Sei sulla pagina 1di 9

IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS, VOL. 54, NO.

2, MARCH/APRIL 2018 1861

Transformer Energization From Low-Voltage Side


With Limited Generation—Power System Constraints
and Protection Considerations—A Case Study
Gautami Bhatt , Senior Member, IEEE, Terry Tadlock , Senior Member, IEEE,
and Dragan Ristanovic , Senior Member, IEEE

Abstract—A large existing delta-wye step-down transformer was sioned. This would allow the DGs to be shut down, which would
proposed to be temporarily used as a step-up transformer and en- avoid diesel fuel consumption and the associated premium costs
ergized from the low-voltage wye winding by multiple small diesel due to a remote project site location.
generators (DGs) to accelerate commissioning activities by utilizing
existing temporary generation. This paper is a case study that dis- Due to project schedule changes and desire to accelerate com-
cusses the associated power system constraints created by this pro- missioning activities, an opportunity was identified to utilize the
posed modified power system configuration. The modified power 13 MVA step-down transformer in reverse operation to back-
system configuration resulted in an ungrounded high-voltage (HV) feed, or step-up, from the temporary power system to the perma-
system created by the transformer’s delta winding, which required nent power system. Implementing this scheme presented several
HV system modifications to create a grounded system. Additionally,
the existing power system had generation and load flow constraints technical challenges.
and had protection and coordination constraints that needed to be First, utilizing the delta-wye resistance grounded step-down
maintained to supply the existing loads. Also, the inrush current transformer in a step-up configuration creates an ungrounded
resulting from the transformer energization needed to be evalu- high-voltage system. Section II of the paper discusses the con-
ated and compared with the generator’s short time current rating. cerns with the ungrounded high-voltage (HV) system and mod-
Finally, modifications to the protection and coordination settings
resulting from the modified power system configuration and con- ifications to the HV system to create system grounding.
firmation that the arc flash incident energy levels were acceptable Additionally, the system short circuit current in this modified
after implementation of modified settings were required. configuration was much lower than the minimum short circuit
Index Terms—Diesel generator (DG), generator short time cur- currents on which the system protection settings were originally
rent rating, inrush restraint, interconnect transformer, reverse based. They were comparable to the expected transformer inrush
power flow, transformer energization, transformer inrush current, current that the system may see during transformer energization.
ungrounded system.
Section III of the paper discusses the power system generation
I. INTRODUCTION and load flow constraints and protection and coordination limits.
Also, energizing the 13 MVA transformer with much smaller
IESEL generators (DGs) were provided to supply power
D to the temporary power system and supply the associated
construction power and man camp loads during the early phases
2.08 MW DGs presented the challenge of large transformer
energization while avoiding nuisance tripping of the DGs, which
were already in service and supplying power to the construction
of the construction of a multitrain liquefied natural gas (LNG) power system. Section IV of the paper discusses transformer
facility. This international facility was designed in accordance energization and inrush currents. This section also shows the
with the International Electrotechnical Commission standards results of the software simulation of the transformer energization
and is a 50-Hz system. A 33–11.55 kV, 13 MVA, delta-wye, and the effect of this energization on the DGs.
step-down transformer was designed and installed to allow the Section V demonstrates the relay logic and interlocks
permanent plant gas turbine generators (GTGs) to provide power implemented to avoid nuisance trip on inrush. This section also
to the temporary power system after the GTGs were commis- shows the new protection settings implemented for the modified
system configuration. Section VI discusses reevaluation of sys-
Manuscript received June 9, 2016; accepted November 29, 2016. Date of tem arc-flash incident energy levels to ensure personnel safety.
publication November 16, 2017; date of current version March 19, 2018. Pa-
per 2016-PCIC-0596, presented at the 2016 Petroleum and Chemical Industry
Section VII shows actual results of transformer energization in
Conference, Philadelphia, PA, USA, Sep. 19–22, and approved for publica- the site conditions.
tion in the IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS by the Petroleum
and Chemical Industry Committee of the IEEE Industry Applications Society.
(Corresponding author: Gautami Bhatt.)
II. SYSTEM GROUNDING
The authors are with Bechtel Oil, Gas, and Chemicals, Houston, TX
77056 USA (e-mail: gnbhatt@bechtel.com; trtadloc@bechtel.com; dristano@
A. Planned Power System Configuration
bechtel.com). During the initial phases on the project, DGs were being
Color versions of one or more of the figures in this paper are available online
at http://ieeexplore.ieee.org. used to supply power to the 11 kV temporary power system
Digital Object Identifier 10.1109/TIA.2017.2774767 and supply the associated construction power and man camp

0093-9994 © 2017 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission.
See http://www.ieee.org/publications standards/publications/rights/index.html for more information.
1862 IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS, VOL. 54, NO. 2, MARCH/APRIL 2018

Fig. 2. “Effect on line-to-ground voltages of a single line to ground fault on


an ungrounded neutral system” [1, Fig. 6.4, p. 343].

