Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
PARTIAL-DEPTH REPAIR OF
CONCRETE PAVEMENTS
April 2012
TechnicalȱReportȱDocumentationȱPage
4.ȱTitleȱandȱSubtitleȱ 5.ȱReportȱDateȱ
GuideȱforȱPartialȬDepthȱRepairȱofȱConcreteȱPavementsȱ Aprilȱ2012ȱ
6.ȱPerformingȱOrganizationȱCode
ȱ
7.ȱAuthor(s)ȱ 8.ȱPerformingȱOrganizationȱReportȱNo.
DanielȱP.ȱFrentressȱandȱDaleȱS.ȱHarringtonȱ ȱ
9.ȱPerformingȱOrganizationȱNameȱandȱAddress 10.ȱWorkȱUnitȱNo.ȱ(TRAIS)ȱ
InstituteȱforȱTransportationȱ ȱ
IowaȱStateȱUniversityȱ 11.ȱContractȱorȱGrantȱNo.ȱ
2711ȱSouthȱLoopȱDrive,ȱSuiteȱ4700ȱ ȱ
Ames,ȱIAȱ50010Ȭ8664ȱ
12.ȱSponsoringȱOrganizationȱNameȱandȱAddress 13.ȱTypeȱofȱReportȱandȱPeriodȱCovered
ȱ ȱ
14.ȱSponsoringȱAgencyȱCodeȱ
ȱ
15.ȱSupplementaryȱNotesȱ
ȱ
16.ȱAbstractȱ
Theȱpurposeȱofȱthisȱguideȱisȱtoȱhelpȱpractitionersȱunderstandȱhowȱtoȱselect,ȱdesign,ȱandȱconstructȱ
successfulȱpartialȬdepthȱrepairsȱofȱconcreteȱpavements.ȱItȱdefinesȱ“partialȬdepth”ȱrepairsȱasȱ
everythingȱfromȱveryȱshallowȱsurfaceȱrepairsȱtoȱthoseȱthatȱextendȱasȱdeepȱasȱtheȱtopȱoneȬhalfȱofȱtheȱ
pavementȱslab.ȱItȱalsoȱprovidesȱqualityȱcontrolȱguidanceȱandȱtroubleshootingȱinformation.ȱ
ȱ
ȱȱ
17.ȱKeyȱWordsȱ 18.ȱDistributionȱStatementȱ
Concreteȱpavement,ȱportlandȱcementȱconcrete,ȱconcreteȱpavementȱjointsȱ Noȱrestrictions.ȱ
19.ȱSecurityȱClassificationȱ(ofȱthisȱ 20.ȱSecurityȱClassificationȱ(ofȱthisȱ 21.ȱNo.ȱofȱPagesȱ 22.ȱPrice
report)ȱ page)ȱ
Unclassified.ȱ Unclassified.ȱ 34ȱplusȱfrontȱmatterȱ ȱ
FormȱDOTȱFȱ1700.7ȱ(8Ȭ72)ȱ Reproductionȱofȱcompletedȱpageȱauthorizedȱ
PARTIAL-DEPTH REPAIR OF
CONCRETE PAVEMENTS
April 2012
Authors
Daniel P. Frentress, Frentress Enterprises, LLC
Dale S. Harrington, Snyder & Associates, Inc.
