Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Managers
Guide to
Successful
Projects
Aligned
with
®
PMBOK
Guide 3rd
Edition
Sturgeon Publishing
Sturgeon Publishing Brent W. Knapp, PMP
.....
Preface
PREFACE
....................................................
Dear Reader -
The Project Management Excellence Center, Inc., is excited to have published this
book titled “A Project Managers Guide to Managing Successful Projects”. We believe it
is the first of its kind in the field of project management.
Just as the Project Management Institute is committed to establishing measurable
standards for the project management professional, The Project Management
Excellence Center, Inc. is happy to help assist professionals with the knowledge
needed to meet those standards.
This book assumes you have at least read “A Guide to the Project Management Body
of Knowledge” (PMBOK®) and have some general project management skills. We
highly recommend that you obtain the PMBOK® if you do not currently have a copy.
COPYRIGHT INFORMATION
....................................................
All rights reserved. Copyright 2005, The Project Management Excellence Center, Inc.
No part of this publication may be stored in a retrieval system, transmitted, or
reproduced in any way, including but not limited to photocopy, photographs, magnetic,
or other record, without the prior agreement and written permission of the publisher.
The author and publisher have made their best efforts to prepare this book. The author
and publisher make no representation or warranties of any kind with regards to the
completeness or accuracy of the contents herein and accepts no liability of any kind,
including but not limited to performance, merchantability, fitness for any particular
purpose or any losses or damages of any kind caused or alleged to be caused directly
or indirectly from this book.
Trademarks: The Project Management Excellence Center, Inc., has attempted
throughout this book to distinguish proprietary trademarks from descriptive terms by
following the capitalization style used by the manufacturer.
Table of Contents
Chapter 1 - Introduction
Introduction ............................................................................................ 1
.....
By reading this book “A Project Managers Guide to Managing Successful Projects”, you
have taken a lasting step in getting a solid understanding of project management methods.
This book will help you gain hands-on experience in proven project management methods
and discover valuable, flexible tools that you can use immediately to ensure the success of
any project in any organization.
After reading this book you will be provided with a broad review of the concepts and
practices used in managing projects effectively in today's business environment. It covers
the basic concepts of the five essential project management processes, defining
requirements, schedules, risk management, and change control. Participants gain an
understanding of how the project management processes are used during the phases of a
project to build a better, more effective project plan.
On completion of this book, you will be able to:
• Define the elements of an effective project charter
• Identify and develop all the elements of a team charter
• Identify the elements of the triple constraint
• Develop a project scope
• Understand the different types of estimates
• Determine strategies for handling change requests
• Learn how to identify, quantify, and manage risk
• Develop, monitor and control schedules
• Understand the importance of a project closeout process
With this book you will get a solid understanding of project management methods. Gain
practical experience in proven project management techniques and discover a wealth of
valuable, flexible tools that you can use immediately to ensure the success of any project in
any organization.
Managing Projects gives you the foundation, experience, techniques and tools to manage
each stage of the project life cycle, work within organizational and cost constraints, set goals
tied directly to stakeholder needs, get the most from your project management team, and
use state-of-the-art project management tools to get the work done on time and within
budget.
Covering the entire project life cycle, this book is built around the latest insights from the
Project Management Institute’s “A Guide to the Project Management Body of Knowledge
(PMBOK® Guide)”, which incorporates information critical to project success.
You’ll learn project management skills through a broad array of practical experiences that
can immediately be applied to your job. This approach yields a comprehensive project
management experience, including the early stages of defining project requirements,
developing work breakdown structures, project change control and closeout.
This book will open the door to more efficient project implementation.
COURSE OBJECTIVES
Project Initiation
• Understanding the role of senior management
• Needs Assessment
• Project selection
• Benefit/cost ratio
• Present value and net present value
• Building SMART objectives
• Developing Requirements
• Project charters
• Project Requirements Document
• Project Planning
Scope planning
• The work breakdown structure
• Estimating
• Schedule Planning
• Network Diagrams - CPM
• Speeding up the Schedule
• Project Management Planning Software
• Cost Planning
• Responsibility Matrix
• Resource Loading and Leveling
• Risk Planning
• Procurement Planning
• Communication and quality planning
Project Implementation
• Baselines
• Developing the project team
• Organizations and team structures
• Managing change
• Managing Risk
• Performance reporting
• Reserves
• Assessing and monitoring project performance
• Earned value
• Sunk costs
Project Closeout
• Scope verification and customer acceptance
• Administrative and contractual closure
• Transferring lessons learned to future projects
.....
e
Co
T im
st
Quality
Resources
Scope
Before we get into any discussion on project management, we need a common definition of
a project. It is a unique effort with limited resources aimed at a specific objective within a
time constraint. The essence of a project is captured here. It is called the triple constraint.
The triple constraint of project management embodies what all good projects are. They
involve Time, Requirements and Resources. Time is the deadline aspect of our projects.
Requirements, or scope are the deliverables that the project will produce. And resources
include the people and materials that we are committing to the effort.
The scope side represents the agreed-upon project work and requirements, the cost side
represents the total dollar cost of the project, and the time side represents the project
duration. Inside the triangle, resources refer to the people and equipment in use on the
project and quality to how close the project is to satisfying client expectations.
What the figure shows is that there is a clear relationship between the scope of a project,
how long the project will take, and how much it will cost. If the scope of a project is
increased once we have established estimates for time and cost, the only way to maintain
the same relationship is for us to increase time and cost.
If time and cost are kept the same, then the other two components suffer. Either resources
are overworked, which may lead to causalities, or quality is reduced, which may lead to
unsatisfied clients. Commonly, both may happen.
Assess Project
Affirms Validity
Needs
NO YES
Continue Establish
Project Plan
Implement
Control Project
Project
Assess Project
Progress
Close out
Project
To serve the triple constraint, we need to manage. We manage the entire cycle of the
process, not just the implementation. And it is important to understand that projects have
iterative cycles; they are not entirely linear.
Let me also offer some insight here on the five planning processes as identified by PMI®—
initiating, planning, executing, controlling and closing. As with the processes in this diagram,
the PMI® processes are iterative. The cycles or iterations in both processes may predicate
change.
A major part of our job is to understand and communicate when and where the change is,
improving our ability to manage. Projects must be reassessed continually as they evolve.
Customers, project managers and organizations all generate change (in scope, resources,
schedules, approaches) throughout the life of a project. Note one other thing. Project
managers in best practice organizations are involved in needs assessments, which we will
talk about shortly. If you are not involved that early in your organization, you are probably
coming in at the second step of the process, even if you are doing it at mid-project. At some
point, project managers need to validate that the project makes good business sense. That
is serving the customer.
Stakeholders in any given project are legion. And the real challenge is that any of them have
the potential to cause us, the project managers, much grief. They can make life wonderful or
inordinately challenging. The trick is to anticipate the challenging participants early so that
they do not catch you off-guard. The other trick is to find the hidden allies within an
organization.
As the project manager, before you are pressed into service on a project, you need to know
whom you will serve. These are the questions that get you started. These are not idle
questions, either. Since competing stakeholders may have competing interests, the project
manager has to know whose needs take precedence. To make this happen on your
projects, you need to work on a master list of who you have to serve; and in some cases,
who you have to serve and in what order.
STAKEHOLDER REVIEW
....................................................
Stakeholder influence is the major reason a project succeeds or fails. I have often heard of
new project managers complain that they did not receive the support they needed to deliver
a project on time, on budget, or to the desired performance level. I later discovered they
had overlooked a key stakeholder or did not identify their stakeholders at all. Managing
stakeholders requires planning, organizing, motivating, directing, and controlling in the
same way they manage a project. In fact, stakeholder management can be thought of as a
project within the project.
A stakeholder is anyone who has a vested interest in the project. Typically, the stakeholders
for most projects will include the project team members, functional managers, other
corporate managers of business or financial groups, the customer, and the end users. Look
also to outside agencies for stakeholders especially if law or special-interest groups regulate
your project.
Some organizational managers do not fit the strict notion of vested interest but still feel they
are stakeholders. The successful project manager will determine who these players are
and include them in his stakeholder management plan. Usually, the unidentified
stakeholder or would-be stakeholders can undermine a project before the project manager
is even aware of a problem.
Identifying the project stakeholders is important, but it is absolutely critical that you discover
their position, that is, whether they are for or against the project and why. A simple
worksheet is located in the Appendix to assist in this process. See Appendix A, Tool 2.
Using the worksheet, identify the stakeholders and check the appropriate column to show if
they are for, neutral toward, or against the project. The next step is to determine the reason
for their position and their strengths and weaknesses relative to their influence on the
project. With this information, the project team can develop a strategy for moving the
stakeholders to a positive position.
The following is a list of steps in the stakeholder management process. The steps for
analyzing stakeholders should be a project team effort. Managing the process is the project
manager’s responsibility.