Fig. 1. Planned Power System Configuration.


GTGs and the associated generator step transformer ET-GSU
would not be energized and, therefore, the generator incomer
breaker CB-GSU would be open.
loads. During normal operation, three DGs were running with By reviewing Fig. 1, it can be seen that the 11 kV neutral
two additional DGs available for peak loading and redundancy. grounding reference can either be developed by the DG’s 100 A
Each 11 kV DG is rated at 2.08 MW. Also during this initial neutral grounding resistor, by the ET-1 transformer’s 100 A
phase, the 33 kV permanent power system was not energized neutral grounding resistor, or by both operating concurrently.
and there was no interconnection between the 11 kV temporary Also, by reviewing Fig. 1, it can be seen that the 33 kV neu-
power system and the 33 kV permanent power system. tral grounding reference can only developed by the ET-GSU
After the GTGs were commissioned and ready to accept load, generator step-up transformer’s 400 A neutral grounding re-
there was a planned interconnection between the 33 kV perma- sistor. However, since CB-GSU is open, the generator step-up
nent power system and the 11 kV temporary power system. As transformer and its associated neutral grounding resistor are not
shown in Fig. 1 for this planned configuration, the GTGs, rep- connected to the 33 kV permanent power system. This results
resented by GTG, would supply power via its generator step-up in an ungrounded 33 kV permanent power system.
transformer, equipment ID meant to indicate ET-GSU, to the
33 kV switchgear ES-33. The 33 kV switchgear would supply
C. Ungrounded HV System
power to the permanent plant commissioning loads and would
supply power to the 11 kV temporary power system, ES-11, An ungrounded system is a system where there is no in-
via the delta-wye step-down transformer ET-1, which was used tentional connection to ground. Since the generator incoming
to interconnect the permanent power system and the temporary breaker, CB-GSU, is open, the 33 kV permanent power system,
power system. The 11 kV temporary power system would then ES-33, has no intentional connection to ground and is thus an
supply the existing construction power and man camp loads. At ungrounded system. However, in any power system, there ex-
that time, the DGs would be turned off [circuit breaker (CB)-DG ists capacitive coupling between the system components, i.e.,
opened], which would save fuel costs. cables, generator windings, motor windings, transformer wind-
ings, etc., to ground. This has the effect of establishing the
neutral reference point via capacitive coupling to ground [1].
B. Modified Power System Configuration
In a steady state, balanced and unfaulted power system, the
Due to project schedule changes and desire to accelerate com- neutral reference point will float at ground potential. However,
missioning activities, an opportunity was identified to utilize the in the event of a line to ground fault, the system’s voltage triangle
transformer ET-1 in reverse operation to backfeed, or step-up, shifts such that, and assuming no fault impedance, the voltage of
from the 11 kV temporary power system to the 33 kV permanent the faulted phase to ground is 0 V. The line-to-ground voltage of
power system. the other two phases becomes equal to the line-to-line voltage.
To support this opportunity, modifications to the planned Fig. 2 shows a phasor representation of the normal unfaulted
power system configuration would be necessary. These mod- condition and shows a phasor representation of a single line-
ifications include that the DGs, DG1 thru DG5, would continue to-ground fault condition from [1]. An ungrounded system can
to supply the 11 kV temporary power system, which means CB- continue to operate with a single line-to-ground fault without
DG would remain closed. The 11 kV temporary power system, protection operation. Only when a second line-to-ground fault
ES-11, would continue to supply the existing construction power occurs or a line-to-line fault occurs will protection trip and
and man camp loads. Additionally, the DGs would supply power isolate the faults [1].
to the 33 kV permanent power system by backfeeding the ET-1 The equipment used for the 33 kV permanent power sys-
transformer. The commissioning loads connected to the 33 kV tem consists of 38 kV rated gas insulated switchgear suitable
power system would then be energized. Also, these modifica- for 38 kV line-line voltage and 21.9 kV line-neutral voltage.
tions to the planned power system configuration include that the The cables used for the 33 kV permanent power system are
BHATT et al.: TRANSFORMER ENERGIZATION FROM LOW-VOLTAGE SIDE WITH LIMITED GENERATION—POWER SYSTEM CONSTRAINTS 1863

