHER UTILITIES:
In location where the pipeline to be laid more or less parallel to an existing
pipeline, cable / or other utilities in the right of way, the work shall be performed
to the satisfaction of the concerned owner / authority of the existing
pipeline/cable/utilities.
7.11 PROVISIONS FOR NEGATIVE BOUYANCY TO THE PIPE
In case of water in the trench bottom when the pipeline is being laid, the trench
shall be drained to extent to make visual inspection of the bottom. Wherever up-
floating of the pipeline after back filling is expected, the same be reckoned with
proper anti-buoyancy measures. Anti-buoyancy shall be provided by
CONTRACTOR for areas indicated in the drawing or as may be encountered
during construction using one or more methods with prior approval from TGPL/
TPIA.
By applying concrete coating by grunting.
Page 22 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Page 23 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
8.2.8 Over bends shall be made in such a manner that the centre of the bend clears
the high points of the trench bottom.
8.3 NATURAL ELASTIC BENDS: The Minimum allowable radius for elastic bends in the
buried pipeline including that for continuous concrete weight coated pipe shall
be as per standards specification. The elastic bend shall be continuously
supported over its full length. A radius smaller than 21 times the pipe diameter
shall call for fabrication of cold bend.
8.4 MITER AND UNSATISFACTORY BENDS - All bends showing buckling, wrinkles,
cracks or other visible and harmful defects or which are in anyway in
disagreement, in whole or in part, with this specification shall be rejected. Each
Bend shall be marked with paint, Bend number, TP number, Degree, Left/Right,
Chainage, Heat Number, and Pipe Number at both ends of Pipe.
9. LINING UP
9.1 Each pipe is to be checked visually internally and externally for pipe / coating
damages, signs of corrosion. Each pipe shall be swabbed if required. Any
damages noticed shall be informed to TGPL.
9.2 PIPE DEFECTS
9.2.1 The maximum permissible depth of gauge in pipe shall not more than 3 mm from
the lowest point of the dent and a prolongation of the original contour of the
pipe dent may be removed by disc grinder and final wall thickness shall be
measured and verified from TGPL/TPIA.
9.3 PIPE HOLDING AND SKID SPACING
9.3.1 When lifting pipe, care must be taken not to kink or over stress it, proper pipe
slings shall be used.
9.3.2 Skid shall be at least 1.2 meters long and shall have width of 200 mm. Pipe
supports shall be stable, so that movement will not cause the supports to move.
Skids shall not be removed before lowering. The welded pipe shall be maintained
on skids at a minimum height of 500 mm to avoid back scattering during
radiography
9.3.3 Night caps: At the end of each day’s work or when welding operation are
interrupted, the open ends on the welded strings of pipe shall be capped.
CONTRACTOR shall arrange the caps as required at his own cost.
Page 24 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
trench bottom shall be checked for the presence of cuts, pipe supports, stones,
roots, debris, stakes, rock projections up to 15 cm below underside of pipe and
any other materials which could lead to perforation/ tearing of the coating is
removed.
10.2 Bottom padding shall be done as per site engineer instruction at places where
rock, gravel or hard soil is encountered. The thickness of the padding shall be at
least 150 mm all around the pipe. Initially a layer of 150 mm shall be spread in
the trench before lowering. Subsequent padding shall be done after lowering.
However, the thickness of padding on the top of pipe shall be 150 mm minimum.
10.3 A complete check by a full circle holiday detector, duly calibrated, for pipe
coating and for field joint coating shall be carried out and damages, if any, shall
be repaired. All points on the pipeline where the coating has been in contact
with either the skids or with the lifting equipment during laying shall be carefully
inspected for damages, denting or other defects and shall be completely
repaired. If, after checking, it becomes necessary to place the pipeline again on
supports at the bottom of the trench, these must be padded in such a way as to
prevent damage to the coating, thus avoiding necessity for further repairs when
the pipe is finally raised and laid.
10.4 The pipeline shall be lifted and laid using, for all movements’ necessary, suitable
slings of non-abrasive material having adequate width for the fragility of the
coating. Care shall be exercised while removing the slings from the coated pipe,
after it has been lowered into the trench. Any damage caused to the coatings
shall be promptly repaired. No sling shall be put around field joint coating.
10.5 Laying shall be carried out under safe conditions so as to avoid stresses and
temporary deformations of the equipment which may cause damage to the
pipeline itself and to the coating. In all localized points where the RoW is
restricted to the minimum necessary for the transit of mechanical equipment,
the laying shall be carried out using other suitable means.
The pipe section shall be placed on the trench bed without jerking, falling, impact
or other similar stresses. It shall be ensured that the pipe is laid gently following
the S’ curve within its elastic limit. Any damage caused to the coating shall be
promptly repaired and repair portion shall be checked by holiday.
10.6 Lowering shall not be permitted in or during bad weather.
10.7 Wherever the pipeline is laid under tension, as a result of undue stresses at
specific points, the trench shall be rectified to the satisfaction of TGPL/TPIA’s, so
that it fits in the excavated trench bed.
Page 25 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
10.8 The pipeline must be laid without interruption for the whole or the length of
section available. Where water is present, no laying shall be permitted until the
ditch has been drained to the extent and for the time necessary to make visual
inspection possible of the bed on which the pipe is to be laid. Following such
inspections, the presence of water will be permitted, provided that it is not so
high as to cause cave in of walls of the trench or floating of the pipeline before
backfilling, when weight is not provided for the pipe. CONTRACTOR shall take
precautions immediately after lowering in to prevent the movement of the pipe
in the trench.
10.9 Subsequent to lowering a pipe section, level of the trench bottom and level by
the side of the trench shall be taken at those locations where levels were taken
prior to lowering. Cover shall be ascertained based on the level difference.
Engineer-in- Charge’s approval of these levels shall be taken and the levels
recorded in pipe book. If the cover is not as per the requirements of this
specification, the lowered pipe section shall be removed from the trench and the
trench rectified, so that the available cover is as per the requirements of this
specification.
10.10 Post padding work shall start immediately after lowering.
11. BACKFILLING
11.1 Backfilling shall be done after ensuring that appurtenances have been properly
fitted and the pipe is following the ditch profile at the required depth that will
provide the required cover and has a bed which is free of extraneous material
and which allows the pipe to rest smoothly and evenly. Before any such work is
done, it shall be CONTRACTOR’s responsibility to first secure the approval of
OWNER. If any backfilling is done without OWNER’s approval, OWNER will have
the right for removal of the backfilling for examination, and the cost of such
uncovering and refilling shall be borne by CONTRACTOR.
11.2 Dewatering shall be carried out prior to back filling. No backfilling shall be
allowed if the trench is not completely de watered. Any saline water found
during Trenching/Backfilling shall be discharged in to Drain/canal at the nearest
location available. Dewatering on ROW shall not be allowed.
11.3 Prior to back filling it should be ensured that the coated portion been previously
Holiday checked, CONTRACTOR checked post padding of 300mm minimum thick
layer of soil is put over and all around the pipe immediately after lowering.
Warning mat to be placed after post padding and before backfilling in the trench.
11.4 Where, rock, gravel, lumps of hard soil or like materials are encountered at the
time of trench excavation, sufficient sand or select backfill materials shall be
placed around and over the pipe to form a protective cushion extending at least
Page 26 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
to a height of 300 mm above the top of the pipe. CONTRACTOR shall select the
backfill materials for padding that are acceptable to TGPL/TPIA, whether such
padding material would be taken from the adjacent spoil bank or imported from
elsewhere shall be directed by TGPL/TPIA. CONTRACTOR shall carry out all these
works at no extra cost to TGPL. Loose rock may be returned to the trench after
the required selected backfill material has been placed, provided the rock placed
in the ditch will not interfere with the use of the land by landowner, or tenant.
11.5 When the trench has been dug through driveways or roads, all backfill shall be
executed with sand or a suitable material as approved by TGPL/TPIA and shall be
thoroughly compacted. In certain cases, special compaction methods, such as
moistening or ramming of the back fill in layers may be required by TGPL/TPIA.
TGPL/TPIA and any public or private authority having jurisdiction over a road,
street or drive way may require that the surface of the backfill be gravelled with
crushed rock or some other purchased material and the road shall be repaved. In
such instances, CONTRACTOR shall comply with said requirements at no extra
cost to TGPL.
11.6 Trenches excavated in dikes which are the properties of railways or which are
parts of main roads shall be graded and backfilled in their original profile and
condition. If necessary, new and/or special backfill materials shall be supplied
and worked-up at no extra cost to TGPL. The materials required may include
gravel, special stabilization materials or stabilized mixtures. Moreover, special
processing and/or compacting methods shall require the approval of TGPL/TPIA
and/or competent authorities.
11.7 The trench in irrigated and paddy fields shall be backfilled to within 300mm of
the top, then rammed and further backfilled until the trench is completely
backfilled. Surplus material remaining after the operation shall be spread over
the ROW as specified in “Clean up and Restoration of RoW", of this specification.
11.8 At the end of each day's work, backfilling shall not be more than 200 meters
behind the head end of lowered-in pipe, which has been padded and approved,
for backfill. The backfill shall be maintained by CONTRACTOR against washouts
etc., until the completion and final acceptance of the work by TGPL/TPIA.
11.9 CONTRACTOR shall furnish materials and install breakers in the trench in steep
areas (slope generally 10% and more) for the purpose of preventing erosion of
the back fill. The type of breakers installed shall be as per the approval drawings.
Breakers shall be constructed of grout bags filled with a mixture of 4:1 Sand:
Portland cement at TGPL’s / TPIA direction. CONTRACTOR may propose other
methods such as foam dams’ etc. which shall be subject to approval of
Page 27 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Page 28 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
and fittings; mount all instruments and make all piping and electronic
connections, etc.
On completion, all elements of each and entire installation shall be checked and
tested for full and correct operation in the presence of, and to the satisfaction of
TGPL/TPIA. All work shall be carried out strictly in accordance with the relevant
codes and as per the approved drawings.
CONTRACTOR shall fabricate all piping and install valves and fittings as required
by and approved by TGPL/TPIA. Stainless steel tubing will be "swaged" using
permanent fittings installed with a hydraulic device. Cold bending for the fitting
of 1/2" and 1/4" pipes is allowed when special bending tools are used with guides
to prevent flattening. The minimum radius allowed shall not be less than R = 10
D, where D = outside diameter of pipe. The bending tool shall be subject to
TGPL/TPIA approval.
CONTRACTOR shall ensure that the piping assemblies are not in a strain prior to
the final bolting or welding. CONTRACTOR shall also ensure that all equipment
and piping are thoroughly swabbed clean of all dust, refuse, welding- spatter,
scales, or any potentially detachable matter prior to the tie-in or final bolting by
means of cardboard blasting method or suitable method up to the satisfaction of
TGPL/TPIA.
12.1.2 Flanged connections
CONTRACTOR shall ensure that all flange faces are parallel and centered,
according to standard practice, prior to final bolting. CONTRACTOR shall not use
bolting forces as a means for attaining alignment. A gasket of proper size and
quality shall be installed between the flanges at each joint.
Bolts shall be tightened in diagonal sequence and shall be centered with equal
amounts of thread visible on both sides. Bolts shall be uniformly tightened to
produce a leak-proof joint. Bolts that yield during tightening shall be removed
and discarded. It is mandatory that a torque wrench is used for bolt tightening
12.1.3 Welded connections
Where the ends of the piping components being welded have an internal surface
misalignment exceeding 1.6 mm, the wall of the component extending internally
shall be trimmed by machining so that the adjoining internal surfaces will be
approximately flush.
12.1.4 Threaded connections
Damaged threads shall be cut from the end of thread and the pipe shall be
rethreaded.
CONTRACTOR shall properly align all threaded joints. Pipe entering unions shall
be true to centreline so the union will not be forced during wake-up. The
Page 29 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
threaded pipe shall not project through fittings to cause interference with valves
or other operating mechanisms.
Except for the threaded connections of instruments, which will require periodic
testing and maintenance, all threaded joints shall be seal welded. The latter
joints shall be made up without pipe joint compound and with a minimum of oil
from the thread cutter. Seal welds should taper into the pipe with as little
discontinuity as possible, and should cover all threads.
12.1.5 Civil work
Civil work shall be provided in accordance with specifications issued for the
purpose.
12.1.6 Painting
All exposed surfaces like piping, Valves structures and miscellaneous
appurtenances shall be painted in accordance with SSPC – SP 1 & SIS - 055900.
The corrosion coating on pipe surface will end approximately 0.3 meter above
the finished grade and it will be necessary for CONTRACTOR to provide a clean
interface at the junction of the protective coating and the paint.
12.1.7 Coating of buried Installations, etc.
All buried valves, insulating joints, flow tees, bends, other in line fittings and
appurtenances shall be coated (Heat Shrink Sleeve or Liquid Epoxy or equivalent).
CONTRACTOR shall submit to TGPL/TPIA, a report regarding the method of
application and the materials used along with the test certificates. Only after
obtaining written approval from the TGPL/TPIA. CONTRACTOR shall commence
coating work.
Multi-pass, pressure retaining welds may be coated prior to pressure testing with
the following exceptions:
Unless prohibited by the design code
Welds in in-plant piping systems as follows:
Socket and seal welds
Single or multi-pass, pressure retaining fillet welds
All welds in systems subject to a sensitive leak test (where sensitive
leak test is permitted by Company)
Other safety critical welds as designated by Company.
12.1.8 Clean-up
After all, required tests have been conducted satisfactorily; CONTRACTOR shall
clean up the site. The site finish shall be graded in accordance with the approved
drawings.
Page 30 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Page 31 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Page 32 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Page 33 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
14.3.4 All dumping fees connected with the disposal of materials shall be to the account
of CONTRACTOR.
14.3.5 All loose stone and rock exposed by the construction operations and scattered
over the ROW and adjacent grounds shall be removed by CONTRACTOR and be
transported to a location considered suitable by the land - owner and or tenant,
or by authorities having jurisdiction, for satisfactory disposal.
14.4 TEMPORARY STRUCTURES
All auxiliary structures such as bridges, dams, culverts, sheet piling, posts, slings,
etc., which were erected or installed by CONTRACTOR as temporary measure,
shall be removed.
Page 34 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
necessary. This restoration might contain but is not limited to the supply and
installation of proper materials for back fill and protection, the sliding or other
precautions to prevent erosion or guarantee the stability. All has to be done after
deliberation and acceptance of the authorities and TGPL/TPIA. Other field drains
have to be restored manually and/or special equipment to be used for that
purpose as soon as possible and if necessary also outside the ROW.
14.10 Any substances, cave-ins, wash-outs, which have been caused during the pipeline
construction and maintenance, caused by whatever reason within the edge of
ditches and open drains, shall be repaired by CONTRACTOR immediately or at
first notice given by TGPL/TPIA.
14.11 After the clean-up, ROW of pastures has to remain fenced as considered suitable
by the tenant and to be removed during the maintenance period. When
agricultural and other traffic (requested by tenant) have to cross the ROW, the
cross-oversee have to be fenced with the same material as the ROW. If
necessary, special materials have to be used to allow traffic on the crossover.
Fencing of the RoW as specified shall not be removed until CONTRACTOR has
obtained written permission by TGPL/TPIA. In general, this has to be done during
the maintenance period.
14.12 All openings in or damage to the fences or enclosures shall be repaired by
installing new fencing of a quality which shall be at least equal to the parts
damaged or removed. Provisional gates shall be removed and replaced with new
fencing. All repairs to fences and enclosures shall be carried out to the complete
satisfaction of TGPL/TPIA, landowner and/or tenant.
14.13 If, in the opinion of TGPL/TPIA, the sod in pasture land had been damaged by
vehicles and wheel tracks are visible, the ROW shall be tilled with a disc-harrow
or rotary cultivator several times. The damaged sod shall be firmly cut up and
thoroughly mixed through the topsoil. In general, the ROW has also to be ripped.
After this procedure no closed-in layers must be found and sufficiently loose
topsoil 25 to 30 cm thick must be present. The whole procedure must be
approved by TGPL/TPIA. Subsequently, the entire ROW, which is part of
pastureland, shall be prepared for seeding and fertilized according to the
instructions of TGPL/TPIA.
14.14 In crop fields the tillage shall consist of passing over the land several times with a
disc harrow, cultivating with a spading machine, or plow, to a depth of approx.
20-cm. In general, the ROW has also to be ripped. After this cultivation process
no closed-in layers must be found any more in the ROW. The equipment used
and methods adopted shall require the approval of TGPL/TPIA. Ripping has to be
Page 35 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
done with rippers with a distance of 50 cm between the ripper blades. The type
to be used shall be approved by TGPL/TPIA.
14.15 A sapling of any plant/tree uprooted or cut during construction shall be planted
along the route as per the direction of the TGPL/TPIA and in accordance with the
forest preservation Act, 1981. The cost of sapling and its plantation shall be to
CONTRACTOR'S account.
14.16 The ROW and the backfilled trench in particular have to be finished in such a way
that after settlement of the soil, the fields are at their original level.
If during the maintenance period certain parts of the ROW are lower than the
original level, TGPL/TPIA can instruct the CONTRACTOR to bring these parts to
the original level.
If during clean-up operations soil shortages become apparent outside the trench,
CONTRACTOR shall supplement said soil shortage using suitable materials,
approved by TGPL/TPIA.
If site and/or climatic conditions should render this necessary, TGPL/TPIA shall
have the right to order CONTRACTOR to suspend certain parts of the WORK
related to the clean-up and postpone it to a later date.
14.17 SOIL SURPLUS
If on site, as a result of the work and after careful back filling and compacting, a
sub-soil surplus exists, this shall be worked up by grading and compacting below
the sub-soil top layer and as a rule this shall be done in the same plot of land. It
shall not be permitted to remove the surplus from the plot concerned, unless it
concerns rejected soil, which has to be removed. Working up surplus soil or
removal of rejected soil shall be considered to pertain to the ROW.
To work a soil surplus into the ground CONTRACTOR shall remove an additional
strip of topsoil beside the trench. Next, the upper layer of sub-soil shall also be
removed. Both soil strips shall be stored separately across a width depending on
the size of the soil surplus. The soil surplus shall then be distributed across the
trench thus widened, after which it shall be graded and compacted and
subsequently the top layer of sub-soil and the topsoil shall be replaced in the
correct order, in accordance with the specifications.
In case TGPL/TPIA has given prior permission for mixed excavation of the sub-soil
as well as in cases where TGPL/TPIA deems mixed excavation permissible, the
above provision of separate storage of the upper layer of sub-soil shall not apply
to the working up of the soil surplus.
In cases where the soil surplus can be worked up in other plots where soil
shortages have arisen due to the ROW, this shall only be done after prior
permission by landowner, land -user and TGPL/TPIA.
Page 36 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
15 AS BUILT
The Company requires that all relevant construction data to be captured in an
electronic database. The database shall be used by the Company for operation
and management of the pipeline through Geographic Information System (GIS).
The Contractor shall record data and features as detailed in this section.
The data shall include full pipe traceability that permits the Company to locate
any individual pipe joint installed in the system.
The Contractor is required to capture the data and supply it to the Company in an
acceptable electronic format. Duly signed paper copies shall also be provided as a
formal record of an activity.
The Contractor shall ensure that all subcontractors and vendors are capable and
are resourced to comply with the approved data tracking system.
The use of the Data tracking system shall not replace the production and
compilation of records to be reviewed and endorsed during the execution of the
works and shall:
Identify the location of the top of pipe in the ground, and the location of the
natural surface in x, y and z coordinates. This shall be achieved by surveying the
location of each weld joint by using a Differential Global Positioning System
(DGPS) of suitable accuracy. In locations where the ground conditions do not
permit the actual survey, the co-ordinates of the intermediate welds may be
determined by interpolation.
Provide sufficient survey data to identify the location of the pipe at each
bend (horizontal and vertical). In addition, relevant as-built data shall be
provided to the Owner prior to commencement of backfilling at the
related pipeline section.
Identify the location of each facility installed as part of the pipeline,
including cathodic protection test points, signs and markers, valves, future
off-takes and other appurtenances.
Page 37 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Identify the location of each service crossed by the pipeline, and the location of
the natural surface in x, y and z co-ordinates. The services shall be identified in
terms of type, owner/authority, size, orientation, product and appearance.
15. DOCUMENTATION
15.1 Quality record for each activity
Page 38 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Page 39 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
TABLE OF CONTENT
1.0 SCOPE
2.0 REFERENCE CODE AND STANDARD
3.0 SUBMITTALS BY CONTRACTOR
4.0 BASE MATERIAL
5.0 WELDING CONSUMABLES
6.0 EQUIPMENT AND ACCESSORIES REQUIREMENT
7.0 WELDING PROCESSES
8.0 BEVEL CLEANING / BEVEL INSPECTION
9.0 ALIGNMENT AND SPACING
10.0 WEATHER CONDITIONS
11.0 WELDING
12.0 HEAT TREATMENT
13.0 INSPECTION AND TESTING
14.0 REPAIRS OF WELDS
15.0 DOCUMENTATION
16.0 ENCLOSURE
Page 40 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
1.0 SCOPE
This specification shall be followed for the fabrication of all types of welded joints
of mild steel pipe line & piping systems connected with the pipeline and related
facilities.
The welded pipe joints shall include the following.
a) All line pipe joints of the longitudinal and circumferential butt-welded and
socket welded types.
b) Attachments of flanges and other supports to pipes.
c) Welded manifold headers and other sub-assemblies.
d) Welded branch connections.
e) Joints in welded / fabricated piping components.
f) The attachments of smaller connections for vents drain drips and other
instrument tapping.
Any approval granted by the Engineer-in-charge/TPIA shall not relieve the
CONTRACTOR of his responsibilities and guarantees.
2.0 REFERENCE CODE AND STANDARD
Following Standards and codes of latest edition have been used in this
specification.
2.1 Governing Standard
ASME B 31.8 - Code for Gas Transmission and Distribution Piping Systems
API 1104 - Standard for welding of Pipelines and Related Facilities -
2.2 Reference Standard
ASME Sec. II, Part – C - Specification for welding Electrodes and Filler Materials
ASME Sec. V. - Non Destructive examination
ASME Section IX - Qualification for welding and brazing
3.0 SUBMITTALS BY CONTRACTOR
3.1 The CONTRACTOR shall submit the Welding Procedure Specification, Procedure
Qualification Record, Welder Qualification Test, Ultrasonic Testing Procedure,
Magnetic Particle Testing Procedure, Dye-Penetrant Testing Procedure and
Radiography Procedure along with quality records and Inspection Test Plan for
Page 41 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
welding and NDT compatible to this specification at least two weeks prior to
commencement of the work for the approval of TGPL/TPIA.
3.2 The CONTRACTOR shall submit Electrode and Welding Consumable Qualification
Records in respect of the electrodes tested by the CONTRACTOR, for obtaining
approval of the Engineer-in-charge/TPIA.
4.0 BASE MATERIAL
4.1 In general, use of MS Pipe & Fittings is envisaged. The details of material
specifications are given in the welding specification chart.
4.2 The CONTRACTOR shall provide the manufacture’s test certificates for every heat
of material, if any, supplied by the CONTRACTOR, also maintain the record of test
certificates of all the materials for the reference of the Engineer-in-charge/TPIA
5.0 WELDING CONSUMABLES
5.1 The CONTRACTOR shall provide at his own expense all the welding consumable
necessary for the execution of the job such as electrodes, oxygen, acetylene etc.,
and these shall bear the approval of the Engineer-in-charge/TPIA.
5.2 The SMYS of electrodes / filler wires shall be equal to or more than the parent
material to be welded.
5.3 Physical properties of the welds produced by electrodes recommended for the
welding of a particular base metal shall not be lower than the minimum values
specified for the base metal. The choice of electrode shall be the sole prerogative
of the Owner/Owner’s Representative.
5.4 The Contractor shall submit batch test certificates from the electrode
manufacturer giving details of physical and chemical tests carried out for each
batch of electrodes to be used.
5.5 For each batch, electrode qualification test report shall be submitted as per
Annexure to the Owner/ Owner’s Representative for approval.
5.6 The welding electrodes / filler wires supplied by the CONTRACTOR shall conform
to the class specified in the welding specifications chart. The materials shall be of
the make approved by the Engineer-in-charge/TPIA.
5.7 All electrodes shall be purchased in sealed containers and stored properly to
prevent deterioration. The electrodes removed from the containers (except
cellulose coated electrodes) shall be kept in holding ovens, at the temperature
recommended by the electrode manufacturer. Ovens shall be used for low
hydrogen electrodes only. Out-of-the oven time of electrodes before they are
consumed shall not exceed the limits recommended by the electrode
manufacturer. The electrodes shall be handled with care to avoid the any
damage to the flux covering. Different grades of electrodes shall be stored
Page 42 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Page 43 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Page 44 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Every effort shall be made to reduce misalignment by the use of the clamp and
rotation of the pipes to the best fit. For pipe of same nominal wall thickness, the
offset/Hi-Low shall not exceed 1.6 mm. The offset/Hi-Low may be checked from
outside using Hi-Low Gauges. Any branch connection sleeve, etc., shall be at
least 150 mm from any other weld (Underground pipeline). The welds for fittings
shall be so located that the toe of the weld shall not come within 50 mm of any
other weld. Cold dressing is permissible only in cases of slight misalignment and
may only be carried out with a bronze-headed hammer. Hot dressing shall not be
permitted. When welding pipes of different wall thickness (as directed by
Engineer-in-charge/TPIA.) A special transition piece shall be used. This shall have
a minimum of 1:4 taper. The welds shall be subject to both ultrasonic and
radiographic inspection.
The root gap shall be accurately checked and shall conform to the qualified
welding procedure. The use of pipe clamp either internal or external is selected
considering requirements of pigging of pipeline in future. However, in some case
(tie in welds, flanges, fittings, diameter of pipe 10” etc.) where it is impossible to
use internal clamps, an external line up clamp may be used.
The internal line up clamp shall not be released before the entire first pass has
been completed.
When an external line up clamp is used, all spaces between bars or at least 60%
of the first pass shall be welded before the clamp is released and the pipe
remaining adequately supported on each side of the joint.
Segments thus welded shall be equally spaced around the circumference of the
pipe. Slag, etc. shall be cleaned off and the ends of the segments shall be
prepared by grindings as to ensure continuity of the weld bead.
10.0 WEATHER CONDITIONS
The parts being welded and the welding personnel shall be adequately protected
from rain and strong winds. In this absence of such a protection no welding shall
be carried out. The completed welds shall be suitably protected in case of bad
weather condition
11.0 WELDING
11.1 Root Pass
11.1.1 Root pass shall be made with electrodes / filler wires recommended in the
welding specification chart.
11.1.2 The size of the electrodes used shall be as per the approved welding procedure.
Page 45 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
11.1.3 The vertical down method of welding shall be adopted for welding pipe held fixed
with its axis horizontal.
11.1.4 The vertical up method of welding shall be used for the root pass of the tie ins,
special crossing, fittings and special parts, fillet welds, repairs and when an
external line clamp is used.
11.1.5 The root pass of butt joints shall be executed properly so as to achieve full
penetration with complete fusion of the root edges. Weld projection inside the
pipe shall not exceed 3 mm wherever not specified by the applicable code.
11.1.6 Any deviations desired from the recommended welding technique and electrodes
indicated in the welding specification chart shall be adopted only after obtaining
express approval of the Engineer-in-charge/TPIA by Deviation Requests.
11.1.7 Welding shall be continuous and uninterrupted during a pass.
11.1.8 On completion of each run, craters, welding irregularities, slag etc., shall be
removed by grinding.
11.1.9 While the welding is in progress care shall be taken to avoid any kind of
movement of the components, shocks, vibration and stresses to prevent
occurrence of weld cracks.
11.1.10 Fillet welds shall be made by shielded metal arc welding process irrespective of
the thickness and class of piping. Electrode size shall not exceed 3.15-mm
diameter for socket joints. At least two passes shall be made on socket weld
joints.
11.2 Joint Completion
The number of welders and the allowable welding sequences shall be as per laid
down in the qualified welding procedure specifications. Once the deposit of the
first pass has been started, it must be completed as rapidly as possible, reducing
interruptions to the minimum. The welding and wire speed shall be
approximately same as that established in the qualified welding procedure
specification.
The pipe shall always be adequately supported and must not be pumped or
shaken during welding. The clamp shall be removed, as indicated in clause 9.0
above. Before starting the second pass, the first pass shall be cleaned and
flattened with rotating grinders.
The interruption between completion of the first pass and starting the second
pass shall be as stated in the procedure specification, normally not exceeding
four minutes.
The Welding/Travel Speed selected shall enable production of a bead which is
sufficiently thick and which shows no undercutting.
Page 46 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
The time lapse between second and third pass shall be as stated in the procedure
specification, normally not exceeding five minutes. After completion of the third
or following passes, welding operations may be suspended, so allowing the joint
to cool down, provided that the thickness of the weld metal deposited is equal to
at least 50% of the pipe thickness. In any case, the welds shall be completed
within 24 Hrs, otherwise it shall be cut-out as per EIC/TPIA instruction. Upon
restarting, depending on the materials, wall thickness and welding process, a
preheating to at least 100oC shall be carried out. Subsequent passes up to weld
completion shall be protected to avoid rapid cooling, if meteorological conditions
so dictate. Cleaning between passes shall be done carefully so as to reduce the
possibility of inclusions.
Electrode starting and finishing points shall be staggered from pass to pass. Arc
strikes outside the bevel on the pipe surface are not permitted. Arc strike or arc
burn on the pipe surface outside the weld, which are caused accidentally by
electrical welding cable or welding cable round and the pipe shall be removed by
grinding in accordance with a procedure approved by Engineer-in-charge/TPIA
and the repair checked by ultrasonic, radiographic, magnetic particle or dye
penetrant tests which the Engineer-In-charge/TPIA feels necessary. The pipe wall
thickness after grinding shall not be less than the minimum thickness limit
permitted for the pipe. Repair of arc strikes by welding is prohibited.
The completed weld shall be carefully brushed and cleaned and shall appear free
from spatters scales, etc.
These requirements apply not only to completed welds but also to the bare strip
at least so wide as to allow full skid examination at both ends of the pipe to allow
a good ultrasonic inspection when it is required.
12.0 HEAT TREATMENT
12.1 Preheating: [Where ever applicable]
12.1.1 Preheating shall be performed using resistance or induction / heating methods.
Preheating by gas burners, utilizing acetylene or propane gas may also be carried
out. Oxy-propane gas may be used with the permission of the Engineer-In-
charge/TPIA under careful supervision.
12.1.2 Preheating shall extend uniformly to at least three times the thickness of the
joint, but not less than 50 mm, on both sides of the weld.
12.1.3 Preheating temperature shall be maintained over the whole length of the joint
during welding. The CONTRACTOR to check the temperature shall provide
temperature indicating crayons or other temperature indicating devices.
Page 47 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Page 48 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
13.3.2 The welders shall always have in their possession the identification card as
shown in Exhibit – D and shall produce it on demand by the TGPL’s/TPIA
Inspector. It shall be the responsibility of the CONTRACTOR to issue the identity
cards after it has been duly certified by the TGPL’s/TPIA Inspector.
13.3.3 No welder shall be permitted to work without the possession of identity card.
13.3.4 If a welder is found to perform a type of welding or in a position for which he is
not qualified, he shall be debarred from doing any further work. All welds
performed by an unqualified welder shall be cut and redone by a qualified
welder at the expense of the CONTRACTOR.
13.4 Visual Inspection
Inspection of all welds shall be carried out as per the latest editions of API – 1104
and other the applicable codes and specifications by the CONTRACTOR at his
expense. In addition to the requirements of API 1104, no root crack shall be
permitted. All finished welds shall be visually inspected for parallel and axial
alignment of the work, excessive reinforcement, and concavity of welds,
shrinkage, cracks, under cuts, dimensions of the weld, surface porosity and other
surface defects. Undercutting adjacent to the completed weld shall not exceed
the limits specified in the applicable standard / code.
13.5 Non-destructive Examination
The non-destructive examination shall mainly consist of examination using X-ray
radiography as detailed in Annexure - III.
Radiographic examination of one hundred percent (100%) butt welds will be
required by the TGPL’s/TPIA. Where ever radiography is not feasible due to weld
/ site condition, same joints shall be examined through Ultrasonic examination.
Welds shall meet the standards of acceptability as set forth in API 1104 as well as
the requirements laid in subsequent paragraphs. In addition, no root crack shall
be permitted; The CONTRACTOR shall make all the arrangements for the
radiographic examination of work covered by the specification at his expense.
The TGPL’s/TPIA will review all the radiographs of welds and inform the
CONTRACTOR regarding unacceptable welds. The decision of the TGPL’s/TPIA
shall be final and binding in this regard. All requirements mentioned in the
specification shall be arranged and executed by the CONTRACTOR through his
own resources. In addition, ultrasonic inspection is required in the following
cases as per Annexure II of this Specification.
a) When 20 mm or more are cut from the pipe end as supplied, the ends
shall be DPT, ultrasonically and Magnate particle test (MPT) inspected for an
additional length of 20 mm to assure no lamination exist.
b) When welds are repaired.
Page 49 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Page 50 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
The CONTRACTOR at his own expense shall carry out the sampling and the re-
execution of welds. If the results are unsatisfactory, welding operations shall be
suspended and may not be restarted until the causes have been identified and
the CONTRACTOR has adopted measures, which guarantee acceptable results. If
it is necessary in the Engineer-in-charge/TPIA opinion the procedure shall be re
qualified. The weld joint represented by unsatisfactory weld shall stand rejected
unless investigation proves otherwise.
14.0 REPAIRS OF WELDS
14.1 With the prior permission of Engineer-in-charge/TPIA welds which do not comply
with the standards of acceptability shall be repaired or the joint cut out and re-
welded.
A separate welding procedure specification sheet shall be formulated and
qualified by CONTRACTOR for repair welds simulating the proposed repair to be
carried out. Separate procedures are required to be qualified for
(a) Through thickness repair
(b) Partial thickness repair.
(c) Capping repair
Welders shall be qualified in advance for repairs. The root pass, for repairs
opening the root, shall be replaced by the vertical uphill technique. The
procedure shall be proven by satisfactory procedure tests to API 1104 including
the special requirements of the specification, and shall also be subjected to
metallographic examination, hardness surveys and Charpy tests to determine the
effects of repair welding on the associated structure.
Root sealing or single pass repair deposit shall not be allowed. Internal root
defects shall be ground thoroughly and welded with a minimum of two passes.
However, while grinding for repairs, care shall be taken to ensure that no
grinding marks are made on the pipe surface anywhere.
The repair shall be subjected, as a minimum requirement to the same testing
and inspection requirements as the original weld. The entire joint shall be re-
radiographed. A 100% ultrasonic test shall be done at the repaired area
externally. Any repaired area that is wide, irregular or rough shall be rejected
and a full cut out shall be done.
Re-repair of welded joints is not allowed. CONTRACTOR shall maintain a report
of all repairs. All repairs shall be carried out the day after initial radiography or
earlier. A full report of all repairs made shall be submitted every day to the
Engineer-in-charge/TPIA.