• Identify stakeholders
• Determine stakeholders’ positions on the project
• Determine the stakeholders’ agenda
• Assess stakeholder strengths and weaknesses relative to their influence on the
project.
• Identify strategy to move stakeholders to a positive position on the project.
• Predict stakeholder reaction to the strategy.
• Implement the stakeholder management strategy
The above list is simple in notion but difficult to implement successfully unless you are
politically aware of the corporate culture and possess effective interpersonal skills. It is
imperative, however for you to manage your stakeholders. Your project successes will
improve significantly if you do.
You just read about who is driving the project. Now we need to know what their needs are.
Every project is created in response to an individual or organization’s needs. There are
internal sources—management, co-workers, and end users. There are Organizational
sources, like an organization’s attempts to change internal efficiencies. There are also
external sources of needs like government regulation, the shifts in the economy and the
marketplace. Many of us, if not most of us have been affected by the cultural influences of
recent technological advances.
Needs for the key stakeholders MUST be addressed for a project to be successful. And
then, they need to be documented. Documentation is key.
Needs drive objectives. We need it. We will aim for it. And if you do not have your customer
and sponsor in agreement on the objectives, there is a serious problem.
The first bullet is often the most difficult. The key is to identify who takes priority in your
organization. Can any stakeholder objectives be dismissed entirely?
If the valid project objective was to pave an Interstate highway, a smart objective would be
more specific. Pave 10 miles of Interstate Highway 10 from mile marker 150 - 160 using the
standard Arizona Department of Transportation process at a cost not to exceed $600,000 by
the end of the month. It is measurable. We concur on what constitutes acceptable road-
paving performance in terms of thickness, strength, look and feel. It is all agreed to by all of
the parties involved, and is actually achievable. That is a SMART objective. What if I said I
needed it done by the end of the week? It would still meet the other criteria, but would not be
realistic. If I said we had a budget of $45,000? It is something any sane contractor would not
agree to.
I understand what many of you are thinking and saying quietly -- I do not even get to set the
project objective. While that may be true, if no one has ever set the objective for the project,
it still needs to be done. Even at mid-project. We need an objective to know where we are
supposed to be going.
Technical
• Detailed
• Physical dimensions
• Performance specifications
• Project team oriented
From needs to objectives, from objectives to functional requirements, and from the
functional to the technical.
The key here is to understand that each step in the process means a leap of faith. Your
printer breaks down and a need has arisen. You should know that needs arise and we
recognize them. Then, we articulate them as objectives. The objective is to get a new
printer. Repair might have been sufficient. The functional requirement? I need a new printer
that works. A used printer could have done the job just as well. Then we go from the
functional to the technical...a HP Color Laser Printer. I may need a printer of that quality. Or
I may just need a cheap printer. Going from the functional to the technical requires expertise
and agreement.
The process again...and this is important: Needs arise. They are recognized, then
articulated...first as functional and then as technical requirements.
After you know what the requirements are, you need to know the environment in which they
will function. And the concerns here are legion. Too much or too little detail. Too much? No
flexibility impedes team creativity/energy, likely to be ignored. Too little/loose? Inconsistent
deliverables, lack of direction for the team, may be ignored. How do we overcome these
problems? We bring the implementers into the definition process as practical, and we
document.
Part of the challenge is to ensure the right level of detail from all of the parties, in all of the
right areas. That is where documentation comes into play (see Appendix A, Tool 3). This
creates a common history and a common framework for how the project can and will evolve.
REQUIREMENTS DOCUMENTATION
....................................................
Documentation is a critical element. You can ask all the questions in the world, but if not
documented properly, all the resulting information will be forgotten or lost. You must ensure
that you are documenting the information in a way that is satisfactory both to you and to
your customer, because the customer will need to approve that documentation as it
ultimately turns out.
Customer relations is an important component of documentation. Who is going to be
responsible for what? What is the chain of command that will exist within the project and
between the project organization and the customer organization? Contract negotiations are
also important. You will need to get documentation for those negotiations—who is getting
what, who promised what to whom. Resource allocations are also important. Sometimes
customers want to know who specifically will be working on their project, and in what
capacities. We must ensure that we give them that information or that we know what their
expectations are.
There is an element of personal growth and development as well. When you document
things, you find out what you do not know. You learn what you need to find out about. It can
be a scary experience—documenting all this information is often a lesson in what we cannot
accomplish and what we cannot do.
(See Appendix A, Tool 4 to view a Basic Requirements Checklist.) As you go through the
checklist, think about which of these are open, unanswered questions with your existing
customers on your current projects.
.....
There are several types of baselines: technical, schedule, and cost. The Requirements drive
the schedule and the overall cost of the project. Cost, schedule, and requirements form the
baseline. That is the measure against which they will judge a project manager’s
performance. Different organizations handle different types of baselines differently.
Do not get pulled into a situation where one type of baseline takes precedence, although in
most organizations it will. Schedule takes precedence over cost. Requirements take
precedence over schedule. For all intents and purposes, they are equal. Once the sponsor
and the customer have concurred on their application, they are equal.
Why is the agreed upon baseline so critical? Because it is the arbiter of what the project is
and what the project is not. If our project is to procure and install 100 workstations around
the office, and that is all the project is supposed to include, the project does not include
updating the computer wiring in the process. It does not include refurbishing the desks.
While in theory those additional projects may make sense as adjunct work, they represent
change. And the baseline establishes what is a change and what is not.
CHANGE MANAGEMENT
....................................................
• External events
• Errors and omissions
• Value-added changes
Where do changes come from? Virtually anywhere and everywhere. As a project manager,
we need to anticipate what will cause change. In change management, a key challenge is
ascribing responsibility, because customers often do not want to pay for change and
organizations are generally somewhat resistant to change. Thus, change can become a
major point of contention. These three drivers represent the causes of most scope changes.
Very few changes are clear, simple, easy-to-follow, order-driven changes. Most are more
subtle. A problem surfaces. Someone neglected an element of the requirement. An
opportunity arises that is too good to pass up. Good change management means there are
points of contact and hopefully processes installed to follow.
One organization that I know in Miami has a change process that details how they will
handle changes driven by natural disaster (hurricanes). And that is given to each customer
at the beginning of the project. That is effective change management, by virtue of knowing
what may drive change.
Conventions
• Documentation
• Communication channels
Building the plans means that we have approaches we can manage. If we do not plan for
change, it will happen without us. (See Appendix A, Tool 5)
There are two extremes in change management. Configuration management takes a
deliverables-oriented approach to change, focusing on modifications to change items or
components. It is forms-driven, extremely time-consuming and demanding on the customer,
the team and the project manager. Change management involves the extremely detailed
breakdown of activities and a contractually oriented adherence to that breakdown.
The antithesis to change management is prototyping. It encourages change, rather than
stifling it. It invites change and works well in fluid, highly conceptual efforts.
The key with a prototype is to know when we are done. We are done with a prototype when
it is ready to do what we want it to do, or when we run out of either time or money.
In both cases? Major issues include communications and documentation. Both have to be
thorough to make the process work.
CHANGE CONTROL
....................................................
The basic objectives of a change control system are to -
• Continually identify changes, actual or proposed, as they occur.
• Evaluate the consequences of the proposed changes in terms of cost and schedule
impacts.
• Permit managerial analysis, investigation of alternatives, and an acceptance or
rejection checkpoint.
• Communicate changes to all stakeholders.
• Insure that approved changes are implemented.
• Update the development process.
YES
Change control is required in a project to eliminate scope creep and to ensure that the
customer and other stakeholders are aware of any changes to the original scope. We
should clearly document the control system and control process in the statement of work
(SOW) and in the project management plan. The change control board (CCB) is a special-
purpose group of three to five functional experts who are responsible for considering
change requests submitted through the project manager. The project manager presents the
requests to the change control board (CCB) along with a reason for the request and the
impact to the project's budget and schedule. If the change control board (CCB) decides the
change request is beneficial to the project, they will make a recommendation to the
customer along with a proposal outlining the benefits and costs. The customer decides
whether to pursue the requested change or not. If he decides to go ahead, then a formal
modification to the contract is written and communicated back to the selling organization.
We make the change and the stakeholders are notified. Finally, once the customer approves
the change request we need to get the appropriate signatures. Do you have all the
signatures necessary to authorize this request?
ESTIMATING FUNDAMENTALS
....................................................
• Order of magnitude
• Budget
• Definitive
When providing an estimate, the project manager should know the level of accuracy and
detail he or she is working toward.
Order of magnitude is a broad estimate often provided early in the project when only the
basic objective has been defined. These are often ballpark, guess, conceptual, or feasibility
estimates. These broad estimates have an accuracy of +75/–25 percent. I have had
students argue “My management will not buy it.” They will say, “Give me a hard number.” If
the original number was a million dollars +75/–25, then say, “Fine, the estimate is 1.75
million.” Management will understand the message you are attempting to convey far more
readily.