the zero-sequence current will flow through the system to the


ET-GSU neutral grounding resistor and the magnitude of the
ground fault current will be limited to 400 A. Additionally, the
ground fault current can now be detected by system relaying
and the appropriate breaker tripped to isolate the ground fault.
As seen in Fig. 3, there are two 33 kV circuit breakers,
CB-33 and CB-GSU, between the 33 kV delta winding of in-
terconnect transformer ET-1 and the ET-GSU generator step-up
transformer’s 400 A neutral grounding resistor. If either of these
breakers were to be opened or tripped, the 33 kV neutral ground-
ing reference would be lost. Since it is important to ensure the
system is grounded at all times, interlocks are implemented in
the system to ensure intertrip of source circuit breaker CB-11 if
either of the two 33 kV circuit breakers, CB-33 and CB-GSU,
Fig. 3. Modified power system configuration.
open or trip. Details of these interlocks are beyond the scope of
this paper.
rated 19/33(36) kV which are suitable for a maximum line-line
The modified power system configuration now has two trans-
voltage of 36 kV and a maximum line- ground voltage of
formers, rated 13 MVA and 20 MVA, connected in series that
20.7 kV. This includes the 1220 m cable that connects trans-
need to be energized from relatively small sized 2.08 MW DGs.
former ET-1 to the 33 kV switchgear ES-33. In this configu-
Moreover, the ET-1 energization is from the low-voltage side
ration, if a line to ground fault were to occur, the line-ground
of the transformer which increases the current and the ET-GSU
voltage of the unfaulted phases would become equal to the line-
energization is over a long cable which increases the system
line voltage of 33 kV. The equipment and the cables are not rated
impedance.
for this magnitude of line-ground voltage. Insulation breakdown
Additionally, the applications of using transformer ET-GSU
due to the overvoltage would occur which would permanently
to develop the 33 kV neutral grounding reference and using
damage the insulation and could result in flashover. Further, the
transformer ET-1 in a step-up application when it was designed
fault could propagate to a line-line-ground fault and cause high
for a step-down application were reviewed with the transformer
magnitude unrestricted ground fault currents [1].
manufacturer. The use of transformer ET-GSU in this applica-
tion was approved without restriction and without any impact
D. Modification to HV System to Create Grounding on equipment warranty. The use of transformer ET-1 in this ap-
In order to avoid damaging the insulation of the equipment plication was conditionally approved and without any impact on
and cables, and to limit ground fault current magnitudes in the equipment warranty. The condition of approval for transformer
event of a fault, the system must be resistance grounded. There ET-1 was that it could not be used in an application where it
are multiple methods available to establish the neutral grounding would experience generator load rejection since it had not been
reference on the 33 kV permanent power system. These include designed as a generator transformer.
adding a grounding transformer or replacing transformer ET- If a transformer that has not been designed as a generator
1 so that the system ground is established when backfeeding transformer is subjected to load rejection, there is a risk of
the transformer. Both these methods involve adding a neutral transformer core saturation due to over-fluxing caused by high-
grounding resistor so that the 33 kV system neutral point is voltage transient during load rejection which could cause trans-
physically connected rather than capacitively coupled to the former damage or insulation degradation. However, by review
ground potential. of Fig. 3, it can be seen that there are two circuit breakers, CB-
For the application described in this paper and to avoid the DG and CB-11, between DG1 thru DG5 and transformer ET-1
purchase of additional equipment or replacement of existing which would trip and isolate the transformer and protect it from
equipment, an innovative solution was evaluated. This inno- experiencing generator load rejection.
vative solution utilized the neutral grounding resistor of the Prior to implementation, a design review was performed for
generator step-up transformer ET-GSU to establish the neutral the proposed modified power system configuration and included
grounding reference. Fig. 3 shows the modified power system representatives from Engineering, Construction, Commission-
configuration with DGs supplying power to the system. ing, and Operations, and included members from both the en-
To implement this, the 11 kV cable connection between gineer of record and the client/owner. The results of the design
the GTG and its generator step-up transformer ET-GSU was review was that the modified power system configuration was
disconnected and isolated at the transformer so that the GTG approved for implementation.
could not be backfed. This is represented in Fig. 3 by the
open switch between GTG and ET-GSU. With circuit breaker III. POWER SYSTEM CONSTRAINTS
CB-GSU closed, the 33 kV permanent power system is now
A. Generation and Load Flow Constraints
grounded by the ET-GSU generator step-up transformer’s
400 A neutral grounding resistor. Under normal conditions, Although the interconnect transformer is rated for the total
no current will flow through ET-GSU. During ground faults, generation capability, the amount of load the temporary power
1864 IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS, VOL. 54, NO. 2, MARCH/APRIL 2018