Page 51 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
15.0 DOCUMENTATION
15.1 Batch Test Certificates, for the Electrodes used, obtained from the electrode
manufacturers.
15.2 Quality records of each process
15.3 Calibration certificate of measuring instruments and testing equipment.
16 ENCLOSURE
ANNEXURE – I- Guideline Destructive testing of welded joint
ANNEXURE – II Guideline for Ultra Sonic inspection
ANNEXURE – III Radiography
EXHIBIT A - Electrode qualification test record
EXHIBIT B - Record form for welding procedure approved test
EXHIBIT C - Record form for welder approved test
EXHIBIT D - Welder’s identification card
EXHIBIT E - Format for radiography procedure
TABLE 1 - Number of specimen for destructive test
Welding Specification Chart.
Page 52 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
ANNEXURE - I
Page 53 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
1.4.1 Preparation
Specimens shall be taken from the positions indicated in Fig. 1 of this
specification and shall be prepared in accordance with ASTM E2 and E3.
The width of the macro section has to be at least three times the width of the
weld. The section is to be prepared by grinding and polishing and etched to
clearly reveal the weld metal and heat affected zone.
1.4.2 Method
Specimens shall be carefully examined under the microscope, with a
magnification of at least 25 times (25:1). TGPL/TPIA may ask for a macrograph
with 5 times (5:1) magnification, for documentation purposes.
1.4.3 Requirements
Under macroscopic examination, the welded joints shall show good penetration
and fusion, without any defect exceeding the limits stated in the evaluation
criteria of the nick break test.
1.5 Hardness Test
1.5.1 Preparation
The prepared macro section is to be used for hardness testing using the Vickers
method with 10 Kg. loads. Indentations are to be made along traverses each
approximately 1 mm below the surface at both side of the weld.
In the weld metal a, minimum of 6 indentations equally spaced along the
traverses are to be made. The HAZ indentations are to be made along the
traverses for approximately 0.5 mm each into unaffected material, and starting
as close to the fusion line as possible.
One indentation at each side of the weld along each traverse has to be made on
parent metal. Reference is made in this specification. The indentations are to be
made in the adjacent region as well as on the opposite side of the macro section
along the specified traverses.
1.5.2 Method
The test shall be carried out in accordance with Recommendation ISO R81,
Vickers hardness, using a laboratory type machine, controlled as pre
recommendation of ISO R 146 and using a diamond pyramid penetrator set at
2.37-rad (1360C) with a load of 10 Kg.
1.5.3 Requirements
Hardness value shall not exceed the maximum limit. In case of a single reading,
slightly (+ 10 HV) higher than the specified limit, further indentations shall be
made to check if the high value was an isolated case.
Page 54 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
All the hardness values contained from the heat-effected zone shall not exceed
100 HV with respect to the average hardness of the values obtained for the base
metal.
1.6 Charpy-V-Notch Impact Test
1.6.1 Specimens shall be taken from the position indicated in this specification. The
test specimens will be prepared in accordance with ISO R 148. Charpy V notch
specimens shall have dimensions as given in Fig. 4 of the specification.
Three test specimens shall be taken from each sample and they shall be cut and
worked so that their length is transversal and perpendicular to the weld bead
with the notch position as per the specification. The notch shall be perpendicular
to the roller surface. The test specimen width shall depend upon the pipe wall
nominal thickness as following:
Page 55 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Note 1: Only one value is permitted to be lower than average value up to the
value specified.
Page 56 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
ANNEXURE – II
ULTRASONIC INSPECTION
1.0 Ultrasonic Inspection
In addition to the radiographic inspection, ultrasonic inspection is
required as per conditions listed in paragraph 13.5 of this specification.
This section covers manual ultrasonic inspection. However ultrasonic
inspection by automatic equipment may be used if approved by the
TGPL/TPIA.
1.1 Equipment and Operators
The Contractor who carries out the ultrasonic inspections shall have sufficient
qualified personnel, equipment and instruments at his disposal to be able to
affect the tests without hindering or delaying the pipeline assembly operations.
The operators shall be fully qualified as per a recognized standard (ASME Sec. V
or equivalent) and they shall have qualified as a minimum level II. The operators
shall be able to:
Calibrate the equipment; Perform an operational test under production
conditions;
Interpret the screen picture;
Evaluate the size and location of reflectors/discontinuity.
Interpret the type of defects detected.
TGPL/TPIA has the option of checking the ability of personnel employed for
ultrasonic testing by means of qualification tests.
The Contractor appointed to carry out ultrasonic inspections shall supply all the
instruments necessary for their execution on site.
1.2 Specification for Ultrasonic Testing Procedure Qualification
Before work begins, the Contractor shall present a specification describing the
proposed U.T. procedure qualification.
This specification shall state, as an indication only but not limited to the following
information:
Page 57 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Record details
Reference to the welding procedure where it is intended to adopt the
specification.
Temperature range of the joints to be inspected.
1.3 Qualification of Ultrasonic Inspection Procedure
The ultrasonic inspection procedure shall be approved by TGPL/TPIA. Before
inspection begins, TGPL/TPIA may require the qualification test of the ultrasonic
inspection procedure. This test consists in testing (under normal operating
conditions) some welds made according to the same production procedure,
where there are typical defects the test intends to detect. This test shall be
conducted in the presence of TGPL/TPIA.
1.4 Test Procedure
Circumferential welds shall be inspected from both sides using angled probes.
The surface with which the probe comes into contact shall be free of metal
spatter, dirt, iron oxide, and scales of any type. Therefore, it shall be necessary to
clean a strip at least 150 mm wide on both sides of the weld with steel wire
brushes and strip must be wide enough to allow full scale examination. The weld
shall be tested from both sides and testing shall include the adjacent area of weld
for laminations, scanning for transverse indication in weld and base material. The
probe movement shall not exceed 100mm/sec.
Manual ultrasonic testing equipment is applicable for pulse echo technique and
for double probe technique and shall cover as a minimum frequency range from
2 to 6 MHz, have a calibrated gain regulator with maximum 2dB per step over a
range of at least 60 dB, allow echoes with amplitudes of 5% of full screen height
to be clearly detectable under test conditions. For flaw detection the corrected
primary gain may be increased by maximum 6 db. Defect size evaluation is not
being performed at this increased gain level. The indications are to be
investigated by maximizing the echoes with different angle probes and by
rotating the probes. All indications exceeding 20 % of the reference curve are to
be investigated and all indications exceeding 50 % are to be reported.
Investigation is to be performed to the extent that the operator can determine
the shape and location of the indication. For dimensional evaluation either the
“20 dB -drop “method, time of flight or maximum amplitude method is to be
used. The half value drop method is to be used for length determination only.
Acceptance criteria for visual examination and surface method testing shall be as
per API 1104 Section 6 and Clause 13.5.
If, during the test, echoes of doubtful origin appear, it shall be necessary to
inspect a convenient area on the pipe surface, close to the weld, with a straight
beam transducer in order to check whether any manufacturing defects are
Page 58 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
present which could have interfered with the ultrasonic beam. By way of an
example, the equipment shall include but not be limited to the following:
Ultrasonic equipment and coupling medium.
Sample sections for calibration of instruments.
Equipment for cleaning of surface to be examined.
Rules calibrated in centimetres for exact location of the position of defects.
The characteristics of the above listed instruments and equipment shall
guarantee:
a) That the required standards of the inspection procedure, as previously
established and approved by TGPL/TPIA, are satisfied.
b) Continuous operation:
All the instruments and equipment shall be approved by the TGPL/TPIA before
being used. TGPL/TPIA has the authority to reject any item, which is considered
unsuitable. The decision of TGPL/TPIA is final. The Contractor appointed to carry
out ultrasonic inspections shall also ensure the operational efficiency and
maintenance of the instruments and equipment, and shall immediately
substitute any item rejected by TGPL/TPIA.
All the instruments and equipment necessary for carrying out ultrasonic
inspection on site shall satisfy the requirements laid down by the public boards of
institutions which regulate safety at work.
1.5 Ultrasonic Instruments
The ultrasonic instrument shall be each pulse type, able to generate, receive and
display, on the screen a cathode ray tube (CRT), pulse at frequencies between 2
and 6 MHz. The useful part of the CRT screen shall be at least 70 mm wide and at
least 50 mm high.
Shall have variable amplification, with steps of 1 or 2 dB over a range of
at-least 60 dB.
The regulation control shall be accurate to within +1 dB and the
Instrument may be powered by a battery or an electric generator.
Manufacturer shall certify this accuracy. In the first case, the autonomy of
operation (endurance) of the instrument shall be sufficient to carry on
working without frequent interruptions, and the instrument shall be
equipped with an automatic switch which switches it off when the battery
runs down; in the second case, there must be a voltage stabilizing device
with a tolerance of +2 Volts.
Page 59 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
1.6 Probes
The probes used shall have dimensions, frequencies, and a refraction angle
suited to the type of steel, the diameter the thickness of the pipeline and to the
joint design.
1.7 Reference Sample Pieces
The efficiency of the equipment used, the effective refraction angle of the probe,
and the beam output point, shall be checked using a V1 and V2 sample block, IIW
type or the calibration block ASTM E- 428.
For the calibration of runs and the regulation of detection sensitivity during the
test, a calibration piece shall be used. This piece shall be taken from the
production material and will be at least 150 mm long (measured in the direction
of the axis), and at least 50 mm wide (measured in the direction of the
circumference) See Fig. 6 of this specification. In the middle of the inside and the
outside surface of the calibration piece a groove shall be made. The groove will
have a rectangular cross section, a flat bottom and the following dimensions:
- Depth: 1 + 0.1 mm
Page 60 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
lines shall be marked on the screen with a pen. Calibration shall be repeated each
time tests are re-started; at intervals not longer than 30 minutes during normal
operations; each time the conditions fixed in advance are altered. This calibration
is applicable provided that the crystal of the probe is 8 x 9 mm size. Should this
size of the crystal be different, the value of the sensitivity obtained from the
calibration by a crystal of a different size shall be brought to the value of
sensitivity obtained from the calibration by a 8 x 9 mm crystal. The sensitivities of
the two different size probes shall be compared through the echoes obtained on
the notch of the test piece with the probe position at half skip of the distance.
1.9 Regulation of Amplification during Production Testing
The amplification during production testing shall be obtained by adding 2 - 6 dB
(according to the surface condition of the pipe and its cleanness) to the
reference amplification.
1.10 Qualification of Ultrasonic Testing Operators
Before the inspection begins or during the same inspection, TGPL/TPIA may
require a qualification test for the ultrasonic equipment operators
1.11 Evaluation of Indications Given by Ultrasonic Tests
Each time the echoes from the weld bead appear during production testing, the
instrument amplification shall be altered to coincide with the reference
amplifications and the probe shall be moved until maximum response is
obtained, paying attention all the time to the probe tube coupling.
If, under these conditions, the height of the defect echo is equal to or greater
than that of the reference echo, the defect shall be evaluated according to clause
1.12.5 of this Specification. If the defect has also been detected by the
radiographic and/or visual examination, the dimensions shall be judged
according to the type of examination, which detects the greater defect. Returns,
which are less than 50% of the reference echo, will not be considered. If returns
are above 50% but lower than 100% of the reference echo, and if the operator
has good reasons to suspect that the returns are caused by unfavourably
oriented cracks, he shall inform the TGPL/TPIA.
Moreover, when there is a defect to be repaired, such defect shall be removed
for a length corresponding to the one where no more return echo is given.
1.12 Other Equipment
The use of rules calibrated in centimetres, attached if possible to the probe, for
the precise location of the position of welding defects, is recommended. Defect
location is effected by measuring the projection distance between the probe
Page 61 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
output and the reflecting surface. The operators carrying out the tests shall have,
besides the probing instrument, tools for cleaning the pipe surface (Files,
Brushes, etc.) as well as the coupling liquid or pastes appropriate for the
temperature of the section to be examined.
Page 62 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
ANNEXURE - III
RADIOGRAPHY
1 SCOPE
This Annexure covers the radiographic inspection of all types of welded joints of
the pipeline.
The welded joints shall include the following:
i) 100% of all Butt Weld Joints.
ii) Full girth welds on the mainline construction including double jointing of
pipe, if adopted.
iii) Welds for installation of block valves, insulating joints and other
appurtenances and tie-ins.
iv) Welds at scraper launching and receiving barrels.
v) Terminal Piping.
2 APPLICABLE STANDARDS
This specification shall apply in conjunction with the following (all latest edition):
1. API 1104, Standard for welding Pipelines and related facilities.
2. ASME B 31.8, Code for Gas Transmission and Distribution Piping Systems.
3. ASTM E 94, recommended practice for Radiographic Testing.
4. ASTM E 142, Standard Method for Controlling Quality of Radiographic
Testing.
5. The American Society for Non-destructive Testing. Recommended
Practice No. SNT-TC-1A supplement A.
6. ASME BPV – Boiler and Pressure Vessel Code – Section IX
7. BARC rules for radioactive isotopes handling.
8. ASME Section V non-destructive examination.
3 PROCEDURE
3.1 The radiographic examination procedure to be adopted shall be submitted by the
Contractor as per Exhibit - E.
3.2 The procedure of radiographic examination shall be qualified to the entire
satisfaction of TGPL/TPIA prior to use. It shall include but not be limited to the
following requirements:
Page 63 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
i) Lead foil intensifying screens, at the rear of the film shall be used for all
exposures.
ii) Type 2 and 3 films as per ASTM E - 94 shall be used.
A densitometer shall be used to determine film density. The transmitted film
density shall be 2.0 to 3.5 throughout the weld. The unexposed base density of
the film shall not exceed 0.30.
iii) Radiographic identification system and documentation for radiographic
interpretation reports and their recording system.
3.3 The Contractor shall qualify each procedure in the presence of the TGPL/TPIA
prior to use.
3.4 The procedure of radiographic examination shall produce radiographs of
sufficient density, clarity and contrast so that defects in the weld or in the pipe
adjacent to the weld, and the outline and holes of the penetrameter are clearly
discernible.
3.5 All butt welds in the Pipeline and all the girth welds of mainline shall be subjected
to 100% radiographic examination. The Contractor shall furnish all the
radiographs to TGPL/TPIA, immediately after processing them, together with the
corresponding interpretation reports on approved format. The details of the
radiographs along with the joint identification number shall be duly entered in a
register and signed by the Contractor and submitted to TGPL/TPIA for approval.
3.6 When the radiation source and the film are both on the outside of the weld and
located diametrically opposite each other, the maximum acceptable length of
film for each exposure shall not exceed the values given in API 1104. The
minimum film overlap, in such cases, shall be 40 mm. The ellipse exposure
technique may be used on nominal pipe sizes of 2 inch and smaller provided that
the source of film distance used is a minimum of 12 inch.
Three copies of each acceptable radiographic procedure (as per Exhibit - E) and
three copies of radiographic qualification records shall be supplied to TGPL. One
set of the qualifying radiographs on the job shall be kept by the Contractor’s
authorized representative to be used as a standard for the quality of production
radiographs during the job. The other two sets shall be retained by TGPL/TPIA for
its permanent record.
Three copies of the exposure charts relating to material thickness, kilo voltage,
source of film distance and exposure time shall also be made available to
TGPL/TPIA by the Contractor.
The Contractor shall, on a daily basis, record for each radiograph
(1) radiograph’s number,
(2) approximate chainage of weld location,
Page 64 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
(3) whether or not the welds meet the specified acceptance standards and
(4) the nature and approximate location of unacceptable defects observed.
It must be possible to relate back to a particular butt weld and welder on piping
drawing and pipe line alignment drawing.
Each day’s production of processed radiographs shall be properly packaged
separately, identified by at least the
(1) date,
(2) radiographic unit,
(3) job locations,
(4) starting and ending progress survey stations and
(5) shall include original and three copies of the daily radiographic record.
The package shall be submitted to the TGPL/TPIA daily when possible, but in no
event later than noon of the following day.
The Contractor shall provide all the necessary facilities at site, such as a dark
room with controlled temperature, film viewer etc. to enable the TGPL/TPIA to
examine the radiographs.
The Contractor, if found necessary, may modify the procedure of radiographic
examination suiting to the local conditions prevailing. This shall, however, be
subject to the approval of the TGPL/TPIA.
3.7 TGPL/TPIA shall have free access to all the Contractor’s work facilities in the field.
3.8 Any approval granted by TGPL/TPIA shall not relieve the Contractor of his
responsibilities and guarantees.
4 RADIATION SOURCE
4.1 Radiographic examination shall be carried out using X-Rays only. Radiographic
examination by Gamma Rays can be done prior approval of TGPL/TPIA.
4.2 Whenever possible, pipeline welds will be inspected by placing the radiation
source inside the pipe, on the pipeline axis, with a radiation of 6.28 rad. (360 oC)
crawler type of x-ray machine shall be used for all main line joints.
If it is impossible to place the radiation source inside the pipe, the weld will be
inspected with the source on the outside. An overlap of at least 40 mm at the
ends of each film shall be required to ensure that the first and last location
increment numbers are common to successive films and to establish that no part
of a weld has been omitted.
Page 65 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
5 LEVEL OF QUALITY
The quality level of radiographic sensitivity required for radiographic inspection
shall be at least equivalent to the values specified in ISO standards (IQI Sensitivity
curve).
6 PENETRAMETERS
6.1 The image quality indicator (abbreviation: IQI) shall be used for the qualification
of the welding procedure and during normal line production.
Radiographic sensitivity shall be measured with the wire image quality indicator
(Penetrameter). The Penetrameter shall be selected according to DIN 54109 or
ISO 1027. For radiographs made with the source on the outside, a Penetrameter
shall be placed on each side of the film with the smaller wire of the
Penetrameter turned towards the end of the film itself. When a complete weld is
radiographed in a single exposure using a source inside the piping, 4
Penetrameter approximately equally spaced around the circumference shall be
used. During the procedure qualification, IQI shall be placed both on the source
side and on the film side. The sensitivity obtained with IQI on the source side
shall not be less than the values shown in the specification.
The sensitivity limit may be considered to have been reached when the outline
of the IQI, its identification number and the wire of the required diameter show
up clearly on the radiograph.
TGPL/TPIA may authorize use of types of IQI other than those planned, provided
that they conform to recognized standards and only if the Contractor is able to
demonstrate that the minimum sensitivity level required is obtained. For this
demonstration, a test shall be carried out comparing the IQI specified and the
Contractor’s. To show up the identification number and other details of the
proposed IQI, this must be visible in the test radiograph.
7 FILM IDENTIFICATION MARKERS
All films shall be clearly identified by lead numbers, letters, and/or markers. The
image of the markers shall appear on the films, without interfering with the weld
interpretation. These marker positions shall also be marked on the part to be
radiographed and shall be maintained during radiography.
8 PROTECTION AND CARE OF FILM
8.1 All unexposed films shall be protected and stored properly as per the
requirements of API 1104 standard and ASTM E-94.
8.2 The exposed and unexposed film shall be protected from heat, light, dust and
moisture. Sufficient shielding shall be supplied to prevent exposure of film to
Page 66 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
damaging radiation prior to and following the use of the film for radiographic
exposure.
9 RE-RADIOGRAPHY
9.1 The weld joints shall be re-radiographed in case of unsatisfactory quality of the
radiographs, at the expense of the Contractor.
9.2 All the repaired weld joints shall be re-radiographed at no extra cost to the TGPL
in the same manner as that followed for the original welds. In addition, the
repaired weld areas shall be identified with the original identification number
plus the letter R to indicate the repair.
9.3 When evaluating repair film, radiographers shall compare each section
(exposure) of the weld with the original film to assure repair was correctly
marked and original defect removed.
TGPL/TPIA will review prior to any repair of welds, all the radiographs of welds,
which contain, according to the Contractor’s interpretation, unacceptable
defects. The final disposition of all unacceptable welds shall be decided by
TGPL/TPIA.
10 QUALIFICATION OF RADIOGRAPHERS
10.1 Pipeline radiographers shall be qualified in accordance with the requirement of
API 1104 and to the full satisfaction of TGPL/TPIA.
10.2 Certification of all the radiographers, qualified as per clause 10.1 above, shall be
furnished by the Contractor to TGPL/TPIA before a radiographer will be
permitted to perform production radiography. The certificate record shall
include
i) Background and Experience Record
ii) Training Course Record.
iii) Doctor’s report on radiographer’s Oaecuer 0-1 acquity eye test.
iv) Date of qualification.
10.3 The radiographers shall be required to qualify with each radiographic procedure
they use, prior to performing the work assigned to him in accordance with the
specification.
11 PRESERVATION OF RADIOGRAPHS
11.1 The radiographs shall be processed to allow storage of films without any
discoloration for at least Five years. All the radiographs shall be presented in
suitable folders for preservation along with necessary documentation.
11.2 All radiographs shall become property of TGPL at the end of project.
Page 67 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Page 68 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
16.2 Contractor shall make outside arrangements for ambulance service and for
treatment of industrial injuries. Names of those providing these services shall be
furnished to TGPL/TPIA prior to start of work and their telephone No. shall be
posted prominently in Contractor’s field office
All critical industrial injuries shall be reported promptly to TGPL/TPIA and a copy
of Contractor’s report covering each personal injury requiring the attention of
physician shall be furnished to TGPL/TPIA.
17 NO EXEMPTION
17.1 Notwithstanding the above there is nothing in these to exempt the Contractor
from the operation of any other act or rules in force.
Page 69 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
EXHIBIT - A
ELECTRODE QUALIFICATION TEST RECORD
A: Tested at
Date :
(Site Name) :
Manufacturer’s Name :
Brand Name :
Batch Number :
Size tested Classification & Code :
Intended for welding in positions :
In Combination with (If any) :
Code of Reference (Used for testing) :
Special requirements (If any) :
Page 70 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
—————————————————————————
E: Fillet Weld Test Results:
Welding Positions :
Base Materials :
Size of Electrode Used :
Page 71 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
2)
3)
4)
5)
—————————————————————————————————————————
Any other tests :
Conclusions :
Page 72 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
EXHIBIT - B
Example of Record form for Welding Procedure Approval Test:
Project/Contract :
Contractor :
Pipe and Fitting Material :
Process :
Outside Diameter :
Pipe Thickness :
Joint design (Sketch Attached):
Make and Type of filler metal:
Diameter :
Current :
Voltage :
Root :
Second Run :
Other Runs :
Other electrical characteristics:
A.C./ D.C :
Electrode Negative / Positive :
Shielding Gas :
Type of Mixture :
Flow :
Shielding Flux :
Position :
Direction of Welding :
Root : Vertical up* / Vertical Down
Second Run : Vertical up* / Vertical Down
Other Runs : Vertical up* / Vertical down Number of Welders :
Root :
Second Run :
Page 73 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Other Runs :
Time Lapse between Commencements of Root and Commencement of Second Run:
Time lapse between commencement of second run and commencement of other runs:
Minimum number of runs before point allowed to cool:
Maximum time between commencements and completion or weld:
Type of line-up clamp :
Removal of clamp after : Run
Lowering off after : Run
Cleaning
Preheating
Minimum temperature 0C : Ambient Temperature 0C :
Type of heater to be used
Inter pass temperature 0C
Minimum 0C : Maximum 0C :
Post weld heat treatment
Speed of travel : Test Results :
[State acceptable non-acceptable (with reasons) or give numerical results]:
Non-destructive tests :
Visual :
Destructive Test 1 2 3 4
Transverse tensile
Tensile strength (with units)
Fracture location
Test temperature
Macro examination
Fillet weld fracture
Hardness survey
Hardness range
Parent Metal
Heat affected zone
Weld
Chary V-notch impact tests
Specimen location and size
Notch location
Test temperature
Results (With units)
Page 74 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Additional test(s) and results, e.g., chemical analysis, micro-examination, CTOD tests, Bend
tests, Nick-Break Tests.
The test joints were prepared, welded and tested in accordance with the
requirements of specification.
The statements in this record are correct.
Contractor Inspector
Designation Witnessed by
Date Date
Page 75 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
EXHIBIT - C
Example of record form for welder approval test
Contractor : Inspector :
Welder’s Name :
Address :
Pipe material :
Pipe thickness :
Pipe outside diameter :
Welding Process For Root: For Filler and Cap:
Direction of travel
Root :
Filler and cap :
Reason for failure :
Visual :
Non-destructive testing :
Butt joint :
Fillet Weld :
Number of attempts :
Comments :
Accepted Date & Time :
Contractor’s Sign :
Inspector’s Sign :
* Delete as necessary.
Page 76 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
EXHIBIT - D
SIGN SIGN
DATE DATE
NOTE:
1) Validity Period of Welder shall be up to the satisfactory performance / 1 year whichever
is lesser.
2) Repair percentage for any welder should be 5% max., minimum of 25 joints shall be
welded by any welder for calculating repair percentage calculation.
3) Contractor shall track the repair percentage of welders and report shall be made
available to TGPL/TPIA on monthly basis. In case, the repair percentage for any welder is
more than the specified limit as mentioned above, at any point of time, contractor shall
terminate the welder immediately.
4) Welder after qualification, if is not performing any welding work due to any reasons for
more than 90 days, welder requalification shall be done.
Page 77 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
EXHIBIT - E
RADIOGRAPHIC PROCEDURE FOR PIPE WELDING
1. Location
2. Date of Testing
3. Name of Supervised Contractor
4. Material
5. Dia. and Thickness
6. Type of Weld Joint
7. Radiation Source (X-ray, iridium)
8. Type of equipment (External / Internal)
9. Intensifying screens and material
10. Filter type and placement mask, Diaphragm Lead screen etc. adjacent to radiation source
or specimen.
11. Geometric relationship (Source local spot size, max and min source strength, object to
film distance, radiation angle with respect to weld and film).
12. Limit of film coverage
13. Film type and make
14. Exposure time
15. Processing (time temperature for development, stop bath or rinse, fixation, washing,
drying etc.)
16. Density
17. Sensitivity
18. Type of Penetrameter
19. Essential wire to be seen on source side.
20. Essential wire accepted for film viewing
Page 78 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
TABLE 1
NUMBER OF SPECIMENS
PIPE SIZE, OUTSIDE
TENSILE TENSILE NICK ROOT FACE SIDE MACRO HARD IMPACT TOTAL
DIAMETER
API ISO BREAK BEND BEND BEND NESS
INCHES
WALL THICKNESS – ½” INCH UNDER (12.7 mm)
UNDER 2 3/8 0 0 2 2 0 0 0 0 0 4
2 3/8 – 4 ½ 0 0 2 2 0 0 0 0 0 4
OVER 4 ½ - 12 ¾ 2 0 2 2 2 0 2 2 12 24
12 ¾ AND OVER 2 2 4 4 4 0 2 2 24 44
4 ½ AND SMALLER 0 0 2 0 0 2 0 0 0 4
12 ¾ AND OVER 2 2 4 0 0 8 2 2 24 44
Page 79 of 123
Page 80 of 123
Page 81 of 123
Page 82 of 123
Page 83 of 123
Page 84 of 123
TABLE OF CONTENTS
1.0 SCOPE
2.0 REFERENCE CODE AND STANDARD
3.0 SUBMITTALS BY CONTRACTOR
4.0 MATERIAL AND EQUIPMENT REQUIREMENTS
5.0 PROCEDURE OF APPLICATION
6.0 INSPECTION & TESTING
7.0 MARKING, PROTECTION, STORAGE AND HANDLING
8.0 REPAIRS
9.0 DOCUMENTATION
Page 85 of 123
1.0 SCOPE
This specification covers minimum requirements of materials, manpower,
equipment, application, inspection and testing of field joints corrosion coating
for pipeline and in-field joint coating of onshore pipelines.
1.1 It shall be read in conjunction with the conditions of all specifications and
documents included in the contract.
1.2 Contractor shall, with care and diligence, execute the work in compliance with all
laws, by-laws, ordinances, regulations, etc. and provide all services and labour,
inclusive of supervision thereof, all materials, excluding the materials indicated
as TGPL supplied materials in the Contract, equipment, appliances or other
things of whatsoever nature required in or about the execution of the work,
whether of a temporary or permanent nature.
2.0 REFERENCE CODE AND STANDARD
Following standards and codes of latest edition have been used in this
specification
2.1 Governing Standard:
DIN 30672: 1991: Coating of corrosion protection tapes and Heat Shrinkable
Products for pipelines for Operational Temperature up to 500 C.
2.2 Reference Standard:
SIS – 055900 : Pictorial surface Preparation Standard for Painting Steel
Surfaces.
SSPC – SP 1 : Solvent Cleaning, Steel Structure Painting council.
SSPC SP10 / NACE 2: A joint standard between the Steel Structures Painting
Council and NACE International for Near-White Blast
Cleaning
ISO 8501-1 : International Organization for Standardization Very
through blast cleaning to SA 2 ½.
SSPC SP 1 : Steel Structure Painting Council for Solvent Cleaning
SSPC-VIS 1-89 : Steel Structures and Painting Council for Visual Standard
for Abrasive Blast Cleaned Steel
In case of conflict between the requirements of this specification and that of
above referred documents, the requirement of this specification shall govern.
Page 86 of 123
4.1.1 General
4.1.2 The Contractor shall be responsible to provide the coating material at site in
compliance with the requirement of this specification.
4.1.4 The material and equipment like joint coating material, material for blasting,
primer, blasting hopper, air compressor, burners etc. shall be approved by
TGPL/TPIA. Sand blasting is not allowed.
4.1.5 Contractor shall be responsible for arranging all manpower required for
application, testing and inspection of coating in the filed in accordance with this
specification
Page 87 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
strength and good resistance to thermal ageing as mentioned in Table-1 & Table-
2 of this specification. Material shall be purchased from vendor approved by the
TGPL.
b) The joint coating system shall utilise a solvent free epoxy primer applied to
the pipe surface prior to sleeve application. The backing shall be coated
with thermo-chrome paint that will change colour when the desired heat
during shrinking process is attained.
4.2.3 The minimum thickness of field joint coating shall be 2.5 mm on the complete
finished field joint coating. Whereas, the thickness at the apex of weld seam shall
not be less than 2.2 mm.
4.2.4 The filed coating material shall be supplied with minimum following physical,
chemical & electrical properties.
Page 88 of 123
A. Physical Properties
Sr. Specified Test
Properties Unit Test Method
No. Requirement Condition
1 Tensile Strength MPa > 15 250 C ASTM D 638
B. Chemical Properties
24 hours at
1 Water Absorption % 0.05 max ASTM D 570
250 C
Resistance to Thermal Change in
2 % 1000 C DIN 30672
Ageing Elongation, < 25
C. Electrical Properties
Page 89 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
A. Physical Properties
Sr. Specified Test
Properties Unit Test Method
No. Requirement Condition
3 Resistance to indentation mm > 0.6 Remaining
500 C DIN 30672
thickness
4 Lap shear strength between
Wrapping & metal surface
N/cm2 ≥ 5 500 C DIN 30672
Wrapping & Mill Coating
B. Chemical Properties
Sr. Specified Test
Properties Unit Test Method
No. Requirement Condition
1 mm ≤ 30 30 days, test
Cathodic Disbondment (Radius of
method A at ASTM G-42
Disbondment)
600 C
C. Electric Properties
Sr. Specified Test
Properties Unit Test Method
No. Requirement Condition
1 Dielectric Strength kV > 30 1000volt /sec DIN 30672 / ASTM D0149
Page 90 of 123
NOTE: Contractor shall obtain prior approval form TGPL/TPIA regarding the
manufacturer of the joint coating, Complete technical details along with tests
certificates complying the requirements shall be submitted to company for the
purpose.
4.3 A fully automatic full circle adjustable holiday detector with a visual and audible
signal shall be used for inspection of coating for pinholes.
5.1 The Contractor shall follow joint coatings application procedure as per
manufacturer’s recommendation and guidelines or the minimum requirements
specified in this specification whichever is more stringent. The contractor shall
prepare procedure indicating mixing ratio and qualify the same procedure
through vendor and TGPL.
The personal performing the job shall be trained enough and shall be having
sufficient experience to perform the job.
5.2 The Contractor shall submit and demonstrate to TGPL/TPIA, the proposed
materials and work procedures. The proposed procedures, materials and
equipment shall be approved by TGPL/TPIA.
5.3.1 Contractor shall remove oil, grease, salts and other contamination on the steel
pipe surface by wiping with rags soaked with suitable solvents such as naptha or
benzene. Kerosene shall not be used for cleaning. The solvent cleaning
procedure shall be in accordance with SSPC-SP-1.
5.3.2 Prior to surface cleaning, the surface shall be completely dried. The uncoated
steel surface shall be then cleaned by shot blasting to SA 2½ of Swedish standard
SIS-055900 and have profile of 60-80 microns roughness. The roughness shall be
checked by PRESS-O-film or by other means as agreed by TGPL/TPIA. Shot
blasting shall be stopped, in case, when Relative Humidity (RH) in the
atmosphere observed is equal to or more than 85%.
5.3.3 The ends of existing pipe coating shall be inspected and chamfered prior to
application and cleaned as per requirement. The unbounded portion of coating
Page 91 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
shall be removed and then suitably trimmed. Portions where parent coating is
removed shall also be prepared as specified in this specification.
5.3.4 The joint coating shall be applied immediately after completion of surface
preparations. The time lapse shall not be more than 30 min.
5.5.1 The wraparound sleeves shall be of a size such that a minimum overlap of 50 mm
is ensured (after shrinking) on both side of mill applied coating of the pipes.
5.5.2 In case where carrier pipe installed by direct boring/jacking, the overlap on the
mill coating for the leading edges of the joints shall not be less than 200 mm (after
shrinking). When this extra overlap is achieved by providing an additional patch of
heat shrink tape/ wraparound, it shall be applied in such a manner that the square
edge of the patch on the joint coating is in the direction opposite to the direction
of boring /jacking.
5.5.3 The bare steel surface shall be preheated over the surface to remove the mist
before centring the wraparound sleeve. The minimum temperature for preheating
shall be as recommended by manufacturer. The temperature of preheat surface
shall be checked by using pyrometer or thermos-crayons or digital thermometer
and shall be recorded.
5.5.4 The wraparound sleeve shall then be entirely wrapped around the pipe positioning
the closure patch to one side of the pipe in 10 o’clock or 2 o’clock position and the
edge of the undergoing layer facing upward. Overlap between the sleeve and
closure patch shall not be less than 50 mm (after shrinking).
Page 92 of 123
5.5.5 A heat shrinking procedure shall be applied to shrink the sleeve in a manner such
that all entrapped air is removed with the help of gloved hands and hand rollers.
The complete shrinking of the entire sleeve shall be obtained without undue
heating of mill coating and providing due bonding between pipe surfaces, sleeve
and pipe coating. The resulting coating shall be free from wrinkles, cold spots, pin
holes and weld profile shall be visible on the sleeve.
5.6.1 Cold applied joint protection tapes shall be such that it can be applied by spirally
wrapping on the pipe.
5.6.2 Approximately 100 mm of tape interleaving paper shall be peeled back and tape
shall be applied with the compound side to the pipe. Whilst continuously
removing the interleaving paper, the tape shall be spirally applied to provide a
minimum of 55% overlap. Sufficient tension shall be applied to ensure good
conformation, avoiding air pockets and also continuously smooth out as the
wrapping proceeds. The wrapping shall start and finish to give a minimum of 75-
mm overlap on to the adjoining yard applied coating.
