Sei sulla pagina 1di 2

CASE kohinoor energy: Turbocharger upgrade

brings economy into plant operations

Ghazanfar Ali Zaidi


General Manager
(Technical) at
Kohinoor Energy Ltd

The original turbochargers installed at Kohinoor Energy Limited (KEL) was founded – There has, however, been a continuous
the Kohinoor power plant in Pakistan in 1994 through a joint venture between the increase in electricity demand, and for the last
had reached their expected service Saigols Group, a multi-industrial group from ten years KEL has been operating as a base
life-cycle. Replacing key components Pakistan, and Toyota Tsusho Corporation, load station, says Ghazanfar Ali Zaidi.
would cause significant costs. Instead a multi-industrial consortium from Japan.
of an overhaul, Wärtsilä offered a KEL is one of the pioneers of the Independent Guaranteed specific fuel oil
retrofit solution which would bring Power Producers in Pakistan. They own and consumption savings
higher efficiency and lower fuel operate a 124 MW power plant equipped The turbochargers originally installed at
oil consumption. A contract was with eight Wärtsilä 18V46 engines having a the Kohinoor power plant had come to the
subsequently made to deliver and install rated capacity of 15.68 MW each, including a end of their life-cycle. Since repairing them
eight TPL 76C turbochargers. combined cycle heat recovery system capable would have become very costly, KEL had
– As fuel prices are increasing of delivering 8 MW through a steam turbine.
rapidly, we felt the need to look for KEL is connected to the national grid and
higher engine efficiency, good reliability is located close to Lahore, the 2nd major
and more generation along with reduced energy-consuming city of Pakistan. The
hazardous emissions, states Ghazanfar Kohinoor Energy power plant was originally
Ali Zaidi, General Manager (Technical) at commissioned in 1997 to meet the peak load
Kohinoor Energy Ltd. demand of the national grid.
“The upgrade has
brought economy into
our operation and the
power plant is now
more reliable.”

to start looking for retrofit options instead,


which would bring higher efficiency and lower
specific fuel oil consumption (SFOC). The Challenge Solution Benefits
The SFOC of the Kohinoor engines were
––Improving the fuel efficiency and ––instead of overhauling ––Extended economic lifetime
measured by Wärtsilä and calculations were reliability of the operation, by replacing the eight ABB VTR 564 of the engines
made for the savings after the installation of the existing turbochargers with new P32 turbochargers ––Reduced fuel costs; even
new turbochargers. Wärtsilä was then able to ones instead of overhauling originally installed at the better than guaranteed
––Minimising downtime and affecting power plant, the engines savings for some engines,
guarantee SFOC savings of 2.5g/KWh, which plant operation as little as possible in were retrofitted with the resulting in lower OPEX
turned out to be one of the major reasons for order to prevent liquidated damages new generation ABB TPL ––Increased annual capacity
KEL choosing Wärtsilä to supply and install the ––Finding a proper installation method 76C turbochargers and thus a significant
on site increase in plant revenue
turbochargers.
––The huge amount of parts needed for ––Lower turbocharger
– We have had a long-lasting healthy the eight retrofits, almost 130,000 kg maintenance costs
business relationship with Wärtsilä, and since in total, of which the turbochargers ––Higher reliability
Wärtsilä is an OEM they understand the weighed 48,000 kg
engines better than anyone else. So because
of the guaranteed SFOC savings we decided
to go with Wärtsilä, despite the fact that proved to us that they really understand their out in issues like water pressure and flow rate
we had received better financial offers from customer’s needs, says Ali Zaidi. adjustments to achieve optimum results.
competitors, explains KEL’s Ali Zaidi. The first retrofit has now completed almost He also recommends other Wärtsilä
8,200 running hours, and the operation has customers to do turbocharger upgrades.
Challenging retrofit schedule been very satisfactory. However, the proper homework must be done
minimising downtime – Wärtsilä guaranteed a 2.5g/KWh first, due to the fact that configurations can be
After the successful installation and trial period reduction in fuel consumption at the alternator complex and there are limitations set by e.g.
of the first turbocharger in December 2012, terminal, and it really turned out to be so. In power purchase agreements.
the remaining seven turbocharger retrofits addition to that, de-rating the engines due to – Going for a retrofit at any plant in the
were completed by the end of December ambient conditions is now almost zero, says a world is a good option, but comprehensive
2013. The retrofit of the remaining seven satisfied Ali Zaidi adding: studies need to first take into consideration
engines took about 15 days each, which was – The upgrade has brought economy into fuel specifications, climatic conditions,
according to the schedule agreed between our operation in the form of SFOC savings, previous running hours of machines, fuel
KEL and Wärtsilä. but also in the form of an annual capacity injection timings, old maintenance records,
– We had to complete the retrofit on each increase. The Wärtsilä 46 engines in our etc. But once this has been done, don’t
engine as quickly as possible, in order to avoid power plant are now more reliable, producing hesitate to do it, concludes Ghazanfar Ali
liquidated damages from the power purchaser. even more electricity. Zaidi.
The completion of one retrofit in less than 15 Ali Zaidi points out that Wärtsilä has been
days was a great challenge. But Wärtsilä really very supportive after the installation, helping

WÄRTSILÄ® is a registered trademark. Copyright © 2014 Wärtsilä Corporation.


Specifications are subject to change without prior notice.

WARTSILA.COM

Potrebbero piacerti anche