Cover Designer
Wendy Stribe
The authors and the National CP Tech Center are grateful to the • Gordon Smith, Iowa Concrete Paving Association
following organizations for providing images used in this guide: • Kurt Smith, Applied Pavement Technology
• City of Ankeny, Iowa: Figure 20 • Sam Tyson, FHWA
• Gordy Bruhn, Minnesota DOT: Figure 66 • Leif Wathne, ACPA
• Dan DeGraaf, Michigan Concrete Association: Figure 67 (r) • Matt Zeller, Concrete Paving Association of Minnesota
• Jim Fox, Minnesota DOT: Figures 3, 4, 29, 39, 43
• Daniel P. Frentress, Frentress Enterprises LLC: Figures 1, 2,
9 (middle), 11, 21, 22, 25, 37, 38, 45, 48, 54, 55, 58, 59, 60 (l), 61,
62, 63, 67 (l), 68
• Andy Gisi, Kansas DOT: Figures 13 (right), 27, 60 (r)
• Todd LaTorella, Missouri/Kansas Chapter, ACPA: Figures 49,
51, 52
• Kevin McMullen, Wisconsin Concrete Pavement Association:
Figures 6, 9 (l and r), 14, 15, 16, 17, 18, 19, 23, 24, 26, 28, 31, 32,
33, 34, 41, 42, 44, 46, 47, 50, 53, 56, 64, 65
Mixture Selection .....................................................8 Placing, Finishing, and Curing Patch Material .....25
Mixtures for Early Opening to Traffic (EOT)............9 Resealing Joints and Cracks ..................................25
Cleanup Responsibilities .......................................25
Bonding (Grout) Agents ....................................... 10
Troubleshooting ...........................................25
Construction Steps ..................................... 10
Compression Relief Failures ................................25
Step 1. Determine Repair Boundaries ................. 10
Curing Failures .....................................................26
Step 2. Concrete Removal .................................... 11
Debonding of Patch ..............................................26
Saw-and-Chip Removal (Type 1 Repairs) ............. 11
Mill Removal (Types 1 and 2 Repairs) .................. 12
Deterioration around Patch ..................................26
Figure 20. Type 2B crack milling ...............................12 Figure 44. Troweling toward the edge of the
repair .........................................................18
Figure 21. V-head milling (Types 1 and 2) ................13
Figure 45. Concrete placement for Type 1 repair
Figure 22. V-head milling ...........................................13 using waxed cardboard ...........................18
Figure 23. Rounded milling (Types 1 and 2) ............13 Figure 46. Tooling the joint........................................ 19
Highway maintenance crews spend a large amount of For example, in 1980 Minnesota implemented a modi-
time and money each year repairing partial-depth spalls fied partial-depth repair on a spalled section of pavement
with quick-to-install but temporary (a few months to a that extended deeper than the top one-third of the slab.
few years) repair material. However, when patch materi- Milling machines were used to remove the concrete in
als and construction techniques are properly selected and the distressed area and form a tapered edge around it.
applied in a timely manner and at appropriate locations, The milled surface was cleaned and a cement grout was
partial-depth repairs can be more cost-effective and can applied; then a cement-based repair material was applied.
last 10 to 15 years or longer. Because of these advantages, In the 1990s Minnesota’s cost-effective method was copied
many jurisdictions use partial-depth repairs in their pave- in Wisconsin and Michigan. In the 2000s Kansas, Missouri,
ment preservation programs. Recent photos of 18th Street Colorado, and South Dakota adopted similar milling
in Hopkins, Minnesota (Figure 1 and Figure 2) demon- approaches to partial-depth repairs. By using new milling
strate the longevity of well constructed, longitudinal and equipment and durable concrete mixtures, these states
transverse partial-depth repairs completed in 1991 on a have successfully demonstrated the use of partial-depth
pavement built in 1965. repairs in pavements where deteriorated areas extend
from one-third to one-half the slab depth. As a result,
In the past, partial-depth repairs were considered only if today partial-depth repairs are used for more joint repairs
the distress was limited to the upper one-third of the slab and at less cost than traditional full-depth repairs.
and the existing load-transfer devices (if any) were still
functional. It was generally believed that deterioration This guide provides the most current information for
extending below the top one-third of the slab warranted a selecting, designing, and constructing partial-depth
full-depth repair. It was also commonly thought that the repairs that extend as deep as the top one-half of the pave-
smaller the partial-depth repair, the better its chance of ment slab. It supplements the section on partial-depth
success and that, with most specifications dictating repairs in the February 2008 resource, Concrete Pavement
Preservation Workshop Reference Manual (Smith et al. 2008).
Figure 1. 20-year-old longitudinal and transverse partial-depth Figure 2. Close-up of partial-depth repair in Hopkins, MN,
repairs in Hopkins, MN (photo taken 2011) constructed in 1991 (photo taken 2011)
Project Selection
Most repair materials used in partial-depth repairs cannot
accommodate movement across working joints and cracks,
load transfer devices, or reinforcing steel without experi-
encing high stress and thus material damage. Therefore,
partial-depth repairs are appropriate only for certain types
of concrete pavement distresses:
• Spalling that is isolated in the upper portion of the slab
and caused by freeze-thaw damage as a result of inad-
equate air-void system, and where the air-void system
of the concrete around the patch is adequate for ensur- Figure 3. View of pavement before core was taken
ing that the life of the concrete is equal to or greater
than the expected life of the partial-depth repair.