The top-down estimate, sometimes called the analogous estimate, is significantly more
accurate. It is based on some historical data, and comparisons with other similar projects
are usually used to develop its costs. The one thing to be cautious about when using
analogy, though, is to make sure the two projects are actually similar. The cost of building a
road in Arizona during the summer is not the same as building the same size road in New
Hampshire in the winter. One other disadvantage of this method is that you can easily
overlook tasks that are required. One project might have some unique requirements that
another one, despite similarities, does not have. This type of estimate is accurate to within -
10% and +25%.
The most accurate method of all is the bottom-up or definitive estimate. It relies on
estimates made at the lowest WBS level and is done by the people responsible for the task.
Once the estimates are completed, the total cost of the project is the sum of the costs of all
the tasks. This type of estimate is accurate to within -5% and +10%.
PROJECT ESTIMATING
....................................................
• Try another approach
• Validate in the marketplace
• Keep records
• Admit—and do not punish—errors
• Review the contract
other organizations were charging for similar work. The average price tag was about $6
million. A thorough review of the contract is what led them to realize that they had actually
not understood the work at all. It was a variety of small facilities within a single location.
Coordinating and integrating those various facilities within that single location was going to
increase the cost by hundreds of thousands of dollars. Had they simply accepted their
original estimate on face value, there would have been a serious loss.
The Work Breakdown Structure (WBS) is a hierarchical description of the work that must be
done to complete the project. It is perhaps the most useful project management tool. When
done correctly, the WBS is the basis for planning, scheduling, budgeting, and controlling the
work of the project. An example of the WBS is shown below.
To begin our discussion of the WBS, you need to be familiar with the terms introduced in the
WBS figure. The first term is activity. An activity is simply a chunk of work. The second term
is task. Note that activities turn to tasks at some level in the hierarchy. A task is a smaller
chunk of work. While these definitions seem a bit informal, the difference between an
activity and a task will become clearer shortly.
GOAL
The terms activity and task have been used interchangeably. Some would use the
convention that activities are made up of tasks, while others would say that tasks are made
up of activities, and still others would use one term to represent both concepts. In this book,
we refer to higher level work as activities, which are made up of tasks.
We also use the term work package. A work package is a complete description of how the
tasks that make up an activity will actually be done. It includes a description of the what,
who, when, and how of the work.
Breaking down work into a hierarchy of activities, tasks, and work packages is called
decomposition. Decomposition is important to the overall project plan because it allows you
to estimate the duration of the project, determine the required resources, and schedule the
work. The complete decomposition will be developed by using the completeness criteria
discussed later in this chapter. By following those criteria, the activities at the lowest levels
of decomposition will possess known properties that allow us to meet planning and
scheduling needs.
This process of decomposition is analogous to the process we all used in grammar school
to prepare a detailed outline of a research paper we were going to write. Despite the
teacher's extolling the value of preparing the outline before we wrote the paper, we chose to
do it the other way around-by writing the paper first and extracting the outline from it. That
won't work in project planning. We have to define the work before we set out to do the work!
Thought process tool. First and maybe foremost, the WBS is a thought
process. As a thought process it is a design and planning tool. It helps the
project manager and the project team visualize exactly how the work of the
project can be defined and managed effectively. It would not be unusual to
consider alternative ways of decomposing the work until an alternative is found
with which the project manager is comfortable.
Architectural design tool. When all is said and done, the WBS is a picture of
the work of the project and how the items of work are related to one another. It
must make sense; in that context it is a design tool.
Planning tool. In the planning phase, the WBS gives the project team a
detailed representation of the project as a collection of activities that must be
completed in order for the project to be completed. It is at the lowest activity
level of WBS that we will estimate effort, elapsed time, and resource
requirements; build a schedule of when the work will be completed; and
estimate deliverable dates and project completion.
Project status reporting tool. The WBS is used as a structure for reporting
project status. The project activities are consolidated (that is, rolled up) from the
bottom as lower-level activities are completed. As work is completed, activities
will be completed. Completion of lower-level activities causes higher-level
activities to be partially complete. Some of these higher-level activities may
represent significant progress whose completion will be milestone events in the
course of the project. Thus, the WBS defines milestone events that can be
reported to senior management and to the customer.
Trying to find a happy compromise between a WBS architecture that lends itself well to the
planning thought process and the rolling up of information for summary reporting can be
difficult. It is best to have input from all the parties that may be using the WBS before settling
on a design. There is no one right way to do it; it's subjective. You will get better with
practice.
ABC Pro j
ec t
Provide Project
Initiate Develop
Management
Project Services System
The work package is the cornerstone of the work breakdown structure (WBS). It is where
work gets done. The rest of the WBS is support for this critical level. In a perfect WBS, these
are all identified with the same number of sets of numbers. All work packages are at the
same numeric level in the WBS. In this example, they are three levels deep. In a great WBS,
they are consistent in size and cover every bit of work. PMI recommends a guideline size of
80 hours of effort, although they can be as small as a few hours in some organizations or as
large as a few months in others.
The verb-object format? For the work package, it helps to clarify. A work package labeled
“Locate contractors” is far more comprehensible than one simply labeled “Contractors”. It
helps us know what we are supposed to be doing.
ABC Pro j
ec t
Control Account Level
Provide Project
Initiate Develop
Management
Project Services
System
One other critical element in breaking down the work is the control account. It is one level
higher than the work package. In other words, if all your work packages are at the 1.1.1
level—as they are here—then the control account level is 1.1. No matter what you call it,
you need a reporting level that will keep upper management from micro-managing your
project. The control account is the current practice.
The control account is not an accounting term. It is a term that highlights that the control
account is an aggregate level where costs are reported back to the organization. It is also
where performance is reported back to the organization.
While we are here—one note. How do you build these? How do you know what goes
where? Most project managers find good examples and re-work them. If you build them
from the ground up, you can do it by breaking the work down from the top OR by identifying
all the work and looking for the natural groupings by function, deliverables and work areas.
But the key is that all the real work is done at the work package level. And all the reporting is
done at the control account level.
PROJECT CHARTER
....................................................
A project charter is a document that formally recognizes the existence of a new project. The
charter gives a general description of the project’s objectives, which are the quantifiable
criteria that indicate completion of the project. An individual with authority must sign the
project charter in order to grant the project manager the authority to spend money and use
the organization’s resources to accomplish project objectives and activities.
Usually the project manager, functional managers, senior managers, and clients all sign the
project charter. However, it is important to have all individuals who will be actively supporting
the project sign the project charter. The reason for this is that it indicates buy in from the
involved parties.
A project charter is not used to manage changes that occur during a project. If large-scale
project changes make the charter out of date, a new charter should be issues rather than
updating the old charter.
The project charter can contain any information that the organization feels is pertinent, but
at the minimum it should contain the following:
• A brief summary of the project scope
• The business or strategic goal that the project was undertaken to address
• A description of the product
• The name of the project manager
• The functional areas supporting the project
• A signature block for all internal stakeholders
• Resources necessary for project completion
• The expected project deliverables
diagram. This is a small part of a plan about conducting a survey. It is a simple example with
a little bit of float, or free time, for that one black square. Can you identify the total project
duration? It is 18 days. Are there any activities that you, as the project manager, are not too
worried about? Probably “Discuss market.” Why? It has 2 “free days” because of the way
the network is laid out.
As you can see, this is nothing more than a sequential relationship. If there are more paths?
The key is simply to add the total duration of each path until you find the biggest total. In this
case, the two paths have duration of 16 and 18 days. The longest of the two becomes the
duration for the project. It is no more complicated than that. In more complicated networks, it
becomes a function of simply adding up more paths—until you find the highest total.
Determine Survey
Objectives
3 3d
Early Start
The early start (ES) of an activity is the least amount of time that must pass from a project
start date before that activity can begin. Finding ES involves making a forward pass through
a network diagram along the longest path toward the activity for which you are estimating
ES. Making a forward pass means starting at the beginning of the diagram and calculating
the duration of each activity preceding the activity for which you are estimating ES. The ES
of an activity is equal to the sum of all duration times for its predecessor activities.
Suppose Activity A is the first activity of a project, so it does not have predecessor activities.
Since Activity A must begin on Day One of the project, it has an ES of zero. Suppose
Activity C is the third activity of a project, so its predecessors are Activities A and B. If
Activity A has a two-day duration and Activity B has a one-day duration, then the ES for
Activity C is three days. Therefore, three days must pass after the project start date before
Activity C can begin.
Early Finish
The early finish (EF) of an activity is the least amount of time that must pass from the project
start date before an activity can finish. As with ES, finding EF involves making a forward
pass through a network diagram. The EF of an activity is equal to the sum of its EST and its
own duration:
EF = ES + activity duration.
Suppose Activity D's ES is four days into the project and that Activity D has a six-day
duration. Therefore, the EF for Activity D is 10 days. The earliest that Activity D can possibly
finish is 10 days from the first day of the project, resulting in the EF.