system can supply to the permanent power system while still double the inrush current when compared to the inrush current
supplying its construction power and man camp loads had to be upon energization from the high-voltage side [2]. Knowledge of
determined in order to define the load limit for commissioning transformer design details is important when an accurate value
activities. The total generation capability of the system is 5 × of transformer inrush is required [2].
2.6 MVA, which is 13 MVA. The system limit also depends on The transformer manufacturer was contacted to obtain de-
medium-voltage motors that need to be started as part of the tails of the transformer design and expected inrush values when
permanent plant commissioning activities. This analysis is done energizing the transformers from the low-voltage side. The
using power system simulation software and it is found that the manufacturer-provided design data are used in transient mag-
modified power system configuration can support a maximum of netizing simulation discussed in the next section. The inrush
5 MVA of permanent plant load, including capability of starting current provided by the transformer manufacturer is based on
the two medium-voltage motors required for commissioning zero-crossing voltage, assumes a zero impedance source, and is
activities, which results in requiring five DGs to be running. conservative for the system design.
The details of the associated power system analysis performed As seen in Section III, the maximum short circuit result of
to obtain these results are beyond the scope of this paper. the new system is 7.743 kA at 11 kV and 1.396 kA at the
While the DGs may be adequately rated to supply electrical 33 kV bus and the estimated inrush current for the 13 MVA
power in the steady state condition, it is necessary to verify their transformer provided by the manufacturer is 5.109 kA at the
short term capability during transformer energization. Accord- 11 kV side and for the 20 MVA transformer it is 1.664 kA
ing to the DG data sheet, generator-rated stator current is equal at the 33 kV side. With the maximum fault currents and esti-
to 137 A, with the short time rating of 786 A. The total short time mated inrush currents within comparable range, it is important
rating of five DGs running in parallel is 5 × 786 A = 3930 A. to obtain a more realistic estimate of the actual inrush when the
transformers are energized from the actual DGs rather than the
B. Protection and Coordination Constraints zero impedance source. This is also critical because the impact
of this energization on the source DGs should be analyzed to
The minimum and maximum short circuit currents of the evaluate the impact on the DGs and determine if DG short time
modified power system configuration are required to determine rating is adequate for transformer energization. The transformer
appropriate protection settings of the modified system. The orig- energization simulation is discussed in the following section.
inal protection settings of the system were based on the planned
power system configuration and modified protection settings are
to be determined. The minimum short circuit of the modified B. Transformer Energization Simulation
power system configuration is based on two DGs running and Before the modification is implemented, the magnitude of
is found to be 1.148 kA at the 11 kV bus and 0.305 kA at the the expected inrush current, the expected decay in inrush cur-
33 kV bus. The maximum short circuit of the system is based rent over time, and its effect on the temporary power system DG
on maximum DGs running and is found to be 7.743 kA at the should be evaluated. This is achieved with the help of a switch-
11 kV bus and 1.396 kA at the 33 kV bus. ing transient analysis software model to simulate transformer
energization. The details of how to perform such analysis is be-
IV. TRANSFORMER ENERGIZATION AND INRUSH yond the scope of this paper. An example of how to develop a
software model to perform the transformer switching transient
A. Transformer Energization and Inrush
simulation is given in [6].
When a transformer is connected to a power source and ener- Design details of the transformers and DGs are obtained from
gized, a transient current flows known as the magnetizing inrush the respective suppliers and applied as input to the analysis.
current. This current lags the applied voltage by 90 degrees elec- Several scenarios with different number of DGs running were
trical. This transient current flows because of the difference in simulated to validate the model. The scenario to be implemented
the pre-energization flux of the transformer and the steady-state involved energizing both the transformers ET-1-rated 13 MVA
flux [2]. and ET-GSU-rated 20 MVA from five DGs. The results of that
The magnitude of inrush current is variable and depends on case are shown in Figs. 4 and 5.
conditions of energization. If the transformer is energized at the Based on the switching transient analysis, the following is
positive peak voltage, there would be little inrush current and estimated for the system.
exciting currents would be 2% to 5% of the full-load current. 1) The magnitude of the peak inrush current when energizing
If the transformer is energized at the zero crossing voltage, the both transformers in series from the DGs is 2.115 kA on
peak current during first magnetization can range between 8 the 11 kV side. The duration of decay to fully dissipate is
and 30 times the full-load current. This event can last from ten approximately 5 s (full scale of the x-axis in Fig. 4).
cycles to as long as 1 min in highly inductive circuits [3]. 2) The magnitude of the peak inrush current when energizing
In the modified power system configuration, the ET-1 trans- both transformers in series from the DGs is 0.798 kA on
former is being applied and energized in the reverse direction the 33 kV side. The duration of decay to fully dissipate is
from the low-voltage side, transformer inrush can be higher approximately 1 s (full scale of the x-axis in Fig. 5).
than expected. In fact, when a core-type transformer is ener- The short time rating of 3930 A for five DGs running in paral-
gized from the low-voltage side, the inrush currents may be lel is greater than the maximum expected peak inrush current of
BHATT et al.: TRANSFORMER ENERGIZATION FROM LOW-VOLTAGE SIDE WITH LIMITED GENERATION—POWER SYSTEM CONSTRAINTS 1865