In the case where carrier pipe is installed by direct boring/jacking, the overlap on
the mill coating for the leading edges of the joints shall be minimum 200 mm.
The direction of spiral wrapping in these cases shall be such that the square edge
of the wrapping with the joint coating is in the direction opposite to the direction
of boring/jacking.
6.0 INSPECTION & TESTING
Page 93 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Page 94 of 123
6.3.8 Coating thickness shall be checked by non-destructive methods for each field
joint. Ten measurements over the cut-back including one over the girth weld
shall be taken and minimum thickness of 2.2 mm shall be guaranteed on apex
and average thickness of 2.5 mm on pipe shall be measured only after the
setting of joint, preferably after 24 hrs.
7.0 MARKING, PROTECTION, STORAGE AND HANDLING
7.1 Contractor shall ensure that the Manufactures have carried out all quality
control tests on each batch of material supplied. All such test certificates/
reports shall be submitted with each batch of the materials.
7.2 Materials shall not be older than their period of validity at the time of
application. Deteriorated and decomposed materials shall be disposed off and
replaced by Contractor at his own expense.
7.3 Contractor shall ensure that the coating materials supplied by supplier are
properly packed and clearly marked with the following:
- Manufacturer’s name
- Materials Description
- Batch Number
- Date of Manufacturing and date of expiry
- Specific storage and handling instructions.
7.4 All materials shall be stored and handled by the contractor in such a manner and
types so as to prevent damage or deterioration.
7.5 Contractor shall provide and maintain mobile facilities equipped with all
necessary equipment and it spares for cleaning, coating, repairs, inspection and
tests.
8.0 REPAIRS
8.1 If the field joint is detected to be unacceptable after testing as per clause 6.0 of
this specification, the Contractor shall, at his own cost,
a. Determine the cause of the faulty results of the field coating;
b. Mobilise the expert of manufacturer, if required;
c. Stop field coating until remedial measures are taken against the causes of
such faults, to the entire satisfaction of the TPIA.
8.2 Contractor shall replace all joint coating found or expected to be unacceptable as
per clause 6.0 of this specification.
Page 95 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
8.3 Contractor shall, at his own cost, repair all areas where the coating has been
removed for testing by the TGPL/TPIA.
8.4 After the coating work on welded joints, fittings and repairs, it shall be tested
with a spark tester before lowering or jacking the pipeline.
8.5 TGPL/TPIA shall be entitled to check the coating on buried pipelines or parts of
pipelines with equipment / instrument such as the “Pearson meter” and the
resistance meter. If coating defects are observed, the Contractor shall be
responsible for excavation at such points, repairing the coating, spark testing and
backfilling the excavations without any extra charge.
9.0 DOCUMENTATION
ITP
Progress Report
Page 96 of 123
Page 97 of 123
CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
TABLE OF CONTENTS
1.0 SCOPE
2.0 REFERENCE CODES AND STANDARDS
3.0 SUBMITTAL BY CONTRACTOR
4.0 GENERAL
5.0 ROAD & RAIL ROAD CROSSING
6.0 CROSSING OF BURIED SERVICES
7.0 MINOR WATER COURSE CROSSINGS
8.0 DOCUMENTATION
Page 98 of 123
1. SCOPE
This specification covers the minimum requirements of various activities to be
carried out by the CONTRACTOR for and about the safe installation of pipelines
crossing highway, railroads & Canal and River etc., by boring or through open cut
method.
The provisions of this specification are not applicable for pipelines crossing
watercourses, which are specifically designated as "Major Water Courses" in the
CONTRACT or BID. For such crossings, separate document to be prepared by
contractor and submitted to TGPL / TPIA for review & approval.
This specification shall be read in conjunction with the conditions of all
specifications and documents included in the CONTRACT between TGPL/TPIA and
CONTRACTOR. Unless specified otherwise, all sections of this specification shall
apply to all specifications referred in this specification.
2. REFERENCE CODES AND STANDARDS
Following standard has been used in this specification.
2.1 Governing Standard
ASME B 31.8 -Gas Transmission and Distribution Piping Systems
API RP 1102 -Recommended Practice for Liquid Petroleum Pipelines Crossing
Railroads and Highways.
2.2 Reference Standard
ASME B 31.4 -Liquid Petroleum Transportation Piping Systems
Part 192 -Transportation of Natural and other Title 49 Gas by Pipeline (US
Department of Standards) Transportation - Pipeline Safety
Part 195 -Transportation of Liquids by Pipeline US Department of
Transportation - Pipeline Safety Standards)
API 1104 -Specification for Welding Pipeline and Related Facilities
OISD - Design and Construction Requirement for Cross Standard 141
Country Hydrocarbon Pipeline
TGPL HSE -TGPL HSE Management System Manual and - TGPL Security
Manual
Page 99 of 123
3. SUBMITTAL BY CONTRACTOR
3.1 The CONTRACTOR shall submit the Procedure for open cut and cased road
crossing, river and water ways crossing, along with activity report / records at
least one week prior to commencement of the work for approval of TGPL/TPIA.
3.2 The CONTRACTOR shall submit construction drawing and Inspection test plans
for all the activities compatible to this specification at least one week prior to
commencement of the work for approval of TGPL/TPIA.
4. GENERAL
4.1 Crossing of roads, buried Services, canals and minor water crossing with
equipment and / or personnel shall be allowed only after acquiring approval
from the authorities having jurisdiction and after making arrangements for
safeguarding the roads, etc. and the verges and / or banks thereof and the
buried services with appropriate provisions.
Where overhead or above ground crossings are required, an appropriately
detailed Risk assessment shall be carried out to ensure that all HSE and integrity
risks are evaluated and adequately mitigated. This shall include consideration of
all long term O&M issues and activities.
All statutory clearances before commencement of work as required from various
authorities having jurisdiction thereof viz. PWD, Forest, Railways, Irrigation,
Traffic, Police, P & T, Electricity Board and MIDC etc., shall be obtained by TGPL
principally and CONTRACTOR shall co-ordinate & obtain necessary approval from
such authority to cross the highway/ Railway & Canal by Push jack boring / HDD /
Open Cut or as approved method by TGPL / TPIA & Authorities having
jurisdiction for timely completion of crossing.
Highways, Main-Roads and Railroads and their verges and banks of water
crossings are not allowed to be used for loading, unloading or stacking of materials
and/or equipment. For secondary roads, such loading / unloading is permitted
only after prior approval from the concerned authorities. CONTRACTOR is not
allowed to close or divert roads or watercourses without prior approval from the
TGPL/TPIA and the concerned authorities. CONTRACTOR shall never unnecessarily
hamper the users of the roads, railroads, buried services and/or watercourses. The
water flow shall not be obstructed in any way.
All Civil and Mechanical works associated with or incidental to the installation of
pipeline crossings shall be carried out in accordance with the approved
procedures.
4.2 TGPL/TPIA reserves the right to demand for individual crossings from the
CONTRACTOR a separate detailed report for approval, containing:
Time Schedule
Working method with equipment
Test procedure
Manpower deployment
Calculations of temporary works
Soil investigations, etc.
Such details shall be provided without additional cost to TGPL.
4.3 Pipeline crossings for road, railroad, canals and rivers etc., shall be hydrostatically
pre-tested, ex-situ, without joint coating and prior to lowering, whenever,
Crossing is executed by boring of casing pipe
Installation of carrier pipe into casing pipe.
River Crossing pipes which are to be continuously concrete weight
coated (to be tested prior to concrete coating)
Whenever the Authorities having jurisdiction over the utility insist upon
pretesting of carrier pipe. The section of the pipeline for the crossings shall be
tested as a single string. Unless specified otherwise in the CONTRACT, the test
pressure shall be the one resulting in hoop stress corresponding to 90 % of
SMYS of pipe material. Test pressure shall be retained in the pipeline for
minimum period of 4 hours or as per approved procedure. Test section shall
be visually examined for leaks / defects, etc.
gradient in order to allow for an easy insertion and, if necessary at a future date,
to allow for the removal or replacement of the pipeline, leaving the casing
undisturbed.
The assembly of vent pipe units as approved by TGPL/TPIA shall be carried out by
the direct insertion and welding to the ends of the casing pipe before
introducing the carrier pipe. The operation of assembling and extending the vent
pipe shall be carried out in such a way that there is no contact with the carrier
pipe. The painting / coating of the vent pipes shall be applied before back filling
as per relevant specification.
5.6 The casing pipe shall be considered ready for installation of the carrier pipe, after
passing a gauge plate of diameter equal to 95% ID of pipe and careful inspection
of internal cleaning with the removal of soil, mud, stones and other foreign
materials.
5.7 Insulators, as approved by TGPL/TPIA, shall be securely fastened to the pipe with
all bolts and fixtures firmly tightened. The number of insulators and spacing shall
be as shown in the drawings or at 2.5 mtr. centre (whichever is more stringent).
At the end of both sides of the casing, a double set of insulators shall be
installed.
5.8 Care must be taken in pushing or pulling carrier pipe into the casing so that the
pipe is aligned correctly in the casing and that the pushing or pulling force is
evenly and constantly applied to avoid damages to the insulators. A nose piece
having a diameter equal to that of the pipe shall be welded on the front and back
end of the carrier pipe to facilitate installation of the carrier pipe properly in the
casing and to keep it dry and clean.
5.9 After installation of the carrier pipe section in the casing and the appurtenances
(but prior to making tie-in welds and back filling), the CONTRACTOR in the
presence of TGPL/TPIA shall conduct an electrical continuity test between casing
pipe and carrier pipe & soil. These tests shall show at least a resistance of
minimum 100,000-ohm m2. After back filling and compaction, additional tests
shall be conducted to determine if the casing is found to be shorted,
CONTRACTOR shall make the necessary corrections and repairs at his cost, unless
a test to the satisfaction of the TGPL/TPIA is obtained.
For new systems, strategic valves shall normally be installed either side of special
crossings (including major river crossings), at off takes for pressure reduction
installations, and at other locations where required for network isolation
purposes (based on risk assessment).
shall prepare a construction drawing, work method and time schedule for
approval by TGPL/TPIA.
The depth of the existing bottom of a minor water course crossing shall be
determined in relation to the adjacent ground level by taking the average of four
measurements. Measurements shall be taken with a gauge rod with dimensions
60 x 60 mm and having a flat bottom. The minimum force to be exerted shall be
36 Kg.
CONTRACTOR shall take special care to check with the responsible authorities for
special condition applying to working on, over, under or through minor water
crossings and CONTRACTOR, shall comply with any such conditions. Written
arrangements with authorities shall be drawn up in cooperation with TGPL/TPIA.
7.6 The minimum cover over the pipe shall be 1.5 meter plus the highest water level
or specified in the relevant approved drawings and job standards. For river /
watercourses that are prone to scour / erosion, the specified cover shall be
measured from the expected lowest bed profile after scouring / erosion.
7.7 For crossings beneath the bed of watercourses, the pipe section shall be made in
such a way that it confirms to the existing or future bed as indicated in the
approved drawings. In crossings for which an individual drawing has not been
prepared, the minimum cover of the pipeline shall not be less than that indicated
in the standard drawings for a similar type of crossing.
7.8 Whenever the crossing requires a straight section of pipe between the lower
bends coinciding with the riverbed, this section shall be laid at a single horizontal
level.
7.9 For crossings of ditches, canals, banked channels, etc. by boring, the pipe section
shall be prepared, laid and tested in accordance with the applicable specification.
7.10 The CONTRACTOR shall arrange temporary installation of diversions as may be
necessary, to ensure the effective functioning of these watercourses crossed, to
the entire satisfaction of the concerned local Authorities as well as the
TGPL/TPIA.
7.11 Banks and trenches of minor water crossings shall be back filled with soil which is
to be approved by TGPL/TPIA and shall be thoroughly compacted to prevent soil
and bank erosion as per the drawings and standards to the satisfaction of
authorities having jurisdiction thereof and the TGPL/TPIA. Whenever boulders,
rock, gravel and other hard objects are encountered, they shall not be placed
directly on the pipe. Sufficient earth, sand or selected and approved backfill
material shall be back filled initially around and over the pipe to provide a
protective padding or cushion extending to a minimum thickness of 300 mm
around the pipe before back filling remainder of the trench with excavated or
other material as per approved drawings and standards.
After the trench has been back filled and during the clean-up works, the minor
water crossing shall be cleaned at least across the whole of the ROW.
When specified in the CONTRACT, CONTRACTOR shall repair the ditch bank with
materials to be supplied by himself as per Civil Specification
8. DOCUMENTATION
CONTRACTOR shall submit following documents as minimum.
8.1 Quality records
Procedure for Crossing
Pipeline Crossing Report
Inspection and test Plan
Inspection Reports.
TABLE OF CONTENTS
1.0 SCOPE
2.0 REFERENCE CODES AND STANDARDS
3.0 SUBMITTAL BY CONTRACTOR
4.0 GENERAL
5.0 HYDROSTATIC TEST PROCEDURE
6.0 TEST DURATION AND PRESSURE
7.0 EQUIPMENT AND INSTRUMENTATION
8.0 PROCEDURES
9.0 ACCEPTANCE
10.0 TERMINATION
11.0 MEASUREMENTS
12.0 CALCULATIONS
13.0 PRECAUTIONS DURING THE TEST
14.0 PRESERVATION OF PIPELINE
15.0 DOCUMENTATION
1. SCOPE
1.1 This specification covers the minimum requirements of supply, works and
operations to be performed by CONTRACTOR for hydrostatic testing of steel
pipelines in CGD Networks transporting hydrocarbons in gaseous phase under
high pressure. This specification does not cover the requirements of drying / pre-
commissioning of the tested pipelines.
1.2 This specification shall be read in conjunction with the conditions of all
specifications and documents included in the CONTRACT between TGPL /TPIA
and CONTRACTOR. Unless specified otherwise, all sections of this specification
shall apply to all specifications referred in this specification.
2. REFERENCE CODES AND STANDARDS
Following standards and codes of latest edition have been used in this
specification.
2.1 Governing Standard
ASME B 31.8 : Gas Transmission and Distribution Piping Systems.
API RP 1110 : Pressure Testing of Liquid Petroleum Pipelines.
2.2 Reference Standard
ASME B 31.4 : Liquid Petroleum Transportation Piping Systems.
ASME Sec. VIII : Boiler & Pressure Vessel Code Div.1
OISD Standard 141 : Design and Construction Requirements for Cross-country
Hydrocarbon Pipelines
IS 2490 (Part-I) : Tolerance limits for industrial effluents Discharged into the
land surface water
In case of conflict between the requirements of this specification and that of the
above-referred codes, standards and specifications, the requirements of this
specification shall govern.
3. SUBMITTAL BY CONTRACTOR
The Contractor shall submit the cleaning, flushing, filling and testing procedure
along with activity report / records and Inspection test plan compatible to this
specification at least one week prior to commencement of the work for approval
of TGPL/TPIA
4. GENERAL
4.1 Hydrostatic test shall be performed on the entire length of the pipeline.
Hydrostatic test shall be performed in accordance with approved Hydrostatic
Test Diagrams for each test section. The maximum length of each test section
shall not exceed 25 kms. For pipeline sections to be tested pipeline profile, with
the line elevations clearly indicating highest and lowest points shall be
submitted.
4.2 Hydro static test for individual sections in case of laying by HDD method shall be
as follows:
General
The pressure tests shall prove the resistance and tightness of the pipeline.
Testing shall be performed in accordance with applicable standard.
The Contractor will transmit all the records of the tests to the TGPL and TPIA.
Pre-testing
Pipe and fittings shall be pre-tested prior to the pullback operation and weld
joint coating a compulsory strength and leak test shall be performed. The
minimum duration for strength testing shall be 4 hours (see tightness test for the
test pressure).
The Pneumatic testing will be carried out using dry air or inert Gas of a minimum
pressure of 0.1 bar less than existing pipeline pressure (see weld points shall be
distempered with soapy water and visually examined (soap bubble test).
Final Test preparation
Tightness test shall be performed with water. The water shall be clean, with a
corrosion inhibitor added if necessary. The pipe shall be filled using pigs to
prevent the formation of air pockets.
The tests should normally be carried out with trenches adequately back-filled, if
any, to avoid the influence of temperature changes. If the ground temperature in
the immediate vicinity of the pipes is less than 2°C, antifreeze shall be added.
On completion of filling operations, time should be allowed for the water in the
sections to stabilise. The water pressures to be maintained and the location and
characteristics of the measuring apparatus (thermometers, dead-weight pressure
gauges etc.) shall be defined before testing commences.
The measuring instruments shall have undergone certified periodic calibration.
Pressure-recording instruments shall be installed in a sheltered place.
4.3 Hydrostatic test shall commence only after mechanical and civil works
completion, i.e., all welds have been accepted and the pipeline has been laid and
back filled according to the specifications. Testing of any pipe section shall
commence only after acceptance / sign-off of Pipe book by TGPL and TPIA.
Hydrostatic test shall include those sections, which have been previously tested,
viz. Rail / Road crossings, major water crossings including test on banks and in
place after installation and scraper traps at the terminals. CONTRACTOR shall
perform all works required for hydrostatic testing after obtaining prior written
approval from the TGPL /TPIA.
5. HYDROSTATIC TEST PROCEDURE
The procedure shall strictly comply with the requirements of these specifications
and shall be submitted to TGPL / TPIA for approval. The procedure manual shall
include all temporary materials and equipment, but not limited to the following
items.
5.1 For the systems to be tested, a diagram indicating all fittings, vents, valves
temporary connections, relevant elevations and ratings. The diagram shall also
indicate injection locations and intake and discharge lines. Approved Pipe Book
shall also be made available.
5.2 Estimated amount of test water, water sources, including required concentration
of corrosion inhibitors and additives, procedure for inhibitor injection and
control of concentration.
5.3 Filling and flushing procedures, including a complete description of all proposed
equipment and instruments (including spares), their location and set-up.
5.4 The type and sequence of pigs and the pig tracking system for filling, testing &
dewatering. Pig inspection procedures, including procedure to be followed in
case the Gauge pig indicates damage.
5.5 Procedures for stabilization after filling and pressurization and to allow for
temperature stabilization.
5.6 Pressure testing procedure including a complete description of all proposed
equipment and instruments (Including spares), their location and set-up, and
proposed system for observation and recording of data during the pressure test.
5.7 Procedure for detection and location of leaks.
5.8 Procedure for de-watering the pipeline section(s) after testing, including a
complete description of all proposed equipment and instruments (including
spares), their location and set-up, the type and sequence of pigs and the pig
tracking system along with the pig specifications. Procedures to cover removal of
liquids shall be provided. This will cover both planned (e.g. following hydro
testing) and unplanned (e.g. groundwater ingress) situations.)
5.9 Forms for recording the test data.
7.2.7 Dead weight tester with an accuracy of 0.01 bar provided with a calibration
certificate not older than one month, which shall be traceable to National
Physical Laboratories.
7.2.8 Two 48 hours-recording pressure gauges with charts and ink gauges tested with
dead weight tester prior to use. These shall be installed at the test heads.
7.2.9 Pressure recording charts.
7.2.10 Two temperature recorders for fill water.
7.2.11 Thermocouples (surface contact type) for measuring the pipe wall temperature
& for soil temperature measurement
7.2.12 Two laboratory thermometers 0oC to 60oC range, accuracy + 0.01 degrees duly
calibrated.
7.2.13 Injection facilities to inject additives into the test medium in the required
proportions
7.2.14 Communication equipment suitable for a continuous communication between
the beginning and the end of the test section and with the inspection team along
the line, in accordance with the requirements of Local Authorities
7.2.15 The temporary scraper traps (Testing Headers) shall be installed according to the
testing sections agreed in the test procedure manual. Proper piping and valve
arrangements shall be available to allow launching and receiving of each pig
independently. The test heads shall be sized in conformity with ASME
specification Section VIII, Division 2 with particular reference to Appendices 4
and 5.
8. PROCEDURES
8.1 Equipment and / or parts which need not or must not be subjected to the test
pressure, or which must not be tested with water, must be disconnected or
separated from the pipeline to be tested.
8.2 If the difference of minimum and maximum atmospheric temperature should
cause thermal instability on the pipe section directly exposed to atmospheric
condition, the scraper (Testing Headers) traps and above ground pipeline shall be
properly protected.
The pipeline test shall exclude long segments of line exposed to atmospheric
conditions, viz. aerial lengths on piers, suspension bridges, etc., which sections
shall be tested separately.
8.3 The test medium shall be soft non-aggressive water furnished by the
CONTRACTOR. The water to be used shall be filtered, shall not be contaminated,
and free from sand or silt. CONTRACTOR shall submit laboratory test reports of
water used for testing. CONTRACTOR shall provide TGPL/TPIA approved
corrosion inhibitors (remidol - 4000), oxygen scavengers and bactericides to be
added to the test water.
The CONTRACTOR shall furnish and install all temporary piping which may be
necessary to connect from source of water to its pumps and manifolds / tank
ages. The CONTRACTOR shall provide Material Test Certificate to TGPL/TPIA prior
approval before furnishing and installing temporary piping.
Note: -
Cleaning of line shall be evaluated by TGPL/TPIA.
8.5 WATER FILLING
The section, which is planned for water filling, shall be cleared from NDT, air
cleaning and gauging. A detailed pipe book for the section to be tested shall be
submitted by Contractor to TPIA for review before commencement of water
filling activity. Filling header shall consist of Minimum 3 pigs and the headers are
to be pre-tested before welding to main line. During filling, the volume of water
used for filling shall be measured by turbine meter / flow meter at every one-
hour interval.
8.6 THERMAL STABILIZATION
After a check has been made to confirm if the pressure has attained at least 1 bar
(g) on the highest section, the thermal stabilization can be started.
Thermal equilibrium between the pipeline and environment shall be checked
through the thermocouples installed on the pipeline.
Temperature readings shall be made at 2 hours - intervals. Thermal stabilization
shall be considered to have been achieved when a difference not higher than 1OC
is attained between the average values of the last two readings from pipe to soil
8.7 PRESSURIZATION
The pressurization shall be performed in the presence of TGPL /TPIA at moderate
and constant rate not exceeding 2 bars / min. One pressure recorder shall be
installed in parallel with the dead weight tester. Volume of water used to reach
the test pressure shall be recorded periodically throughout the pressurization by
recording no of stroke. The pressurizing shall be cycled according to the following
sequence:
- Each 5 bar increments up to 80% of test pressure as recorded by the dead
weight tester.
- Each 2 bar increment between 80% of test pressure as recorded by the
dead weight tester.
- Each 0.2 bar increments between 90% of the test pressure up to full test
pressure as recorded by dead weight tester.
iii) Re-Pressurise to 75% of test pressure, hold pressure for 1 hour, and collect
water for air volume calculations.
iv) Drop pressure to static head of test section at the test head.
v) Re-pressurise to test pressure and hold for stabilization.
During the pressurization to each test pressure, two tests shall be carried out for
the calculation of air volume in the pipeline under test.
In case, during the hold pressure periods indicated above, a decrease in pressure
is observed, the operations shall not be repeated more than twice, after which
the line shall not be considered capable of test, until the CONTRACTOR has
isolated and eliminated the cause for the lack of water tightness.
8.8 AIR VOLUME CALCULATION
In order to check the presence of air in the pipeline, two separate consecutive
pressure lowering of 0.5 bar shall be carried out.
For calculation of air in the pipeline the second pressure lowering shall be used,
and the relevant drained water shall be accurately measured (V1). This amount
measured shall be compared to the theoretical amount (V2) corresponding to
the pressure lowering that has been carried out, by using the procedure outlined
in the specification.
If no air is present in the length under test:
V1
--- = 1
V2
The above ratio is acceptable, provided it shall not differ from ‘1’ by more than
6% (i.e. 1.06).
If ratio is found to be above within limits, then pressurization can proceed. If not,
water refilling shall be carried out by another run of batching pigs after
depressurizing the pipeline.
The test shall be repeated as per the above procedure until above estimated
tolerances are satisfied. The pressurizing can then continue, to reach the value of
test pressure.
8.9 MECHANICAL STRENGTH TESTING
After the section has been pressurized and the air volume test has given
acceptable results the test pressure shall be held for a minimum of 24 hours
after stabilization. After temperature and pressure has stabilized, the injection
pump shall be disconnected and all connections at the test heads shall be
checked for leakage. The pressure recorders shall then be started with the charts
in a real time orientation for continuous recording throughout the test.
During the testing period the following measurements shall be recorded:
- every one-hour pressure measurements form dead weight testers.
- every two hours the ambient temperature and the pipe temperature at the
thermocouples.
All data shall be recorded on appropriate forms attached to the hydrostatic test
procedure manual. Care shall be taken that the maximum test pressures are not
exceeded.
Bleed-off water shall be accurately measured and recorded.
9. ACCEPTANCE
9.1 The hydrostatic test shall be considered as positive, if pressure has kept a
constant value throughout the test duration, except for change due to
temperature effects. Such changes shall be evaluated as described under clause
12.2 of this specification.
shall be replaced with same degree of bends. After completion of repairs, the
hydrostatic test shall be repeated in full, as per this specification.
9.3 The cost of repairs or replacements, followed by refilling and re-pressurizing the
line, due to poor workmanship, shall be borne by the CONTRACTOR. In the event
of leaks or failures resulting from faulty TGPL furnished materials, CONTRACTOR
shall be reimbursed for furnishing all labor, equipment, materials, except those
materials furnished by the TGPL and transportation necessary to repair and re-
pressurize the section of the pipeline to the pressure at the time of recognition
of leak or line failure.
10. TERMINATION
After the positive results of testing and all the data have been gathered, the test
shall be terminated upon written approval given by the TGPL / TPIA.
10.1 DEPRESSURIZATION AND DEWATERING
The pipeline shall be slowly depressurized at a moderate and constant rate as
instructed by TGPL /TPIA.
CONTRACTOR shall de-water the tested line as per the following requirement
after test acceptance.
Using four-cup pigs (polycups) and foam shall carry out the de-watering.
Pigs shall be driven by compressed air.
10.3 Upon completion of the testing and dewatering operation, any provisional traps
for pigs and all other temporary installation relating to the test shall be removed.
Subsequently, the individual sections of the line already tested shall be joined in
accordance with the requirements of relevant specifications issued for the
purpose. Upon completion of dewatering, swabbing shall be followed by using
foam pigs.
Weight of last pig received, shall not be more than 10 % of initial weight.
11. MEASUREMENTS
11.1 WATER AMOUNT MEASUREMENT
The water volume added to the section to be tested shall be measured during
the filling stage through a positive displacement meter (a turbine meter may also
be used). Calibration certificates shall not be older than one month. Satisfactory
performance on site to be established
In the calculation, as per clause 12.1 of this specification, use shall be made of
the geometrical volume of the section. The water amount that has been let into
the section shall be measured during the pressurization stages through positive
displacement meters or turbine meters.
11.3.1 Water temperature shall be taken at every 2 hours through the thermocouples
that have been installed along the section under test on the pipe wall.
12.2 The pressure change due to a water temperature change shall be calculated
through the following Formula:
∆P = B x ∆T/(0.884 * (ri/ti) +A)
Where,
∆P = Pressure change resulting from temperature change (bar)
∆T = algebraic difference between water temperature at the beginning of the
test and water temperature as measured at the end of the test (ºC)
B = value of the difference between the thermal expansion of water at the
pressure and temperature as measured at the end of test and that of steel (0°C-1)
x 10-6
A = Isothermal compressibility value of water as estimated at the pressure and
temperature values obtained at the end of the test (bar –1) x 106
ri = average nominal inner radius of the pipe (mm)
ti = average nominal pipe thickness (mm)
13. PRECAUTIONS DURING THE TEST
In addition to all that has been expressly described in the procedures for carrying
out the tests, the following additional requirements shall be complied with:
13.1 Provision shall be made for the installation of no-admittance signs to
unauthorized personnel from the roads to the R.O.W.
13.2 Signs stating “PIPE UNDER TEST KEEP OFF” with local language translation shall
be placed where the pipeline is uncovered, and particularly where the
provisional traps and stations are located. Such areas shall be suitably fenced in
such a way as to prevent access of unauthorized personnel. No unauthorized
personnel shall be closer than 40 m to the pipeline or equipment under test
13.3 Provisional scraper traps shall be installed in compliance with methods and
suitable locations so that their rupture cannot cause any injuries to the
personnel or third parties.
13.4 The test station shall be placed in such a location as to prevent it from being
affected by a catastrophic failure in the test head.
13.5 Once dewatering is over, the sectionalizing valves and other valve assemblies
tested previously, shall be installed at locations shown in the drawings and in
accordance with the procedures contained in the relevant specifications. All
15. DOCUMENTATION
Contractor shall provide following as minimum
15.1 Schematic layout of cleaning, filling and testing facilities.
15.2 Calibration certificate of measuring instrument and testing equipment.
15.3 A profile of the pipeline that shows the test sites, all instrument and injection
connection.
15.4 Pipe filling logs and records.
15.5 Additive specification, required concentration and additive injection records.
15.6 Pig inspection records including photographs of the damages.
15.7 Records of gauging pig, calliper pigging (intelligent pigging) and photograph, if
occurs.
15.8 Quality records.
Pipeline cleaning, Water filling, Thermal stabilization, Pressurization, Pressure
Holding, De pressurization, De watering report.
Inspection and Test Plan
Test procedure for cleaning, flushing, filling and testing.
15.9 Air-volume calculation
15.10 Pressure change due to temperature change calculation.
15.11 Records and photograph of all leaks.
Page 1 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
TABLE OF CONTENTS
1.0 SCOPE
2.0 REFERENCE CODES & STANDARDS
3.0 SUBMITTAL BY CONTRACTOR
4.0 GENERAL
5.0 SWABBING
6.0 DRYING
7.0 DOCUMENTATION
Page 2 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
1. SCOPE
This Specification covers the Swabbing & drying of Pipeline after completion of
hydro testing.
2. REFERENCE CODES & STANDARDS
2.1 Governing Standard
ASME B 31.8 - Gas Transmission and Distribution piping system
2.2 Reference Standard : Nil
3. SUBMITTAL BY CONTRACTOR
The CONTRACTOR shall submit the swabbing & drying procedure along with
activity report / records and inspection test plan compatible to this specification
at least one week prior to commencement of the work for approval of
TGPL/TPIA.
4. GENERAL
4.1 Drying shall be carried out using dry air method and the out let of drying unit
shall give a dew point of – 45°C. The drying unit shall be mobile type (desiccant
type) fitted with oil separator. The discharge capacity of drying unit should be of
adequate capacity to dry the pipeline.
4.2 A digital dew point meter (with self-calibration and with valid calibration
certificate) shall only be used for checking the reading.
4.3 Dryer shall achieve a dew point of -8 to -100C in the entire pipeline by propelling
foam pigs from Launcher to Receiver.
5. SWABBING
5.1 To ensure smoother and speedy final drying operation of entire pipeline length,
CONTRACTOR shall conduct preliminary drying separately on each Hydrotest
section after swabbing operation.
Page 3 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
5.2.1 Poly pigs followed by high and medium density foam pigs shall be propelled with
compressed / Dry air for removal of Residual water for swabbing operation.
5.2.2 For checking the contents of water, each pig shall be weighed before launching
and after receiving and recorded.
5.2.3 The difference in weight of receiving foam pig shall be 10% of initial weight of
same foam pig to ensure that there is no physical water in line. If more than one
foam pig is launched at same time, then at least one of the received pig should
qualify the weight criteria for satisfactory swabbing.
5.2.4 During the above operation log of pigging shall be maintained at site.
5.2.5 Drying shall be carried out round the clock, once started after the swabbing
operation. If possible, the swabbing shall be preferably conducted using
drying air to reduce the drying time.
5.2.6 Valves, tap off, launcher, receiver etc. as coming in the section shall be tied
up before start of drying operation.
5.2.7 Mainline valves shall be kept fully open during operation and by passes shall
be used only to check drying stage in between length and drying of valves.
5.2.8 CONTRACTOR shall provide communication facility at both launching and
receiving ends.
5.2.9 Skilled, semi-skilled manpower shall be provided for 24 hrs operations.
5.2.10 Adequate lighting arrangement shall be provided for operation in night.
6. DRYING
After completion of swabbing and tie-in of valves, tap off etc. in each Hydro
test section, following operations shall be carried out for the drying.
6.1 Air pigging header shall be installed at both launching and receiving ends and
connections shall be made.
6.2 A sequence of three nos. of foam pigs, High, Medium & Low density (7 to 10-
kg ranges) shall be launched with the super dry air at the interval of 30
minutes each.
6.3 The discharge of drying unit shall be measured at every 06 hours using digital
dew point meter and – 45°C at the outlet of dryer shall be maintained.
6.4 The foam pigs when received at other end shall be removed and vents shall
be kept open on receiving end to ensure min. backpressure. The dry air shall
be allowed to flow continuously till – (8 to 10°C) is achieved at the receiving
end.
Page 4 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
6.5 The drying time calculation shall be conducted using temperature– moisture
chart for reference calculation.
6.6 All pre-dried sections shall be finally tied up and final drying of entire
pipeline shall be conducted in similar manner using super dry air by
propelling with foam pigs between pig launching and receiving station. The
final drying shall be conducted to achieve –10°C at receiving end.
7. DOCUMENTATION
CONTRACTOR shall submit the following document as minimum.
7.1 Calibration certificates of measuring instrument
7.2 Quality records
7.3 Drawing indicating swabbing & drying operation connection
Page 5 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Page 6 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
TABLE OF CONTENTS
1.0 SCOPE
2.0 SUBMITTALS BY CONTRACTOR
3.0 FUNCTIONAL REQUIREMENT
4.0 DESIGN REQUIREMENT
5.0 MATERIAL REQUIREMENT
6.0 INSPECTION AND TESTING
7.0 DOCUMENTATION
Page 7 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
1. SCOPE
This specification covers the minimum requirement of design, material,
manufacture and supply of casing insulators and casing seals intended to be
used for pipeline crossing.
2. SUBMITTALS BY CONTRACTOR
2.1 Prior to procurements of casing insulators and casing seals, Contractor shall
furnish copies of, but not limited to, the following for qualification of the
manufacturer and material
i. Complete descriptive technical catalogues or data sheet describing the
materials offered along with samples of materials, its properties and
application instruction as applicable specifically to the project.
ii. Test certificates and results of previously conducted tests, for all properties
of this specification
iii. Reference list of previous supplies of the similar material indicating the
project details such as diameter, quantity, operating parameter, year of
supply, project name, contact person and feedback on performance.
Once the TGPL/TPIA approval has been given, any change in material or
manufacturer shall be notified to TGPL/TPIA, whose approval in writing of all
changes shall be obtained before the materials are used.
2.2 The Contractor shall submit the Installation procedure and Inspection test
plan compatible to this specification at least one week prior to
commencement of the work for approval of TGPL/TPIA.