Late finish
The late finish (LF) of an activity is the greatest amount of time that can pass between the
project start date and the activity finish date without affecting the end date of the entire
project. LF is calculated by making a backward pass through the network. In other words,
LF calculation starts at the end of a project and works backward to the beginning of a
project. LF calculation assumes that constraints are already factored into the network
diagram.
Suppose that you calculated a 50-day EF for an entire project, which means that the project
must be completed by the end of Day 50. The final two project activities are Activities Y and
Z. The latest that Activity Z can finish without disrupting timely project completion is Day 50.
Since Activity Z cannot begin until Activity Y ends, if Activity Z takes exactly 10 days to
complete, then the LFT for Activity Y is no later than the end of Day 40.
Late Start
Latest start time (LS) is the latest time that an activity can start without affecting the end date
of the entire project. The latest start time of an activity is equal to the difference between its
latest finish time and its duration:
LS = LF - activity duration
Suppose that Activity Y has an eight-day duration and has an LF of 40 days before the end
of the project. The LS for Activity Y is 32 days. If Activity Y does not begin by Day 32, then
the project will not finish on time.
START
By Supplies Scrape Old Wall Paper
Clean up Mess
Duration = 4 days Duration = 7 days
FInish
Cut & Size Wall Paper Hang Wall Paper Clean Up Room
Duration = 5 days Duration 6 days Duration = 4 days
If you have trouble following that logic, imagine that each time is 8AM. Buy supplies begins
at 8AM on Day Zero and Finishes at 8AM on Day Four. So when can the next two activities
begin? Day Four. Scrape off old paper begins on Day Four and ends on Day Eleven. Cut
and size the wallpaper has an Early Start of Day Four and an Early Finish on Day Nine.
Dispose of old wallpaper mess has an Early Start of Day 11 and an Early Finish of Day 15.
Hang the Paper has two predecessors. So the question is “When is the earliest it can start?”
Both predecessors have to be done first. So the Early Start of that activity is Day 11. With its
six-day duration, it ends on Day 17. The clean-up activity must wait until both of its
predecessors are complete, so it will begin on Day 17. It finishes—on Day 21.
We now have the Early Start and Early Finish for each activity.
To get the numbers across the bottom, we work the same process in reverse. If the last task
is to end at 8AM on day 21—when is the latest it can start? Right—Day 17. Note they now
have the same thing for an Early Start and a Late Start. That means that last task is critical.
If the latest it can start and still get the project done on time is Day 17...what is the latest
time its two predecessors can finish? Day 17! They have to finish by Day 17 in order for the
project to get done on time. That means that the latest we can finish getting rid of the
wallpaper mess is Day 17...and the latest we can start it is Day 13...But look at the
EARLIEST we can start it. The latest we can start is Day 13. The earliest is Day 11. That
means there is some time to play with there. 2 days of difference. That is two days of free
time or float. This task is not critical. Along the bottom...hang paper has a Late Finish of 17
and an Early Finish of 11. It has no float. It is critical. One more task we need to look at to
make this complete is scrape off old paper. What is the latest it can finish? Here, it is Day 11.
It is driven by the lower of the two numbers. Because if it is any later than that, the project
will be delayed.
Going forward? We carry the high numbers. Backward...we carry the low ones.
EFFECTIVE SCHEDULING
....................................................
This is an assignment on schedule display. Here is a Gantt chart. This is one of the most
common approaches to displaying a schedule. Most of us are very used to seeing this piece
of documentation. We are used to seeing it on our projects, and we use it in our reports. But
there are other options.
There is activity-on-arrow diagramming. It communicates information in an entirely different
fashion. Some people find these diagrams terribly confusing. Others, however, find them to
be a lesson in clarity. Activity-on-node diagramming is something that we are a little more
familiar with—the precedence diagrams you just worked with. It is the way that most project
management software displays the information. There are also others that we do not see
very often—some of the conditional diagramming approaches, such as GERT, the Graphical
Evaluation Review Technique. It allows for circular relationships among activities.
SCHEDULE ACCELERATION:
....................................................
Taking action to decrease the total project duration after analyzing a number of alternatives to determine
how to get the maximum duration compression for the least cost (PMBOK® Guide)
1 window washer can clean a building in 1 week
10 window washers cab clean a building in 1 day
Once a schedule has been created, it might be necessary to reduce activity duration to
ensure that the project can be completed on time. Duration compression is the process by
which a project's completion time is reduced without altering the project scope. While the
project scope should not change, duration compression often affects quality and cost, and
leads to additional risk. There are several methods of duration compression that project
managers can consider during scheduling.
These methods are:
• Crashing
• Fast tracking
• Assigning limited overtime
• Implementing shortcuts
Crashing
Crashing accelerates activity completion by using more resources to complete activities on
the critical path. Crashing alters the duration of activities on the original critical path and can
lead to the creation of a new critical path. Since crashing uses more resources, it often
results in a higher cost for activity completion. Crash plans illustrate crash cost versus
original cost, as well as changes in activity duration. Project managers can use a crash plan
to determine whether crashing is compatible with the project's budget and goals.
It is important to understand that critical path activities are the only activities eligible for
crashing, since crashing other activities will not affect the project's completion date. Before
crashing a project, always make sure that it is a feasible option for schedule compression.
Fast tracking
Fast tracking rearranges activities based on precedence relationships so that those
activities are performed at the same time rather than in sequence. Performing activities
simultaneously reduces project duration.
It is important to understand that fast tracking involves a high level of risk. Therefore, a
project's major stakeholders must be aware of the risks before agreeing to fast tracking.
Because of the risk involved, fast tracking is used only when the other schedule
compression techniques are found to be inadequate.
Assigning limited overtime
Assigning limited overtime to project team members for certain activities can shorten overall
project duration. It is important to carefully consider which project team members to include
when assigning overtime. Too many hours of overtime can lead to burnout.
Implementing shortcuts
Shortcuts might include using a specialized computer program to design a construction
model, acquiring resources based on availability rather than specification, or reducing the
amount of time allotted for product testing. It is important to note that there is risk involved
when using shortcuts. You must be careful when implementing shortcuts, so they do not
have an adverse effect on the final project deliverable.
SCHEDULING ISSUES
....................................................
When you go to use virtually any display, there can be some pitfall as to how you are
presenting the information. Here are just a few of the items that you can run into.
The examples above are just a few things to watch for. With particularly long schedules, you
want to be aware of what we call “network spaghetti.” In the long relationships, with all those
dependencies that are woven into your project, it is very easy to lose the relationships or
forget critical relationships. For project managers who do not like network diagrams, the
Gantt chart is a godsend, but you do need the network. And beware the Gantt time-scale
network diagrams or dependency Gantts you sometimes see in the software. They can be
somewhat deceiving in that the relationships are hard to track. Milestone people sometimes
lean toward “inchstones,” which is putting a milestone at every small incremental step along
the way. And finally, there may be dysfunction among the network relationships that you
have established. Not all relationships are finish-to-start, but they are not all fancy with lead
and lag either. Ensure realism as you build relationships into your network diagrams.
Building a cost estimate is a task that comes in a variety of types, shapes and sizes. The
trick is to know what information you need and where to get it. The information in the left-
hand column is from the PMBOK® and refers to what input is necessary to a good cost
estimate. The WBS—what is the work? Resource requirements: Whose do we need and
how many of them do we need? Resource rates: Who is more expensive? Duration
estimates: How long is this thing going to take? How long has it taken historically? What are
the customer’s time constraints? History? Ours, and that of other organizations published in
other sources.
As soon as you see the term “chart of accounts,” it can be unsettling, because it sounds like
high finance. Do not fear. PMI® defines a chart of accounts as any numbering system used
to monitor project costs by category (such as, labor, supplies, materials). The project chart
of accounts is usually based on the corporate chart of accounts of the primary performing
organization. Who do I report costs to and what is the format? In many organizations, such
information is not available to the project manager.
As these are the key inputs to cost estimates, they ultimately become the inputs to the next
level of process as well...cost management. Since the performance of the cost estimate is
going to be based on our performance in these specific areas, they become extremely
important to our success not just as project managers, but also as cost managers.
2000000
1750000
1500000
1250000
1000000
750000
500000
250000
0
May
March
November
January
July
April
June
August
February
September
October
December
Months
COST MANAGEMENT
....................................................
• Where is the data coming from?
• How is the data reported?
• Does it provide additional insight?
• Can it be misinterpreted?
• Does it tell the story you need to tell?
When it comes to the information you have been looking for, these are the big issues you
need to be looking at. Where is that data coming from? In many cases we get it from
sources that are somewhat less than reliable. Is it coming from a database? Is it being
tweaked by professionals in accounting or finance? Or is it simply being provided by team
members who really are not sure where the cost data is coming from? Or in some cases,
the team members provide the best possible cost data.