• Spalling caused by intrusion of incompressible
materials into the joint or crack.
• Spalling caused by poor consolidation, inadequate
curing or over finishing.
• Spalling caused by localized areas of scaling, weak
concrete, clay balls, or high steel.
• Non-working cracks, either longitudinal or transverse.
• Spalling caused by dowel bar misalignment or lockup,
where the misplaced steel can be removed.
Distresses that are not appropriate for partial-depth repair
include the following:
• Spalling caused by D-cracking or reactive aggregates
such as alkili-silica reactive (ASR), alkili-carbonate
reactive (ACR), ettringite, etc. Figure 4. Core #3 of existing pavement (Figure 3)
Type 2: Repairs of extended length (greater than 6 ft) of Type 1 spot repairs are less than 6 ft along a transverse or
deterioration along a longitudinal or transverse joint (2A) longitudinal joint or crack. When applied at transverse
or crack (2B). joints, Type 1 spot repairs are typically used for pave-
ments in which the existing load transfer devices (if any)
Type 3: Spot repairs that extend full-depth at joint inter-
are still functional.
sections or slab edges for short distances.
It should be noted that when spot repair areas are closer
Type 1–Spot Repairs of Joints, Cracks, and than 2 ft apart, they should be combined.
Spalls
Usually, only about 2 in. of depth is removed to expose
Type 1 spot repairs are generally used for small, isolated sound concrete in the existing joint or crack or at the bot-
areas of deterioration (Figure 6) and are not intended for tom of the repair area. For surface spalls and scaled areas,
long, continuous partial-depth repairs. the boundary of the repair area should be extended a
Figure 6. Type 1 spot repair candidates; left to right: spalling, crack, joint
Preformed
Preformed
Figure 9. Candidates for Type 2 extended-length repair; left to right: longitudinal joint, transverse crack, transverse joint
Payment for the overall repair has two parts: Payment Payment Methods
for the Type 3 bottom-half area is by square foot; the top
The following dialog outlines a general payment approach
based on types of partial-depth repairs. This approach
may be modified to fit a jurisdiction’s preference.
Payment for partial-depth repairs can be determined in
one of two ways: by linear foot of repair area or by square
foot of repair area.
Length/Linear Foot
Payment by linear foot is reserved for Type 2A partial-
depth repairs of longitudinal or transverse joints longer
than 6 ft.
Portland cement concrete materials generally require the Step 1. Determine Repair Boundaries
placement of a bonding agent or grout to enhance the
The first step is to determine the extent to which the exist-
bond between the repair material and the existing pave-
ing concrete has deteriorated and to identify the repair
ment. Sand-cement grouts have proven adequate when
boundaries.
used as bonding agents with concrete repair materials.
The actual extent of deterioration in a concrete pave-
A successful grout recipe used by many states for coating
ment is often greater than the distress that is visible at the
all areas of the repair is described below.
surface. In the early stages of spall formation, weakened
• 2 parts Type I cement planes may exist in the slab with no signs of deterioration
• 1 part water (may be more or less to develop a creamy visible at the surface.
consistency)
During the survey, the extent of deterioration should be
• 1 part sand determined by “sounding” the concrete with a steel pipe,
chains, or a hammer (Figure 13). Areas yielding a sharp
This sand-cement-water grout mixture produces a mortar
metallic ringing sound are judged to be acceptable, while
with a thick, creamy consistency, which helps to fill any
those emitting a dull or hollow thud are delaminated or
small spalls left by the milling process. However, if it dries
unsound. Sometimes it helps to drop a small amount of
out, sand blasting will be needed to ensure a good bond.
sand on the questionable concrete and hit the concrete
The Kansas DOT uses a different approach regarding with a hammer, watching the sand bounce in delaminated
bonding agents. Its approach is to use a more watery mix sections.
2 in.