3. FUNCTIONAL REQUIREMENT
3.1 The pipeline insulator shall be used to support the carrier pipe inside the
casing pipe and electrically isolate the carrier pipe from the casing pipe for
the cased crossing The casing insulators shall:
Resist cold flow and will not soften at design temperature
Resist corrosion
Resist mechanical damage while being pulled into the casing
Have high electrical insulating value and low water absorption, thus
preventing leakage and ensure required electrical isolation between
carrier and casing pipes
Have high compressive strength in order to assure a permanent support
to the carrier pipe
3.2 Casing end - seals are intended to be used for sealing the annular space
between casing pipe and carrier pipe at casing ends so as to prevent ingress
of moisture and water.
Page 8 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
4. DESIGN REQUIREMENT
4.1 The arrangement of insulator shall be generally in accordance with
recommendations of authority having jurisdiction if not specify it shall be as
per Dwg. TGPL/E&P/STEEL/CROSSING/08. It shall be made in segments duly
held together with cadmium-plated bolts and nuts, to be supplied along with
casing insulators.
The numbers of segments shall be two for pipe Diameters up to 12”
(generally). For larger Diameters, the numbers of segments may be more
than two, but their number shall be kept minimum, as directed by
TGPL/TPIA.
The assembly height shall be such that it is slightly less than the value
obtained by following formula,
= Casing internal Dia - Carrier outer Dia
2
Contractor shall obtain prior approval from TGPL/TPIA on casing insulators
drawing / design.
Bolting used in casing insulation shall be cadmium coated and it shall not
touch casing pipe.
4.2 The seals shall be suitable for the casing and carrier pipe diameters as
applicable for each case.
The casing end seal shall be flexible to cater for the expansion and
contraction of carrier and casing pipes and shall be able to tolerate both
angular and concentric misalignment of casing pipe without loss of
sealing efficiency.
The design of the casing end seals shall permit easy installation of the seal
to the cased pipeline crossing.
Contractor shall obtain prior approval from TGPL/TPIA on casing end seals
drawings / designs.
5. MATERIAL REQUIREMENT
Page 9 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
TGPL/TPIA. Insulators shall be of Heavy duty HDPE materials and shall meet
the following specification:
Test
Sr. No. Property Acceptance Criteria Test Method
Condition
Compressive
2 3200 psi - ASTM D – 695
strength
5.2 The casing end seals shall be made of heat shrink high-density radiation cross
linked polyethylene with an adhesive having a melt point suitable for the
pipeline service temperature and ambient temperatures foreseen during
construction. End seals material shall be resistant to heat, cold, vibration,
impact, abrasion, corrosive fluids, disbonding, organic and bio -
deterioration. Contractor shall ensure the compatibility of end seals with
carrier pipe coating.
Casing end seals shall be of only ReyChem RPG Limited and equivalent made.
Page 10 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Casing end seals shall meet the following specification:
Acceptance
Sr.No. Property Test Condition Test Method
Criteria
No visual
1.3 Heat Shock flow cracks, Flow or At 225 0C, 4 hrs D – 2671
drips
2 Adhesive
3.1 Peel strength (To casing and 5 psi (10 ASTM D –1000
carrier pipe and closure patch) inch/min)
Installation Procedure
Inspection & Test Plan
Inspection Report
Page 11 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Page 12 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
TABLE OF CONTENT
1.0 SCOPE
2.0 REFERENCE CODES AND STANDARD
3.0 SUBMITTAL BY CONTRACTOR
4.0 GENERAL REQUIREMENTS
5.0 DIRECTIONAL AERIAL MARKERS
6.0 KILOMETER MARKERS
7.0 ROW BOUNDARY MARKERS (RCC)
8.0 PIPELINE WARNING SIGNS
9.0 NAVIGATION WATERWAY PIPELINE CROSSING WARNING SIGN
10.0 DOCUMENTATION
Page 13 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
1. SCOPE
1.1 This specification covers the minimum requirements for supply, fabrication and
erection of pipeline markers to be installed by CONTRACTOR at various locations
along the route of a pipeline.
1.2 This specification shall be read in conjunction with the conditions of all
specifications and documents included in the CONTRACT between TGPL/TPIA and
CONTRACTOR.
2. REFERENCE CODES AND STANDARD
Following standards of latest edition have been referred in this specification:
2.1 Governing Standard
API RP 1109-Recommended Practice for Marking Liquid Petroleum Pipeline Facilities
2.2 Reference Standard – Nil
3. SUBMITTAL BY CONTRACTOR
The CONTRACTOR shall submit the Installation procedure of markers along with
activity report / record and inspection test plan compatible to this specification
at least one week prior to commencement of the work for approval of
TGPL/TPIA.
4. GENERAL REQUIREMENTS
4.1 CONTRACTOR shall supply, fabricate and install the Pipeline Markers along the
pipeline route. The locations of markers shall be based on AS BUILT chainage and
as directed by TGPL / TPIA.
4.2 The pipeline markers shall be fabricated and installed in accordance with the
standard drawings. Before start of fabrication of the markers, CONTRACTOR shall
prepare and submit for TGPL/TPIA approval the detailed scheme for the marker
plates as applicable for the project.
The pipeline markers shall be installed, as far as possible, at locations such that
no hindrance is caused to the regular uses of the land or to the traffic.
5. DIRECTION AERIAL MARKERS
Direction Aerial markers shall be installed along the pipeline route at every 5 Km
intervals and or at places specified by TGPL/TPIA as per Ref. Drg. No.
TGPL/E&P/STEEL/MARKER/02.
Aerial markers shall be installed at 1000 mm to the left of the pipe centreline
viewing towards the direction of flow.
6. KILOMETER MARKERS
These shall in general be installed along the pipeline between the aerial markers
at every one-kilometre interval. These shall indicate cumulative distance in km
for the reference base station or as desired by TGPL / TPIA.
Page 14 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
KILOMETER post shall be 1000 mm to the left of the pipe centreline viewing
towards the direction of flow and as directed by TGPL/TPIA as per Drg. No.
TGPL/E&P/STEEL/MARKER/01.
7. ROW BOUNDARY MARKERS (RCC)
Right-of-way boundary markers shall be fabricated and installed as per the
drawings at every 250 mtrs interval along the entire pipeline route. These shall
be installed on the side of the pipeline alignment to define the ROW boundary.
These shall also be installed at pipeline turning points to maintain the continuity
of the ROW limits. Refer Drg. No. TGPL/E&P/STEEL/MARKER/08.
And any other location as shown in the approved drawings and as directed by the
TGPL / TPIA.
Pipeline warning signs shall identify the existence of the pipeline and display the
name of the OWNER with an emergency telephone, and a Warning - “High
Pressure Gas Line, Dial before Digging” etc. as per standard documented drawing
Drg.No. TGPL/ E&P/STEEL/MARKER/03.
Warning sign shall be installed to the left of the pipeline center viewing in the
direction of flow at 1000 mm from pipeline.
Page 15 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
9. NAVIGATION WATERWAY PIPELINE CROSSING WARNING SIGN
Painting and stencilling for all the aforesaid shall be done as indicated in
respective standards.
10. DOCUMENTATION
Quality records
Page 16 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Page 17 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
TABLE OF CONTENTS
1.0 SCOPE
2.0 REFERENCE CODES AND STANDARDS
3.0 SUBMITTAL BY CONTRACTOR
4.0 MATERIALS & EQUIPMENT REQUIREMENTS
5.0 APPLICATION PROCEDURE
6.0 INSPECTION AND TESTS
7.0 COATING OF FIELD WELDS
8.0 REPAIRS
9.0 MARKING, PROTECTION, STORAGE, TRANSPORTATION, UNLOADING, HAULING
AND HANDLING
10.0 DOCUMENTATION
Page 18 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
1. SCOPE
1.1 This specification covers the minimum requirements for the materials,
application, inspection, handling and other activities for external continuous
concrete weight coating of pipelines.
1.2 It shall be read in conjunction with the conditions of all specifications and
documents included in the contract between TGPL and Contractor.
1.3 Contractor shall, with care and diligence, execute the work in compliance with all
laws, by-laws, ordinances, regulations, etc. and provide all services and labor,
inclusive of supervision thereof, all materials, excluding the materials indicated as
Owner supplied materials in the Contract, equipment, appliances or other things
of whatsoever nature required in or about the execution of the work, whether of
a temporary or permanent nature.
1.4 Unless otherwise specified, all sections of this specification shall apply to all the
specification referred in this specification.
Page 19 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
2.2 Reference Standard - Nil
In case of conflict between the requirements of this specification and that of the
above referred codes and standards, the requirements of this specification shall
govern.
3. SUBMITTAL BY CONTRACTOR
The Contractor shall submit the Concrete Coating procedure along with quality
records and inspection test plan compatible to this specification (Refer Annexure
II) at least one week prior to commencement of work for approval of TGPL / TPIA.
4. MATERIALS & EQUIPMENT REQUIREMENTS
The Contractor shall supply all the materials and equipment necessary for the
performance of the work.
Materials for concrete coating shall comply with following requirements. All
materials supplied by the Contractor, which in the opinion of TPIA / TGPL, do not
comply with the appropriate specifications shall be rejected and immediately
removed from site by Contractor at his expense.
4.1 CEMENT
Portland Cement (conforming to IS-269), or High Strength Ordinary Portland
Cement (Conforming to IS-8112) shall be used. Cement which has hardened or
partially set or which has become lumpy shall not be used. Test certificates from
the cement Manufacturer shall be supplied to the TPIA / TGPL for all cement
delivered to site.
4.2 AGGREGATES
Aggregates shall comply with the requirements of IS:383 and shall be tested in
accordance with IS:2386.
Fine Aggregates
Fine aggregates shall mean any of the following, as defined in IS: 383:
a) Natural sand;
b) Crushed stone sand;
c) Crushed gravel sand;
Sand shall be well-graded from fine to coarse in accordance with table 4 of IS:383
Coarse Aggregates
Use of coarse aggregates shall be subjected to TPIA/TGPL approval.
Aggregates shall be clean and free from injurious amounts of salt, alkali,
deterious substances or organic impurities.
Page 20 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
4.3 WATER
The water shall preferably be limpid, fresh and clean and shall be free from
injurious amounts of oils, acids, alkalis, salts, sugar, organic materials or other
substances that may be deterious to concrete or steel. It shall not contain
chlorides, sulphates, and magnesium salts. Water from doubtful sources shall be
tested by the Contractor at his expense and approved by TPIA/TGPL before use.
4.4 REINFORCEMENT
Concrete coating shall be reinforced by a layer or layers of steel reinforcement
according to the provisions described here after.
Reinforcement shall consist of welded steel wire fabric manufactured in flat
sheets or in rolls (ribbon mesh) and shall conform ASTM A-185. Wires shall
conform to ASTM A-82.
Steel wires shall be galvanized at finished size as per ASTM A - 641. The
diameter of the wire and spacing of wires (mesh dimensions) shall be selected
according to the following criteria.
Wire fabric manufactured in rolls (ribbon mesh) shall be 1 x 2.5 inches of 14
gauge U.S. Steel wires (2 mm wire). The above dimensions will be applied unless
otherwise specified by designs. Ribbon mesh (rolls) shall be used when concrete
coating is applied by impingement method.
4.5 COATING
Pipes shall be concrete coated to a thickness as specified in the drawings and
documents. The concrete unit weight shall be minimum 2245 kg/cm 3 (140
pounds per cubic foot) and the compressive strength shall not be less than 200
kg/cm2 in 28 days and 140 kg/cm2 in 7 days. Concrete coating shape shall be
circular and concentric to pipe outside diameter. Other concrete coating shapes
are not acceptable.
Contractor shall be permitted to select any proportion of materials to achieve the
specified requirements of concrete density and weight.
4.6 EQUIPMENT
The equipment used for performing the concrete coating shall be capable of
doing so with a reasonable degree of uniformity with respect to thickness,
Page 21 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
density and strength. The proportioning equipment and procedure shall be of the
type to assure consistently proportioned materials by weight. Concrete shall be
mixed in a mechanical mixer, which shall ensure thorough mixing of all materials.
Any equipment that tends to separate the ingredients shall not be used.
5. APPLICATION PROCEDURE
5.1 PROCEDURE QUALIFICATION
Before commencement of the work, Contractor shall perform all tests, either in
laboratory or in field and trials necessary to properly select type of mix, which
meets the requirements of section 4.5 of this specification.
5.1.1 The type of mix, i.e. the correct combination of the cement, aggregates and
water which results in the desired properties of concrete shall be at first
determined. For each mix the following shall be accurately checked and
recorded:
Proportions and weights of the respective materials used;
The water / cement ratio;
The grading of the aggregates.
Samples shall be prepared and tested in accordance with ASTM C-642 to
determine the dry specific gravity of the concrete.
In parallel, test according to ASTM C-138 shall be performed so as to determine
the expected correlation between concrete weight after placing and dry specific
gravity (28 days after placing).
Test for concrete specific gravity at intermediate time (7 days after coating)
shall be performed.
When the results of the above tests do not meet the requirements, the mix
shall be modified and concrete samples tested until a proper mix has been
determined.
The mix so determined, shall then be used for sampling of concrete to be
submitted to compressive strength tests as per ASTM C39.
Frequency of sampling for tests for density and compressive strength of
concrete shall be as follows:
“Quantity” of Concrete in the Work Number of Samples
Page 22 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Up to 25 m3 03
26 to 50 m3 04
3
51 m and above 04
Plus one additional sample for each additional 50 M3 or part thereof.
Quantity means the volume of concrete to be used for each qualified mix.
Page 23 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
coating of girth weld joints shall be required. The reinforcement shall protrude a
minimum 50 mm from the finished concrete coating.
Reinforcement shall rest on synthetic resin spacers forming a “Crown” whose
number shall be such as to avoid any contact with the pipe’s protective coating.
Spacing between the two consecutive “crown” centers, shall be 500 to 1000 mm.
Splices and attachments shall be done by binding with steel wire having 1.5
mm diameter. Circular and longitudinal joints of wire fabric in sheets shall be
lapped at least for one mesh while the spliced lap shall be three meshes.
One layer of reinforcement steel shall be provided for concrete thickness less
than 50 mm. The reinforcing steel shall be embedded approximately midway in
the concrete coating thickness. For concrete thickness 50 mm and above two
layers of reinforcing steel shall be provided. If application method requires more
than one pass concrete, one reinforcement layer for each pass concrete is to be
applied independently from concrete coating thickness.
Page 24 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
All pipes shall be kept clean and free from cement concrete and grout either
inside or outside of the uncoated sections.
Bevel protectors shall be kept in place throughout the coating application and
after.
The coating at each end of the pipe shall be bevelled to a slope of
approximately two-to-one (2:1). It shall terminate about 50 mm short of the
end of the corrosion coating applied on the pipe surface.
5.3.4 Curing
Immediately after concreting, the exposed surfaces of the concrete shall be
protected during hardening from the effects of sunshine, drying winds, rain, etc.
and then after the initial set has taken places, the concrete coating shall be
properly cured. The coated pipe sections shall be handled gently by suitable
means to prevent undue distortion.
Curing shall be started after completion of initial setting time of cement or
after hardening of surface or as instructed by TPIA /TGPL. The pipe surface shall
be kept wet during daylight hours for seven days after application of the concrete
coating. The concrete coating shall not be allowed to dehydrate. Prior approval
of “TPIA/TGPL” shall be taken by Contractor for using admixture/chemical in
concrete mix, in order to increase / decrease setting time, strength of concrete
mortar.
Before handling and hauling the concrete coated pipes, a check shall be made
to make sure that the concrete coating is properly cured. Stacking and shipment
of the coated pipes shall be initiated only after seven days provided that the
concrete coating suffers no damage.
6. INSPECTION AND TESTS
6.1 After curing, every length of concrete coated pipe shall be non-destructively
tested by means such as “ringing” to determine if any suspected defects are
present. In case this indicates faulty coating, cores shall be removed from coating
and inspected. When defective coating, appears from cores, the concrete coating
shall be removed from the pipe lengths.
Page 25 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
6.2 Every length of concrete coated pipe shall be checked to verify insulation
between steel reinforcement and pipe by means of a megger or equivalent
device. To this purpose provisions shall be made during placing of concrete such
as to leave at least a point of exposed steel reinforcement whenever the latter
shall terminate inside of concrete coating.
6.3 During the tests as per clause 6.2 above, and before transporting of concrete
coated pipes, every length shall be visually inspected to detect whether any
damages and/or defects are present. Possible damages and/or defects with their
allowable limits are described in clause 8.0. Repairable Concrete coatings shall be
clearly marked while the non-repairable ones shall be removed from the pipe
length
Page 26 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
burlap between the ends of the mould and the existing concrete coating. After
the mould has been filled with concrete the filling opening must also be closed
off by clamping a strip of burlap under the sealing cover.
8. REPAIRS
The following are repairs that will be permitted to coating due to unavoidable
damage in handling and in storage (This applies only to concrete that has
hardened).
8.1 Spelling due to compression or shearing caused by impact against other object.
Spelling is defined as damage, which causes a loss in concrete of more than 25
percent of the total thickness of the coating at the point of damage.
8.2 Damage due to spelling of an area of less than 0.1 m2 (1 square foot) where the
remaining concrete is sound will be accepted without repairs.
8.3 Damage due to spelling of an area of more than 0.1 m2 and less than 0.3 m2 shall
have the concrete remaining in place over that area removed as necessary to
expose the reinforcing steel throughout the damaged area. Edges of the spelled
area shall be under-cut so as to provide a key lock for the repair material. A stiff
mixture of cement, water and aggregate shall be trowelled into and through the
reinforcement and built up until the surface is level with the coating around the
repair. The pipe shall then be carefully laid with the repaired area at the top and
shall be moist cured for a minimum of thirty-six (36) hours before further
handling.
8.4 If damaged area be more than 0.3 m2, coating shall be removed around the
entire damaged area. A repair shall be made by satisfactorily restoring the
reinforcement, forming the area with a metal form and pouring a complete
replacement of materials similar to that from which the coating was made. The
mixture shall be one (1) part of cement to three (3) parts of aggregate and
necessary water to produce a slump not to exceed 100 mm (four inches). The
resulting coating shall be equal in weight, density, uniformity, thickness, strength
and characteristics to the originally applied coating. The pipe shall then be
carefully laid in a position where it shall be allowed to remain for a minimum of
36 hours before further handling.
Page 27 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Page 28 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
delivery point at laying field or storage areas as previously established. Thus,
providing each time the necessary storage.
During the operations of loading, unloading and stock piling, the pipe sections
shall be handled in such a way so as to avoid dents, cuts, cracks and other
damages especially at bevelled ends or damages to protective and/or concrete
coating.
10. DOCUMENTATION
The CONTRACTOR shall submit following as minimum.
Test Certificates
Quality records
Procedure of concrete Coating
Concrete coating report
Inspection and test plan
Page 29 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Page 30 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
TABLE OF CONTENTS
1.0 INTRODUCTION
2.0 Quality Goals, Objectives and Critical Success Factors
3.0 Quality Management Organization and Responsibilities
4.0 SUBMITAL BY CONTRACTOR
5.0 QUALITY ASSURANCE SYSTEM REQUIREMENTS: ANNEXURE – I
1.0 QUALITY ASSURANCE / DEPARTMENTAL ACTIVITY CONTROL MANUAL
1.2.1 General:
1.2.2 Procurement:
1.2.3 Procedure:
1.2.4 Construction:
1.2.5 Pre Commissioning activity:
2.0 QUALITY PLAN:
2.1 For Procurement and Construction:
2.2 For Pre-commissioning:
ANNEXURE – II
Page 31 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
1. INTRODUCTION
1.1 This specification establishes the Quality Assurance requirements to be met by
the CONTRACTOR during execution of work. In case of any conflict between the
requirements of this specification and other documents such as technical
specifications, contract conditions etc. and the latter shall generally take
precedence. The CONTRACTOR shall notify TPIA of all such conflicts for final
resolution.
1.2 Requirements stipulated in this specification conform to ISO: 9000, 9001, 9002,
9003 and 9004.
1.3 Quality Goals, Objectives and Critical Success Factors
2. Goal:
To generate and maintain an overarching culture of quality throughout all project
activities conducted within Project Management Team and the associated
contractors and suppliers.
Objective:
To undertake all Quality assurance inspections in accordance with the Quality
Assurance Plan
To close out all non-conformances on procured items prior to deliver
To close out all non-conformances within PMT and Contractors’ Project
(Quality) Management Systems
To complete the Third Party Verification Scheme, documenting that all
performance standards have been met, prior to start of commissioning
Quality Critical Success Factors:
To apply the ‘Plan – Do – Check – Act’ cycle of quality management to all
aspects of the project, including undertaking suitable quality assurance
inspections of the PMT and of principal contractors and subcontractors, and
conducting QC surveillance of contractors’ own QC activities based on
criticality of the product
To provide suitable numbers of QA/QC personnel to ensure that the quality of
the project processes followed and all project deliverables is suitable
Page 32 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
To maintain management support of the Quality Management Process,
including rigorously supporting the Quality Assurance function and
maintaining the pressure for closure of non-conformances
To co-ordinate and proactively drive the Third Party Verification Scheme to
completion.
3. Quality Management Organization and Responsibilities
Page 33 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
C. Sharing quality related information:
1. Electrode qualification test result : Contractor to TPI and TGPL
3. Field joint coating procedure qualification records: Contractor to TPI and TGPL
7. Line pipe coating damage / holiday report : Contractor to TPI and TGPL
4. SUBMITAL BY CONTRACTOR
The following documents shall be submitted along with the bid for evaluation.
4.1 Quality Assurance plan and /or Departmental Activity Control procedure l.
A. Quality Plans
The CONTRACTOR shall obtain approval on his Quality Assurance plan and / or
Department activity control procedure and Quality Plans. The Contractor shall
participate in the kick-off meeting with TPIA to finalize “Quality Plans “as regards
to the following:
Page 34 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Performance of internal quality audits, preparation of audit reports
and submission for TPIA’s review.
IS : 10201
ISO :9000, 9001, 9002, 9003, and 9004
5.2 The CONTRACTOR shall ensure that the quality system is clearly understood and
faithfully implemented at all levels in his organization.
5.3 The CONTRACTOR shall develop quality consciousness among all personnel
working for the contract.
5.4 Non-conformance Handling (Internal Sources):
Non-conformances brought out by Contractors’ / Sub-Contractor’s own review /
audit shall be resolved by Contractors’ / Sub-Contractor’s themselves. One level
higher than those responsible to carry out the activity shall resolve the non-
conformities. Such resolution shall be in full knowledge of Departmental
Manager. Corrective action shall be initiated at the earliest. Report of such
resolution shall be submitted to TPIA for satisfaction of the quality.
5.5 Non-conformance Handling (External Sources):
Page 35 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Non-conformance brought out by TPIA or its engaged agencies through any of
the following but not limited to:
Technical Reviews
QA Reviews and Surveillance
Inspection and External Audit (TPIA)
Corrective Action Report (CAR)
NC shall be resolved by the Contractor / Sub-Contractor. Such corrective actions
shall be submitted to TPIA for review. However, corrective action shall be
implemented within weekdays.
5.6 The CONTRACTOR shall evolve a comprehensive system of planned and
documented audit to verify whether various performed activities comply with
detailed procedures, specifications, guidelines etc., and to determine the
effectiveness of Quality System. Scope of such internal audits shall be furnished
to TPIA for review.
5.6.1 Verifiable documents shall be generated during audit and submitted periodically
to TPIA for review. Audits shall be carried out by independent engineers not
responsible for execution of the activity to be audited. Whenever so desired,
TPIA may join in the above audit as observer.
5.7 Throughout all stages of the scope of contract, the Contractor’s procedures,
documents, activities, products and services and those of his Sub-Contractor’s
shall be subjected to Quality surveillance and audit by TPIA. Such surveillance and
audit are optional and shall not relieve the Contractor of his contractual
obligations and liabilities.
5.8 The CONTRACTOR shall submit all quality records (generated during activity
execution) and audit results on well-laid formats / Proforma for TPIA review. The
rights of such review are reserved by TPIA. TPIA may review it in full, parts or
selectively. However, complete correctness of the QA records shall be the sole
responsibility of the Contractor irrespective of its review by TPIA.
5.9 The CONTRACTOR shall get similar QA System implemented at his Sub-
Contractor’s works/office. Q A records from the sub-Contractor shall be reviewed
Page 36 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
and certified for compliance by the Contractor before submitting to TPIA for
information.
5.9.1 CONTRACTOR shall carry out audits at Sub-Contractor’s office / works and shall
submit the report to TPIA for information. Whenever so desired, TPIA shall have
accessibility to Sub-Contractor’s offices/works.
5.10 All personnel shall be assigned tasks commensurate with their qualification &
experience. Specialized operators shall be qualified and certified.
Page 37 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
ANNEXURE – I
GUIDELINES TO BIDDERS FOR COVERAGE OF DOCUMENTS
1.2.1 General:
Document control
Non-conformance resolution
Output identification and traceability
Internal audit
1.2.2 Procurement:
Page 38 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Handling & storage of Materials.
Stringing of line pipes.
Trenching.
Cold field bending.
Concrete coating.
Cased crossing.
Open cut crossing.
Lowering.
Main line welding.
Weld joint numbering.
Weld repair.
Post heat treatment
Radiography.
Dye penetration test.
Ultrasonic test.
Tie in welding.
Field joint coating pipe to pipe and pipe to bends / tee.
Field joint repair.
Back filling.
Minor water crossing.
Pre hydro-testing
Hydro-testing Dewatering
Marker installation
Cleaning, swabbing and drying
Special installation (SV’s, Pig Launcher & Receiver, Metering skid, Hook-up
fabrication)
Restoration
Painting of above ground piping
Pre-commissioning
Reconciliation
Page 39 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Inspection / Test plans for all specific and mandatory tests (as per drawings and
codes) with clear indication of witness, verification and hold points shall be
submitted along with relevant procedures.
1.2.4 Construction:
Pre-construction activities viz., incoming material control, Approval of
procedures and process etc.
Storage and identification of Received materials
Certifications and approval of Contractor supplied materials
Calibration certificates of Instruments
Approval of Construction drawing for crossings
Welding qualification and repair
Waste Management
1.2.5 Pre Commissioning activity:
Activity description.
Procedure number / Inspection and Test Plan number.
Conformance code.
Testing and inspection code.
Type of surveillance.
Internal audit scope.
2.2 For Pre-commissioning:
Activity Description
Page 40 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Procedure / Inspection and Test plan number
Type of Surveillance.
Internal audit scope
Page 41 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
ANNEXURE – II
1. WITNESS POINT
1.1 An activity designed by TPIA, which requires witnessing by TPIA as the activity be
performed.
1.2 After proper notification has been provided (notification modalities and period
shall be communicated in kick-off meeting) the Contractor is not obliged to hold
further processing if TPIA is not available to witness the activity or does not
provide comments before the date notified. Basis of acceptance shall be as per
relevant technical specification.
2. VERIFICATION POINT
2.1 Point where TPIA plans to audit, monitor or witness an in-process activity.
3.1 “Review” means checking, identifying & certification of the documents for
conformance of standards & specifications.
3.3 The Contractor shall not process the activity / item beyond a review point,
without written approval by TPIA except where prior written permission for
further processing is available.
4. QUALITY SURVEILLANCE
5. Q. A. RECORDS:
Page 42 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
5.1 Documents which demonstrate achievement of required quality and verify
effective operation of Quality System, viz., but not limited to:
Inspection reports (All Construction activities)
Test data / inspection test plans
Qualification reports
Validation reports
Audit reports
Material Test Certificates
Calibration Reports
Quality cost report
Pipe Book
Rework/ Rejection Report
6. QUALITY AUDIT:
6.1 A systematic examination of the acts and decisions by people with respect to
quality in order to independently verify or evaluate and report degree of
compliance to the operational requirements of the quality Program, or the
specifications or contract requirements of the product or service.
Page 43 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Page 44 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
TABLE OF CONTENTS
1.0 Scope
2.0 References
3.0 Specifications
4.0 Design and Engineering
5.0 Installation Procedure
6.0 Drilling profile
7.0 Bentonite Disposal Scheme
8.0 Rights of way and work space
9.0 Rights of way
10.0 Quality and Inspection Plan
11.0 Pre Reaming Operation
12.0 Pipe line Installation Operations
13.0 Inspection and Testing
14.0 Special Instructions
15.0 As-built records
Page 45 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
1. SCOPE
The specification covers the minimum requirements of various activities to be
carried out by the Contractor for engineering and “Laying of Pipeline through
Horizontal Directional Drilling” under the contract.
2. References
Page 46 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
3. Specifications
Pipeline Size = Different thickness as mentioned in specification
Pipeline Material = Specifications as mentioned in specification
Anti-Corrosion Coating = Specifications as mentioned in specification
Joint Coating= For HDD Joint Coating fibre glass reinforced heat shrinkable
sleeve certified to Stress class C60 type CANUSA-TBK or COVALENCE / DlRAX
shall be used. Directional drilling kit, multilayer sleeve system or equivalent
to be approved by Owner / Engineer.
4. Design and Engineering
INTRODUCTION
The following calculations shall be done and examine the stress imposed on a
pipeline during the installation of a horizontal directionally drilled crossing prior
to pullback during pullback and post installation to confirm that the pipeline will
not fail.
The calculations are based on the following:
Pipe empty on conveyors
Pipe full of water on conveyors
Pipe Pull back- empty
Page 47 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Hoop Stress
Stress summery
PERMISSIBLE OVERBURDEN
PIPELINE calculation
The Contractor will submit for approval to the Third Party Inspection agency the
stress calculation as described in the Deutsche standard NEN 3650 and NEN 3651
or equivalent.
The following phases should be analysed in the pipeline design process:
Predisposition of the launching catenary:
Before the pulling operation, the pipeline is outside the bore-hole and has a
configuration which allows it to enter the hole. During this phase, the only
bending moment is due to the curvature of the catenary and the weight. The
pipeline should be designed so that it behaves elastically.
Pull-back operation:
In this phase the pipeline will be pulled back through the bore-hole. The
following forces should be considered: bending moment due to curvature of the
hole; Friction force between the pipe and drilling mud including the friction due
to extra cables/sleeves attached to the string; Friction force inside the hole, at
the location where the soil reaction occurs; stress due to soil reaction; The
Contractor will specify the means he intends to use in order to reduce the friction
during the pull-back operation. The resultant stress should be calculated and the
pipeline designed to behave elastically.
Operating conditions:
In this phase the loads acting on the pipeline are:
Page 48 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Bending moment due to curvature of the hole; internal pressure of the gas;
temperature difference of the line between the pipe-laying and operating
conditions; dead loads Vertical soil load at the top of the pipe can be calculated
for different pipe laying conditions.
The following effects should be combined for the purposes of calculating the
resultant stress:
calculated longitudinal effects on the entire pipeline system;
Calculated effects on the cross-section of the pipeline.
The stress/strain shall not exceed the relevant allowable stress. The effects of soil
load on the cross-section of the pipe may be analysed. This analysis should be
carried out at the deepest point reached in drilling.
Mobilization:
Page 49 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Drilling Equipment shall be mobilized to site through access roads to Entry point
and Exit point. Necessary grading shall be done for the placement of pipe string
and drilling spread
The Contractor will supply with his tender the different documents listed here
below.
Key staff organization chart.
Curriculum vitae of his key staff
A complete description of the anti-corrosion pipe wraps he intends to use for
pipeline field joints and repairs.
A description of the major drilling equipment as
Drill rig specification
Maximum dynamic torque
Pull back capacity
Drilling fluid trailer tank specification
Control cab
Pipe racks
Workshop
Generators
Positioning system
Drilling head
Ancillary equipment.
A complete description of the directional drilling working method as: The
positioning record system and procedure Drilling of the pilot hole and wash over
pipe. Hearing operation (type and size of the reamer) Mix compound of the
bentonite mud.
Soil cuttings/Bentonite mud separation and treatment process and reuse of the
Bentonite.
Pipelines pull back operation.
Alignment and positioning of the pipe string.
Rollers support used. The support will be designed so as not to damage the pipe
coating. Detail drawing showing the theoretical profile, the final design profile,
Page 50 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
the position of the pipe string (with support arrangement) before pull back
operation
The method he intends to use for controlling the integrity of the pipeline coating
as well as "anticorrosion" pipe-wraps.
The method he intends to use for verification of the pipeline final profile after
the pull-back operations.
Installation of pipeline
Before starting the activity, the Contractor will submit for approval to the
Owner the final profile of the HDD including any deflexion of the drilling head.
The Contractor can start the operation only after the Owner approval.
This document needs to demonstrate that after completion (operating condition)
and under internal pressure (MOP and test pressure), soil load and hydrostatic
load the section of the pipeline will not have a radius of curvature smaller than
those permitted by the design.
The document shall also indicate the pulling force on the pipe at the beginning,
during and at the end of the process and the rate of progress of the pipe.
During the different execution phases of the HDD the Contractor will record
all the information regarding the different operations which includes, among
others:
The measurements of mud pressure, mud flow rate, pulling force, X-Y-Z of the
drill head recorded during drilling and any other relevant statistics.
After completions of the HDD the Contractor will transmit to the Owner the
horizontal drilling operation record of the relevant activities which includes.
Concerning the drilling mud quantity of mud used; mud pressure (at the drilling)
Page 51 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
the density of the drilling fluid and soil cuttings;
The localisation of storage site for the waste from the drilling operation and the
measures taken to comply with environmental constraints.
During drilling operation (per drill pipe element) the maximum force applied
(push/pull/torque); time duration for assembling 2 elements; the drilling head
position in X-Y-Z- co-ordinates; deviation compared to the required position; The
proposed corrective measures.
During drill pipe pull-back (per drill pipe element) pull-back duration per
element;
Maximum pulling force per element.
An alignment sheet with length profile of the pipeline (scale 1/500) showing
the location of each weld joint and their X-Y-Z co-ordinates.
An official certificate concerning the discharge of the drilling operations
tailings approved by the relevant Authorities.
Page 52 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Pilot Hole
Rig up shall be done, after mobilizing the equipment at drill location. Rig shall be
anchored at the specified angle as per the approved drawing before start of pilot
hole with dead men in ground.
The pilot hole shall by drilled with a Horizontal Directional drilling rig, to enter
the ground at an angle of entry as specified in the drawings. Pilot hole directional
capability is accomplished by using a Drill Bit. The offset creates a steering bias in
its direction and plane. If a change in direction is required, the same will be done
by pushing drill string so that the direction of bias is the same as desired change
in direction.
Mechanical cutting action can be achieved by the bit attached to the offset drill
string.
The actual path of the pilot hole will be monitored by a state-of-art magnetic
guidance system (attached). The actual path of the pilot hole is monitored during
drilling by taking periodic readings of the inclination and azimuth of the leading
edge. These readings, in conjunction with measurements of the distance drilled
since the last survey, are used to calculate the horizontal and vertical co-
ordinates along the pilot hole relative to the initial entry point on the surface and
profile is plotted for the actual path being taken along the proposed alignment.
Readings are taken at every joint (normally a road length). When the bit
penetrates the surface at the exit point, the pilot hole is complete.