One big issue is, does the cost information that we have been gathering provide additional
insight? Does it really give us more information than we had before? Or can it more readily
be misinterpreted? That can create some serious problems throughout the organization.
How often are we getting it? Are we getting it monthly? Does it come with or without any
commentary? Is it data or, as somebody once explained to me, is it information (making the
distinction that data is simply a pile of numbers, whereas information is information we can
use)?
Does it tell the story that you really need to tell? Does it present the information the way it
needs to be presented? S-curves may be appropriate—variances, monthly, cumulative—
you need to be considering this information whenever you are analyzing or presenting cost
data.
.....
STAFFING CONSIDERATIONS
....................................................
• Experience
• Interest
• Personal traits
• Availability
• Productivity
If you do not consider all parameters associated with project team, you will not know how
well the staff will function.
The project manager has to consider all of the performance attributes of the project team.
Some team members are brilliant, and there is little doubt about their performance. Others
leave us with less optimism, and force us into decisions based on limited parameters. In
some organizations, the emphasis is on who is available. In others—it is who will be most
productive. In still others, it is a function of who has done it before. Team formation often
reflects corporate strategy…and we may not even be aware of it.
On all of these issues, more is not inherently better. When it comes to experience, we may
want less experienced people if the project calls for a fresh perspective. As for personal
interest, we do not always want every team member who is excited about a project.
Someone needs to bring perspective along. Sometimes, it is just a matter of who is
available and who will fit in with the team.
All too often, project managers complain that they get no say in the matter. Even if you do
not, you need to have a sense of what your staff shortcomings may be if staff is assigned
from outside or above.
ESTABLISHING RESPONSIBILITY
....................................................
You need an overview of who is doing what or you will not know who to manage and who is
supporting you. This matrix provides that overview. It is a resource matrix. It is easy to
construct. List project activities down the side. List team members across the top. Identify
key functions for each person for each task.
Jayson
Robert
Janice
Janet
Milestone/Task
Buy Paint P R A
Prep Room A P R
Paint Trim A R P
Paint Walls P A R
P = Perform
A = Approve
R = Review
You can probably do a similar type of analysis on your projects. And it provides a wealth of
information.
It is vital that someone have primary responsibility. If two folks have primary responsibility,
tasks will have either too many people in charge, or no one would take charge.
Responsibility matrixes can lead to chicken-egg discussions: they are sometimes built at a
high level for sake of bringing the team on board, but in their technical rendering, they are
built on detail level against the WBS. The key? Make sure the whole team concurs on who
is responsible for what.
It is one thing to identify the right team members. It is another to actually recruit them. The
question here is how do you get who you need? You know (based on the organization, the
project, the resources) who you want. How do you get them? Even the best plan will fail if
you can not win the resources.
We can acquire them through negotiation...which has its advantages. There is the give and
take, the opportunity to present perspectives, and the chance for collaborative win-win
solutions. Of course, if you are a lousy negotiator, you lose.
Some organizations thrive on preassigning resources. There is not much thinking required.
And the project manager can test him/herself with a team of management’s design.
Although not a healthy measure, the project manager may be able to blame someone else
for project failure. Of course, you may get a team you can not work with and can not stand.
If you buy the resources, you definitely have purse-string authority. You know who you are
getting. But, the team may have mercenary tendencies. They may lack loyalty.
Finally, you can beg, borrow, and steal. This is the default setting in some organizations. It is
realistic. You know what you are getting. But then again, you may not get what you need.
One of the keys is to know what resource acquisition strategies work in your organization.
What applies...and what works well.
RESOURCE ALLOCATION
....................................................
Does your resource allocation reflect the best interests of your —
• Organization?
• Resources?
• Project?
Before you read any further think the realities of your world in regards to resource allocation.
You cannot possibly make one person happy without upsetting some of the others.
Competing interests is the hallmark of quality resource allocation. It is one battling against
the other, trying to come to resolution on whose best interests must be served. It is up to you
to balance them.
This goes back to some of the issues we have already examined. We go back and we need
to look at our stakeholders. Look at all the various parties who are participating in the
project. What are their needs? Whose needs are going to take priority over other persons’
needs? Look at the various schedules that are involved and how we can tweak and modify
those schedules. And look at the costs and the cost tables. How are we going to deal with
cost issues when it comes to resource allocations? Is money more important, or are the
people? Is project schedule more important, or are people? Are the organization’s interests
more important, or are the team members’ interests? It becomes a critical issue in resource
allocation, and it is one that you need to work on and resolve. All those needs need to be
considered.
RESOURCE LEVELING
....................................................
The demand for resources can vary drastically throughout a project. Varying degrees of
demand can result in limited productivity and wasted resources. Resource leveling is the
process by which project managers adjust scheduled activities so that all resources are
distributed evenly.
It is important to note that resource leveling can affect activity duration, which ultimately
affects duration for the entire project. During resource leveling, resources might be taken
away from an activity in order to spread them more evenly across the project. With fewer
resources used for that activity, the activity might take longer to complete. The increase in
activity duration might then increase the total cost of project completion.
RISK ISSUES
....................................................
• What risks exist?
• Who knows our risks?
• What may drive risk?
• What risks may drive our project?
If you do not know the risks, you do not know the project. No matter how attractive a project
looks in revenue, the risks may become the show-stoppers.
Early in the project, we deal with risk at an extremely high level. What risks exist almost
universally in your projects? Customer commitment, timetable/schedule risks, previous
experiences, resource coordination (internal and external), time allowed for evaluation of
requirements, technology risks, product maturities risk, geographic distribution risk. All of
these may consistently be resident.
If we know there are always going to be certain types of risks, we should be documenting
the solutions to those risks early on.
MANAGING RISK
....................................................
Just finding the risks is not enough. The project manager has to do something about them.
This is a risk management course boiled down to a single page. It is also the approach
recommended in the 2000 edition of PMI®’s Guide to the Project Management Body of
Knowledge.
Risk planning is the development of infrastructure and support for risk management. It is
knowing how you will approach the risk management process.
Risk identification: What are the risks? For setting up a project website, for example, what
are the risks? Non-functional links. Difficult connections. Weak communications
infrastructure. Poor navigation. We need to identify the risks.
Qualitative risk analysis is setting risks into relative categories of high, medium and low to
allow for quick assessments of relative severity.
Quantitative analysis: We can quantify risks based on their potential value and the
probability of their occurrence.
For risk response planning, the PMBOK® Guide stresses that the four real responses are
avoidance (do not do it), mitigation (control it), deflection (give it away), and retention (face
it). These strategies give you options on how you can actually manage your risks.
And finally, the last step? Risk monitoring and control. Doing what needs to be done to
follow through and implement the risk plans.
RISK TOOLS
....................................................
Risk Management Planning
• Planning meetings
Risk Identification
• Documentation reviews
• Information-gathering techniques
• Checklists
• Assumptions analysis
• Diagramming techniques
Qualitative Analysis
• Risk probability and impact
• Assumptions testing
• Data precision ranking
Quantitative Analysis
• Interviewing
• Sensitivity analysis
• Decision trees
• Simulation
Risk Response Planning
• Response strategies
Risk Monitoring and Control
• Response audits
• Reviews
• Performance Measurement
As with most aspects of project management, risk is rife with tools…there are planning tools
like meetings and risk identification tools like brainstorms. For qualification, we have tools
like internally set metrics for high, medium and low. Quantification tools like Monte Carlo
simulations afford the ability to look at the range of possibilities.
The key is to use the right tool in the right situation. With Monte Carlo, for example, the tool
uses iterative simulations to examine ranges of options and possibilities. If we have access
to the data and knowledge of how to use the simulations, Monte Carlo is wonderful.
Otherwise, its output becomes a work of fiction.
The point? Thinking about risk tools? It is the same as with most project management tools.
Get the right tool for the right situation.
As project managers, we are always concerned about the issues relating to evaluation and
control. Management frequently expresses concerns about evaluations. They want reports.
Formal reports. They want information. We, by contrast, as project managers, frequently
lean toward control mechanisms. We want to manage at the personal level. We want to
facilitate team members and their experiences.
That is the core difference between evaluation and control. Evaluations are planned events.
They are detailed. They are expensive to conduct. They take time and energy. Control steps
are small and incremental. They are the day-to-day of personnel management. We need to
allot time for both in the project day…but if you are ever wondering which takes more
time…it is definitely evaluation. Let’s look at a key evaluation tool.
EARNED VALUE
....................................................
What’s the dollar value of the work scheduled as of today? (planned value—PV)
What’s the actual amount spent? (actual cost—AC)
What did the organization plan to spend for the work performed as of today?
(earned value—EV)
Comparing planned cash flow with actual cash flow has it uses, but it does not tell you
whether the project will be over or under budget. To get the true picture of cost
performance, the planned and actual costs for all completed tasks need to be compared.