Figure 14. Deteriorated pavement marked for sawing Figure 15: Saw-and-chip removal
Figure 24. Example of rounded milling with rock saw Figure 26. Vertical edge mill head
Figure 27. Excess chipping from mill Figure 29. Type 3 repair – Removal by milling and chipping
Figure 28. Type 3 repair – Removal with small jackhammer Figure 30. Sweeping loose material
General patch material placement guidelines are as Almost all repair materials require consolidation during
follow: placement. Consolidation provides a more dense mixture
by releasing trapped air from the fresh mix, thereby con-
• Batch in small quantities.
tributing to the overall performance of the patch. Failure
• Consolidate the patch material on larger patches us- to properly consolidate concrete results in poor repair
ing vibrators or vibrating screeds. Smaller patches are durability, spalling, and rapid deterioration. The common
consolidated using small spud vibrators or by-hand consolidation methods are as follow:
rodding and tamping.
• Texture the surface of the repair to match that of the
surrounding slab as much as possible, unless diamond-
grinding is the final texture.
• Floating toward the edge is recommended. It is impor-
tant to work the material away from the center of the
patch and toward the edges to promote bonding . This
action will help pinch the edge of the repair together
with the existing pavement (Figure 40).
Repair Material Mixing
For Type I and Type 3 repairs, the volume of material
required for a partial-depth repair is usually small (0.5 to
Figure 40. Finishing tip: move from inside to outside
2.0 ft³). Small drum or paddle-type mixers with capacities
of up to 2.0 ft³ are often used. Based on trial batches, repair
materials may be weighed and bagged in advance to facili-
tate the batching process. Batches can also be mixed (by
volume) using 5-gallon buckets for each ingredient in the
same manner as continuous mobile concrete feed mixers
that proportion concrete mixes by volume.
Careful observation of mixing times and water content for
prepackaged rapid-setting materials is important because
of the quick-setting nature of the materials. Mixing longer
than needed for good blending reduces the already short
time available for placing and finishing the material. For Figure 41. Placement of repair material
Step 7. Curing
Because partial-depth repairs have large surface areas in
relation to their volumes, moisture can be lost quickly.
Therefore, curing is an important component of the con-
struction process and must be effectively conducted to
prevent the development of shrinkage cracks, which may
cause the repair to fail prematurely.
Figure 47. Sawing following tooling the joint The most effective curing procedure in hot weather is to
apply a white-pigmented curing compound as soon as
placement without causing excessive raveling. The set bleed water evaporates from the repair surface (Figure 53).
time of a mix will help determine the time to saw. Some agencies require that curing compound be applied
at 1.5 to 2 times the normal application rate to prevent
It should be noted that sawing Type 1 and Type 2A joints
shrinkage cracks in the repairs. Moist burlap and poly-
for joint sealing is different from sawing for compression
ethylene sheets may also be used and, in cold weather,
relief. If a compression relief material was used it will be
insulating blankets or tarps may be required, to help re-
removed during joint sealing operations.
tain heat. Curing of proprietary repair materials should be
If complete joint resealing is specified, all Type 1 repairs conducted in accordance with the manufacturer’s recom-
will be widened for joint resealing operations to the same mendations.
width as the adjacent joint. If only the repair area is to be
After the concrete repair has been placed and cured,
sealed, the width of the joint reservoir will be wider than
excess compression relief board is cut (Figure 54).
the crack under the repair. In these cases it is common for
the existing joint reservoir on either side of a Type 1 repair The opening time for traffic is mix and temperature
to be wider than the sealed joint in the repair area. dependent. Generally, compressive strengths of approxi-
mately 2,000 psi are required by most agencies before the
Screeding and Finishing
partial-depth repair is opened to traffic.
Partial-depth repairs typically cover only a small percent-
age of the pavement surface and have little effect on skid
resistance. However, the surface texture of the patch
material should match that of the existing pavement as
closely as possible. Partial-depth repairs are usually small
enough so that a stiff board can be used to screed the
repair surface on each side of the compression relief
material and make it flush with the existing pavement. At
least two passes should be made to ensure a smooth repair
surface.
The final finishing procedure is to paint a sand-cement
grout, the same grout used for bonding, at the edges of Figure 48. Placement of grout at edge of partial-depth repair
10" min.
5" 5" min.
