Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Management (EPM)
Lecture 6
Dr Yasir Ahmad
1492
???WHAT IS TO BE DONE
Plan
Scope
Mgmt پالن
دائرہ
Collect
Control کار کو معلومات Requir-
Scope قابو میں اکٹھا ements
رکھنا کرنا
Project
کا دا ئرہ
کار دائرہ
دائرہ
کار Define
Validate کار کی
Scope وضع Scope
تصدیق کام کو کرنا
چھوٹے
حصوں
میں تقسیم Create
کرنا WBS
Considerations for Agile/Adaptive
Environments
In projects with evolving requirements, high
risk, or significant uncertainty, the scope is
often not understood at the beginning of the
project or it evolves during the project.
LEVEL DESCRIPTION
1 Total Program
2 Project(s)
3 Task(s)
4 Subtask(s)
5 Work Package(s)
6 Level of Effort
DEVELOPING WBS
1 PROGRAM 1.00.00
But important point is till the cost and time be best approx
It makes sense
WBS IN MS WORD
ACTIVITY - WBS
Project Schedule
Mgmt
CPM
PERT
Activity
name
EXAMPLE: FRANK’S FINE
FLOATS
B D
3 3 G
6
F
3
Start
A
Finish
3 E
7
C H
2 2
EARLIEST START AND FINISH
TIMES
3 5
7
C H 5 7
2 2
3 5
7 5 12
C H 5 7
2 3 5 2 16 18
Activity ES EF LS LF Slack
A 0 3 0 3 0 (critical)
B 3 6 6 9 3
C 3 5 3 5 0 (critical)
D 6 9 9 12 3
E 5 12 5 12 0 (critical)
F 6 9 15 18 9
G 12 18 12 18 0 (critical)
H 5 7 16 18 11
EXAMPLE: FRANK’S FINE
FLOATS
• Determining the Critical Path
• A critical path is a path of activities, from the Start node to
the Finish node, with 0 slack times.
B 3 6 D 6 9
3 6 9 3 9 12 G 12 18
6 12 18
F 6 9
3 15 18
Start
A 0 3
Finish
3 0 3 E 5 12
3 5
7 5 12
C H 5 7
2 3 5 2 16 18
Critical Path
UNCERTAIN ACTIVITY TIMES
• In the three-time estimate approach, the time to
complete an activity is assumed to follow a triangular
distribution.
• An activity’s mean completion time is:
t = (a + m + b)/3