TABLE I
COMPARISON OF FAULT CURRENTS AND EXPECTED PEAK TRANSFORMER
INRUSH CURRENTS

Bus Minimum Maximum Estimated Total


Fault Fault Peak Inrush
Current (kA) Current (kA) Current (kA)

11 kV bus 1.148 (L-L) 7.743 (3 PH) 2.115


33 kV bus 0.305 (L-G) 1.396 (3 PH) 0.798 a

a
Inrush current for the 13 MVA transformer does not flow through the
33 kV secondary circuit.

protective functions applied on the transformer or adjacent


equipment [4].
Fig. 4. Expected inrush current at 11 kV.
2) The magnitude of the modified system short circuit cur-
rents are comparable to the expected magnetizing inrush
currents of the transformers. Table I is a comparison of the
fault currents with the peak inrush current, as tabulated in
Table I. The settings should be such that the overcurrent
functions protect for the fault current but do not trip on
transformer inrush current.
3) The DGs in the temporary power system were already in
service and supplying power to the associated construction
power and man camp loads. The new settings should co-
ordinate with the existing settings of the temporary power
system such that the DGs do not trip for a fault due to the
interconnect transformer. A trip of the DGs will disrupt
service to construction power and man camp loads and im-
pact the ongoing construction activities, which potentially
Fig. 5. Expected inrush current at 33 kV. would impact the project schedule.
4) The arc-flash incident energy levels with the new settings
should be within acceptable levels for personnel safety.
2115 A, with sufficient margin of 3930−2115 A = 1815 A at the The system arc flash incident energy levels without mod-
11 kV level to supply the running loads in the temporary power ifications for the protection settings cause the time taken
system. The short time generator rating is considered adequate to trip longer. This increases the system incident energy
for transformer energization. to unacceptable levels.
Based on the switching transient analysis, it is found that the
system should be capable of energizing the transformers. The
transformer inrush current waveform is used in the next section B. Avoiding Trip on Inrush
for proper protection of the transformer. Industrial power transformers are typically furnished with dif-
ferential protection that is fast operating and set to pick up for
V. PROTECTION small magnitudes of in-zone fault currents. Magnetizing inrush
currents are seen as in-zone faults by the relays. The leading
A. Challenges in Determining New Settings and Coordination
component of the harmonics in the inrush current is the second
The magnitudes of short circuit current for the modified power harmonic component, which forms about 25% of the fundamen-
system configuration are significantly lower than their corre- tal value [5]. Many of the modern microprocessor relays have
sponding values for the planned power system configuration. inrush detection function that detects inrush condition based on
The minimum and maximum short circuit currents of the orig- harmonic content in the current flowing through the system.
inal system design are 8.36 and 35.6 kA at the 33 kV bus. The This feature in the relay is available for some of the relays in
protection settings of the planned power system configuration the system and will be used in implementation of the modified
are based on those short circuit currents and need to be modified protection scheme to avoid trip due to inrush current.
for proper protection. The temporary power system relays that are already in ser-
The challenges in determining new protection settings of the vice have inrush detection function that has not been utilized
system are as follows. because it was not required for the original system design. The
1) The high-harmonic content in the current during trans- differential relays for transformers ET-1 and ET-GSU and the
former energization contains dc currents that decay slowly overcurrent relay from the 11 kV feeder breaker CB-11 have
and can cause CT saturation and nuisance trip of sensitive inrush detection function. The overcurrent relays for the 33 kV
1866 IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS, VOL. 54, NO. 2, MARCH/APRIL 2018