This is accomplished with a technique called earned value management. Earned value
management uses cost data to give more accurate cost and schedule reports. It does this
by combining cost and schedule status to provide a complete picture of the project. For
example, projects can be ahead of schedule (good), but over budget (bad). Alternatively,
they can be ahead of schedule (good) and under budget (good).
All EVM control account plans must continuously measure project performance by relating
three independent values: the planned value, the earned value, and the actual costs
incurred.
....................................................
Question Answer Acronym
Planned value (PV) = portion of approved cost estimate planned to be spent on the activity
in a given period.
Actual cost (AC) = total of costs incurred in accomplishing work on the activity during a given
period.
Earned value (EV) = value of work actually completed.
Interpretation of EV: "Task A, which I was supposed to complete today, is scheduled to cost
$1,000. I have completed only 85 percent of this task. Thus, I have completed $850 worth of
work, which is my earned value (EV)."
With those three key pieces of information, we can use earned value to evaluate change—
to see if anything has changed and to manage future change.
By the middle of the second quarter, it may have looked like we were seriously
underspending here. The actuals were well below what was scheduled to have been spent.
But the actuals were tracking very closely to the work that was done. Which is what we
would hope for…or expect. As those ultimately will determine how well we do.
Most of us are not rewarded for spending money on time. We are rewarded for spending
money on the work it was supposed to accomplish.
The three pieces here again are…the planned…the budgeted cost of work scheduled…the
actuals…what we spent…the actual cost of the work performed…and the earned
value…the budgeted cost for the work performed…what we planned to spend…for what we
did.
In this diagram, the fact that all three lines converge is considered a very healthy sign. It
means we are on time and we are spending according to plan, and according to the work.
The following calculations are used during earned value analysis:
• Schedule Variance (SV)
• Cost Variance (CV)
• Cost Performance Index (CPI)
• Schedule Performance Index (SPI)
Using the cost figures as the basis for schedule measurement is useful because it takes into
account the number and size of tasks that are behind schedule. That means if 10 concurrent
tasks, each worth $25,000, are all one week behind schedule, the scheduled variances will
be larger than if only one of those tasks is one week behind schedule.
Schedule variance (SV) = EV - PV
Interpretation of SV: "As of today, I was supposed to have done $1,000 worth of work on
Task A (PV). I have actually done $850 worth of work (EV). Thus, I am behind in my
schedule by $150 worth of work (SV)."
The formulas for cost variance (CV) and schedule variance (SV) will yield either a positive or
negative numeric value. If the value is positive, then the project is under budget and ahead
of schedule; if negative, then the project is over budget and behind schedule.
It is common to have a negative cost variance (i.e., to be over budget) but to have a positive
schedule variance. This means that although you have overspent at that point, you are
ahead of schedule. So the project is not necessarily in trouble. It may mean that you were
able to begin some tasks sooner than planned.
PROJECT PROGRESS
....................................................
• Do your approaches to monitoring and control match the size of the project?
• Do they match the personnel?
• Do they deal with the organizational issues?
• Can you actually manage them?
I have to say, I have seen some pretty remarkable control processes. They range from the
sublime to the ridiculous. Some organizations create incredibly complex and ornate systems
to monitor, track, and evaluate projects. Others have no tracking mechanisms required
whatsoever. The trick is to ensure that yours matches the organizational, personnel, and
personal tolerances that exist in your project.
That is no easy feat. You need to evaluate and assess what you can handle and what your
project mandates. If the organization demands far more evaluation than the project merits,
you may want to challenge it. If the organization does not require proper tracking, you still
should consider a tracking and control approach that matches your project needs. It is a
matter of balance.
TYPES OF ORGANIZATIONS
....................................................
The types of controls that are put in place are frequently driven by organizational demands.
The organizations depicted above are from the Guide to the Project Management Body of
Knowledge (PMBOK® Guide), and they represent the extremes in terms of where project
management functions
The one extreme is the classic functional organization... “Any organizational structure in
which staff are grouped hierarchically by specialty” (according to the PMBOK® Guide). It is
conventional line authority. Stovepipe management. Often territorial in nature, functional
managers may have “their own way” of doing business. Here, the project manager is
challenged, battling against the territories.
Chief
Executive
Functional Matrix
Chief
Executive
Projectized
The opposite extreme is the projectized organization…The PMBOK® Guide refers to this as
“Any organizational structure in which the project manager has full authority to assign
priorities and to direct the work of individuals assigned to the project” Only a few
organizations adopt projectized cultures because of expense and loss of efficiency splitting
apart the conventional functional organizations.
Why show you the extremes? So you have a sense of where your world falls in-between.
Chief
Executive
Strong Matrix
Manager of
Functional Manager Functional M anager Project Manager
Project
Staff Staff Manager
Project
Staff Staff Manager
Project
Staff Staff Manager
Chief
Executive
Weak Matrix
These are the more classic project environments. These are matrix environments.
The matrix is the most common project management organization. This is where most
modern project management organizations function. In fact, most are actually weak matrix
organizations. Very few organizations have been able to wrest financial tracking from the
functions and hand it over to the project managers.
The difference between weak and strong is who is responsible for financial tracking and is
perceived as generating revenue for the organization. In a weak matrix, the functional
organizations get credit for profit and loss. In the strong matrix, that responsibility rests with
the project managers.
The Project Management Institute® also recognizes the “balanced matrix” where the
authority is delicately poised between these two structures.
But for most of us. It is a weak matrix world, which means a lot of long-term cooperation with
the functional management of our organizations.
In many cases, we do not realize what it is going to take to get people moving in the project
environment. In the matrix environment, some people just are not motivated. We need to be
aware of the keys to managing borrowed resources. Are we looking at the employees as
valued employees? Do the employees really know what their role is and know what they are
contributing to the project? Does management know that the employees are contributing as
well? In many cases, employees and resources find themselves in a situation where they
really do not see the value of what they are doing. You need to be communicating that value
to your team members.
Are the various bosses that are involved in the matrix environment communicating with
each other? Do they all know what they are contributing and what the other parties are
contributing? Do the employees have their priorities—from you and from their functional
managers as well? All this information needs to be integrated to properly manage borrowed
resources.
type, you might consider another to get the job done more effectively. Each has its
advantages.
Scheduling
Task efficiency
Structuring the team establishes the framework in which the team will ultimately operate.
Each team structure has different implications. In Isomorphic, the team takes on the same
shape as the project, with individuals or subteams responsible for specific activities. It is
good for individuals who can do their jobs but are lousy at synergy.
On specialty teams, the individuals and subteams share responsibility for activities, based
on their capabilities. Higher synergy is generated. It is good for a team that works well
together with balanced skills.
Dave Frame’s book “Managing Projects in Organizations” goes into more depth on each of
these teams. The key is that you match the team to the need. The egoless team is
assembled for the greater glory of the effort’s objective; no specific leader; working with no
regard for the individual.
Surgical teams need one highly skilled person (“surgeon”) leading the effort to do specific
tasks with support staff. Surgeons often get most of the credit, the project manager serves
as the facilitator. Is it good if you need staff development and you have a single brilliant team
member.
There are some de facto teams that form on their own and have no formal roles assigned.
Individuals take on specific roles and responsibilities based on their activities and perform
well together as a team. Individual development is often not emphasized.
In all cases, the key is to pick the team structure that complements the skill sets of the
people involved.
COMMUNICATION TOOLS
....................................................
• Meetings
• E-mail
• One-on-one
• Phone calls
• Fascimiles
• Memorandums
• Letters
• Typed
• Handwritten
• Video conferences
• Telephone conferences
This is a rather substantial list of communications tools. As with tools in any toolkit, some
are appropriate at different times than others. And your choice of which to use may largely
depend on how many team members you have.
If you have only yourself and one other team member, you have only one channel for
communication. One-on-one will probably suffice. Four team members? There are SIX
communications channels to be maintained. 10 team members? 45 communications
channels. Time to start looking at conferences and e-mail.
And the reason that is important is that it takes that bit of knowledge to know which of these
tools is going to be appropriate for your project. As Marshall McLuhan was quick to point
out, the medium is the message.
• Bureaucratic
• Coercive
• Reward
The most common complaint of project managers is that they have enormous responsibility
with no authority. There are myriad types of authority out there...and project managers need
not rely on formal authority.
Chief
Executive
Functional Matrix
Some of these authority types are from the basic leadership books, while others are from
the Guide to the Project Management Body of Knowledge. What all three resources
emphasize is that there are a lot of types of authority we can draw on.
Yes, there is real, formal authority…like the CEO has.
And there is referent, as well...which is authority handed down by reference from someone
with real formal authority. Authority by virtue of a relationship with someone in the
organization with power.
We have authority over vendors when we control the purse strings or money.
There is expert authority... Technical authority derived from understanding a particular
subject matter, like an expert in Microsoft Project®. But when the paradigm on expert
authority changes, the level of authority changes significantly.