Ream and Pull Back
After the completion of pilot hole, depending on the drilled cuttings and actual
soil encountered during the pilot hole, combinations of Cutters /Reamers will be
used to enlarge the hole.
The Cutter / Reamer will be fixed to the drill string will be rotated and
pulled/pushed through the pilot hole. The cutter will cut through the hole with
the cutting action of bentonite pumped through the drill string. On completion of
first pass other Reamer (sizes may vary as per actual condition) shall be used to
enlarge the hole. Cleaning passes as required shall be done depending on the soil
conditions encountered. It is to be noted that the passes mentioned in the
Page 53 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
schedule are tentative and might change as per the soil conditions encountered
as per the pilot hole logs. It will be decided at the site to use various combination
of down hole tools as per the requirement by the Driller. Also the sizes of
Reamers/Cutters and sequences to use these can be varying as per actual site
conditions.
Once the cutting passes are complete a non-rotating swivel will be attached to
the pull head welded to the pipeline section to prevent torsional stress on the
pipeline. The drill string is aligned with the product pipe, upon completion of
hydro testing and field joint coating. An overhead bend will be formed by lifting
the product pipe to the correct height to allow smooth entry in the borehole. As
the pipeline section is drawn towards the drill rig the pipeline section will be
adequately cradled with rolling cradles IUM) to facilitate a stress free line-up with
the pre-reamed hole. Product pipe shall be placed on rollers to minimize the
friction during pulling.
Bentonite will be pumped during pullback. Bentonite slurry and returns from the
drilled hole shall be disposed off either in the river through the small ditch or in
the mud pit to be excavated at site. Bentonite to be used does not contain any
constituents hazardous to the environment. During drilling process check shall be
maintained to check the viscosity and mixing of mud shall be controlled as per
the soil conditions in countered. Upon reaching rig side, the final reamer and pull
back swivel are removed and the pulling head cut from in the product pipe. After
completion of pull back, the rig down shall be done and the equipment is
demobilized after clearing/cleaning the work area.
Drilling Accuracy
The instrument used to survey the pilot hole during drilling is magnetic and
therefore subject to some inaccuracy. Additionally, some deviation from the
designed drilled path may be experienced due to soil reaction. Therefore, we
generally anticipate a deviation in actual verses designed pilot hole course of +/-
0.5% of the horizontal and vertical directions drilled length. The error, when it is
unacceptable, can be largely eliminated by re drilling after "punch out" in the
Page 54 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
right of way limits. Best drilling standards shall be followed to minimize the
deflection as per the client’s requirements.
Performance of the down hole survey system is monitored during drilling by
diagnostic system which confirms the suitability of the transmitted signal.
Additionally, the accuracy of the surveyed hole can be determined by comparing
the actual exit point with the anticipated exit point. Any error measured in this
manner is then distributed linearly over the entire length of the pilot hole to
produce an accurate as built survey. Immediately after completion of pilot hole
reaming operation shall start without any delay.
5 Drilling profile
The Owner will provide a basic profile drawing and the constraints and
particularities of the obstacle to be crossed.
The Contractor shall specify and submit to the Owner for approval his final profile
and the different parameters or their limited value which define the location and
configuration of the drilled path.
It is acceptable that the entry and exit will vary from the design proposed
location. They have to be located inside an area (5 x 10 m) centred around the
proposed location, 10 m shall be measured parallel to the HDD alignment.
Except if otherwise specified in the tender document, the minimum radius shall
be not less than 1000 times the Nominal Diameter (ND). The predetermined
theoretical profile shall be closely adhered to when drilling the pilot hole. The
permitted deviation shall not exceed 2 m laterally and 1 m vertically from the
approved theoretical profile.
Page 55 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
6 Bentonite Disposal Scheme
Bentonite slurry and returns from the drilled hole shall be disposed off in the
mud pit to be excavated at site. Bentonite to be used does not contain any
constituents hazardous to the environment.
8 Rights of way
The working space and the site location is specified in the TENDER DOCUMENT.
The right to use the specified working space will be granted by the Owner.
Should Contractor require more space, it will be Contractor's responsibility to
negotiate such additional space in close co-ordination with the Owner.
Contractor shall support all relevant costs.
Page 56 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
vertical alignment taken at each road length intervals. The steering tool
technician is responsible for this Quality Assurance activity. This activity is
conducted during pilot hole installation.
Page 57 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
radius of 40 times the pipe O.D. and a straight pipe of sufficient length, such that
at the ends the top of the pipeline is minimum 2.5 m below the natural ground
level.
The drill rig will be demobilized and the job site secured. These activities are also
a part of the Quality Assurance responsibilities of the Driller.
12 Inspection and Testing
Contractor will maintain the Inspection and Testing procedure for the HDD works
at site as mentioned below:
i) Daily Maintenance
Page 58 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
13 Special Instructions
For access route to the working strip the Contractor will be responsible to
negotiate with the relevant Owner, tenant or authorities. Any deemed
compensation will be borne by the Contractor.
Contractor proponent shall have to preserve top soil dug and shall be restored to
original condition on completion of the work wherever required / as required.
Contractor shall construct the pipeline and other infrastructure by adopting
safety measures as per the standards & specification laid down by the concerned
agencies from time to time. All the safety and personnel protection measures
shall be properly provided to meet any mishap / hazard / during operation and
HDD method.
Contractor proponent is required to comply with the manufacturing, Storage and
Import of Hazardous Chemicals Rules-1989 framed under the Environment
(Protection) Act-1986.
On completion of all temporary work structures, surplus materials and wastes
shall be suitably disposed off.
14 As-built records
As work advances, the position of the pipe shall be surveyed and plotted on the
drawings.
"As-Built" documents shall maximise the use of CAD, computer database (Access
2007 and Excel) and digital records in such a way to allow later integration in a
"Geographical Information System" (GIS).
All equipment shall be duly traced with reference to initial supplier Identification
Reference (ID) - weld log-book - Certificates - etc.
The exact position "As-built" of these elements shall be accurately located with
reference to ID and geographical co-ordinates.
Page 59 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Page 60 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
TABLE OF CONTENTS
Page 61 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
TECHNICAL REQUIREMENTS FOR TEMPORARY CATHODIC PROTECTION
2 Corrosion Data
Graphical representation of existing structure / pipe to soil potential records,
T/R unit current / voltage readings.
Remedial measures existing on foreign pipeline / services to prevent
interaction.
Possibility of integration / isolation of TCP & PCP system
Crossing and parallel running of electrified and non-electrified traction (along
with information regarding operating voltage, type AC / DC etc.,) as well as
abandoned tracks near ROW having electrical continuity with the tracks in
use.
AC Interference Survey
Crossing or parallel running of any HT AC / DC overhead line (existing /
proposed) along with details of voltage, type AC / DC etc.
Voltage rating, number of cores and sheathing details of underground power
cables, along ROW or in its vicinity.
Page 62 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Information on existing and proposed DC/AC power sources and system
having earth as return path, in the vicinity of the entire pipeline route such as
HV DC sub stations and fabrication yards with electric welding etc.
Any other relevant information that may be needed in designing and
implementing proper protection scheme for the proposed pipeline.
If required, SERVICE PROVIDER shall conduct necessary potential gradient
survey for any existing anode ground bed that may interfere with the TCP
system of the pipeline covered under this Bid.
3 System Details
The system shall include the following major equipment / sub systems unless
otherwise specified.
Sacrificial anodes for TCP
Zinc anode for HT crossing
Test stations for TCP
C.P system at cased crossing
Surge diverted / Grounding cell / Polarization cell
Interconnecting cables
Cable to pipe connections
All equipment shall be new and supplied by approved reputed manufactures
Equipment offered should be field proven. Equipment requiring special
maintenance or operation shall be avoided as far as possible and prototype
Page 63 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
equipment shall not be accepted. Make and construction of all materials shall be
subject to TGPL/TPIA’s approval.
SERVICE PROVIDER shall furnish the detail specification of each system and
equipment. However, certain minimum requirements for the major equipment
are highlighted in this document.
As far as possible, equipment including test stations, anode etc., shall be located
in safe area. All equipment located in hazardous areas shall be of flameproof type
as per IS: 2148 for gas groups IIA, IIB and temp. Class T3, EX-d Type (Explosion
Proof).
Approved make of equipment/component for TCP system
a. Test Station (TLP)/Junction boxes
M/s Ex Protecta, Mumbai
M/s FCG Limited Mumbai
M/s Flexpro, Navsari
M/s Baliga Lighting Equipments, Chennai
M/s Underground pipeline & NDT services, Noida
M/s Corrosion Control Services, Mumbai
M/s Corrtech International, Ahmedabad
b. Sacrificial Anode (Mg & Zn with backfills)
M/s Metal Founders Mumbai
M/s Shakti Enterprises Ahmedabad
M/s Protech Alloy Anodes Karaikudi
M/s Scientific Metal Engineers Karaikudi
M/s Corpen Anodes
M/s Electro – protection services
c. Reference Electrode – Cu CuSO4
M/s Harco USA
M/S MC Miller USA
M/s Borin USA
M/s Electrochemical Devices USA
d. Cables
Page 64 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
M/s Netco Cables
M/s Fort Gloster Cables
M/s Cable Corporation of India Ltd.
e. Pin Brazing
M/s Safetrack
f. Thermit weld/Cad weld
M/s Erico Europa
g. Surge Diverter
M/s Dehn GmbH
M/s CITEL
M/s Mc Miller
M/s Control Technology
M/s Dairyland Electrical Industries
M/s International Corrosion Control Inc.
M/s Raychem
h. Polarization Cell/AC Decoupling device (Solid State)
M/s Kirk Engineering
M/s International Corrosion Control Inc.
M/s Elk Engineering associates Inc.
M/s Metricorr
a. Sacrificial anode
CONTRACTOR shall decide the type of sacrificial anode as per design & detail
engineering and provide the same. It shall be Mg, Zn or ribbon with necessary
backfills. Location of sacrificial anode installation shall be decided considering no
underground utilities.
CONTRACTOR shall install it vertically, depth shall be as per design, from the
bottom of pipeline at the specified distance from skin of pipeline laid. In case of
multiple anode installation distance between two anodes shall be kept as per
design/2-3 Mtr.
Page 65 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
b. Grounding Cell
The Grounding cell shall compose of 2 Nos. of high purity Zn anodes with tail
cables and will be pre-packed in a cotton bag with special backfill. Insulated
spacers shall separate the two anodes.
c. Test Stations
Test stations shall be provided along the pipeline ROW for monitoring the
performance of the cathodic protection system at intervals not exceeding 1000
meters unless otherwise specified. In addition to above, test stations shall also be
provided at the following locations:
a) At both sides of major road crossings
b) At all insulating joints
c) At vulnerable locations with drastic changes in soil resistivity.
d) At connections of surge diverts, grounding cells and polarization cells.
e) At HT AC/DC overhead lines crossings and selected locations where HT
overhead line is in the vicinity of the pipeline.
f) Both side at railway line crossings and running parallel to the pipeline.
g) At both sides of major river crossings.
h) At high voltage cable crossings or along routes where HV cables are running in
parallel.
i) In the vicinity of DC networks or grounding system where interference
problems are suspected
j) At crossings / parallel running of other pipelines / structures.
k) At both sides of cased crossings.
l) At any other locations considered vulnerable / locations where interference is
expected.
m) At any other locations considered necessary by TGPL / TPIA.
Test stations for bonding shall be provided with shunt and resistor as a means
to monitor and control current.
Test stations used for sacrificial anodes shall have shunt for measurement of
anode current, and provision for resistance insertion to limit the anode
current output.
Page 66 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Test station with current measuring shall be provided at each intermediate CP
station drainage point (to measure pipeline current on any one side of
pipeline from drainage point), at interference prone areas, on both sides of
major river crossings and at least at two additional locations along the pipeline
ROW between two CP stations.
All test stations shall have weatherproof enclosure, having degree of
protection IP 55 with hinged lockable shutter. IP-55 uses as a Weather and
Dust proof.
Enclosure shall be made of sheet steel of at least 3 mm thickness and shall be
suitable for M. S. post mounting. The test stations shall be designed with
terminals required for permanent CP system and shall be suitable for total life
of permanent CP system.
The test stations shall be installed with the front of the test station facing the
pipeline. The nameplate of test stations shall in minimum carry following
information.
Test station number
Chainage in km.
Test station connection scheme type
Distance from pipeline in meters
Direction of product flow
The installation of the test station shall be as per attached Specifications.
The location of all the test stations shall be marked with their connection
schemes and other relevant information’s on alignment sheets. A detailed test
station schedule shall be prepared.
Test station shall be post-mounted type of 100 mm MS pipe with base plate.
The Test station box will be fabricated from 3 – mm thick MS sheet having
weatherproof enclosure and hinged lockable shutter and having degree of
protection IP 55.
The Test station box size shall be 250 X 200 X 230 mm fitted with necessary
terminals, Inside the box, a Bakelite plate of 6 mm thickness will be provided with
necessary brass studs and washer of size M6 x 50 for cable connection. The cable
Page 67 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
entries will be through bottom bend provided in the foundation casting. The
height of Test station will be 1.0 m from ground level.
d. CP at Cased Crossing (Wherever Required)
Page 68 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
The cables shall be laid in the excavated trench of 400 mm wide at a minimum
depth of 1000 mm along with fine sand bedding & padding with brick layer
f. Permanent Cu / CuSo4 Reference cell
At each TCP location 1 No. of Permanent copper-copper sulphate Reference cells
will be installed to measure the pipe to soil potential. Reference Cell will consist
of High purity Cu element embedded in chemical grade CuSo4. The assembly will
be housed in unglazed ceramic pot to contain the Cu element surrounded by
chemical grade CuSo4 crystals. The assembly will be pre-packaged in cotton bag
with chemical backfill.
The reference cell will be installed at the bottom level of the pipeline at an
approximate distance of 300mm from the pipeline. If the pipeline has already
been backfilled the reference electrode may be installed on the top of the
pipeline approximately 100 mm above the pipeline.
The reference cell will be installed horizontally. The reference cell will be soaked
in clean water for 24 hours before installation. The area around the pre-packaged
reference cell cable will be routed along the top of the carrier pipe and strapped
to the pipe with adhesive tape at an approximate interval of 3m. The cable will
be routed to test station box.
g. Thermite weld / Cad weld
Thermite / Cad welding will be used for cable to pipe connections. Typically,
Thermite weld equipment would comprise of
Graphite mould with handle.
Weld metal + starting powder and metal disc.
Grinder or a file for exposing a good pipe surface.
Flint Gun.
15 gm of charge powder
Thermite welding of cable to pipe shall be carried out in the following steps.
Cable Preparation
25mm of the protective sheathing and insulation shall be removed from the
cable end. The bare conductor shall be clean, bright and dry.
Page 69 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Surface Preparation
The cable connection to pipe shall be at least 150mm from any field joint coating.
The protective coating and any mastic, adhesive or primer shall be removed from
the top of the pipe to provide an exposed steel surface area suitable for the cable
connection.
Cable Connection
The cable connection shall be carried out as follows.
1. Position the conductor over the centre of the cleaned pipe surface
area.
2. Locate the mould over the conductor so that conductor can be seen
through the hole in the bottom of the mould.
3. Place metal discover hole.
Open charge cartridge and pour the powder into the mould. Tap the side of the
cartridge to ensure that all the powder is emptied from the container. Continue
to shake and tap the cartridge to ensure placement of the ignition powder on top
of the charge powder.
4. Close the mould and ignite the ignition powder with a flint igniter.
5. Open the mould and remove after (approximately) 10 seconds
minimum.
Test after Thermite welding
The following tests shall be carried out before repairing the coating of the
finished cable connections.
1. Remove flux and any other debris using a hand or power wire brush
2. Check all the conductor is incorporated in the weld metal
3. Check the mechanical integrity of the weld
4. Check the continuity of the bare cable conductor to the pipe.
5. Coating Repair and its documentation.
6. All bare conductors shall be covered by the coating repair.
7. Two-part epoxy will be used for coating repair at Thermite weld
location. The boundary of epoxy with pipe coating will be covered
Page 70 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
with mastic. Care will be exercised not to damage original coating,
Cable insulation.
Page 71 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Test station identification as per TGPL requirement
b) Anode
Check location of anode
Check depth of anode
Measure and record resistance of anode
Check termination and tagging of anode cables
Check anode markers and cable markers
Check reference cells have been installed and cables terminated as per
specification
c) Reference Cell CuCUSO4
Location of ref cell installation
Cable termination in test station
d) Cables
Check cable number, cable size, cable tag, voltage grade.
Check cable depth
Ensure that bricks and cable tiles have been installed as per the drawing
Measure and record insulation resistance between core and earth
Check cable termination
e) Insulating Joints
Measure and record the insulation resistance across the insulating joint
Measure and record pipe-to-soil potential across the joint before and after
energization of CP System.
f) Surge Diverter
Page 72 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Check for proper termination
h) Polarization cell
B. Commissioning
The system will be allowed to polarize and a complete set of fairly stabilized
potentials will be recorded.
The final pipe to soil potential at each test station will be minimum protective
potential, (-) 0.85V is achieved at all the points. The maximum potential will be (-
) 1.2V (OFF) for 3LPE coated pipeline.
A full set of potentials will be recorded.
6 Equipment and Instruments
The following equipment and instruments shall be available on site as a minimum
requirement.
7 Documentation
SERVICE PROVIDER shall furnish the Complete Total Design Document for
Temporary Cathodic Protection System, which shall include but not, limited to
following:
7.1 Reports:
1.1 Corrosion Survey
Page 73 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
1.4 Soil Resistivity Review and Interpretation
7.2 Procedures:
3.2 Commissioning
7.7 Detailed Cost Estimates for Material and Installation of TCP System
One copy of all above Reports (Documents), Drawings and one Soft copy each on
Compaq Disc (CD) shall be submitted. No extra payment shall be made to Bidder
for the preparation of Report (Documents) and Drawings.
Page 74 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Page 75 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Page 76 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
21 Stacking of pipe done in safe manner by crane or mechanical means.
Traffic control ensured. Pipes are staked (on wooden planks with groves or on sand bags) so
22
that they don`t roll back on road and harm the public.
23 If blasting is required at some hard rocky area, the work shall be carried out as per approved
procedure and check the near by utility should not effected and be sure that in this area
stringing shall be done after trenching. No blasting is allowed within 15m of any existing
pipeline or structures (either above or below ground). All approvals related to blasting as per
Explosives acts and Rules or others as necessary shall be checked with the vendor allotted
with the job
Underground/above ground utility shall be notified & demarcated. Official permissions, if
24
required, from concerned authorities shall be obtained
At the crossing like road and railway, before start of trenching, trench and near by area use
for heavy equipment, area shall be checked with cable locator and pipe locator and also
identify the all under ground exiting utility and obstacle. The areas to be identify and mark
25
them with the temporary painted post. And expose/uncovered them by manually. Using an
excavator bucket is not allowed. In any case of damage of any cable or pipeline, work should
be halt immediately and inform to the TGPL and concerned company without any delay.
26 Trenching activity shall be carried out as per approved procedures/drawings only.
27 Soil is stacked minimum 300 mm away from the trench edge. No vehicle parked within 1 m
distance of the pit.
28 Crossover plates provided for pedestrian safety.
Flow of any Channel/Drain/Nala/river etc. shall not be obstructed for movement of
29
construction machinery without obtaining necessary permission from concerned authorities
30 Trenching planning shall be done according to lowering in spools, & shall be done near by
time of lowering.
31 For lowering proper lifting plan to be in place. Check SWL & load radius indicator of crane.
Standard pipe cradle can be used and a demonstration shall be carried out that pipe coating
is not damaged.
32 Alternatively non-abrasive pipe belts shall be used and care must be taken while removing
the belts. Wire rope slings or other material which may damage the PE coating shall not be
used to the lift the pipes. No slings shall be put around the field coated joints.
Before lowering in a complete check by a circle holiday detector for pipe coating (PE Coating)
33 and for field joint coating (HTLP 80 Sleeve) shall be carried out at 25KV, the damages if any
observed during the examination shall be repaired as per the approved procedure.
Where water is present, no lying shall be permitted. However, water shall be removed to the
extent and for the time necessary to make visual inspection possible of the bed on which the
pipeline is to be laid. Following such inspection the presence of water is permitted provided
34
it is not so high as to cause cave-in of the walls of the trench or floating of the pipeline
before backfilling, when weighting is not provided for the pipe. Care shall be taken to
prevent the floating of pipe section before backfilling.
Page 77 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Hydra/Cranes as required minimum numbers shall be used for holding the pipeline in gentle
35 S curve maintaining the minimum elastic bending radius as specified in the job standard. The
pipeline must be laid without interruption of whole section length available
Leveling of bottom of trench will be maintained by dumpy level & recorded at distance
36
interval of approx 12 to 15 meter or as per site condition
In all cases where rock is encountered in the bottom of the trench, at least 150mm sand /
37
soft soil bedding shall be done
38 Immediately after lowering level of pipe to be checked with level machine, same to be
recorded for as –built
When ever the pipe sections are left open at intervals to be tied in at a later date under
39 road, marshy locations etc shall be capped with a securely closed metal caps to prevent
entry of dirt, water or any foreign matter into the pipe section. Barricade the open trench.
40 Immediately after lowering back-filling shall be started as per approved procedure.
Minimum depth of cover shall be measured from top of pipe corrosion coating as applicable
41 to the top of undisturbed surface of the soil or top of graded working strip or top of rail or
top of road whichever is lower.
Backfilling shall be carried out immediately after the pipeline has been laid in the trench, so
as to provide a natural anchorage for the pipeline, thus avoiding long exposure of coating to
high temperature, damaging actions of adverse weather conditions, sliding down of trench
42
sides and pipe movement in the trench. If immediate filling is not possible, a covering of at
least 200mm of earth, free of rock and hard lumps shall be placed over and around the pipe
and coating.
The backfill material shall contain no extraneous material and/or hard limps of soil which
43
could damage the pipe/coating or leave voids in the backfilled trench.
When backfilling the trenches in sloping terrains or steep areas, the backfill may be washed
out of the trench, sheet piling or other effective water breakers across the trench shall be
44
provided. This is to divert the flow of water away from the trench into normal drainage
followed before laying the line.
First 300 mm backfilling shall be done by manually / by JCB/ excavator. Once post padding /
45 backfilling is complete surplus excavated soil should be placed over the trench so as to avoid
setting of the earth at the pipeline trench which may affect proper covering of the pipe.
2, Machine Boring Safety
Sr.
Work Instructions
No
1 As per PTW Matrix, Permit to be obtained.
2 Proper supervision as per PTW matrix for execution & safety to be ensured.
3 TGPL WPI as per permit to work requirement to be implemented.
4 Tool Box talk to be performed prior to start job.
Ensure to protect employees from falling into the entrance or exit pit by the placement of
5
a guardrail or fence at ground level around the pits/provide barricade around trench.
Page 78 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
6 Be sure all personnel have complete understanding of all safety signs.
7 Ensure that earthing is properly provided to machine.
8 The cable strike alarm must be in working condition and checked.
Always remove machine from tracks before lifting, then lift machine and tracks separately.
9
Before transporting, always secure machine to tracks with dogs engaged.
10 Always secure auger in casing before lifting.
11 No work shall be done on any part of the auger while the power source is running.
12 Make sure that all protective guards, doors, etc. are in place and secure.
13 Ensure that out riggers are proper and placed on rigid ground.
14 Start and operate the machine only from the operator’s station.
15 Always turn the engine off before leaving the operator’s station for any reason.
16 Never leave operator station while machine is in operation.
17 Avoid loose fitting clothing, loose or uncovered jewellery.
18 Remove all loose objects stored in or on the machine. Remove all objects which do not
belong in process.
19 Make sure all personnel know and stay in their prescribed areas to ensure a safe operation.
20 Do not start machine until all personnel are clearly away from any rotating or moving
parts.
21 In built / external cranes for machine must be proper, inspected & certified.
22 Relieve pressure in hydraulic system before servicing.
23 Shut down machine at first sign of malfunction or hazardous condition.
24 Shut down power source and relieve system pressures before doing any maintenance.
Engine must be turned off before:
- Opening spoil ejector door
- Working in casing
25
- Working in exit pit
- Doing any maintenance.
- Doing any Servicing
26 Do not refuel while engine is running, or while the engine is hot.
27 Do not smoke or permit open flames (which includes welding) while fuelling or near
fuelling operation.
28 Do not refuel to tank capacity. Allow room for fuel expansion.
29 Be aware that machine may move without warning while in operation.
30 Know and obey all statutory, state, and local codes and regulations.
31 Know and use the hand signals required for particular jobs and know who has the
responsibility for signaling.
It is the operator’s responsibility to know that all underground utilities have been located
32
before the bore is started, and to avoid them by using proper boring techniques.
Page 79 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
It is the responsibility of the operator to read and understand the Operator’s Manual and
33 other information provided and uses the correct operating procedure. Machines should be
operated only by qualified operators and trained helpers.
It is the operator’s responsibility to point out each of the safety signs on the machine and
34
ensure the crew understands the importance of adhering to each of the safety signs.
35 No crew shall consist of less than two persons.
It is recommended that the exit pit be excavated at the beginning of the boring process. If
36
not possible adequate distance for pit to be kept for doing excavations.
Always perform a pilot test that ensures that pilot is indicating it’s correct position &
37
values in tracker before executing HDD operation
38 Disengage rotation of the auger during spoil removal from entrance pit.
39 All engine exhaust must be vented to the open atmosphere.
In some instances venting of exhaust may be required. It is the operator’s responsibility to
40
be sure that the exhaust fumes have been properly vented.
41 Do not modify this machine.
3 Shot blasting, field joint, coating, holiday testing, charged pipeline buffing, painting
3.1 Grinding
Sr.
Work Instructions
No
1 As per PTW Matrix, Permit to be obtained.
2 Proper supervision as per PTW matrix for execution & safety to be ensured.
3 TGPL WPI as per permit to work requirement to be followed.
4 Tool Box talk to be performed prior to start job.
5 All Hazards to be identified through site specific risk assessment. Cordoning to be as per
site condition.
6 Rescue arrangements ensured in case of an emergency
7 Special care to be taken while overhead grinding, proper space to be ensured for sitting
and doing grinding.
8 Ear protecting equipment (Ear muff/plug) shall be used.
Inspection of grinding wheel and machine to be done & damaged wheel to be replaced.
9
Machine guard to be ensured. Electrical supply to be with ELCB boards only.
10 Care shall be taken to ensure that no grinding marks are made on pipe surface anywhere
3.2 Cutting/Welding of Steel Pipeline
Sr.
Work Instructions
No
1 As per PTW Matrix, Permit to be obtained.
2 Proper supervision as per PTW matrix for execution & safety to be ensured.
Page 80 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
TGPL WPI as per permit to work requirement to be followed. Cordoning of site as per site
3
condition.
4 Tool Box talk to be performed prior to start job.
5 All Hazards to be identified through site specific risk assessment.
6 Rescue arrangements ensured in case of an emergency.
7 Minimum persons to be kept near work place.
8 First Aid arrangements and Fire Extinguishers to be placed on site.
9 If required fire water arrangements to be done.
10 At public places proper risk assessment to be done prior to start of hot jobs.
11 Precaution for burn injuries for welding, hot coating workneeds to be ensured.
12 Welding huts to be ensured for welding purpose provide proper earthing during the
welding.
13 Quality of welding rods ensured.
For tie in proper holding arrangements to be in place. It should be ensured that pipes
14
don`t get dislocated and injure the nearby working crew members.
15 Adequate space needs to be ensured for welder to perform welding work.
16 Precautions for gas escape (if project is on existing gas network) and monitoring to be
ensured before any hot work on the pipelines construction.
17 Inspection of hose connection, flash back arrestor of gas cutting set.
All air/ gas pipe lines and air/ gas hoses are frequently inspected. Air/gas hoses shall not be
18
used for de-dusting or cooling purposes.
19 Ensure electrical cables, extension boards; machines are free from electric shock hazard.
Oxygen cylinders must not be stored near other cylinders containing gas or oil, grease or
20
other combustible materials.
21 While cylinder is in use, the cylinder valve, key or wrench must be placed on the valve
spindle.
22 Before a cylinder is moved, the cylinder valve must be closed.
Gas cylinders should not be stored near furnaces, cupolas, stove or any other source of
23
heat. The cylinders lying in the open should be protected from direct rays of the sun.
Gas cutting torch must be lighted by means of friction flames or similar other methods and
24
not with matches. Flash back arrester must be used.
Gas cylinders should be placed in locations where sparks or flame from welding or cutting
25
work cannot contact them.
26 All dissolved Acetylene cylinders should be kept in upright position whenever in use. (in
trolley)
The unloading and loading of gas cylinders must be carried out with utmost care:
Cylinders should not be allowed to drop or come into violent contact with one
27 another.
Adequate arrangement should be made to prevent cylinders falling from the
vehicles.
Page 81 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Rolling of gas cylinders should be avoided and they should be transported by
proper trolleys.
Oxygen and Acetylene cylinders should not be stored together. Stored cylinder to be
28
chained and should be in upright position. (in trolley)
Application of oil, grease or any other lubricating materials to regulators, valves or fittings
29 of gas cylinders is STRICTLY PROHIBITED. Cylinders and fitting should be kept free from oil
or grease to avoid ignition and explosion.
In case of leakage from regulators, valves or others fittings of the gas cylinders, the
30
cylinders should be immediately removed and sent for necessary repair.
31 When torches are being changed or welding stopped for short time, all cylinder valves
must be closed.
32 The coloured lenses used for welding or gas cutting must be of proper shade for the work
being done.
Before any heavy structural member is gas cut, it should be ensured that it is cleared and
33
supported by ropes, cables, chains or any other means to prevent its dropping or swinging.
Substantial and non-combustible screen must be used below or near the welding
34 operations, if there is a possibility of a spark falling on other workmen engaged in work
close by.
Proper protective clothing and appliances such as goggles, face shield, leather gloves,
35
leather apron etc should be worn for protection against radiating heat and spark.
36 One should not watch an arc-welding operation with naked eyes.
When arc-welding operations are performed in an area not enclosed or isolated, workers
37 or other persons connected with arc -welding job should wear coloured or welder’s goggles
or face shields
38 It is preferable to provide portable shields in the area where arc -welding is carried out.
39 When welding or gas cutting is performed in a confined space, the cylinders should be left
out side.
40 Suitable fire extinguishers in working condition should be kept closed to all welding and
gas cutting operations.
In confined spaces, where the means of exit is a manhole other small opening, means
should be provided, such as life belt and lift-line for quickly removing the workers in case
41
of an emergency. An attendant should be stationed outside the exit at all times while the
work is in progress. No entry inside the pipeline is allowed in any case.
In case of electrical extension is required, only ELCB/RCCB electrical extension board with
42
proper wire length is to be use. (ELCB/RCCB of 30mA sensitivity to be used)
Welding procedure qualification shall be carried out in accordance with the relevant
43 requirements Section 5 QUALIFICATION OF WELDING PROCEDURES CONTAINING FILLER
METAL ADDITIVES of API-1104, 2005 edition and TGPL Specification.
All welding procedure specification shall be submitted to TGPL for review & release and for
44
Page 82 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
releasing the procedure for procedure qualification test.
Once welded specimens cleared visually it shall be subjected to radiographic testing and
45 subsequently to destructive testing. Destructive testing shall be done as per TGPL
Specification and Section 5.6 for manual welding of API 1104, 2005 edition.
A complete set of test results shall be submitted to TGPL for approval immediately after
46
completing the procedure qualification tests.
Prior to start of fit-up bevel cleaning shall be carried out using power brush for a width of
47 25 mm from the edge of bevel for inside and outside of pipe. Bevel shall be visually
inspected for any dent/damage or improper machining.
Before start the welding full weld joint if required it should be cover with temporary booth
48 which contains fire resistance cloth to protect welding space from weather until the weld
completed.
Pipes shall be checked for correct thickness, dia. and spec, with respect to the approved
alignment sheets. The first pipe shall be positioned on skids of appropriate height from the
ground Supports shall be minimum two per pipe and skid shall have soft pads placed over
49 them to avoid damage to the PE coating, Pipes shall be locked to prevent their rolling from
the skids. External clamp shall be loaded outside. The second pipe shall be held by side
boom/ crane and shall be aligned with the first pipe and the external clamp shall be
actuated. The root gap shall be checked as per qualified WPS.
When an external line-up clamp is used, all spaces between bars or minimum 60% of the
50 root pass length shall be welded before the clamp is released. The remaining pipe shall be
adequately supported on each side of the joint.
The root pass of butt joints shall be executed properly so as to achieve full penetration
51 with complete fusion of the root edges. Welding shall not be interrupted during a pass and
shall be completed as early as possible. Penning shall not be permitted.
The time lapse between second and third pass shall be as stated in the procedure
specification, normally not exceeding 4 to 5 minutes. Welding can be suspended, so as to
allow the joint to cool down, provided that the thickness of the weld metal deposited is at
52 least 50% of the pipe thickness. Upon restarting, Pre-heating to at least of 100°C shall be
carried out. Subsequent passes tip to weld completion shall be protected to avoid rapid
cooling, if meteorological conditions so dictate. Cleaning between passes shall be done
carefully so as to reduce the possibility of inclusions.
53 Only one welder shall be used for main line welding up to the 8” Dia. Pipeline and two
welders shall be used for main line welding work above 8” dia. Pipeline.
In case of two welders to be used, Welder No. 1 shall start from 12'O' clock position and
proceed towards 6'O' clock, In respect to Anti-clock wise direction Welder No.2 shall start
54
from 3`O`clock position and proceed towards 6`O`clock and then start from 12 o’clock to 3
o’clock, in respect to clock wise direction
All finished welds shall be visually inspected for excessive reinforcement, concavity of
55 welds, shrinkage, cracks, undercuts, dimensions of weld surface porosity and other surface
defects. If any such defects are noticed they shall be rectified
Page 83 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
For welded pipes, circumferential weld seam and longitudinal weld seams of adjoining
pipes shall be staggered such that a minimum distance of 100 mm is maintained along the
56 circumference and both longitudinal welds or at top 90ºC quadrant of the pipeline
whichever is lesser (Except for bends). A longitudinal joint shall pass an appurtenance of a
structural element at a minimum distance of 50 mm.
The branch connection sleeve, etc. shall be minimum 150 mm from any other weld. The
welds for fittings shall be so located that the toe of the weld shall not come within 50mm
57
of any other weld. Cold dressing is permissible only in cases of slight misalignment and may
only be carried out with a bronze headed hammer. Hot dressing shall not be permitted.
Pipe shall be pre-heated using open flame heating. Preheat temperature of 100ºC
Minimum shall be maintained prior to commencement of root run and subsequent runs.
58 Preheating shall extend to 3 times the thickness of the joint & preheating shall be applied
on not less than 50mm on both sides of the weld. Preheating shall be checked by using
temperature indicating crayons/thermo pens. Max inter pass temperature shall be 250C
59 Earthing clamp shall be used for connecting pipe to welding machine terminal.
3.3 Holiday Testing of Steel Pipeline
Sr.