Install 1/4" preformed
Min. 2" compression relief filler
Max. T/2 prior to concrete placement
Remove unsound Coat exposed surface of dowel bar
concrete with 35-lb max. with duct tape for bond breaker
chipping hammer
AREA TO BE REMOVED
Place sand if necessary
10" min. width
Limits of deteriorating concrete
6 ' min. length
Leave in place below top of dowels
Figure 57. Crack or joint repair when deterioration is in the lower half of the slab
• Ensure air and surface temperature meets manufac- • After concrete removal, the patch area is cleaned by
turer and contract requirements (typically 4°C or 40°F sand blasting or water blasting to remove any dirt,
and above) for concrete placement. debris, or laitance.
• Ensure patching does not proceed if rain is imminent. • The patch area is cleaned by air blasting. A second air
blasting may be required immediately before place-
ment of bonding agent if patches are left exposed
Traffic Control longer than specified in the contract documents.
The traffic control plan should be reviewed by field per- Patch Preparation
sonnel prior to construction. Specifically, the following
Verify or ensure the following:
pre- and post-construction traffic-related items should be
verified: • Compressible material (joint/crack re-formers) is
inserted into existing cracks/joints in accordance with
• The signs and devices used match the traffic control contract documents. Joint inserts are typically required
plan presented in the contract documents. to extend both below and outside the patch area by ¼
• The setup complies with the federal or local agency in. (6 mm). When a patch abuts a bituminous shoulder,
Manual on Uniform Traffic Control Devices (MUTCD) or ensure that a form is used to prevent patch material
local agency procedures. from entering the shoulder joint.
• Traffic control personnel are trained/qualified, accord- • Bonding agent (epoxy- or cement-based) is placed on
ing to contract documents and agency requirements. the clean, prepared surface of existing concrete imme-
• Unsafe conditions, if any, are reported to a supervisor. diately prior to the placement of patch material, as re-
quired by the contract documents. If the bonding agent
• The repaired pavement is not opened to traffic until the
shows any sign of drying before the patch material is
patch material meets strength requirements presented
placed, it must be removed by sand blasting, cleaned
in the contract documents.
with compressed air, and re-applied.)
• Signs are removed or covered when no longer needed.
• Cement-based bonding agents are applied using a wire
brush; epoxy bonding agents, a soft brush.
Debonding of Patch
Debonding of partial-depth repair may occur if the bond-
ing grout is placed too early (Figure 65 and Figure 66). The
concrete patch mix material must be placed immediately
after placement of the bonding grout. If the bonding grout
shows any signs of drying, such as a white color, it must
be sand blasted and re-done.
Many states incorporate a 30-day warranty into the
specifications primarily to catch this particular problem.
If a debonding failure occurs, it usually does so within the
first 30 days of service.
GENERAL DESCRIPTION: REMOVE CONCRETE, FURNISH AND PLACE CONCRETE, SAW AND SEAL JOINTS/CRACKS.
AREA TO BE REMOVED
PROFILE VIEW 10'' min. width
PLAN VIEW
<6' max. length
Roadway 10" min.
3
1
min. 2"
1 2
max. T/2
T
JOINT and CRACK RE-ESTABLISHMENT shall be accomplished as quickly as possible to prevent failure.
Type 1 at Joints
1 Joint compression relief for the upper part of the joint will be of equal width to the joint on
either side of the repair. Compression relief will be provided either by installing preformed
joint filler (such as wax-coated cardboard) as wide as the existing joint (¼-in. min.) before
concrete placement or by tooling the plastic concrete, then accomplishing a relief saw cut
(¼-in. min. width) to the full depth of the repair as soon as possible after concrete placement.
2 If dowel bar is exposed, coat exposed area with duct tape as a bond breaker to allow move-
ment of the joint.
$PLTDRVL$
Type 1 at Cracks
3 Preformed compression material such as wax-coated cardboard (3/16-in. to ¼-in. thick) should
be installed as deep as possible in the crack (below the patch area at least ½ in., up to an inch
if possible) to provide compression relief.
WORK TO BE DONE
1 Define removal area and payment based on sq-ft of area to be patched, with a min. depth of
2 in.