Charismatic authority is another key. It is derived from the ability to obtain influence via
personality (for example, to motivate and inspire others to take action).
Ever known someone who knew your organization better than you do? They have
Bureaucratic authority. Knowing the system.
Some managers derive coercive authority through threats...while others derive reward
authority by providing opportunities for others.
With all these different types of authority at the project manager’s disposal, the options...and
opportunities...are legion.
DEPLOYING AUTHORITY
....................................................
• Leading
• Communicating
• Negotiating
• Problem solving
• Influencing
It is not just a function of having authority...it is a function of using it. PMI ascribes to these
key leadership traits, that some folks have re-ordered into the acronym of
“PLINC”...Problem-solving, Leading, Influencing, Negotiating and Communicating.
To succeed in USING authority, the idea is to maximize the use of those skills you do best.
If you identified that you have purse-string authority in the last lecture, then this is where you
decide how to use it. You can use it to lead through incentives. You can use it to
communicate the relative importance of a message by attaching monetary value to it.
Having potential authority is not enough. That authority must be deployed.
These are core competencies of project management, and there will be some that you use
to deploy authority better than others. One idea or ideal is to ensure that you know what
your strengths are and find allies to help work through your weaknesses.
The point here is to know that our team members will not naturally recognize authority. They
will recognize it when it is deployed well, and these are the different means by which we
highlight and illustrate our authority.
In any management role, it is important to select styles and approaches that are appropriate
to you. I am sure a lot of you can empathize with an experience I had working in an
unfamiliar environment. I was told that the team members I was working with were
“different” from other people I had worked with in the past. These team members were going
to be a special group and required a different style of management than that to which I had
become accustomed. I worked very hard to learn their environment, to learn their
conditions, and I changed my management approach altogether. I failed miserably.
You can only build authority with skills that you have. Do not try to rely on different tactics,
styles, and approaches with every group. Work within the context of your personal strengths
and your personal weaknesses. While you play to your strengths, you need to recognize the
organizational ties you maintain. The organization needs you to work within the context of
their approaches to management and their leadership protocols. You need to work within
the environment. And remember: it is an art, not a science. There are no specific formulas
that are going to make this easy for you. Work with what you know.
Team members will not have a sense of accomplishment if they do not know what they are
supposed to accomplish.
Different parts of the organization have different expectations. What does the organization
want? Perhaps financial gain, customer satisfaction, management satisfaction, public
relations.
What does the customer want? Increased capabilities, clearer organization, end-user
delight, regulatory conformance. Customers also look to their ability to use the product or
service for their success.
What does your team want? New skills acquired, new capabilities, image enhancement, and
a host of personal successes as well.
In some instances, there is the perception that one person’s success is another person’s
failure. If that is the case, then we have an obligation to identify whose success is whose,
and how we will resolve that issue.
The classic story is one of the project manager who had completed a successful effort, with
customer and organizational satisfaction and buy-in, but continued to hammer on the
success with the customer so long and with such vigor that the customer eventually tired of
the project manager’s presence. Out of the hand of victory, the project manager was able to
snatch a defeat!
The sooner we define the parameters of success for all concerned, the sooner we can
achieve it.
PERSONAL CLOSEOUT
....................................................
• Conduct public relations
• Look to the future
• Document success
• Track team members
• Facilitate team member transitions
SELF-
ACTUALIZATION
Pursue Inner Talent,
Creativity, Fulfillment
SELF-ESTEEM
Achievement, Mastery.
Recognition, Respect
BELONGING - LOVE
Friends, Family, Spouse, Lover
SAFETY
Security, Stability, Freedom from Fear
PHYSIOLOGICAL
Food, Water, Shelter, Warmth
Success is often a personal experience. What do team members want out of a project?
What rewards do they seek?
Maslow, the creator of the famed “hierarchy of needs” posited that different people are at
different stages on the hierarchy.
Some simply need to feel safe, while others already feel safe and have their social needs
addressed and are looking more at self-esteem. This concept, which is tested on the PMP®
exam, goes to the idea that people have different needs based on what needs have already
been addressed. In the ideal, we are setting up an environment where team members can
self-actualize...where they can achieve well.
Herzberg argued that if you want people to feel successful you have to motivate them. And
he felt motivation was closely tied to opportunity. Give people the opportunities (like those in
Maslow’s hierarchy) and they will be motivated. Toward the end of the project, this is doubly
challenging. The key, according to Herzberg, was not to shower them with money or
trinkets, but to give them chances to be more than they are.
Why discuss this now? At the end of the project, we declare successes. Or are declared as
failures. It is often up to us to make the distinction.
Successes need to be documented for both our interests and our organizations’. Without
documentation, insight is lost.
And public relations—PR—is important as well. We can do it for both the project and the
team. They need recognition and credit, too. Public relations does not necessarily mean
sending out press releases. It may simply be talking positively about your project in the
organization. Those who are obsessed with communicating negatives about their project
will find that others pick up on the negative tone. As the project managers, we set the tone.
.....
ADMINISTRATIVE CLOSEOUT
....................................................
Input
• Performance measurement documentation
• Documentation of project products
Tools
• Performance reporting tools and techniques
• Project reports
• Project presentations
Output
• Project archives
• Project closure
• Lessons learned
The project is not over until the paperwork is complete. And in most projects, by the time we
hit administrative closure; team members are running for the door. We cannot afford to let
that happen. Customers have expectations right through administrative closure, and
improperly done, we run the risk of customer dissatisfaction.
Closure is supposed to be structured. In many projects, it is when people simply abandon
the project. To keep that from happening, we need to ensure that others know the value.
That they understand how the data will be used and why it is important. They also need to
know the data has value. On the outputs, the tragedy is that they are often stored on a shelf
and forgotten. Never dragged out again until it is time to throw them away. The more we can
do to build lessons learned into our systems, through the project management software,
through the processes and templates the more we do to ensure that we build our
organizational memory.
CONTRACT CLOSEOUT
....................................................
• Documentation
• Contract
• Supporting schedules
• Approved changes
• Technical documentation
• Financial documentation
• Procurement audits
• Contract file
SCOPE VERIFICATION
....................................................
• Did the project meet the stated scope?
• Is there sufficient documentation to prove it?
At the beginning of the book, we talked about setting objectives…clarifying the work to be
done. At the end, it is just as important. Even if everyone seems happy, it is important to
verify that all the work is done—just in case.
In both project and customer organizations, there are changes. Management changes,
project management changes, approach and vision changes. All of these may change the
potential influence of a given project for the better or worse.
Scope verification is the only documentation that is going to count in terms of proving
customer satisfaction. Without this kind of thorough reassurance that the deliverable met the
scope, the project cannot be considered complete.
In some cases, a customer may express satisfaction with the deliverables, only to change
his/her perspective at a later date. Or a different customer may replace the PM’s contact on
the project and have a different set of values. That customer may go back to ensure that the
deliverables were provided as promised. Without a clear verification that the scope of the
project was met, there cannot be proper closure.
ORGANIZATIONAL
....................................................
At the end, as at the beginning, the question needs to be asked—does this project make
sense in our organization. Does it change our capabilities and/or competencies.
Even the best projects are bad if they are not in line with what the organization should be
doing.
Some organizations refer to the organizational ‘fit’ as “portfolio management.” Some
organizations work on nothing BUT portfolio management. The key is to know what the
portfolio really is. And to ask the question as to whether or not the portfolio is influenced in
any way by the latest accomplishments (or failures).
Working within an organization’s capabilities does not mean that organizations should
refrain from expanding their strategic perspective. It does mean, however, that they need to
pursue directions that are within the framework of their existing capabilities.
• Can we serve this customer base?
• Will we get anything from this?
• Can we do it?
This goes back to the very first lesson you learned in this book. What is a project? We need
to make sure that when we apply project management, we are applying it appropriately—we
are applying it to real projects. You are going to achieve your best success that way when
you apply it to projects rather than applying project management to every effort that comes
through the door. The greater the consistency of application, the greater the opportunities
for success, because you become repeatable—you are able to do the same things over and
over again and able to achieve success consistently. And if you are following practices that
everybody can recognize as best practice, there is a better chance you will be able to
replicate success.
The last two bullets really do work together: applying project management progressively and
applying best practice. That means watching what other people are doing and learning from
them. Keep your eye on the trade journals for some of the latest activities that are going on
in project management. It is a very progressive practice. New practices are being applied
every single day. It is a good idea to keep your eyes wide open!
LESSONS LEARNED
....................................................
When creating lessons learned make sure that they are -
• Timely
• Relevant
• In context
• Detailed
Lessons learned. Lessons learned are the organizational memory. (See Appendix A, Tool
9).
In this book, you have gradually, through the readings, built up a database of more than a
dozen “lessons learned.” The key now is to find a way to actually implement them. The key
is to explore and find ways to put them to work.