Work Instructions
No
1 As per PTW Matrix, Permit to be obtained.
2 Proper supervision as per PTW matrix for execution & safety to be ensured.
TGPL WPI as per permit to work requirement to be followed. Cordoning as per site
3
condition to be performed.
4 Tool Box talk to be performed prior to start job.
5 All Hazards to be identified through site specific risk assessment.
6 Rescue arrangements ensured in case of an emergency.
7 Trained and experience person shall do this work. Keep person away from pipe for holiday
tests.
8 No one allowed sitting, crossing or touching the pipe section during test.
9 Electrical safety precautions to be taken. Electrical supply to be from ELCB/RCCB boards
only.
10 Holiday detector can be used to detect for cracks in the coating generated due to corrosion
on Cold bent pipes
It is carried out before lowering in a complete check by a circle holiday detector for pipe
coating (PE Coating) and for field joint coating (HTLP 80 Sleeve) shall be carried out at
11
25KV, the damages if any observed during the examination shall be repaired as per the
approved procedure.
12 The holiday detector used shall be checked and calibrated daily before the commencement
of work with an accurate D.C. voltmeter. The detector electrode shall be in direct contact
with the surface of coating to be inspected.
The entire surface of the coated field joint shall be inspected by means of a full circle
13
holiday detector with a visual & audible signal. The test voltage shall be 5 KV + 5 KV/mm of
Page 84 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
total thickness of coating, subject to a maximum of 25KV. Inspection of the sleeves shall be
conducted only after the joint has cooled below 50ºC.
Page 85 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
2 Proper supervision as per PTW matrix for execution & safety to be ensured.
3 TGPL WPI as per permit to work requirement to be followed. Areas to be cordoned off &
barricaded if called for.
4 Tool Box talk to be performed prior to start job.
5 All Hazards to be identified through site specific risk assessment.
6 Silica free shots to be used and chlorides in it to be as per accepted limits.
Compressed air use is done for shot blasting and hence all the components of the system
to be inspected for robustness (no wear tear or cracks etc in hoses or air carrying
7
arrangements) before start of the procedure. Air to be free from moisture, oil etc
contaminants.
8 Any chemical use to be used for surface cleaning should be done by proper care in
respect of applicable PPEs.
There could be exposure to noise, vapours, fumes, dust etc in the operation and hence
9
proper cordoning, PPE use and warning signs must be put on site.
10 Care must be taken for electrical hazards and static charge generation.
Page 86 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
When non-destructive testing is required, the following percentages of each day's field
butt welds, selected at random by the operator, must be non-destructively tested over
their entire circumference; In Class 1 location, except offshore, at least 10 percent.
In Class 2 locations, at least 15 percent.
10 In Class 3 and Class 4 locations, at crossings of major or navigable rivers, offshore,
and within railroad or public highway rights-of-way, including tunnels, bridges, and
overhead road crossings, 100 percent unless impracticable, in which case at least
90 percent.
At pipeline tie-ins, including tie-ins of replacement sections, 100 percent.
Procedures must be established for the proper interpretation of each non-destructive
11 test of a weld to ensure the acceptability of the weld.
The welds containing following repairs are not acceptable under Non-Destructive Test
Cracks Cracks of any type size and shape including crater
cracks are Not acceptable
Incomplete root penetration Not acceptable
Lack of fusion at the root Not acceptable
12
Burn through Un-repaired burn through are not acceptable
Excess weld penetration > 2mm Not acceptable
(1ntcnial)
Excess weld reinforcement > 3mm Not acceptable
(External)
Except for a welder whose work is isolated from the principal welding activity, a sample of
13 each welder's work for each day must be non-destructively tested, when non-destructive
testing is required as per standard or statutory requirements.
When non-destructive testing is required, each operator must retain, for the life of the
pipeline, a record showing by milepost, engineering station, or by geographic feature, the
14
number of girth welds made, the number non-destructively tested, the number rejected,
and the disposition of the rejects.
4. Non-Destructive Test by Gama Rays & X-Rays
Page 87 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Reduce Exposure. Minimizing short-term exposure to radiation sources such as X-ray
devices and gamma emitting materials is one of the most effective ways to avoid long-
7
term radiation accumulation. Table-A indicates the most common methods of reducing
exposure to harmful radiation.
All Radiography Technicians shall have responsibilities to ensure to evacuate the public
and Non-Classified worker to the safe distance (Minimum 25 to 30 meters from radiation
8
source but to be finalized as per time of survey) and the area where radiography is being
performed. If Required Effective radiography area has to be barricaded.
All Radiography Personnel shall have responsibilities to themselves and other persons with
9 regard to safety and shall ensure site facilities are adequate with regard to lighting,
scaffolding and the like prior to commencement of operations.
Qualified personals of ASNT recommended practice SNT-TC-1A is engaged for avoidance of
10
radiography work Injuries. Provide personal dosimeter for radiograph workers.
11 Working Crew informed about Hazards due to Radiation.
12 Radiography team shall have a personal TLD for determining the personal dose.
If the TLD badge evaluation shows exposure to be in excess of the allowable limits of a
13 member, then non-radiation work shall be given to him until return to active radiographic
work as per BARC guidelines.
14 Use of Calibrated Radiation Survey meter for marking/cordoning of radiation exposure
zone shall be done.
15 A radiation survey shall be conducted during the activation of the source.
A long-standing, reliable safety tool for industrial radiographers is the film badge Carried
17 around in a protective container, the film badge is an exposure measurement tool used
for a finite period of time.
Lead cones (collimators) on the X-ray machine should be used to confine the beam to a
18
single direction and angle for maximum effectiveness in usage.
In gamma ray situations, distance is an important factor when operating in the field;
Proper signage around the testing area will alert personnel and third parties of radiation
19
activity. The safety zone to be decided based on the capacity of the source indicated on
the source.
Common isotopes such as Selenium-75, Iridium-192, and Cobalt-60 emit gamma rays that
20 can be extremely harmful when used without proper safety consideration, so safety must
be reviewed on top priority.
Use of Selenium-75 must be considered as its energy spectrum poses less of a risk of
21
radiation exposure to workers and the public.
The intensely penetrating nature of gamma rays forces scrutiny on not only shielding and
22
protection methods, but also distance from the source.
An “exclusion” zone is roped off around the location of the radioactive material, and
23 personnel are forbidden to enter the zone while the source is exposed. Proper signage
should be placed liberally near the testing site to warn third parties.
Page 88 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
The radiographer and agency must be approved by BARC and we must check the
24
documents related to it. The camera and the source must be approved for our site use.
The dose contamination of the radiographer and its check date to be ensured and
25 radiographer whose dose limit has crossed the approved limit must not be allowed on
site.
26 These tests must be done during night hours to avoid exposure to general public and
workers nearby.
This Procedure describes Radiographic Testing of welds by using X-Radiations from
27
respective Source for detecting the discontinuities of pipeline butt welds.
All butt weld joints of pipeline shall be subjected to 100% radiography.
Radiographic examinations of pipe to pipe butt weld shall be carried out using X-
28 radiations only.
Radiographic examinations of pipe to fittings and fittings to fittings butt weld shall
be carried out using Gamma-radiations only.
Pipeline radiographers shall be qualified in accordance with the requirement of API 1104
29
and to the full satisfaction of TGPL and as per ASNT-TC-1A Level 2
I.Q.I. Selection (mage Quality Indicator):
Image Quality Indicator shall be as per ASME Section V article 2 Table T 276 for ASTM
WIRE TYPE PENETRAMETER. The reference table is as follow:
Pipe Wall Thickness
Essential Wire Dia
or Weld ASTM SET DIN SET
(mm)
Thickness(mm)
30 0-6.4 0.20 A 10 ISO 16
6.4-9.5 0.25 A OR B 10 ISO 16
10 ISO 16 OR
9.5-12.7 0.33 B
6 ISO 12
12.7-19.1 0.41 B 6 ISO 12
19.1-25.4 0.51 B 6 ISO 12
25.4-50.8 0.64 B 6 ISO 12
Film Selection:
31 Radiographs shall be obtained using Industrial Radiography films. The Films used (D7 or
equivalent); Fine grain, High contrast Film
32 Lead screen of thickness 0.005”/0.1 to 0.15 mm and 0.2 to 0.25 mm front & back
respectively shall be used.
Surface Penetration: As far as possible all irregularities from the surface (to the extent of
33 coverage of films) shall be removed for better results and interpretation
Prevention of Back Scattering:
To achieve Radiography definition, it is required to check back scattering by placing lead
34
no. B on the backside of film holder to ensure the back scattering does not harm the film
quality. In such case, it is advised to place lead sheets on the backside of holder.
Page 89 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Placement of Marker & I.Q.I.:
Lead markers shall be kept to identify the test Object, Date of Radiography, area of
interest of the object, the weld numbers location of the Radiographs and any
other information as specified by the TGPL.
I.Q.I. shall be placed approximately 25mm away from the location marker such that
the thinnest wire of the ASTM/DIN type penetrameter shall be far most from the
35 source side. In case of Panoramic Exposure Techniques, minimum 4 Nos. of IQI’s
shall be placed equal distant along the circumference.
All films shall be clearly identified by lead numbers, letters, and/or markers. The
image of the markers shall appear on the films, without interfering with the
interpretation. These markers positions shall also be marked on the part to be
radiograph and shall be maintained during radiography.
Film Loading:
Film shall be loaded in the dark room under proper safe light, Filter. Films shall be cut
36
carefully without any damages, scratches or finger marks/Nail marks. Sandwich the film
between pair of screens & loaded into tight PVC cassettes or holders.
Number of Exposures:
The number of Exposures will be such that the area of Interest is completely covered and
37 when multiple films are used the overlap between any 2 films will be a minimum of
40mm. One exposure shall be taken for single wall single Image and Minimum of three
exposures for Double Wall single Image technique for Pipeline joints.
Film Processing:
Film shall be process in a dark room under safe light. The temperature of the chemical
38 shall be 20°C ± 1°C or as specified. The film shall be unloaded in hangers/ spools carefully
to avoid any marks.
Film Viewing:
The films shall be viewed under a high intensity Film Viewer capable of reading
39 Radiographs of Density up to 4 & with adjustable light intensity. Viewing shall be done
under subdued background lighting of an intensity that will not cause troublesome
reflection.
Film Contrast:
Contrast of the film shall be adequate to manifest on the Radiograph even the smallest
40
thickness differential.
Better the contrast; better the visibility of discontinuity during interpretation
Film Sensitivity:
41 The film sensitivity shall be better than 2 % & shall be confirmed by computing or in
accordance with ASME Section V, Article 2, and Table 276 equivalent wire size.
Interpretation:
All indications that are equal to or greater than rejection level described in acceptance /
42 rejection criteria of API 1104 or as agreed by client’s inspector shall be considered
representing defects and may be cause of rejection or repair of the weld or base metal. All
Radiographs showing film marks in the area of interest shall be reshoot in accordance with
Page 90 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
this procedure
Page 91 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
required will be positioned at site.
11 If the location of testing close to other activities, barricade area with rope.
12 Nobody standing behind end of pipe that being tested.
13 Persons on site to be at safe distance from testing areas
14 For hydrostatic testing the test medium shall in general be fresh water.
15 All pressure gauges and pressure recorders to be used for testing shall be calibrated.
The chloride ion content of the water used for pressure testing stainless steel lines shall
16 be less than 150ppm and the line shall be properly drained soon after testing. pH value of
the water shall be between 6.5 and 7.5.
17 Check the thickness of temporary blind, flange or spool piece as per design.
18 The thickness of plate, which will be used for temporary blind, shall be attached on the
test package.
19 All flange connection shall be checked to avoid the loose bolt that it can cause injury.
20 During test, the pressure shall be closely monitored by an engineer as a safety precaution.
Equipment that is not to be subjected to pressure test shall be either disconnected from
21
the piping system or isolated by blanks or similar means of suitable pressure class.
The strings shall be filled in full and ensured that there is no air entrapment. For all bolted
22
fittings spiral wound shall be used.
All equipment that is removed from lines during hydrostatic testing (particularly control
23 valves) must be disconnected by qualified mechanic, technicians and protected with
wooden plugs or plastic caps.
24 All drains, vents, sample point shall be isolated or plugged prior to hydrostatic test.
The test pressure shall be maintained for a sufficient length of time to permit visual
examination to be made of all surfaces, welds and connections, but not less than thirty
minutes. One-hour test duration shall apply for piping systems with pressure rating class
25
600# and above. Care shall be taken to ensure that over pressuring due to static head
does not take place. The piping systems shall not show any sign of plastic deformation or
leakage. Dispose off the water after hydro testing properly.
Duration of Testing:
The test duration mentioned above is a thumb rule but if any statute, standard or
regulation requires other duration same should be followed, confirmation in this regards
to be ensured before planning by Design &
Technical Dept/ Project Dept/O&M dept as required Pressure at which to be Tested:
26 ASME B31.8 specifies the test pressure factors for pipeline operation at hoop stress of
code also limits the maximum hoop stress permitted during tests for various class
locations if the test medium is air or gas. There are different factors associated with
different pipeline class and division locations. During planning of hydro test pressure
should be decided and mentioned in plan.
Pressurizing Method:
27
Pressurization shall be done in the presence of the TPIA/Contractor /TGPL at a moderate
Page 92 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
and cons exceeding 2 bar/min and pressurize up to the final test pressure as per
Specification.
Pressure shall be applied by means of a suitable test pump, which shall not be
connected to a system until ready to test. In bringing the system up to the test
pressure. An authorize operator shall attend to the pump constantly, during the
test. The pressure shall be allowed to stabilize for a period of 15 min after
attainment of test pressure during which pressure shall be established i.e. checked
and test pump shall be disconnected the test section shall be completely isolated
and all connections shall be checked for leakage. The test pressure ‘hold period
‘shall be 4 hours. Test section shall be visually examined for leaks/defects etc.
Pressurize to test pressure i.e. 75 Kg/cm2
During the test, care shall be taken that the hydrostatic test pressure never exceeds
119 Kg/cm2. Water shall be bleed off, if required
Acceptance:
Hydrostatic test shall be considered as positive if no abrupt drop in the pressure is
28 observed through the test du except for a change due to temperature effects as per the
applicable specifications. It should also be observing there is no evidence of sweating
before, during and after the ‘hold period’ on all the weld joints.
De-Pressuring Method:
The line and equipment shall be completely drained by suitable means after completion of
29 hydrostatic test of the system. Vent shall be opened before draining the section.
Subsequently, de-watering operation shall be carried out. Water shall be disposed off at
suitable location.
6. Pneumatic Testing of Steel Pipeline by Air or Nitrogen
Page 93 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
Test procedures must clearly define the points in time during the test when test
personnel are permitted to leave sheltered areas and enter the exclusion zone. Prior to
proving the system at the full pneumatic test pressure, it is suggested that personnel
enter the exclusion zone only when the circumferential stress in the piping is no greater
than 50% of the specified minimum yield strength (SMYS) of the piping materials in the
test system, and only after prescribed holding times at such pressures. As per availability
10 exclusion zone to be decided if possible at least 5 mtr zone must be in place by putting
cordoning and warning signs.
When the system test pressure results in circumferential stresses that exceed 50% SMYS,
test personnel should enter the exclusion zone only after the test system has first been
proven for the prescribed time period at full test pressure. Test personnel should never
enter the exclusion zone when the test pressure exceeds the piping system design
pressure.
Materials must be procured only from manufacturers that have been determined to
11
adhere to suitable, documented quality control and production processes.
12 Materials received must be carefully checked to ensure compliance with material
specifications.
The project must have a suitable positive material identification procedure in place that
13
effectively ensures proper materials in the fabricated piping.
Pressure design calculations for both operating and test pressures must be documented
14
and checked for all piping.
For pneumatic testing, the test media shall be oil free, dry air or any inert gas (N2 -
nitrogen). The use of air for testing shall be limited to a maximum pressure of 7.0 barg.
15
Above this pressure nitrogen shall be used. The extent of pneumatic testing shall be
approved.
The limits of each test system must be clearly defined in test package documentation,
and the methods of isolation (test blinds, etc.) must be well defined. Test blind designs
16
must be checked to ensure suitability for the system test pressures. The proposed design
of test systems must be checked by qualified personnel.
17 All piping shall be adequately supported / anchored before the pressure test.
Unless otherwise noted, all valves are to be through body tested. First block valve for
18
pressure instruments shall be included in the test.
Piping containing check valves shall have the source of test pressure on the upstream
19
side. If this is not possible, the check valve disc shall be removed or jacked open.
Ball valves shall be pressure tested in the half open position. Other valves shall be tested
20
in the fully open position.
Where the test pressure to be applied to the piping is greater than the maximum
21 allowable test pressure for valves, the valves shall be blinded off on the side to be tested,
or removed and replaced by dummy spools.
22 Compressors and vessels shall be blinded off prior to pressure testing.
Page 94 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
A list shall be prepared for sensitive equipment that shall be removed, blocked off or
23 isolated during testing, such as relief valves, inline instruments, compressors and vessels.
This list shall be a part of the test procedure.
24 Formalized check lists must be utilized to document that pre-test preparations have been
completed.
Minimum of one gauge shall be positioned at the highest point and one recorder to be
25
positioned at the lowest point.
Accuracy of pressure gauge shall be at least 1-2% at full scale and 1-2% for the recorder.
26 The test pressure shall be within 60% of the gauge range (20% from top and 20% from
bottom).
If there is a deviation of more than 2% between gauge and recorder during test, the test
27
shall be stopped and the equipment recalibrated.
Pressure gauges and recorders used to indicate and record test pressure shall be dead
28
weight tested for accuracy according to a procedure, dependent of type of equipment.
The use of non-destructive examination (NDE) must be maximized to ensure the quality
29 of all welded joints in the system. Butt welded joints should be 100% ultrasonically or
radio graphically tested.
The intended use of “golden welds” (i.e., welds that are not proven by pressure testing)
30 to join sections of pre-tested piping must be carefully reviewed to ensure guaranteed
quality of the weld joint.
The following are excluded from pressure tests:
All small bore instrument control piping downstream of the first piping block valve.
31
Open drains and vents to atmosphere (leak test only).
Piping joints and welds shall not be insulated or physically covered until satisfactory
completion of testing in accordance with this specification, except for painting of
32
prefabricated welds.
Page 95 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
The pressure shall then be increased in steps of 10% of the specified test pressure, until
7 the specified test pressure is reached. At each step, the pressure shall be kept for 10
minutes minimum to equalize strain.
The specified test pressure shall be kept for one hour. The pressure shall then be reduced
8
to the design pressure before examining for leakage.
9 The piping systems shall not show any sign of plastic deformation or leakage.
The test duration mentioned above is a thumb rule but if any statute, standard or
10 regulation requires other duration same should be followed, confirmation in this regards
to be ensured before planning by Design & Technical Dept.
8. Commissioning of Steel Pipeline With Odorized Gas
Page 96 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
21 Gas percentage & pressure monitoring in charging line is performed constantly.
22 Gas venting to be done in controlled manner at 3 meters height from working level.
23 O&M person should be present at charging site till completion of all the work.
Other safety Precautions to be as per Section 7.8 below, for pre-commissioning,
24
commissioning of gas in to steel pipelines without odorant.
9. Commissioning of Steel Pipeline/DRS with Un-Odorized Gas
Page 97 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
In case of line is pigable following to be ensured for pigging, swabbing, drying and flushing
adequate precautions are taken i.e. launcher, receiver ends are cordoned and un-
authorized entry/exit restricted. The adequate space provided for launching and receiving
of pigs.(If pigging is not envisaged or not possible other safety precautions applicable from
these instructions to be followed).
Swabbing operation:
The swabbing operation shall be done subsequent to dewatering operation for
removal of residual water in the pipeline prior to final drying, inertisation and
9
commissioning of the pipeline system. This is done by driving number of suitably
designed absorbent pigs propelled by oil free compressed dry air. For the purpose
of swabbing, air compressors of required capacity, after-coolers and driers should
be deployed.
Acceptance Criteria : Swabbing operation shall be considered to be complete when
there is no free water left in the pipeline as pig runs & indicated by increase in
weight of less than 10 percent of the original weight (prior to launching) of the last
retrieved pig or when pigs are received in touch dry condition.
GENERAL Procedures shall be established for pre-commissioning and commissioning
activities. These shall consider the characteristics of the gas being conveyed, the need to
isolate the pipeline from other facilities and the transfer of the pipeline for operation. The
procedures and devices shall be such that nothing, that is, incompatible with the gas being
10 conveyed or with the materials in the pipeline components is introduced into the pipeline
system. Pre-commissioning shall be commenced only on completion of all activities
related to the pipeline construction which includes hydrostatic testing, complete
backfilling, installation of field instruments/equipments and suitable Cathodic protection
system.
The commissioning of the pipelines shall essentially consist of the following operations:
Pre-commissioning checks shall be carried out for the pipeline system up to first isolation
valve to ascertain that the pipeline system has been mechanically completed in all
11
respects. These checks-shall cover the main pipeline including distribution network
system, dispatch and receipt stations, intermediate pigging stations, sectionalizing valve
stations and the hook up points.
The pre-commissioning checks shall include the following:
Checking of pipe cover -- Cover-check over pipeline for every 500 m with suitable
instruments (like pipe current measurement, PCM; etc) shall be carried out.
Low Pressure Leak Check for Above Ground Piping: The above the ground piping
sections of the pipeline system shall be checked for leaks at flange points of piping and
12
equipment, instrument impulse tubing points, etc. This shall be done by pressurizing the.
Piping system/equipment with dry compressed air (for this purpose, oil free air
compressors shall be used) and testing by means of soap solution/suitable digital gauge
for leaks. The leak check operation shall be considered to have been completed when the
piping system/ equipment is free of leaks when tested at a pressure of 6.0 kg/cm2 System
Page 98 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
checks:
The entire facilities shall be checked against drawings documents and other design
specifications. Any observation requiring correction/corrective action shall be
recorded and complied with.
Checking of field instrumentals/equipment, the field instruments like actuated valves,
control valves, shut down valves, transmitters, solenoid valves, shut down
switches, alarms etc, shall be checked physically and also for their intended
application. It will also include checking of different meters, gauges, actuated
valves, control valves, shut down valves, etc.
Pipeline survey -- This shall be performed to confirm that proper fittings/supports,
Cathodic protection system, route markers, warning signs, fencing around
sectionalizing valve stations, crash barriers, etc, have been installed along the
pipeline and crossings.
Communication system -- Communication systems shall be checked for adequacy to
ensure uninterrupted communication.
Electrical distribution system -- Electrical instrumentation system shall be checked to
ensure an uninterrupted power supply during start up and normal pipeline
operation. Earth resistance of all earth pits and equipment, towers, lightning
arresters, etc, shall also be carried out. Electrical fixtures shall be checked for their
compliance to the area classification requirements for such purpose.
Checking -of instruments control and interlocks -- This check shall be carried out to
ensure that instrument controls and interlocks are functional as per the normal
operating conditions.
Utilities -- Utilities like power, UPS, water, air, instrument air conditioning, etc,
shall be checked.
Alarm systems -- Setting off alarms and its functioning shall be ensured.
Safety-- Identification of possible emergencies and preparedness for its mitigation
shall be checked.
Any other checks as considered necessary shall also be carried out.
COMMISSIONING (In the subsequent serial numbers i.e. magnetic cleaning, electronic
geometry pigging etc if not applicable for the pipelines the other safety instructions
mentioned in these serial numbers to be followed as applicable) :
General Commissioning of a pipeline shall be considered to be complete when the line has
13
been charged with product natural gas at-the operating pressure and the entire system
has been operated at operating parameters for a minimum period of 72 h with all
instruments, controls and interlocks working at normal operating conditions.
Commissioning shall include magnetic cleaning, drying, inertisation, gas-in, stabilization
Page 99 of 109
Contractor Sign & Stamp
TECHNICAL SPECIFICATION FOR LAYNG, TESTING AND COMMISSIONING OF CGD-
STEEL PIPELINE NETWORK
Document No-TGPL/STEEL/18-19/001/R0-
Version: 1.0 DEC 2018
DEC-2018
and 72 h run.
Magnetic Cleaning (If magnetic cleaning is in scope of work):
In order to ensure that the pipeline is free from metallic debris, the magnetic
cleaning shall be carried out using a train of hi-directional brush magnetic pigs after
the completion of swabbing and tie in. The operation shall be carried out using
14
super dry air. A detailed procedure and the sequence of the operations shall be
prepared before starting the operation.
The magnetic cleaning of the section will be acceptable if the total ferrous debris
collected is less than 50gms/ 1 km in the last pig.
Electronic geometry pig runs (IF Electronic geometry pig runs are planned in scope of
work):
The electronic geometry pig should be capable of recording the entire length of each
segment that is, from the launcher to receiver, in one single run and therefore its
electronic recorder system should have the requisite data storage capacity. The
measurement shall cover the entire (360 degree) of internal pipe wall
circumference using properly oriented and sufficient quantity of sensors. The tool
shall be capable of identifying and locating the following features: individual girth
weld; dent, ovality, buckles or any other out of roundness; change in pipeline
internal diameter and difference of thickness; and valves.
Detailed report of the running of the electronic geometry pig including but not
limited to the operational and functional details;
Detailed description of the type, size and location of individual mechanical defects.
The location and orientation of each defect should be suitably listed with reference
15 to permanent pipeline features, girth weld number, relative and absolute distance;
A detailed report in respect of each defect for which sizing has to be done, indicating
its length, depth and axial location suitably referenced;
Preliminary site report for each pipe segment for each running of magnetic cleaning,
and electronic geometry pig runs, stating the comments/observations of each run,
pig condition, operating parameters, and total time required; and
Velocity plot of the electronic geometry pig along the length of the segment.
The following information/performance shall be expected out of the electronic
geometry pig inspection: Inspection of entire length of each segment to be
completed in one single run; and Tools of a minimum detection level of 2 percent
of internal diameter shall be selected. The accuracy of measurement shall be 1
percent of the internal diameter and 2.5 percent of the measured value. The
location accuracy of the axial measurement shall be 0.1 percent from permanent
features. The tool shall be capable of negotiating a minimum bend of 3 times the
diameter and a 15 percent reduction in internal diameter of the pipe.
Pipeline Drying:
16 The pipeline system including the underground pipelines and the above ground
piping at dispatch and receipt stations, sectionalizing valve station, intermediate
MAHESH GAS
PUNE
MAHARASTRA
DESIGN PRESSURE AND TEMPERATURE: 19 BARg for 150#, 49 BARg for 300#, 98 BAR g for 600# @ -20 to
65 °C
19 BARg for 150#, 49 BARg for 300#, 98 BAR g for 600# @ -29
DESIGN PRESSURE AND TEMPERATURE:
to 65 °C
CLIENT Torrent Gas Pvt. Ltd. PROJECT: CITY GAS DISTRIBUTION PROJECT
SIZE/QUANTITY
DATA SHEET FOR GLOBE VALVES –800# (LOW TEMP.)
Process Fluid NG ANSI Rating 800#
Design Temperature ( -20 to 65 deg C) Design Pressure 98 barg
Design Standard API 6D Piping Class D2
Size, mm (inch) 1/2" to 1- 1/2" -SW (S.B) 2 "-FLG (L.B)
Bore Full Bore
End Connection Type SW / FLG Standard ASME B.16.34/BS 5352
Flanged Finish RF 125 AARH
Locking Device Reqd. *
VALV E DESIGN CONDITIONS
Corrosion Allowance 1.5 mm Design Factor 0.5
Installation Aboveground Stem Ext Length, mm N.A.
Seat Parabolic Disc / Bi-Directional
Gland Type Bolted Bonnet – Non Rotating System
Pattern Straight Through Globe
Valve Operation Hand Wheel
VALVE MATERIAL SPECIFICATION
PART DISCRIPTION MATERIAL
SPECIFIED
Body, Bonnet & Yoke Material A 350 Gr. LF2 (S.B.) / A 352 Gr. LCB (L.B.) * OFFERED
DISC (Plug) A350 Gr. LF2 / A351 Gr. CF8M / SS 410 + STELLITED * (Equivalen
Seat Ring A350 Gr. LF2 / A351 Gr. CF8M / SS 410 + STELLITED * t or
Stem ASTM A276 TP410 / ASTM A479 GR SS316 / (17-4) PH (NO * Higher)
Handle Wheel Carbon Steel CASTING) *
Gasket and Packing Spiral Wound AISI 304, Filling Pure GRAPHITE, Centering Ring CS *
Stud Bolts A320 Gr. L 7 *
Nuts A194 Gr. 4 *
TESTING REQUIREMENT
Hydrostatic Test Pressure As per API 598 or relevant standard
Fire safe test As per API 598 or relevant standard
Air Test Pressure 7 bar or As per API 598 or relevant standard
Anti-Static Testing As per API 598 or relevant standard
Hardness Test Requirement 248 HV 10
Charpy Impact Test/Temperature Yes (at 0 deg C)
Fire Safe Test As per API 6FA
Valve Painting Specification Suitable for Corrosive Industrial Environment
Manufacturer's Painting Specification Number *
Notes
1.This Data Sheet Shall be read in conjunction with the Technical Specification, which are enclosed along with this requisition.
* To be filled by Vendor.
Valve
CLIENT Torrent Gas Pvt. Ltd.
PROJECT: CITY GAS DISTRIBUTION PROJECT
SIZE/QUANTITY
DATA SHEET FOR BALL VALVES – 150#, 300#, 600# (LOW TEMP.)
Process Fluid NG ANSI Rating 150#, 300 #, 600#
Design Temperature ( -20 to 65 deg C) Design Pressure 19 barg, 49 barg, 99 barg
Design Standard API 6D Piping Class A2, B2, D2
Size, mm (inch) 1/2" to 1- 1/2" (S.B) 2 " (L.B)
Body Construction Floating type Ball Trunion mounted Ball
Double Block & Bleed *
Bore & Construction Full Bore, bolted Construction
End Connection Type B.W./ FLG Standard ASME B16.25/ B 16.5
Pup piece length/Flng Finish 300mm (for 2") / RF 125 AARH Vent, drain &
Special Requirement
Locking Device Reqd. * Sealant
VALV E DESIGN CONDITIONS connection
Corrosion Allowance 1.5 mm Design Factor 0.5 Anti-Blow out
Installation Aboveground Stem Ext Length, mm N.A. system
Opening/Closing time *
VALVE MATERIAL SPECIFICATION
PART DISCRIPTION MATERIAL
Body SPECIFIED
A 350 Gr. LF2(S.B. ) / A 352 Gr. LCB (L.B. ) * OFFERED
Ball A350 Gr. LF2 + 75 micrometer (0.003") ENP/ A351 Gr. CF8M * (Equivalent or
Seat Rings A 350 Gr. LF2 + 0.075 mm ENP * Higher)
Seat Seal VITON A ED O-RING *
Stem AISI 4140 + 75 micrometer (0.003") ENP/ AISI 410 *
Stem Seal PTFE / VITON *
Stud Bolts A320 Gr. L 7 *
Nuts A194 Gr. 4 *
TESTING REQUIREMENT
Hydrostatic Test Pressure As per relevant ASME Standard
Air Test Pressure 7 bar
Anti-Static Testing Requirement As per API 6D Latest Edition
Hardness Test 248 HV 10
Charpy Impact Yes (at 0 deg C)
Fire Safe Test Test/Temperature As per API 6FA
Valve Painting Specification Suitable for Corrosive Industrial Environment
Manufacturer's Painting Specification Number *
Notes
1.This Data Sheet Shall be read in conjunction with the Technical Specification, which are enclosed along with this requisition.
2. Valve shall be joined with a pup piece integrally welded (in controlled factory conditions only) to the valve whose provide
strength shall be equivalent to attached pipe specification.
* To be filled by Vendor.
TECHNICAL SPECIFICATIONS
a. Pipes - All sizes (except 4”,8”, 12” and 16” pipes) and schedule
g. Specialty items like online filters, ejectors, sample coolers, steam traps,
strainers, air traps etc.
h. Online instruments like control valve, orifice flange, rotameter, safety
valves etc.
2.3 Shop & field fabrication and erection of piping in accordance with documents
listed under ‘BASIS OF WORK’ including erection of all piping materials
enumerated above.
2.4 Fabrication and erection of pipe supports like shoe, saddle, guide, stops,
anchors, clips, cradles, hangers, turn buckles, supporting fixtures, bracket
cantilevers, struts, tee-posts including erection of spring supports and sway
braces.
2.5 Guidelines
2.5.1 Fabrication of piping specials like special radius bends, reducers, etc.
2.5.2 Fabrication of plain and threaded nipples from pipes as required during erection.
2.5.3 Fabrication of swage nipples as and when required
2.5.4 Fabrication of odd angle elbow like 60º, 30° or any other angle from 90/45°
elbows as and when required.
2.5.5 Fabrication of flange, reducing flange, blind flange, spectacle blinds as and when
required.
2.5.6 Fabrication of stub-in connection with or without reinforcement as and when
required.
2.5.7 Grinding of edges of pipes, fittings, flanges etc. to match mating edges of
uneven/different thickness wherever required.
2.6 Modifications like providing additional cleats, extension of stem of valve, locking
arrangement of valves etc. as and when required.
2.7 Preparation of Isometrics, bill of materials, supporting details within the unit
battery limit and get subsequent approval from Engineer-in-Charge before
starting of job, as and when called for.
d. Line list
e. Piping support indices (only in offsite), if supports are not shown in plan.
Note: All codes referred shall be latest edition, at the time of award of
contract.
3.3 Deviations
Where a deviation from the “Basis of Work and approved job procedure
described above is required or where the basis of work does not cover a
particular situation, the matter shall be brought to the notice of Engineer - in -
Charge and the work carried out only after obtaining written approval from him
in each case.
4.0 FABRICATION
Pipe, pipe fittings, flanges, valves, gaskets, studs bolts etc. used in a given piping
system shall be strictly as per the “Piping Material Specification” for the “Pipe
Class” specified for that system. To ensure the above requirement, all piping
material supplied by the Owner/Contractor shall have proper identification
marks as per relevant standards/specifications/Licensors specification.
Contractor shall provide identification marks on left over pipe lengths wherever
marked up pipe lengths have been fabricated/ erected. Material traceability is to
be maintained for C.S., S.S., LTCS, material, i.e. hard punching or other method as
per approved procedure. This shall be in addition to colour coding for all piping
materials to avoid mix-up. For the purpose of common understanding the
construction job procedure, to be submitted by the contractor, shall include
proposal for - Maximizing prefabrication, inspection and testing at fabrication
shop with minimum field joints.
The piping class of each line specifies the type of pipe joints to be adopted. In
general, joining of lines 2” and above in process and utility piping shall be
accomplished by butt welds. Joining of lines 1-1/2” and below shall be by socket
welding/butt welding/threaded joints as specified in “Piping Material
Specifications”. However, in piping 1-1/2” and below where socket
welding/threaded joints are specified butt - welds may be used with the approval
of Engineer-in-Charge for pipe to pipe joining in long runs of piping. This is only
applicable for non-galvanized piping without lining.