2 Remove all concrete including unsound concrete using either saw-and-chip (35-lb max
hammer) or milling. Remove concrete to limits shown in detail, with a min. depth of 2 in. and a
max. depth of T/2 or the top of the dowels. The sides of the removed area must be tapered 30
to 60 degrees from vertical.
3 Prepare surfaces:
- Clean exposed surfaces by sand blasting and air blasting.
- Coat any exposed dowel surfaces with duct tape as a bond breaker.
- Immediately before placing the repair material, apply bonding grout to exposed concrete
surfaces.
4 Restore joints and cracks by installing preformed filler (3/16-in. min.) as described above.
5 Furnish and place specified concrete mix. Finish to grade, slope, and texture. Seal edges with
grout of specified concrete mix. Apply cure.
6 Saw and seal joints and cracks according to specifications.
BASIS OF PAYMENT
$FILE$
• Type 1 partial-depth repairs are based on square feet of repair area. Measurements should be
taken to the nearest tenth of a foot and rounded to the nearest square foot. Minimum size of
repair for payment is one square foot.
• The 30- to 60- degree taper, preformed filler, and sawing and sealing are incidental to Type 1
repairs.
$DATE$
JOINT (2A) and CRACK (2B) RE-ESTABLISHMENT shall be accomplished as quickly as possible to prevent failure.
Type 2A at Joints
1 Joint compression relief for the upper part of the joint will be of equal width to the joint on
either side of the repair. Compression relief will be provided with a saw cut (¼-in. min. width)
to the full depth of the repair (and, if possible, ½-in. deeper) as soon as possible after concrete
placement.
2 If dowel bar is exposed, coat exposed area with duct tape as a bond breaker to allow move-
ment of the joint.
Type 2B at Cracks
3 Preformed compression material such as wax-coated cardboard (3/16-in. to ¼-in. thick) should
$PLTDRVL$
be installed as deep as possible in the crack (below the patch area at least ½ in., up to an inch
if possible) to provide compression relief.
WORK TO BE DONE
1 Define removal area, with a 2-in. min. (T/2 max.) depth, 10-in. min. width, and 6-ft min. length.
2 Using milling and chipping hammer (35-lb max. hammer), remove all concrete including
unsound concrete to limits shown in detail (min. depth of 2 in. and a max. depth of T/2 the
pavement depth or the top of the dowels), tapering the sides of the removed area 30 to 60
degrees from vertical.
3 Prepare surfaces:
- Clean exposed surfaces by sand blasting and air blasting.
- Coat any exposed dowel surfaces with duct tape as a bond breaker.
- Immediately before placing the repair material, apply bonding grout to exposed concrete
surfaces.
4 Restore cracks by installing preformed filler (3/16-in. min.) as described above.
5 Furnish and place specified concrete mix. Finish to grade, slope, and texture. Seal edges with
grout of specified concrete mix. Apply cure.
6 Saw and seal joints and cracks according to specifications.
BASIS OF PAYMENT
• Type 2A (joint) repairs are based on linear feet of repair. Linear measurements should be made
to the nearest foot of repair length.
$FILE$
• Type 2B (crack) repairs are based on square feet of repair area. Measurements should be taken
to the nearest tenth of a foot and rounded to the nearest square foot. Min. size of repair for
payment is one square foot.
• The 30- to 60- degree taper, preformed filler, and sawing and sealing are incidental to all Type 2
repairs.
$DATE$
DESCRIPTION: REMOVE CONCRETE, INSTALL REINFORCING STEEL, FURNISH & PLACE CONCRETE.
AREA TO BE REMOVED
PLAN VIEW PROFILE VIEW
Joint
No. 4 tiebar
Full depth 1/4" min. 12" long
preformed joint filler *T/2
T
Remove
deteriorated
6" min. concrete
$PENTBLL$
No. 4 tiebar
12" long Subbase or Subgrade
Taper edge
WORK TO BE DONE
1 Define removal area T/2 below in-place surface.
2 Remove all deteriorated concrete to limits shown in detail. Taper the sides of the removed area
30 to 60 degrees from vertical with a 35-lb max. chipping hammer.
3 Prepare surface:
- Clean exposed surfaces by sand blasting and air blasting.
- Coat any exposed dowel surfaces with approved bond breaker.