That is the essence of a good lesson learned. It captures more information. It provides
specific guidance. It is reviewed and followed up on. It is applicable and applied. And like the
data you’ve generated here, it is not all bad news. Much of it is good news. Tricks you can
apply...new ways of doing business. That is where the victories are achieved.
.....
Appendix A - Project Management Tools
Tool 1 - Project Plan Outline ................................................................ 75
Tool 2 - Stakeholder Analysis .............................................................. 77
Tool 3 - Project Requirements Document ............................................ 79
Tool 4 - Basic Requirements Checklist ................................................ 81
Tool 5 - Change Request Form............................................................ 85
Tool 6 - Communication Plan ............................................................... 87
Tool 7 - Closeout Procedures .............................................................. 89
Tool 8 - Final Project Report ................................................................ 93
Tool 9 - Lessons Learned .................................................................... 95
Management Summary
Executive summary
Project charter
PM designation letter
Proposed solution
Milestones
Acceptance criteria
Contract conditions
Budget/finance agreements
Customer role
Project objective
Project scope
Deliverables
Overall description
Components
Services
Third-party deliverables
Project Requirements
Statement of work
WBS
Resources
Internal organization
Customer organization
Third-party organization
Project team
Roles and responsibilities
Risk Plan
Assessment
Mitigation strategies
Schedule
Customer schedule
Project plan schedule
Milestones
Reporting
Internal
External
Regulations and Standards
Evaluations
Status reporting
Customer reporting
Supporting Plans
Implementation
Documentation
Hardware
Software
Service
Finance
Integration
Customer training
Internal training
Quality assurance
Subcontracting
Risk management
Testing
Acceptance
Safety
Transition
Life cycle management
Configuration management
Support Documentation
TOOL 2
Stakeholder Analysis
BACKGROUND/SUMMARY OF PROJECT
COMMENTS
PROJECT OBJECTIVES
COMMENTS
PROJECT PHASES/DELIVERABLES
COMMENTS
KEY MILESTONES
COMMENTS
ASSUMPTIONS
COMMENTS
RISKS
COMMENTS
INTERRELATED PROJECTS
COMMENTS
ACCEPTANCE CRITERIA
COMMENTS
SIGNATURES
COMMENTS
REVIEWS
COMMENTS
COMMUNICATION PLAN
COMMENTS
FINANCIAL ANALYSIS
COMMENTS
TOOL 4
Basic Requirements Checklist
q Authority
• Who’s in charge here (who’s the PM)?
• Who is in charge of the project manager?
q Market
• What’s the anticipated price?
• What consumer market is targeted?
• What are the customer benefits?
• Who is the competition?
• What competitive advantage does it present?
• How does it differ from other similar products?
• What research has been done on the product and its customer base?
• Are there existing market surveys?
• What is the intended market?
• What are the advertising plans?
• What is the market entry strategy?
• Could it be used in other market segments?
• What is the appropriate sales channel? Distribution methodology?
• Are there discount plans?
• Have you conducted a trademark search?
• Is this the only product of its kind?
• Why hasn’t the product been introduced before?
• Why are you interested in the market you’ve selected?
• Why did you select this product?
• What will people love? Talk about?
• What do you want people to experience in using this?
• What is the perceived benefit of this product?
• What is the value added for the consumer?
• What’s motivating you in this market?
• What’s the next step in the market strategy?
• Are there market alliances or partnerships?
• Is there legal liability? To what degree?
• Do we share liability with any partners?
• Have you conducted a patent search?
• What’s the planning schedule?
Tool 4 Basic Requirements Checklist
• What’s the development schedule?
• What’s the volume for the initial rollout?
• What is the rollout schedule?
• What’s the anticipated production life?
• What production facilities are available?
• What is the organization’s conventional product or service life cycle?
• How much of our manufacturing capacity will this consume?
• Where will it be manufactured?
• What internal resources are available?
• Are there supporting vendors and subcontractors?
• Is engineering staff available for modifications?
q Budget
• What’s the budget?
• What’s the cost to build?
• What’s the anticipated price to the consumer?
• What’s the volume?
q Capability
• What does it do?
• How does it work?
• Does it use any breakthrough technologies?
• How is it used?
• How can it be misused?
• Are there any uses that might be dangerous to children? Adults? Pets?
• Is it safe? (For everyone? Heart patients?)
• How easy should it be to use?
• Is the product oriented primarily or exclusively for right- or left-handed people?
• Does it have varying levels of capability based on the usage environment?
• Are there specific products that can or cannot be used with it?
• How does it function?
• Has it been tested? Will it be? How?
• Is there a prototype?
• How will it be built?
• Are there specific environmental requirements?
• Can the product be recycled?
• Is it single-location-oriented, or is it portable?
• Are there supplemental products to support it?
• Are there peripherals?
• Can it be used in conjunction with other products developed by us?
• Can it be used in conjunction with other products developed by other firms?
• Are upgrades available?
• Will it be compatible with the upgrades?
• Will there be more than one model? What other models are there?
• Are repair parts available?
Tool 4 Basic Requirements Checklist
• Can it be repaired by the “average” user?
• What repair cycle will be used to implement repairs?
• What are the storage requirements?
q Appearance, Capacity, and Functionality
• What does it look like? (Draw it for me!)
• What color?
• What size? What dimensions?
• What weight?
• Does it have adjustable capabilities? (Speed? Physical action?)
• Will all the products be identical?
• What’s it made of?
• How is it constructed?
• What are the key components?
• How will those components operate and interact?
• Can we use those components in other products or services?
• Do we already produce any of those components?
• Can this product serve as an upgrade for existing products?
• How will they integrate?
• Will the components be readily available?
• What are their dimensions?
• What are their construction materials?
• What are its mandatory performance capabilities?
• Is it powered?
• By what source?
• Are there alternative sources?
• Does it have a limited life span? What is it?
q Regulation
• Does it meet regulatory requirements?
• Does it meet industry requirements?
• Does it meet UL requirements? (Should it?)
• What’s the life span on the power source?
• What customer criteria must the power source meet?
• Are there limitations on the decibels the unit can produce?
• Are there limitations on the vibration levels of the unit?
• Will the power capabilities be within manageable levels for the “average” user?
q Support
• Is there computer support?
• Is any programming required either before production or by the user?
q Training
• Will auxiliary training be required?
• How much training is required?
Tool 4 Basic Requirements Checklist
q Documentation
• Is supporting documentation required?
• What types of documentation?
• Are formats required for that documentation?
• Will the documentation be developed in any languages besides English?
q Storage and Retrieval
• What are the storage requirements?
• How will the product be packaged?
• Are there additional products you want sharing the limelight with this one?
• If so, how will they help you achieve your vision?
• How will delivery be accomplished?
q Maintenance
• How will this product/system/service be maintained?
• What warranties will it carry?
• What service networks are required?
• What off-the-shelf support is available? Will be available?
• Are there disposal issues?
• How will it be recycled?
TOOL 5
Change Request Form
ORIGINATOR DEPARTMENT/COMPANY
PROPOSED CHANGE
BASELINE DESCRIPTION
CHANGE DESCRIPTION
RATIONALE
MODIFIED ACTIVITIES
WBS NO. ACTIVITY NAME/TITLE
OTHER REFERENCES
Tool 5 Change Request Form
APPROVALS
NAME (PRINT) SIGNATURE DATE
IMPACT REVIEW
MEETING DATE
TECHNICAL IMPACT
BUDGET IMPACT
SCHEDULE IMPACT
PERFORMANCE IMPACT
CONTRACT IMPACT
Deny
CUSTOMER DECISION
COMMENTS (IF APPROPRIATE)
Approved
Tabled
Disapproved
CUSTOMER SIGNATURE
NAME (PRINT) SIGNATURE DATE
EXAMPLE
E091498D E-mail sent September 14, File description cross-referenced in document control
1998, was deleted
V012399C Voice mail sent January 23, File description cross-referenced in document control
1999, was stored in a computer
reference
DOCUMENT CONTROL
Code Description Source Name
TOOL 7
Closeout Procedures
2.0 SPECIFICATIONS
Include updated technical plans. Reference any long-form diagrams or support documentation in
Appendix A.
3.0 SCHEDULE
Assess major areas of delay and acceleration. Reference Gantt charts and network diagrams in
Appendix B, showing baseline performance versus actual performance.
5.0 CLOSEOUT
Insert copies of administrative and contract closeout plans.
APPENDIXES
A: Specifications: Insert specification diagrams or support documentation.
B: Gantt Charts and Network Diagrams: Insert final schedule results from the project
management software tool in Gantt and/or network diagram formats.
C: Financial Issues: Insert final project invoice and billing reconciliation.
TOOL 9
Lessons Learned Documentation
SUMMARY
PROJECT BACKGROUND
LEARNING HIGHLIGHTS
RECOMMENDATIONS SUMMARY
TECHNICAL REVIEW
PROJECT EXPERIENCE