In general, Galvanized piping shall have threads as per IS: 554 or ANSI B2.1 NPT
as required to match threads on fittings, valves etc. All other piping shall have
threads as per ANSI B2.1, tapered unless specified otherwise.
Threads shall be clean cut, without any burrs or stripping and the ends shall be
reamed. Threading of pipes shall be done preferably after bending, forging or
heat treating operations. If this is not possible, threads shall be gauge checked
and chased after welding heat treatment etc.
All flange facings shall be true and perpendicular to the axis of pipe to which they
are attached. Flanged holes shall straddle the normal centrelines unless different
orientation is shown in the drawing.
Wherever a spectacle blind is to be provided, drilling and tapping for the jack
screws in the flange, shall be done before welding it to the pipe.
Forging and forming of small bore fittings, like reducing nipples for piping 1-1/2”
and below, shall be as per ASME B 31.3.
Before erection all pre-fabricated spool pieces, pipes, fittings etc. shall be
cleaned inside and outside by suitable means. The cleaning process shall include
removal of all foreign matter such as scale, sand, weld spatter chips etc. by wire
brushes, cleaning tools etc. and blowing with compressed air/or flushing out with
water. Special cleaning requirements for some services, if any shall be as
specified in the piping material specification or isometric or line list. S.S jacketed
piping requiring pickling shall be pickled to remove oxidation and discolouring
due to welding.
High point vents and low point drains shall be provided as per the instructions of
Engineer- in-Charge, even if these are not shown in the drawings. The details of
vents and drains shall be as per piping material specifications / job standards.
5.4 Valves
5.5 Instruments
Installation of line mounted items like filters, Regulators, valves, terminal piping
and ancillaries etc. including their supporting arrangements shall form part of
piping erection work.
The Contractor shall apply molycoat grease mixed with graphite powder (unless
otherwise specified in piping classes) all Studs, bolts and nuts during storage,
after erection and wherever flange connections are broken and made-up for any
purpose whatsoever. The grease and graphite powder shall be supplied by the
Contractor within the rates for piping work.
Pipe supports are designed for and located to effectively sustain the weight and
thermal effects of the piping system and to prevent its vibrations. No pipe
shoe/cradle shall be offset.
Page 11 of 11 CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATIONS
FOR FLANGES TGPL-TS-STEEL-PTS-005
TECHNICAL SPECIFICATIONS
FOR FLANGES
TABLE OF CONTENTS
1. SCOPE .................................................................................................................................... 3
2. REFERENCE DOCUMENTS ....................................................................................................... 3
3. MANUFACTURER’S QUALIFICATION........................................................................................ 4
4. MATERIALS............................................................................................................................. 4
5. DESIGN AND MANUFACTURE ................................................................................................. 4
6. INSPECTION AND TESTS .......................................................................................................... 5
7. Hydrotest ............................................................................................................................... 5
8. TEST CERTIFICATES ................................................................................................................. 6
9. MARKING ............................................................................................................................... 6
10. DOCUMENTATION.................................................................................................................. 6
11. PACKING, SHIPPING & HANDLING........................................................................................... 6
1. SCOPE
This specification covers the minimum requirements for the design, manufacture
and supply of following carbon steel flanges of size to be installed in pipeline
systems handling Natural Gas.
- Flanges such as weld neck flanges, blind flanges, spectacle blinds, spacers and
blinds, etc.
2. REFERENCE DOCUMENTS
Reference has been made in this specification to the latest edition of the
following codes, standards and specifications:
ASME B3 1.3 - Process Piping
ASME B3 1.4 - Pipeline Transportation System for Liquid Hydrocarbons and
Other Liquids
ASME B3 1.8 - Gas Transmission and Distribution Piping Systems
ASME B 16.5 - Pipe Flanges and Flanged Fittings
ASME B 16.9 - Factory Made Wrought Steel Butt Welding Fittings (1/2” to 24”)
ASME B 16.25 - Butt-welding Ends
ASME B16.47 - Large Diameter Steel Flanges (26” to 60”)
ASME B 16.48 - Steel Line Blanks
ASME Sec VIll/IX - Boiler and Pressure Vessel Code
ASTM A 370 - Standard Test Methods and Definitions for Mechanical Testing of
Steel Products.
MSS-SP-25 - Standard Marking System for Valves, Fittings, Flanges and Unions
MSS-SP-75 - Specification for High Test Wrought Welded Fittings.
MSS-SP-97 - Forged Carbon Steel Branch Outlet Fittings- Socket Welding,
Threaded and Butt Welding Ends. In case of conflict between various
requirements of this specification and reference standard mentioned above, the
more stringent requirement shall apply.
3. MANUFACTURER’S QUALIFICATION
Manufacturer of flanges must possess the records of a successful proof test, in
accordance with the provisions of ASME B 16.9/ MSSSP- 75, as applicable. These
records shall be submitted for approval.
4. MATERIALS
4.1 The basic material for flanges shall meet the requirements specified hereinafter.
4.2 The Carbon steel used for the manufacture of Flanges shall be fully killed.
4.3 Each heat of steel used for the manufacture of flanges shall have carbon
equivalent (CE) not greater than 0.45 % calculated from check analysis in
accordance with following formula:
CE = C + Mn + Cr + Mo + V + Ni+Cu
6 5 15
Carbon contents on check analysis shall not exceed 0.22%.
4.4 Unless specified otherwise, Charpy V-notch test shall be conducted for each heat
of steel, in accordance with the impact test provision of ASTM A370 at 0°C. The
average absorbed impact energy values of three full- sized specimens shall be 32
joules.
The minimum impact energy value of any one specimen of the three specimens
analysed as above, shall not be less than 80% of the above- mentioned average
value.
When Low Temperature Carbon Steel (LTCS) materials are specified in, the
Charpy V-notch test requirements of applicable material standard shall be
complied with.
4.5 For flanges specified to be used for Natural Gas service, hardness test shall be
carried out in accordance with ASTM A 370. Hardness testing shall cover at least
10% per item, per size, per heat, per manufacturing method. A full thickness
cross section shall be taken for this purpose and the maximum hardness shall not
exceed 248 HV10.
5. DESIGN AND MANUFACTURE
5.1 Flanges such as weld neck flanges and blind flanges shall conform to the
requirements of ASME B16.5 up to sizes DN 300 mm (12”).
5.2 Type, face and face finish of flanges shall be as specified in Purchase Requisition.
5.3 Flanges manufactured from bar stock are not acceptable.
5.4 Repair by welding on flanges and parent metal of fittings is not permitted.
6. INSPECTION AND TESTS
6.1 The Manufacturer shall perform all inspection and tests as per the requirement
of this specification and the relevant codes, prior to shipment at his works. Such
inspection and tests shall be, but not limited to, the following:
6.1.1 All flanges shall be visually inspected. The internal and external surfaces of the
fittings shall be free from any earth strikes, gauges and other detrimental
defects.
6.1.2 Dimensional checks shall be carried out on finished products as per ASME
B16.5/MSS-SP - 44/ASME B16.47 as applicable for flanges, ASME B 16.48 for
spacers and blinds and ASME B16.9/MSS-SP-75/MSS-SP-97 as applicable for
fittings and as per this specification.
6.1.3 Chemical composition and mechanical properties shall be checked as per
relevant material standards and this specification, for each heat of steel used.
6.2 Purchaser’s Inspector reserves the right to perform stage wise inspection and
witness tests at Manufacturer’s Works prior to shipment.
Manufacturer shall give reasonable notice of time and shall provide, without
charge, reasonable access and facilities required for inspection, to the
Purchaser’s Inspector.
Inspection and tests performed/witnessed by Purchaser’s Inspector shall in no
way relieve the Manufacturer’s obligation to perform the required inspection
and tests.
7. Hydrotest
All fitting under this specification shall be designed to withstand a field
hydrostatic test pressure with non-corrosive water, after installation , during 24
hours at a following pressure level:
The pressure level will however not exceed MOP 1.5 times the 38Degree C
pressure rating of flanges.
8. TEST CERTIFICATES
Manufacturer shall submit following certificates to Purchaser’s Inspector:
a) Test certificates relevant to the chemical analysis and mechanical
properties of the materials used for construction as per this specification and
relevant standards.
b) Test Reports on radiography, ultrasonic inspection and magnetic
particle examination.
c) Test reports of heat treatment carried out as per the specification.
d) EN 10204 3.1 Certificate stating the quality of relevant Flanges.
9. MARKING
All Flanges shall be marked with:
• PO Number
• Item/ Material Code
• Material Class rating
10. DOCUMENTATION
10.1 Prior to shipment, the Manufacturer shall submit six copies of the test
certificates as listed above.
10.2 All documents shall be in English Language only.
11. PACKING, SHIPPING & HANDLING
After all inspection and tests required have been carried out; all external
surfaces shall be thoroughly cleaned to remove grease, dust and rust and shall
be applied with standard mill paints.
TECHNICAL SPECIFICATIONS
TABLE OF CONTENTS
1.0 SCOPE
This specification covers the general requirements for inspection, flushing and
testing of piping systems. Flushing and testing of all piping systems shall be
witnessed by the Engineer-In-Charge.
2.0 DEFINITIONS
Should: This verbal form indicates that among several possibilities one is
particularly suitable without mentioning or excluding others or that a certain
course of action is preferred but not necessarily required.
May: This verbal form indicates a course of action permissible within the limits of
this standard.
Can: This verbal form used for statements of possibility & capability, whether
material, physical or casual.
ABBREVIATIONS:
During various stages and after completion of fabrication and erection, the
piping system shall be inspected by the Engineer-In-Charge to ensure that:
Flushing shall be done by fresh potable water or dry compressed air, wherever
water flushing is not desirable, to clean the pipe of all dirt, debris or loose foreign
material Required pressure for water flushing shall meet the fire hydrant
pressure or utility water pressure.
For air flushing, the line / system will be pressurized by compressed air at the
required pressure which shall be 50 PSI maximum. The pressure shall then be
released by quick opening of a valve, already in line or installed temporarily for
this purpose. This procedure shall be repeated as many times as required till the
inside of the pipe is fully cleaned.
In line instruments like control valves, orifice plates, Rotary meters, safety valves
and other instruments like thermo-wells which may interfere with flushing shall
not be included in flushing circuit.
The screens / meshes shall be removed from all permanent strainers before
flushing. Screens/meshes shall be reinstalled after flushing but before testing
During flushing discharged water/air shall be drained to the place directed by the
Engineer-In-Charge. If Necessary, proper temporary drainage shall be provided
by the contractor.
The contractor shall carry out all the activities required before, during and after
the flushing operation, arising because of flushing requirements, such as but not
limited to the following
Dropping of valves, specials, distance pieces, inline instruments and any other
piping part before flushing. The flanges to be disengaged for this purpose shall
be envisaged by the contractor and approved by the Engineer-In-Charge. These
flanges shall be provided with temporary gaskets at the time of flushing.
After flushing is completed and approved, the valve distance pieces, piping
specials etc. shall be reinstalled by the contractor with permanent gaskets.
However, flanges at equipment nozzles and other places where isolation is
required during testing, only temporary gaskets shall be provided.
Records in triplicate shall be prepared and submitted by the contractor for each
piping system for the flushing done in the Performa provided/approved by the
Engineer-in-Charge.
5.0 TESTING
To facilitate the testing of piping systems, valves and other equipment may be
included in the system with the prior approval of Engineer-In-Charge if the test
pressure specified is equal to or less than that for the valves and other
equipment.
Lines which are directly open to atmosphere such as vents, drains, safety valves
discharge need not be tested, but all joints shall be visually inspected. Wherever
necessary, such lines shall be tested by continuous flow of fluid to eliminate the
possibility of blockade. However, such lines if provided with block valve shall be
pressure tested up to the first block valve.
Seats of all valves shall not be subjected to a pressure in excess of the maximum
cold working pressure of the valve. Test pressure applied to valves shall not be
greater than the manufacturer’s recommendation nor less than that required by
the applicable code. Where allowable seat pressure is less than test pressure,
test shall be made through an open valve.
Restrictions which interfere with filling, venting and draining such as orifice
plates etc. shall not be installed unless testing is complete.
Page 5 of 9 CONTRACTOR Sign & Stamp
INSPECTION, FLUSHING AND TGPL-TS-STEEL-PTS-008
TESTING OF PIPING SYSTEMS
Control valves shall not be included in the test system. Where bypasses are
provided test shall be performed through the bypass and necessary spool shall
be used in place of the control valve.
Pressure gauges which are part of the finished system, but cannot withstand test
pressure shall not be installed until the system has been tested. Where piping
systems to be tested are directly connected at the battery limits to piping for
which the responsibility rests with other agencies, the piping to be tested shall
be isolated from such piping by physical disconnection such as valve or blinds.
Testing shall be carried out with permanent gaskets installed unless specified
otherwise or instructed by the Engineer-in-Charge.
No pressure test shall be carried out against closed valve unless approved by the
Engineer-in-Charge. The Engineer-in-Charge shall be notified in advance by the
Contractor, of the testing sequence and program, to enable him to be present
for witnessing the test.
Before testing, all piping shall be cleaned by flushing to make it free from dirt,
loose scale, debris and other loose foreign materials by a method approved by
Owner.
All piping systems to be hydrostatically tested shall be vented at the high points
and the systems purged of air before the test pressure is applied.
Wherever in the line any void exists due to any reasons, like absence of control
valves, safety valves, check valves etc. it shall be filled with temporary spools.
All joints welded, screwed or flanged shall be left exposed for examination during
the test. Before pressuring the lines, each weld joint shall be cleaned by wire
brush to free it from rust and any other foreign matter.
For lines containing check valves any of the following alternatives shall be
adopted for pressure testing: Whenever possible pressurize up-stream side of
valve. Replace the valve by a temporary spool and reinstall the valve after
testing.
Provide blind on valve flanges and test the upstream and downstream of the line
separately and remove the blind after testing. At these flanges, temporary
gaskets shall be provided during testing and shall be replaced by permanent
gaskets subsequently.
When testing any piping system, air or steam of approximately 2 kg/cm 2 may be
used as preliminary test to detect missing gaskets etc. as this avoids the
necessity of draining the line to make repairs.
In general, all pressure tests shall be hydrostatic using sulphur free water, which
is clean and free of silt. Water shall be tested in approved laboratory and
approval shall be taken from Owner before water filling.
The selection of the piping system for one individual test shall be based on the
following:
All gauges used for field testing shall have suitable range so that the test
pressure of the various systems falls in 40% to 80% of gauge scale range. Gauge
shall be of a good quality and in good working condition.
Prior to the start of any test or periodically during the field test program, all test
gauges shall be calibrated using a standard dead weight gauge tester or other
suitable approved testing apparatus. Any gauge showing an incorrect zero
reading or error of more than ± 2% of full scale range shall be discarded. The
Engineer-In-Charge shall check the accuracy of master pressure gauge used for
calibration.
5.4 Testing Procedure
5.4.1 Hydrostatic Test
All vents and other connections used as vents shall be left open while filling the
line with test fluid for complete removal of air. In all lines for pressurizing and
depressurizing the system, temporary isolating valves shall be provided if valves
vents, drains do not exist in the system.
Pressure shall be applied only after the system / line is ready and approved by
the Engineer-in- charge. Pressure shall be applied by means of a suitable test
pump or other pressure source which shall be isolated from the system as soon
as test pressure is reached and stabilized in the system.
The pump shall be attended constantly during the test by an authorized person.
The pump shall be isolated from the system whenever the pump is to be left
unattended.
The pump and the piping system to be tested are to be provided with separate
pressure indicating test gauges. These gauges are to be checked by the standard
test gauge before each pressure test. Care shall be taken to avoid increase in the
pressure due to temperature variation during the test.
When testing with air, pressure shall be supplied by means of a compressor. The
compressor shall be portable type with a receiver, after cooler and oil separator.
Piping to be tested by air shall have joints covered with a soap and water
solution so that the joints can be examined for leaks.
All other details shall be same as per hydro testing procedure (specified above)
After the hydrostatic test has been completed, pressure shall be released in a
manner and at a rate so as not to endanger personnel or damage equipment.
All vents and drains shall be opened before the system is to be drained and shall
remain open till all draining is complete, so as to prevent formation of vacuum in
the system. After draining, lines / systems shall be dried by air.
Pressure test shall be considered complete only after approved by the Engineer-
in-Charge. Defects, if any, noticed during testing shall be rectified immediately
and retesting of the system / line shall be done by the contractor at his cost.
Records in triplicate shall be prepared and submitted by the contractor for each
piping system, for the pressure test done in the Performa provided/approved by
the Engineer-in-Charge. Records shall also be submitted for the PMI.
TECHNICAL SPECIFICATIONS
PAINTING
TABLE OF CONTENTS
1. GENERAL ...................................................................................................................................... 3
2. 2.0 CODES & STANDARDS .................................................................................................... 4
3. 3.0 CONDITIONS OF DELIVERY .................................................................................................... 5
4. 4.0 IDENTIFICATION..................................................................................................................... 5
5. 5.0 SURFACE PREPARATION STANDARDS ................................................................................... 5
6. PREPARATION OF THE SURFACES................................................................................................ 6
7. CARRYING OUT THE PAINTWORK................................................................................................ 9
Conditions for carrying out paintwork .................................................................................................... 9
1. GENERAL
1.1 These technical specifications shall be applicable for the work covered by the
contract, and without prejudice to the provisions of various codes of practice,
standard specifications etc. It is understood that contractor shall carry out the
work in all respects with the best quality of materials and workmanship and in
accordance with the best engineering practice and instructions of Engineer-In-
Charge.
1.2 SCOPE
1.2.1 Scope of work covered in the specification shall include, without being limited to
the following.
1.2.2 This specification defines the requirements for surface preparation, selection and
application of primers and paints on external surfaces of piping, structures,
Valves etc. The items listed in the heading of tables of paint systems is indicative
only, however, the contractor is fully responsible for carrying out all the
necessary painting, coating and lining on external and internal surfaces as per
the tender requirement.
1.2.3.1 The following surfaces and materials shall require shop, pre-erection and field
painting:
a. All carbon and low alloy piping, fittings and valves (including painting of
identification marks).
b. All items contained in a package unit as necessary.
c. All structural steel work, pipe, structural steel supports, walkways,
handrails, ladders, platforms etc.
1.2.4 Unless otherwise instructed, final painting on pre-erection/ shop primed pipes
and equipment shall be painted in the field, only after the mechanical
completion, testing on systems are completed as well as after completion of
steam purging wherever required.
1.2.5 Changes and deviations required for any specific job due to client’s requirement
or otherwise shall be referred to for deviation permit.
2. CODES & STANDARDS
Without prejudice to the specifications of the contract, the following codes and
standards shall be followed for the work covered by this contract.
IS: 101 Methods of test for ready mixed paints and enamels,
IS: 2074 Specifications for ready mixed paint, red oxide zinc chrome priming.
3. CONDITIONS OF DELIVERY
Packaging
Every recipient will be fitted with a hermetically-sealed lid with an opening that is
sufficiently large to allow the contents to be stirred: the outside and inside are
protected against oxidation, and, the lid, are marked with a strip of colour
identical to the contents.
4. IDENTIFICATION
At the time of delivery, this packaging must bear labels in conformity with the
legal stipulations in force.
The removal of paint and cleaning of the stains from the floor.
5. SURFACE PREPARATION STANDARDS
a) The contractor shall arrange, at his own cost to keep a set of latest
edition of above standards and codes at site.
The Contractor should have the required material at his disposal to clean the
surfaces to be coated thoroughly in accordance with the preparation methods
regardless of the form or the condition of such surfaces. The cleaning devices
that might be damaged during the surface preparation shall be screened off by
the Contractor.
6.2 Sandblasting
Before beginning cleaning by blasting, the person carrying out the work will take
the following measures:
To prevent rust forming quickly as the result of humidity on the blasted surface,
cleaning by blasting may only be carried out when the temperature of the steel
surface is higher than the dew-point of the ambient air.
Blasting may not be carried out if the relative degree of humidity exceeds 80%.
The choice of the type of blasting medium used depends on local circumstances
such as the possible presence of gas and the material to be blasted.
The abrasive to be used must conform to the local low i.e. it may contain no
carbon and less than 1% free silicon dioxide. Profile surface must at least reach
Sa 2½ during the initial stage of the paintwork. The degree of cleanliness to be
obtained will be inspected in accordance with the Swedish standard SVENSK
STANDARD ISO 8501-1-1988/SS 055900.
Sa 2 1/2: blasted very carefully. Scale, rust and foreign bodies must be removed
in such a way that anything left behind will only be visible as nuances (shading)
or strips.
The blast-cleaning will be carried out by means of compressed air free of water
and oil.
After the blasting and before painting, the surface should be completely cleaned
of blasting material and so forth with a soft brush, a dry cloth or dry compressed
air.
If sandblasting is not permitted or if the metal structures are not easily accessible
for blasting or blasting for one reason or another is technically unfeasible,
mechanical de-rusting can be used instead. With mechanical cleaning by means
of chipping, rotating steel brushes and sanding discs, a degree of cleanliness SA.
3 should be reached.
St 3: removal of the old paint layers of which the adhesion leaves something to
be desired and/or of which the paint layer no longer fulfils the requirements.
If parts are present that are so corroded that St 3 is difficult to achieve, this
should be notified to the OWNER representative prior to the start of the works.
N.B:
St. 3: means removal of every old paint layer. Retouching means local polishing
with St. 3 or Sa 3 followed by application of the desired painting system.
After mechanical cleaning, the surface should be made dust-flee with a cloth or a
so brush, washed with an organic solvent and thoroughly dried off with a dry
cloth (e.g. with 1.1.1. Trichoroethane such as Solvethane, Chloroethene).
Manual de-rusting with the aid of scrapers. steel brushes, sandpaper etc. shall
only be permitted in exceptional cases for local repairs. Any deviation there from
must be requested from the OWNER/ OWNER 's Representative.
Remove unsound paint layers and loose components with scrapers, blades or
rotating steel brushes. Thoroughly clean the entire surface with water containing
ammonia. Thoroughly remove moss, algae and fungal growths. Where these
growths have been removed, treat the area with a fungicide in accordance with
the instructions for use.
Once the entire area is completely dry, brush off the dead residue of moss, algae
and fungus with a hard brush. In the case of reinforcement steel that has been
laid bare, remove as rust, dust and grease as possible and treat with a printer
coat. When painting concrete surfaces, they must first be checked for cracks.
Page 8 of 15 CONTRACTOR Sign & Stamp
PAINTING TGPL-TS-STEEL-PTS-010
The Contractor must have the equipment necessary for the removal of asphalt
from the pipe without damaging the latter (scratching, impact, etc.). The
Contractor undertakes to carry out the work in accordance with an approved
procedure.
All preparatory work and painting may only he carried out in dry weather and at
a minimum temperature of 10° C, except for special eases requested by the
OWNER's Representative.
Coats that have not yet dried and have been exposed to frost, mist, snow or rain
and might thereby be damaged must be removed after drying and the surfaces
must be repainted at the expense of the Contractor.
The first coat of paint must be applied maximum 3 hours after the preparation of
the surface of the relative humidity of the air is between 50% and 80%. This time
span may be increased to 6 hours if the relative humidity is less than 50%. In all
cases, the preparation of the surface must exhibit degree Sa 3 and at the very
least the appearance of degree Sa 2 ½ at the time of painting.
The coats of paint may only be applied on carefully cleaned surfaces that must be
dry and free of grease and dust.
Special conditions
Painting may be carried out when the Contractor can be sure that the
instructions of the paint supplier have been scrupulously followed with regard to
the parameters in the following (non-exhaustive) list:
Ambient temperature.
Surface temperature.
Relative humidity.
Dew point.
Drying times.
The Contractor must in this respect be able to produce the instructions for the
paint on the site. The
Paint Materials
d. After 3 hrs. DFT shall be checked and it should be within 75-100 microns.
Top Coat (Polyurethane):
a. Top coat shall be applied only after drying of Intermediate coat.
b. Top coat (Polyurethane) shall be applied on surface area using air less spray
gun.
c. Mixing ration shall be 4:1 (Base: Accelerator)
d. Hand brush / roller shall be used for small areas.
e. After 3 hrs. DFT shall be checked and it should be 30-40 microns.
MANUFACTURERS
The paints shall conform to the specifications given above and Class-I quality in
their products range of any of the-following manufacturers:
STORAGE
All paints and painting material shall be stored only in rooms to be provided by
contractor and approved by OWNER/ OWNER’s Representative for the purpose.
All necessary precautions shall be taken to prevent fire.
A signboard bearing the words given below shall be clearly displayed outside:
PAINT STORAGE No NAKED LIGHT highly -inflammable
COLOR CODE:
Page 11 of 15 CONTRACTOR Sign & Stamp
PAINTING TGPL-TS-STEEL-PTS-010
PRIMER APPLICATION:
Dry film thickness of each coat, surface profile gauge for checking of surface
profile in case of sand blasting. Holiday detectors and pinhole detector and
protector whenever required for checking in case of immerse conditions.
PAINT SYSTEMS:
The paint system should vary, with type of environment envisaged in and around
the plants. The types of environment are considered for selection of paint
system.
Primers and finish coats for any particular paint systems shall be from same
manufacturer in order to ensure compatibility.
Table – 1
Colour Coding Scheme for Pipes and Equipment
SI. No. Content Ground Colour First Colour Band Second Colour
Band
1 COMPRESSED AIR
a) Plant Air Sky Blue Silver Grey -
b) Instrument Air Sky Blue French Blue -
2 GASES
a) Charge Gas Golden Yellow Signal Red Smoke Grey
Precautions to be taken
Neither the environment of the site nor the marking labels of devices may be
covered with paint and they must be kept free of paint splashes. To this end, it is
advisable to use removable masking tape.
Otherwise, the OWNER will be obliged to have the cleaning carried out at the
expense of the Contractor. The paint recipient will only be opened at the time of
use (unless otherwise specified by the manufacturer).
Method of application
Normally, three methods of application will be used on the construction site for
the paint products. i.e. with a brush, with a roller or with a spray gun.
The Contractor must guarantee that all safety measures have been taken for
such work. The spray gun method may only he used on site for places that are
difficult to reach with the brush. In this case, a request must be made to the
OWNER/ OWNER's Representative for a deviation.
All paintwork will be carried out with good brushes or rollers that are suitable for
the type of paint being used and for the form of the material to be painted and
fitted with short handles.
Application of the paint will be carried out in accordance with best practice in
order to obtain a homogeneous and continuous layer. The OWNER or the TPIA
may demand that painting of a layer will only be started after acceptance by
them of the surface preparation or of the previous layer of paint.
The layers of paint must have a uniform thickness. They must he spread in such a
way that all concave parts are dried out and that the surface is completely
covered and has a glossy appearance without leaving brush marks and without
exhibiting bubbles, foam, wrinkles, drips, craters, skins or gums that arise from
weathered paint,
Each layer must have the colour stipulated in the tables of the present
specifications, which clearly differs from the previous layer, taking account of the
Colour of the top layer, all of which for the purpose of being able to identify the
number of coats and their order of sequence
The dry coating thickness indicated in the description of the paint systems are
minimum thickness. In this connection, the Contractor is obliged to contact the
paint manufacturer and conform to his guidelines. The Contractor must respect
the thickness specified by the supplier.
The Contractor should have the required calibrated monitoring apparatus for this
purpose on site (with calibration certificates). The personnel who will have to use
this apparatus should have the training for this purpose.
The OWNER or his representative and possibly the approved supervisory body
indicated by the OWNER will maintain supervision during the works and inspect
the works with random checks. A daily report will be drawn up in relation to the
department that maintains supervision of these works.
TECHNICAL SPECIFICATIONS
TABLE OF CONTENTS
1. GENERAL ................................................................................................................................ 3
2. MARKING AND DISPATCH ....................................................................................................... 4
1. GENERAL
Chemical composition, physical properties, tests, dimensions and tolerances,
heat treatment and marking shall conform to the applicable latest
codes/standards/specifications. Any deviation shall be highlighted on a separate
sheet by the vendor in the quotation itself.
Test reports shall be supplied for all mandatory tests as per the material
specifications. Test reports shall also be furnished for any supplementary tests as
when required will be informed. Material test certificates (physical properties,
chemical composition & heat treatment report) shall also be furnished for
fittings supplied.
All fittings shall be seamless in construction unless otherwise specified. Seamless
fittings shall be with no negative tolerance on wall thickness. Welded fittings
shall not be acceptable.
Outside diameters and wall thickness (unless otherwise mentioned) of butt
welded fittings shall be in accordance with ASME B36.10 and ASME B36.19 as
applicable.
For reducing butt weld fittings having different wall thicknesses at each end, the
greater wall thickness of the fitting shall be employed and inside bore at each
end shall be matched with the specified inside diameter.
Bevelled ends for all fittings shall conform to ASME B16.25.
Fittings under “NACE” category shall meet the requirements of MR-01-75.
Thickness/schedule lower than specified shall not be accepted.
The gasket contact surfaces of stub ends shall be flat with face finish as specified
below:
• Serrated Finish Serrations with 250 to 500µ in AARH
• Smooth Finish: Serrations with 125 to 250 µ in AARH
Seamless stub ends shall not have any welds on the body.
Threaded ends shall have NPT taper threads in accordance with ASME/ANSI.
All socket welded and screwed fittings shall be in accordance with ASME B16. 11
to the extent covered in the specification except for unions which shall be in
accordance with MSS-SP-83.
Page 3 of 5 CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATIONS BUTT
WELDED, SOCKET WELDED AND TGPL-TS-STEEL-PTS-003
SCREWED FITTINGS
Special fittings like weld-o-let, sock-o-let, sweep-o-let etc. which are not covered
in ASME, MSS-SP & Standards shall be as per manufacturer’s std. Contours of
these fittings shall meet the requirements of ASME B31.3. Manufacturer shall
submit drawings / catalogues of these items along with the offer.
Length of all long half couplings shall be 100 mm unless otherwise specified.
All seamless fittings shall be required to have undergone hydro test at a test
pressure of 90% SMYS of the material.
The bevel ends of all butt weld fittings shall undergo 100% MP/DP test.
Swage nipples (concentric/eccentric) if specified as pipe materials are acceptable
in forging materials (up to 1½”) and wrought fitting materials (above 1½”) also in
the corresponding material grades.
Abbreviations for ends of swages and nipples shall be as follows:
PBE : Plain Both Ends
TBE : Threaded Both Ends
2. MARKING AND DISPATCH
Each fitting shall be legibly and conspicuously stamped in accordance with the
requirements of applicable standards.
Steel die marking with round bottom punch may be permitted on body of butt
weld CS & lower alloy steel fittings.
Paint or ink for marking shall not contain any harmful metals or metal salts such
as Zinc, Lead or Copper which causes corrosive attack on heating.
Fittings shall be dry, clean and free of moisture, dirt and loose foreign materials
of any kind.
Fittings shall be protected from rust, corrosion and mechanical damage during
transportation, shipment and storage.
Rust preventive used on machined surfaces to be welded shall be easily
removable with a petroleum solvent and the same shall not be harmful to
welding.
Each end of fitting shall be protected with a wood, metal or plastic cover.
Each size of fitting shall be supplied in separate packaging marked with the
purchase order number, item code number, material specification, size and
schedule/thickness / rating.
TECHNICAL SPECIFICATIONS
SEAMLESS FITTINGS
TABLE OF CONTENTS
1. SCOPE .................................................................................................................................... 3
2. REFERENCE DOCUMENTS ....................................................................................................... 3
3. MANUFACTURE’S QUALIFICATION .......................................................................................... 4
4. MATERIAL .............................................................................................................................. 4
5. DESIGN AND MANUFACTURE ................................................................................................. 4
6. INSPECTION AND TESTS .......................................................................................................... 5
7. TEST CERTIFICATES ................................................................................................................. 5
8. PAINTING, MARKING AND SHIPMENT ..................................................................................... 6
9. WARRANTY ............................................................................................................................ 6
10. DOCUMENTATION.................................................................................................................. 7
1. SCOPE
1.1 This specification covers the minimum requirements for the design, manufacture
and supply of following fittings in size NB 300mm and smaller to be installed in
natural gas piping system.
1.1.1 Fittings such as tees, elbows, caps etc. shall conform to the requirements of
MSSSP-75, latest edition. Dimensions standard for Screwed/SW fittings shall be
as per ANSI B16.11.
1.2 All requirements contained in the above standards shall be fully valid unless
cancelled, replaced or amended by more requirements as stated in this
specification.
2. REFERENCE DOCUMENTS
2.1 Reference has also been made in this specification to the latest edition of the
following codes, standards and specifications:
ASME B 31.4: Liquid transportation system for hydrocarbon liquid petroleum gas,
anhydrous ammonia and alcohols
MSS-SP-97: Forged carbon steel branch outlet fittings – socket welding, threaded
and butt welding ends.
MSS-SP-25: Standard marking system for valves, fittings, flanges and unions.
2.2 In case of conflict between the requirement of MSS-SP-75, & above reference
documents and this specification, the requirements of this specification shall
govern.
3. MANUFACTURE’S QUALIFICATION
Manufacturer for fittings must possess the records of a successful proof test in
accordance with the provisions of relevant MSS-SP-75 and/or ANSI B16.9/ANSI
B16.11 as applicable. These records shall be submitted at the time of bidding.
4. MATERIAL
4.1 The basic material for fittings shall be as indicated in the Purchase Requisition
Additionally; the material shall also meet the requirements specified hereinafter.
This specification and the relevant codes, prior to shipment, at his works. Such
inspection and tests shall be, but not limited to the following:
4.3 Each heat of steel used for the manufacture of fittings shall have carbon
equivalent (CE) not greater than 0.45 calculated from check analysis in
accordance with the following formula:
Mn Cr + Mo + V NI + Cu
CE = C + ------- + ------------------- + ------------
6 5 15
4.4 Unless specified otherwise, Charpy V-notch test shall be conducted for each heat
of steel, in accordance with the impact test provisions of ASTM A370 at
temperature of 0ºC. The average absorbed impact energy values of three full-
sized specimens shall be 30 joules.
The minimum impact energy value of any one specimen of the three specimens
analysed as above, shall not be less than 80% of the above mentioned average
value.
5.1 Fittings such as tees, elbows and reducers shall be seamless type and shall
conform to ASME B16.9 for sizes 50mm (2”) NB and above ASME B16.11 for sizes
below 50mm (2”) NB.
5.3 Stub-in or pipe-to-pipe connection shall not be used in the manufacture of tees.
Tees shall be manufactured by forging or extrusion methods. Fittings shall not
have any circumferential joints.
5.4 All butt weld ends shall be bevelled as per ASME B16.25.
6.1 The Manufacturer shall perform all inspection and tests as per the requirements
of this specification and the relevant codes, prior to shipment, at his works. Such
inspection and tests shall be, but not limited to the following:
6.1.4 All finished wrought weld ends shall be 100% ultrasonically tested for lamination
type defects. Any lamination larger than 6.35 mm shall not be acceptable.
6.1.5 All other tests not specifically listed but are required as per applicable standard/
specification.