- Immediately before placing the repair material, apply bonding grout to exposed concrete
$PLTDRVL$
surfaces.
4 Furnish and install No. 4 reinforcement tiebars at mid-depth, as shown in detail. Ensure that
there is at least 1 in. of concrete around the bar. Place with an approved non-shrink grout.
5 Restore joints and cracks by installing preformed joint filler such as wax-coated cardboard
(3/16-in. to ¼-in. thick) as deep as possible in the crack (below the patch area at least ½ in., up to
an inch if possible) to provide compression relief.
6 Furnish and place specified concrete mix. Finish to grade, slope, and texture. Seal edges with
grout of specified concrete mix. Apply cure.
7 Saw and seal joints and cracks according to specifications.
BASIS OF PAYMENT
• Payment for Type 3 repairs (bottom half of repair area) is based on square feet of repair area.
Since the repair will have a sloping face, payment should be measured at mid-depth of the
pavement thickness. Measurements should be taken to the nearest tenth of a foot and rounded
to the nearest square foot. Minimum size of repair for payment is one square foot.
• Payment for the top half of the repair is treated as a Type 1 or Type 2B repair, both of which are
based on sq ft. The 30- to 60-degree edge taper will be included in the top half measurement.
• The 30- to 60-degree edge taper, furnish and installation of preformed joint filler (such as
wax-coated cardboard) are incidental to the repair.
$FILE$
$DATE$
AREA TO BE REMOVED
10'' min. width
Limits of deteriorated concrete 2 Sand backfill 6' min. length
$PENTBLL$
JOINT and CRACK RE-ESTABLISHMENT shall be accomplished as quickly as possible to prevent failure.
Type 1 at Joints
1 Joint compression relief for the upper part of the joint will be of equal width to the joint on either side of
the repair. Compression relief will be provided by installing preformed joint filler (such as wax-coated
cardboard) as wide as the existing joint (¼-in. min.) before concrete placement.
2 Joint compression relief for the lower part of the repair (below the top of the dowel bars) will be provided
by extending the preformed material through the full depth of the deterioration and at least ½ in. beyond.
If that is impossible, the sand backfill (see “Work to Be Done,” below) must provide or supplement
compression relief for this area.
3 If only one or two dowel bars are exposed, cut the bar(s). If more than two bars are exposed, coat the bars
with an approved bond breaker such as duct tape.
Type 1 at Cracks
$PLTDRVL$
4 Preformed compression material such as wax-coated cardboard (3/16-in. to ¼-in. thick) should be installed
as deep as possible in the crack (below the patch area at least ½ in., up to an inch if possible) to provide
compression relief.
WORK TO BE DONE
1 Define removal area with a min. depth of 2 in., min. width of 10 in., and min. length of 6 ft.
2 In the top half of the slab, remove all concrete including unsound concrete using either saw-and-chip (35-lb
max hammer) or milling. Remove concrete to limits shown in detail to a max. depth of T/2 or the top of the
dowels. The sides of the removed area must be tapered 30 to 60 degrees from vertical.
3 In pavements with dowel bars, remove deterioration in the bottom half of the slab (below the top of dowel
bars) by sand blasting.
4 Fill the void in the bottom half of the slab with clean sand to provide a form for the concrete patch mix and
to supplement compression relief in this area.
5 Prepare surfaces:
- Clean exposed surfaces by sand blasting and air blasting.
- As described in 3 above, cut or coat any exposed dowel bar surfaces with duct tape as a bond breaker.
- Immediately before placing the repair material, apply bonding grout to exposed concrete
surfaces.
6 Restore joints and cracks as described above.
7 Furnish and place specified concrete mix. Finish to grade, slope, and texture. Seal edges with grout of
specified concrete mix. Apply cure.
8 Saw and seal joints and cracks according to specifications.
$FILE$
BASIS OF PAYMENT
• Short-term partial-depth repairs are paid as either Type 1 or Type 2 partial-depth repairs. The 30-day warranty
may be waived based on the amount of sand needed to complete the repair. A shorter life is to be expected,
depending on the amount of deterioration, and a change to a full-depth repair may be needed.
• The 30- to 60- degree edge taper, preformed filler, and sawing and sealing are incidental to short-term
partial-depth repairs.
$DATE$