Jammu & Kashmir State Electricity Regulatory Commission

406, BBC, Ward No. 03, behind Makeen Guest House, Shivpora, Srinagar-190004 (J&K).

Website: http://www.jkserc.nic.in & Email ID’s: jkserc@gmail.com,

Notification No.JKSERC/30 of 2013

Dated: - 02-07-2013

Pursuant to Regulation 12, 13, 15 and 16 of the J&K SERC (Open Access in
Intra-State Transmission and Distribution) Regulation, 2006 notified under
No.6/J&K/SERC/Jammu, 25-1-2006, the Jammu and Kashmir State Electricity
Regulatory Commission hereby notifies the charges payable during FY 2013-14 by
Open Access Customers:-

1. Transmission / Distribution (Wheeling Charges):

Regulation 12 (A) –

The ST- rate applicable to short term Open Access Customers shall be as
under: For transmission – Rs.587/MW/day. For distribution (Wheeling) –
Rs.1560/MW/day.

2. Cross – subsidy surcharge:

Regulation No. 12 (B) –

Cross – subsidy Surcharge shall be nil.

3. Additional surcharge:

Regulation No. 12 (C) –

The additional surcharge shall be fixed on case to case basis keeping in view
the amount of fixed/capacity cost allowed to distribution utility/ licensee.

4. Scheduling and System Operation Charges:

1
Regulation No. 12 (D) –

Rs.1000/- per day or part thereof shall be paid by short term Open Access
User.

Rs.30,000/- per month or part of the month shall be paid by long term Open
Access User.

Note.- The Operating charges include fee for scheduling and system operation fee
affecting revision in schedule on bona fide grounds and collection and
disbursement charges.

5. Reactive Charges:

Regulation No. 12 (E) –

If the voltage at the point of drawal is below 97% of the normal voltage, or
if at the injection point the voltage is higher than 103% of the normal
voltage, the Open Access Customer shall pay charges to the concerned
utility/ licensee for drawal/ injection of reactive energy at the point of
drawal/injection at the rates fixed by CERC for Inter—State Transmission for
the year. Both drawal and injection of reactive energy shall be measured at
15 minutes time block along with voltage.

6. Restoration Charges:

Regulation No. 12 (F) –

For HT Open Access connection – Rs.600.00

For LT Open Access connection – Rs.120.00

7. UI Charges under Intra-State ABT Tariff:

Regulation No. 13 –

Unscheduled interchange rates for over/ under-drawals shall be 100% of the


UI rate.

2
8. Energy Loss:

Regulation No. 15 –

The average technical loss allowable and to be considered for Open Access
Users during FY 2013-14 shall be:-

Transmission Losses (EHV) 5%

Distribution Loses (HV) 5%

(Excluding LV & MV)

9. Special Energy Meter:

Regulation No. 16 –

Charges for rental of meter (if provided by the utility/licensee), charges for
meter reading and other related charges including the charges for
communicating the meter reading to SLDC shall be paid by the Open Access
Customer @ Rs.1000/- (Rupees one thousand only) per month for each
meter and shall be paid to the utility/ licensee who is rendering such service.

By order of the Commission

Sd/-

Secretary

JKSERC