6.2 Purchaser’s Inspector may also perform stage wise inspection and witness tests
as indicated in Para 6.1 at manufacturer’s works prior to shipment. Manufacturer
shall give reasonable notice of time and shall provide without charges reasonable
access and facilities required for inspection to the Purchaser’s Inspector
Inspection and tests performed/witnessed by Purchaser’s Inspector shall in no
way relieve the Manufacturer’s obligation to perform the required inspection
and test.
7. TEST CERTIFICATES
Manufacturer shall produce the certificates (in original) for all, including, but not
limited, the following tests:
d) In case any of the said certificates is not available during the final test, the
supply shall be considered incomplete.
All loose material and foreign material i.e. rust, grease, etc. shall be removed
from the inside and outside of the fittings.
Ends of all fittings shall be suitably protected to avoid any damage during transit.
Metallic bevel protectors shall be used for fittings of size 18” and larger each item
shall be marked with indelible paint with the following data:
a) Manufacturer marking
b) Material Specification
d) Heat No.
Package shall be marked legibly with suitable marking ink to indicate the
following:
a) Order Number
b) Package Number
c) Manufacturer’s Name
d) Type of Fitting
Manufacturer will reimburse purchaser for any fitting furnished on this order
that fails under field hydrostatic test if such failure is caused by a defect in the
fitting, which is outside the acceptance limits of this specification. The
reimbursement cost shall include fitting, labour and equipment rental for finding,
excavation, cutting out and installation of replaced fitting in position. The field
hydrostatic test pressure will not exceed that value which will cause a calculated
hoop stress equivalent to 100% of specified minimum yield strength for the pipe
with which the fitting is to be attached without impairing its serviceability.
10. DOCUMENTATION
10.2 At the time of bidding bidder shall submit the following documents:
10.3 Within two weeks of placement of order, the manufacturer shall submit four
copies of method of manufacture and quality control procedure for raw material
and finished product.
Once the approval has been given by Purchaser, any change in material, method
of manufacture and quality control procedure shall be notified to Purchaser
whose approval in writing of all changes shall be obtained before the fittings are
manufactured
TECHNICAL SPECIFICATIONS
TABLE OF CONTENTS
1. GENERAL ...................................................................................................................................... 3
2. WELDING PROCEDURES .............................................................................................................. 4
3. NON DESTRUCTIVE EXAMINATION ........................................................................................... 18
4. REPAIRS OF WELDS .................................................................................................................... 26
5. INSPECTION ............................................................................................................................... 27
6. DOCUMENTS TO BE SUBMITTED BY THE CONTRACTOR ........................................................... 28
1. GENERAL
1.1 Scope
This specification shall be followed for the fabrication of all types to welding
joints of piping system within the battery limits of all pressure piping of station.
This specification shall apply to all suppliers, vendors, manufacturers, and
fabricators. The CONTRACTOR is responsible for all and shall ensure that all
components to be incorporated into the work meeting this specification.
No supplier, vendor, manufacturer or fabricator shall subcontract the welding
fabrication of any item without written approval from the OWNER and the
OWNER will not issue such an approval unless the proposed welding fabricator
has received prior OWNER approval for the type of welding to be carried out.
The welded pipe joints shall include the following and shall not relieve the
contractor of his responsibilities and guarantee.
a) All pipe joints, longitudinal butt welds, circumferential butt welds and
socket welds.
b) Attachments of forging, flanges and other supports to pipes.
c) Welded manifold headers and other sub-assemblies.
d) Welded branch connections with or without reinforcing pads.
e) Joints in welded / fabricated piping components.
f) The attachments of smaller connection for vents drain drips and other
instrument tapings.
1.2 Codes, Standards and Regulations
All welding performed under this Specification shall meet or exceed the
requirements specified by the latest revisions of the following applicable Codes
and Regulations
Indian Provincial regulations governing the welding of piping systems,
augmented with the following:
All welding procedures used by fabricators and CONTRACTORS shall have been
established and qualified in accordance with the appropriate sections of one or
more of the codes and standards listed above, and approved by the OWNER.
Where a conflict occurs between these specifications and / or any of the above
codes or standards the more stringent shall apply.
2. WELDING PROCEDURES
2.1 CONSUMABLES
All the welding consumables necessary for the execution of the job such as
electrodes, filler wires, argon etc., the CONTRACTOR shall provide at his own
expenses, and these should bear the approval of the OWNER before starting the
work.
The welding electrodes and filler wires supplied by the contractor shall confirm
to this specification and standard codes and shall be of the make approved by
the OWNER and shall submit all test certificates to the Owner for review and
approval.
The contractor shall submit batch test certificates from the electrodes
manufacturers, giving details of physical and chemical tests carried out by them,
for each batch of the electrodes to be used.
Electrode qualification test records for each batch shall be carried by contractor
and test records submitted, for obtaining the approval of the ENGINEER
INCHARGE.
The electrodes, filler wires and flux used shall be free from rust, oil, grease, earth
and other foreign matter, which affect the quality of the welding.
All coated metal arc-welding electrodes shall comply with AWS specification A
5.5, A5.1 type unless approved otherwise by the OWNER.
All welding consumables including fluxes shall be supplied in sealed containers
and stored in a dry location at a minimum temperature of 68°F/20 o C and a
maximum relative humidity of 70%. Low-hydrogen electrodes, after removal
from factory seal containers, shall be stored at a minimum temperature of
150°F/66o C and suitably dried prior to use.
The welding filler metals shall have a chemical composition as near as possible to
the parent metals to be welded. The finished weld as deposited, or after post
weld heat treatment (PWHT) when required, shall be at least equal to the parent
metal as to unit strength, ductile, and other physical properties and in resistance
to corrosion, hydrogen attack, or other operating environment factors as
required. Permission to change filler metals to those other than the ones
qualified in accordance with this specification must be obtained in writing, from
the OWNER.
Electrode and rod diameters shall conform to the parameters of the weld
procedure.
The CONTRACTOR shall provide adequate drying ovens and take proper
precautions in the storage and handling of low-hydrogen electrodes.
When a gas mixture is used, which has specified additions viz. 2% O2, 5% CO2,
the variation of such addition shall not exceed +10% of that stated. Moisture
content shall correspond to a dew point of -300 C or lower. All shielding gas
containers shall have clear identification labels which include the gas type.
Shielded Metal Arc Welding (SMAW) and Gas Tungsten Arc Welding
For pipe sizes 2” and below, the entire joint shall be carried out by
GTAW.
For pipe sizes above 2”, root pass shall be carried out by GTAW and
The CONTRACTOR shall have a separate welding procedure for each method of
welding be intends to employ.
The CONTRACTOR shall only employ welders who have a valid welding certificate
for the procedures being used.
The CONTRACTOR shall have all welders tested in accordance with the applicable
code or standard. Testing shall be at the Contractor's expense including test
pieces. Irrespective of pre-qualification all welders proposed to be deployed in
the work shall be tested and qualified a fresh. No welder shall be allowed to
make any weld for which he is not qualified.
Welding with larger-size electrodes for specific applications may be allowed only
if each welder qualifies with the largest-size electrode to be used in production.
This option is strictly at the OWNER discretion.
OWNER shall specify the details of the welder qualification tests.
For carbon steel, filler wire combinations shall be chosen such that the deposited
hardness of the cap pass shall not exceed 240 BHN. For low-temperature
materials and other materials heat input shall be minimized and comply with the
WPS parameters.
The CONTRACTOR may propose alternate process in addition to those listed. Any
proposed process shall require written OWNER approval and qualification prior
to implement. CONTRACTOR and OWNER shall agree on tests, results, and other
criteria before OWNER approval is granted.
All butt welds in pipe smaller than 60.3 mm O/D ("NPS 2" inch) Schedule 80 shall
be made by GTAW. Root pass by gas metal arc is acceptable for pipe larger than
60.3 mm O/D (NP (2'') inch).
All welds in pressure equipment must be qualified for Charpy V impact testing at
0°C.
Page 9 of 28 CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATIONS
WELDING OF STATION PIPING TGPL-TS-STEEL-PTS-006
When impact tests are required, tests shall be taken from the weld metal, fusion
line, 2mm from fusion line, and 5mm from fusion line.
Permanently installed backing rings shall not be used.
All butt welds in pressure equipment shall have the same chemical and
mechanical properties as the parent metal.
All welding procedures must be qualified for Charpy-V impact testing.
Extreme care shall be taken to ensure that electrode separation by classification
is maintained in the CONTRACTOR's inventory. All storage bins and ovens for
welding consumables shall be clearly labelled. In addition, all GTAW bare rod
filler metals shall be tagged with the AWS designation of the filler metal. Any
welding consumables not readily identifiable shall not be used.
All pressure containing welds shall be of a minimum of two passes with overlap
of starts and stops. This shall include socket welds and seal welds of threaded
connections.
Weld stops and starts shall he staggered so that adjacent weld passes do not
contain stops/starts within 25mm (1 "inch) of each other.
The electrodes shall be purchased from the list of approved manufacturer's and
the same shall be supplied with proper certificates and batch certificates.
The width of weave during production welding shall be within the acceptable
limit of the OWNER approved and qualified welding procedure, qualification
certificates, and production welding operating sheets. As a norm this will be
limited to a maximum of 3 times the core diameter of SMAW electrodes,
whichever is the lesser.
Each weld pass layer shall be completed in one full cycle/ circumference before
proceeding with the next. Blocking out or segmental welding is not permitted.
All tools and equipment used in the welding operations shall be in good
operating condition and shall be of sufficient capacity to ensure welds of the
specified quality are achieved throughout the work. It shall be the right of the
OWNER to request at any times the re-calibration of gauges and meters etc. to
ensure compliance with welding procedure-operating sheets/ WPS.
When joints of unequal thickness are joined, the internal offset shall not exceed
1.6 mm (1/16"). If this value is exceeded, the excess thickness of the heavier end
shall be machined or ground back from the bevel on a one-to-four (1:4) taper.
Maximum bore mismatch shall not exceed 0.8mm (1/32 inch), Where ends are
to be Joined and the internal misalignment due to difference in wall thickness,
etc. exceeds 1.6 min (1/16 inch), the wall extending internally shall be internally
2.4 Preheating
Preheat for pressure piping and furnace tubs shall be in accordance with ASME
B31.3 and B31.8 or as per approved WPS.
All pipe joints having a wall thickness greater than 9.5 mm (0.375") shall he
preheated to 100°C prior to welding.
Preheating shall he carried out with an approved torch system which will provide
uniform heating.
The preheating area shall be at least 100 mm (4") wide cantered about the weld
and shall extend around the entire circumference of the pipe.
Preheat temperatures shall be checked with temperature sensitive crayons or by
other approved methods. If a joint requires preheating, the same temperature
requirements shall be maintained for each succeeding pass.
2.5.7 Fillet welds shall be of a specified size with full throat and the legs of uniform
length.
2.5.8 Arcs shall only be struck in the weld groove. A controlled arc must be maintained
while welding. Should an arc strike occur, it shall be removed by grinding and the
area shall be etched (10% Nital) to confirm heat affected area removal, and MT
examined to ensure absence of any surface cracking.
Repair of arc strikes by welding is prohibited.
2.5.9 After each pass the layer of weld metal must be cleaned to remove all slag, scale
dirt etc. wire brushes, grinder, or chipping hammer shall be used as needed to
prepare proper surface for each succeeding weld pass.
2.5.10 Repair, chipping or grinding of welds shall be done in such a manner as not to
gouge, groove or reduce the base metal thickness.
2.5.11 No welding shall be done if the temperature of the base metal is below 50°F. Nor
shall there be any wedding done if there is moisture, grease, or any foreign
material on the joint to be welded.
2.5.12 A qualified welder shall make tack welds. Cracked tack welds shall be completely
ground out and NDE by MT/PT prior to re-weld.
2.5.13 The CONTRACTORS shall make no substitution of materials or modifications to
details without the prior written approval of the OWNER.
2.5.14 Welders and welding operators shall not be qualified on production welds.
2.5.15 The CONTRACTOR shall ensure that welders and welding operators are only
employed on those parts of the work for which they are qualified.
2.5.16 Each welder and welding operator shall possess an appropriate temperature
measuring device. All supervisors shall possess a copy of the approved welding
procedures.
2.5.17 Alternatively, welding procedures may he clearly display at each welding
location. Welders shall be familiar with the requirements of the appropriate
approved welding procedures. Any welder found not complying with the
approved welding procedures during production welding shall be removed from
the work and the non-conforming weld(s) may be completely rejected, at the
discretion of the OWNER.
2.6.2 Cleaning
a) All weld impurities shall be removed between passes. Cleaning may
be done with either hand or power tools.
b) All rough irregularities in the cover pass and weld spatter shall be
removed.
2.8.2 PWHT of pressure piping and furnace tubes shall be in accordance with ASME
B31.3, B31.8 and the specification for Post Weld - Heat Treating.
2.8.3 Controlled atmosphere furnaces are preferred for heat treatment. Procedures
using electric resistance, induction, or flame burner rings are acceptable for
shop or field heat treatment. OWNER prior to heat treatment must approve
these procedures.
2.8.4 CONTRACTOR must notify the OWNER prior to starting PWHT operations.
2.8.5 CONTRACTOR shall furnish a PWHT record chart. The chart must be dated,
numbered and labelled with job identification. CONTRACTOR name and person
Responsible for the PWHT. Heat-treated lane, welds and spool numbers shall be
identified on the chart.
2.8.6 The completed PM/HT record chart shall be submitted for OWNER approval
following completion of heat treatment.
2.8.7 Stress relieving of piping shall be performed as per ASME B31.3 ASME B31.8. as
applicable.
2.8.8 Stress relieving may he performed by electrical induction or by electric resistance
heating devices, or by furnace that has a large enough capacity to accommodate
the entire piece being heat-treated.
2.8.9 The stress relieving temperature to be attained shall be 1100°F/593oC minimum
1150°F/621oC maximum. The soak period of this temperature shall be one hour
per 25.0 mm (1 inch) of pipe wall thickness and in no case shall the soak period
be less than one hour.
2.8.10 Rate of heating and cooling shall be in accordance with the requirements for
thermal stress relief presented in Section VIII of the ASME Boiler and Pressure
Vessel Code. In any event, the rate of heating above 600°F/315 o C may not be
more than 400°F/205oC per hour, nor the rate of cooling more than
500°F/260oC per hour when above 600°F/315o C.
2.8.11 For field stress relieving, a continuous temperature record Log shall be
furnished of the program from heating, soaking and cooling to 600°F. A
minimum of two thermocouples shall be installed at each weld so that
continuous readings can be assured in the event of thermocouple failure.
2.8.12 Local heat treatment of welds shall consist of heating ID pipe length completely
around the circumference of the pipe welds or pipes as required to eliminate
thermally induced stresses. A continuous record of time and temperature shall
be maintained for at least two points on each weld during the course of heat
treatment with methods other than exothermic kits.
2.8.13 During heat treatment, the ends of the pipe shall be temporarily plugged to
minimize air-cooling. Sufficient insulation shall be applied to maintain the
required heat treatment temperature. The full thickness of 75mm (3"-inch)
insulation shall be continued for a minimum distance of 610 mm (2 feet) on
each side of the heating elements, and shall be in place until the weld has
cooled to below 100°F/37
2.8.14 When local heat treatment is used, care shall be exercised with restrained piping
so that no upsetting will be caused by thermal expansion.
2.8.15 A minimum 10% of all locally (field) heat-treated welds shall require Brinell
hardness testing.
2.8.16 Unless otherwise indicated by OWNER, Brinell hardness limits apply to welds
after PWHT. The hardness of the weld shall be determined by the average value
of three tests (of 3 indentations) taken per 120 degrees’ quadrant around the
weld.
2.8.17 The test areas of the weld shall be ground or filled to provide a suitable surface
for testing. If a Tele brineller is used to measure the hardness the bar shall be as
close as practical to the anticipated weld hardness. If a poor indention is
obtained on an individual test, a retest shall be made on an adjacent area.
2.8.18 Hardness tests other than Brinell may be used if the values obtained can be
equated to the Brinell hardness numbers, and the proposed equipment and
procedures have received prior OWNER approval.
2.8.19 Flange facing and threaded connections must be adequately protected against
oxidation during stress relieving and must be cleaned and freed of defects after
stress relieving.
2.8.20 No heating or welding may be applied to any piping or weld joint after stress
relieving is complete.
2.8.21 All stress relieving equipment and execution shall be supplied at Contractor’s
expense.
2.9 WELDING PROCEDURE QUALIFICATION
Welding procedure qualification shall be in accordance with the relevant
requirement of API 1104/ ASME Sec. IX latest edition or other applicable codes
and the job requirements. The Contractor shall submit the welding procedure
specification in format as per PQR. Format immediately after the receipt of the
order. Owner’s representative will review, check and approve the welding
procedure submitted and shall release the procedure for qualification test. The
complete set of test result as per API 1104 / ASME sec. IX shall be submitted to
the OWNER/ OWNER’s representative for approval immediately after completing
the procedure qualification test and at least 2 weeks before the commencement
of actual work. Standard test specified in the code shall be carried out in all
cases.
All materials to be welded shall be subjected to visual examination as per the
code.
In addition to these test the following test shall be carried out.
Radiography testing
Macro/ Micro Examination.
Hardness test.
Dye Penetrate examination.
Chemical Examination
Bend Test
Charpy V-notch Impact test at Weld and HAZ at 0 °C & -20 °C .
These tests shall be carried out on specimens depending upon the type of base
material, operating conditions and requirements laid down in the detailed
drawing and specification. It shall be the responsibility of the Contractor to carry
out all the tests required to the satisfaction of the OWNER/ OWNER’s
representative.
The procedure qualification test shall be carried out by the Contractor under
field conditions at his own expense.
proposed NDE SUBCONTRACTOR has received prior OWNER approval for the
type of NDE work proposed.
The non-destructive examination of 100% girth welds shall be carried out.
3.3 ABBREVIATIONS
ASME- American Society of Mechanical Engineers
ANST- American Society for Non-Destructive Testing
ASTM- American Society for Testing and Materials
AWS- American Welding Society
DPI- Dye Penetrant Inspection
HS&E- Health Safety and Environment
MPI- Magnetic Particle Inspection
Page 19 of 28 CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATIONS
WELDING OF STATION PIPING TGPL-TS-STEEL-PTS-006
5 Concave root surface (SLICK For single sided welded joints concavity of the
UP) root surface shall not reduce the total
thickness of joint including reinforcement to
less than the thickness of the thinner of the
components being joined.
However, number of times of repair welding for the same weld shall be as
follows:
MATERIAL NO. OF TIMES OF REPAIR WELDING
1.0 CS UPTO 300# 1 OR LESS
2.0 CS ABOVE 300# 1 OR LESS
Notes:
1) Ultrasonic testing, in lieu of radiography, is acceptable only where
radiography is not practicable e.g. branch connections.
2) UPI or DPI of branch welds to be performed prior to and lifter
attachment of compensating plate if applicable.
3) Open drains vents or other open ended line shall be leak tested only.
4) For piping within skid packages, the CONTRACTOR shall use this table as
a guide only and prepared NDE plan for review and approval by OWNER
as required in the respective package specification.
5) Vat required where wall thickness of scanning surfaces is less than
10mm and where branch size is less than NPS 4". Non-ferrite materials
shall not be examined with UT methods.
4. REPAIRS OF WELDS
4.1 With the prior permission of ENGINEER IN CHARGE welds that do not comply
with the standards of acceptability shall be repaired or the joint cut out and re-
welded.
A separate welding procedure specification sheet shall be formulated and
qualified by CONTRACTOR for repair welds simulating the proposed repair to be
carried out. Separate procedures are required to be qualified for (a) through
thickness repair (b) partial repair and (c) capping repair. Welders shall be
qualified in advance for repairs. The root pass, for repairs opening the root, shall
be replaced by the vertical uphill technique. The procedure shall be proven by
satisfactory procedure tests to API 1104 including the special requirements of
the specification, and shall also be subjected to metallographic examination,
hardness surveys and Charpy test to determine the effects of repair welding on
the associated structure.
Root sealing or single pass repair deposit shall not be allowed. Internal root
defects shall be ground thoroughly and welded with a minimum of two passes.
However, while grinding for repairs, care shall be taken to ensure that no
grinding marks are made on the pipe surface anywhere.
The repair shall be subjected, as a minimum requirement, to the same testing
and inspection requirements as the original weld. Re-radiography of the repaired
area shall be carried out. In addition, a minimum of 6” weld length on the either
side of the repaired area shall be re-radiographed. A 100% ultrasonic test shall
be done at the repaired area externally. Any repaired area that is wide, irregular
or rough shall be rejected and a full cut out shall be done.
Repairs are limited to a maximum of 30% of the weld length. Welds containing
cracks shall be cut out and re-bevelled to make a joint. TGPL shall authorize all
repairs.
4.2 Weld Rejected by Accumulation of Defects
Where a weld is rejected by accumulation of defect clause, as defined by API
1104 and this specification, repairs within these limitations are permitted.
Defects in the filling and capping passes shall be repaired preferentially.
5. INSPECTION
5.1 The CONTRACTOR shall extend all facilities, assistance and co-operate fully with
the OWNER in all aspects of inspection and NDE and shall give adequate notice
of any required fabrication inspection stages, together with sufficient time for
thorough inspection by the OWNER. OWNER shall have the right to establish
hold points at any point in the fabrication sequence.
5.2 Although is the Contractor’s primary responsibility to perform weld examination,
OWNER shall have the right to observe the examination of all welds by non-
destructive means. The inspection may be at any time before, during and after
fabrication. The CONTRACTOR shall conduct daily NDE of welds to assess weld
quality. Up-to-date examinations are required to identify and prevent the
reoccurrence of weld defects on subsequent welds. Records and evidence of all
weld examinations shall be available at all times for OWNER to review and
approve.
5.3 OWNER may use any method of inspection necessary to establish quality control
and ensure adherence to welding procedures. OWNER shall have the right to
accept or reject any weld not meeting the requirements of this specification.
5.4 OWNER reserves the right to perform inspection at shop / field where fabrication
and erection of piping is in progress for (but not limited) for the following
objective:
TECHNICAL SPECIFICATIONS
TABLE OF CONTENTS
1. SCOPE .................................................................................................................................... 3
2. STANDARDS & CODES............................................................................................................. 3
PNGRB – Petroleum and Natural Gas Regulatory Board.................................................................................................... 3
3. ABBREVIATIONS ..................................................................................................................... 3
4. TECHNICAL NOTES FOR BOLTS AND NUTS............................................................................... 3
5. TECHNICAL NOTES FOR GASKETS ............................................................................................ 5
1. SCOPE
This specification provides minimum requirement for design, manufacturing,
Inspection, Testing and supply of Nuts, Studs, Bolts and Gaskets covering sizes ½”
NB through 12” NB (300mm) for ANSI pressure classes # 150 through # 800 to be
used in City Gas distribution for handling Natural Gas.
2. STANDARDS & CODES
4.2.4 Stress Rupture Test as detailed in ASTM A453 shall be carried out for all ASTM
A453 bolting material irrespective of the temperature.
4.3 All bolting shall be as per ANSI B 18.2.1 for studs, M/c bolts and jackscrews and
ANSI B18.2.2 for nuts.
4.4 Threads shall be unified (UNC for 1” dia and 8UN for > 1” dia) as per ANSI B.1.1
with class 2A fit for studs, M/c bolts and jackscrews and class 2B fit for nuts.
4.5 Stud bolts shall be threaded full length with two heavy hexagonal nuts. Length
tolerance shall be in accordance with the requirement of ANSI B 16.5.
4.6 The nuts shall be double chamfered, semi-finished, heavy hexagonal type and
shall be made by the hot forged process and stamped as per respective material
specification.
4.7 Heads of jackscrews and m/c bolts shall be heavy hexagonal type. Jackscrew end
shall be rounded.
4.8 Each size of studs & m/c bolts with nuts and jackscrews shall be supplied in
separate containers marked with size and material specifications. ‘CRYO’ shall be
marked additionally in case ‘CRYO’ is specified in the requisition. Inner rings
shall be provided for the following:
4.9 The heat treatment for stud bolts & nuts shall be as per code unless mentioned
otherwise.
4.10 For S.S. nuts and bolts minimum impact energy absorption shall be 35 Joules and
test temperature shall be - 196°C unless mentioned otherwise. For other
materials impact energy and test shall be as per respective code.
4.11 Bolts/nuts of material of construction B7M/ 2HM shall be 100% Hardness tested
as per supplementary requirement S3 of ASTM A 193.
4.12 When specified as galvanized, the studs, M/C bolts and nuts shall be ‘hot dip zinc
coated’ in accordance with requirements of ‘class C’ of ‘ASTM A 153’. As an
alternative, electro galvanizing as per IS 1573, ‘Service Grade Number 2’ is also
acceptable.
5.3 Testing
5.3.1 Test reports shall be supplied for all mandatory tests for gaskets as per the codes
& standards specified in this technical specification.
5.3.2 For Spiral wound material following shall be furnished:
a) Manufacturer’s test certificate for filler material and spiral material as per the
relevant material specifications.
b) Manufacturer’s test certificate for raw materials and tests for compressibility/
seal-ability & recovery as per the relevant material specifications.
5.4 Full face gaskets shall have bolt holes punched out.
5.5 Filler material for spiral wound gaskets shall not have any colour or dye.
5.6 All spiral wound gaskets shall be supplied with Outer ring. Material of the outer
ring shall be CS unless otherwise specified.
5.7 For spiral wound gaskets, material of Inner Compression ring shall be same as
Spiral Strip material.
TECHNICAL SPECIFICATIONS
TABLE OF CONTENTS
1. SCOPE .................................................................................................................................... 3
2. REFERENCE DOCUMENTS ....................................................................................................... 3
3. Abbreviations ......................................................................................................................... 4
4. MATERIALS............................................................................................................................. 4
5. DESIGN AND CONSTRUCTION REQUIREMENTS ....................................................................... 6
6. INSPECTION AND TESTS .......................................................................................................... 7
7. TEST CERTIFICATES ................................................................................................................. 9
8. PAINTING, MARKING AND SHIPMENT ..................................................................................... 9
9. SPARES AND ACCESSORIES ................................................................................................... 10
10. DOCUMENTATION................................................................................................................ 10
1. SCOPE
This specification covers the minimum requirements for design, manufacture, testing
and supply of low temperature carbon steel ball, plug and globe valves designed and
manufactured to BS EN ISO 17292/API 6D standard for size DN 100 mm (4”) and
below and ANSI pressure rating Class 150, 300, 600, 800 (Socket weld end and Flange
connection) for use in pipeline systems handling Natural Gas.
2. REFERENCE DOCUMENTS
All valves shall be manufactured and supplied in accordance with the BS EN ISO
17292/API 6D Latest edition, Petroleum and Natural Gas Regulatory Board – Pipeline
Transportation Systems – Pipeline valves, with additions and modifications as
indicated in the following sections of this specification.
Reference has also been made in this specification to the latest edition (edition
enforce at the time of issue of enquiry) of the following Codes, Standards and
Specifications.
The ratio of body yield strength and body ultimate tensile strength of each test valve
on which body yield strength and body ultimate tensile strength are determined,
shall not exceed 0.90.
The carbon equivalent (CE) of valve end connections which are subject to further
field welding by TGPL shall not exceed 0.43 on check analysis for each heat of steel
used, as calculated by the following formula:
Mn Cr + Mo +V Ni + Cu
CE = C + + +
6 5 15
For all forge material the fine grained perlitic structure of the steel shall be
verified by at least one micrographic examination per lot according to ASTM E
112. The grain size shall be as per ASTM Standards.
5. DESIGN AND CONSTRUCTION REQUIREMENTS
Valve design shall meet the requirements of BS EN ISO 17292/API 6D and shall
be suitable for the service conditions indicated in the Valve Data Sheet. The
ASME Boiler & Pressure Vessel Code, Section VIII, Division 1 shall be used to
design the valve body. Valve shall be manufacturing as per QSL-3 (Quality
Specification Level) requirements of Annexure-J of API 6D Allowable stress
requirements shall comply the provisions of above code. In addition, corrosion
allowance indicated in Valve Data Sheet shall be considered in valve design.
The ball valves shall be bi-directional.
For above ground valves, body design shall be either fully welded or bolted
type. Valve end connection shall be socket weld and flanged ends, as per
requirement. Valve body joints with threads are not permitted. In the valve
body outlets also, threading is not permitted.
Ball shall be of single piece, solid type construction. And non -lubricating type.
All ball valve shall be Full bore (FB). Reduced Bore (RB) valves shall not be
permitted.
Ball mounting shall be floating type only for all valves of size below 2”.
All valves shall be wrench operated valve. Direction of operation of wrench
shall be in clock-wise direction while closing the valve
Valves shall be designed to withstand a sustained internal vacuum of at least 1
(one) milli-bar (a) in both open and closed positions.
Valve shall be provided with indicator to show position of ball port
Valve shall be provided with stops for both fully open and fully closed position.
Bolted valve shall be used.
Valve ends shall be as indicated in the Valve Data Sheet. End-to-end
dimensions for valve shall be in accordance with ASME B 16.11 shall be as per
Manufacturer Standard and shall be subject to approval by TGPL.
Valves shall be suitable for above ground installation as indicated in Valve Data
Sheet.
Valve design shall ensure repair of stem seals/packing under full line pressure.
Valve shall be fire tested design.
Valve shall be long pattern with anti-static features.
Repair by welding is not permitted for cast body and forged body valves.
No casting is permitted for stem material of all valves. Valve stem shall be
capable of withstanding the maximum operating torque required to operate
the valve against the maximum differential pressure corresponding to
applicable class rating for a minimum of 500 open-close-open cycles for a
design life of 40 years. The combined stress shall not exceed the maximum
allowable stresses specified in ASME section VIII, Division 1.
6. INSPECTION AND TESTS
The Manufacturer shall perform all inspection and tests as per the
requirements of this specification, approved quality assurance plan (QAP) and
the relevant codes, prior to shipment, at his Works. Such inspection and tests
shall be, but not limited to, the following:
All valves shall be visually inspected. The internal and external surfaces of the
valves shall be free from any strikes, gouges and other detrimental defects. The
surfaces shall be thoroughly cleaned and free from dirt, rust and scales.
Dimensional check on all valves shall be carried out as per the TGPL approved
drawings.
Chemical composition and mechanical properties shall be checked as per this
specification and relevant material standards, for each heat of steel used. All
testing frequency shall be as per Inspection & Test Plan/ QAP. Heat treatment
chart for forging material shall be witness & start/stop time signed by TPIA.
Valve body and seat shall be hydro-test as per ISO 5208/ API 598 latest
edition/applicable codes and standard.
In addition to above, pneumatic testing and functional testing shall be carried
out at 7 bar (g) for 800# pressure rating valves, using nitrogen for 15 minutes.
High pressure shell and seat pneumatic testing shall be submerged in water.
Page 7 of 11 CONTRACTOR Sign & Stamp
TECHNICAL SPECIFICATIONS
FOR VALVE (Size – Below 4”) TGPL-TS-STEEL-PTS-002
A supplementary air seat test as per API 6D (Annexure H) shall be carried out
for all valves. A bubble tight seal is required without the use of any sealant. No
leakage is allowed. Test pressure shall be held for at least 15 minutes.
Valves shall be subjected to Operational Torque Test as per API 6D (Annexure
H) under hydraulic pressure equal to maximum differential pressure
corresponding to the applicable ANSI class rating of valve. It shall be
established that the force required to operate the valve does not exceed the
requirements stated in this specification.
Non-destructive examination of individual valve material and component
consisting of but not limited to castings, forgings, plates and assembly welds
shall be carried out by the Manufacturer.
7. TEST CERTIFICATES
Manufacturer shall submit the following certificates:
a. Mill test certificates relevant to the chemical analysis and mechanical
properties of the materials used for the valve construction as per the
relevant standards.
b. Test certificates of hydrostatic and pneumatic tests, helium test
complete with records of timing and pressure of each test.
c. Test reports of ultrasonic inspection, if applicable.
d. Test report on operation of valves conforming.
e. All other test reports and certificates as required by Standard – BS EN
ISO 17292/API 6D latest edition and this specification.
The certificates shall be considered valid only when signed by TGPL's Inspector.
Only those valves which have been certified by TGPL's Inspector shall be
dispatched from Manufacturer's works. TPIA shall issue 3.1 certificates as per
EN 10204.
8. PAINTING, MARKING AND SHIPMENT
Valve surface shall be thoroughly cleaned, freed from rust and grease and
applied with sufficient coats of corrosion resistant paint. Surface preparation
shall be carried out by shot blasting to SP-6 in accordance with "Steel
Structures Painting Council - Visual Standard SSPC-VIS-1"/ Sa 2 ½ in accordance
with "Swedish standard - SIS- 055900" as per Painting specification.
The external surfaces of all valves shall be provided with high build epoxy
coating with a min. thickness of 300 microns DFT (dry film thickness).
All above ground valves shall be painted as per Painting specifications suitable
for highly/normal corrosive environment as applicable.
All valves shall be marked as per API 6D. The units of marking shall be metric
except nominal diameter, which shall be in inches.
Valve ends shall be suitably protected to avoid any damage during transit. All
threaded and machined surfaces subject to corrosion shall be well protected by
Moly coat type grease or other suitable material. Socket Weld Ends shall be
protected with metallic or high impact plastic protectors.
Packaging and shipping shall be as per Specification/ as per Applicable
Standards.
10. DOCUMENTATION
Documentation to be submitted by Manufacturer to TGPL is summarized
below. Number of Copies (Hard copies / soft copies etc.) shall be as indicated
in CONTRACT document.
TGPL shall approve the following documents from manufacturer/supplier and
verify before placement of order:
a) General arrangement/ Sectional drawing & blow-up drawing of seat
assembly shall be submitted. Number of turns for Gear Operated
valves shall be indicated in the GA or shall be furnished separately.
b) Reference list of similar ball valves manufactured and supplied in last
ten years indicating all relevant details including project, year, client,
location, size, rating, service etc.
Safety Safety Hi Visibility Ear Welding Grinding Safety Safety Leather Gas
Employees Handgloves
Shoes Helmet Jacket plug/muff Screen Screen belt googles apron Mask
Engineers, (Area Incharge/ Zone
Incharge Contractors,Engineers,
Executives, GET)
Supervisors
Project Managers
TPE
Contractor Labours (Depending on
HIRA, he may have to use other PPE
also as per requirements)
Welders
Grinders
PE technician
GI/Cu technician
O&M technician/Those engaged at
CGS/Odourant filling
Dispenser/Compressor operators
Crane Operator
Plumber/Those who will work at
heights more than 2 m
Breaker Operator
Note: Based on HIRA and Line Managers requirements, additional PPE may be required to be used
MEDICAL FITNESS REQUIREMENTS
All the employees deputed for Torrent Gas Pvt. Limited (TGPL) work should undergo
pre employment medical examination covering the basic height, Weight, Eye Vision
Basic Requirement test , Chest X ray & Blood Test , Urine Routine and produce a physical fitness
certificate from a MBBS doctor and shall submit a copy of the entire medical fitness
certificate to an authorized representative of TGPL