circuit breakers CB-33 and CB-GSU do not have the harmonic


detection function.
Since the temporary power system is already energized and
serving construction and camp loads, disrupting its service due
to trip on inrush should be avoided. In order to do that, the
current transformers (CTs) to unit protection relays need to be
checked for adequacy for saturation against the inrush. In this
case, the generator differential protection relay is the only unit
protection relay in the temporary power system for which this
verification is needed.
In normal operation, the existing temporary power system
has three generators in service and two are out of service. Each
DG has generator differential protection relay receiving input
from a 200/1, 0.1 PX 15 R 0.5 CTs. For a peak inrush current
of 7.743 kA, the current is divided equally among the three
generators as 2.581 kA. Accounting for the CT ratio, the current Fig. 6. Power system with protective devices and relays identified.
seen by the CT secondary circuit is 12.905 A. With an internal
resistance of the CT as 0.5 Ω, the secondary voltage developed
due to peak inrush will be 6.45 V where the knee voltage of the
CT is 15 V. It is found that the CTs for generator differential
protection are adequately rated and that the differential function
will not trip on inrush due to CT saturation.
Further, the phase and ground overcurrent protection settings
of the DG incomers should coordinate with the relay for CB-11
such that the CB-11 circuit breaker is always the first to trip.
Although this feature may impinge upon the ability to actualize
the modified scheme, the likelihood of system black out should
be avoided.
To ensure that in the event of energization, the DG incomers
do not trip, the harmonic restraint function in the overcurrent
relay for CB-11 is also not utilized. The phase and ground over-
current settings of the CB-11 overcurrent relay are set to coor-
dinate with the DG incomer overcurrent relay on circuit breaker
CB-DG. This is discussed in further detail in Section V-C
and V-D.
The transformers that are being energized, ET-1 and ET-GSU,
have dedicated relays for transformer differential and restricted
earth fault protection with harmonic block and harmonic re-
straint function that is set to detect the second and the fourth
harmonics and is utilized with a maximum time delay of 0.9 s
to avoid transformer differential functions tripping during a non-
fault inrush condition.
Although all sensitive differential functions will not trip dur- Fig. 7. Phase overcurrent coordination curve—33 kV circuit.
ing energization, it should be noted that the overcurrent relays
need to be set for the new lower fault currents that are compa-
rable to the expected inrush. Relay logic that is implemented settings implemented in the interconnect transformer 33 kV side
in the transformer differential relays is utilized as an interlock for the modified system.
for the overcurrent relays over a communication link. This in- 1) The inrush curve is plotted on the time current curve to
terlock would block tripping of the overcurrent relays during avoid tripping of phase overcurrent functions when inrush
a non-faulted inrush condition for a maximum of 0.9 s. This current has reduced from its peak value but still signifi-
ensures the overcurrent functions do not trip due to inrush. The cant enough to cause relay misoperation. The peak inrush
actual settings are discussed in Section V-C and V-D. current provided by the transformer manufacturer is also
plotted on the curve as a point to avoid trip on inrush.
2) Discrimination and selectivity on the interconnect trans-
C. Phase Overcurrent Protection former has been sacrificed due to the intertrips imple-
Fig. 6 shows the power system with protective devices and mented in the system that would initiate trip of all inter-
relays identified. Fig. 7 shows the phase overcurrent protection connect breakers to avoid an ungrounded system.
BHATT et al.: TRANSFORMER ENERGIZATION FROM LOW-VOLTAGE SIDE WITH LIMITED GENERATION—POWER SYSTEM CONSTRAINTS 1867

Fig. 8. Phase overcurrent coordination curve—11 kV circuit. Fig. 9. Ground fault protection coordination.

Fig. 8 shows the phase overcurrent protection settings imple-


mented on the 11 kV circuit breaker CB-11-RELAY to coordi- with a time delay of 100 ms to coordinate with the source
nate with the existing setting of DG incomer. relay setting with five DGs in service.
Therefore, five DGs are required if existing temporary power
system settings are to be maintained. The increase in the number
D. Ground Fault Protection
of generators also increases the system capability to meet the
The ground fault relay setting of the 11 kV feeder relay in reactive power demand during inrush condition. Five genera-
the system CB-11-RELAY should be set in a way that it meets tors are also required for motor starting of the medium-voltage
below criteria. motors in the permanent power system, the details of which are
1) It should coordinate with the existing ground fault settings beyond the scope of this paper.
of the temporary power system.
2) It should be set high enough to avoid trip on zero-sequence
component of the magnetizing inrush current. VI. REEVALUATION OF SYSTEM ARC FLASH INCIDENT
ENERGY LEVELS
Fig. 9 shows the ground fault protection settings implemented
in the modified configuration. Before implementation of the modified protection settings
1) When coordinating settings on a system with multiple and energization of the transformer, it is critical to re-evaluate the
sources, the relay curves need to be multiplied with the system for arc-flash incident energy levels to ensure personnel
appropriate factor to account for contribution from each safety. Although the fault currents in the modified system are
source. Each DG incomer is set to operate at 30 A, 300 ms. low, the incident energy levels may be higher due to much
This setting will be maintained to avoid DG shutdown to slower relay trip times at the lower fault currents or fault currents
modify and test new settings. that were below the pickup values of the original protection
2) With three DGs operating, all the three DG incomers will settings. The system is reevaluated for incident arc-flash energy
trip if the total zero-sequence current is 90 A (3 × 30 A levels. This analysis was done using a power system simulation
per DG). software. Relay settings of permanent power system that were
3) If five DGs are operating, all the five DG incomers will going to be commissioned as part of the modified power system
trip if the total zero-sequence current is 150 A (5 × 30 A configuration are also part of this evaluation. After modifications
per DG). to system protection settings, the analysis confirms the incident
4) The CT ratio of the 11 kV feeder is 1250:1 and 0.1 is energy levels are within acceptable levels and are bounded by
the minimum pickup available for the relay. The 11 kV existing arc flash incident energy levels and personal protective
feeder ground fault setting is set at 125 A (0.1 pickup) equipment requirements.
1868 IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS, VOL. 54, NO. 2, MARCH/APRIL 2018

insulation. Grounding the system to avoid such conditions


and to limit the ground fault currents to reasonable limits
is important.
2) Note the following when energizing transformers with
small or comparable sources.
a) It is preferred to ramp the system voltage from low
voltage to system voltage while the transformer is
connected. This would reduce the undesired effects
of high inrush currents on system voltage sources
and sensitive protective devices. However, in this
Fig. 10. Waveforms and signals at the 11 kV side during transformer ener- application, existing loads had to remain energized
gization. and this was not an option.
b) Effect of energization on source voltage should be
evaluated.
VII. FIELD RESULTS FROM TRANSFORMER ENERGIZATION c) Effect on high harmonic content on CTs and sensi-
After the anticipated inrush currents have been analyzed as de- tive differential protection settings need to be eval-
scribed in Section IV and relay settings and interlocks have been uated to avoid tripping due to energization.
modified as presented in Section V for the new temporary sys- d) Harmonic restraint feature within the relay that
tem configuration, the transformer backfeed energization from block operation in the event of inrush should be
five parallel DGs was successfully implemented. utilized where available.
Transformers ET-1-rated 13 MVA and ET-GSU-rated 20 e) Transformer energization is a non-symmetrical
MVA were energized in series, and transformer protection relay event with transient currents far exceeding the nor-
at ET-1 captured the 11 kV side waveforms, as shown in Fig. 10 mal system currents. Analysis of the impact of trans-
From Fig. 10, the peak inrush equal to 1020 A occurred former inrush on protective relay functions is nec-
in phase A, which is less than the expected maximum inrush essary, and implementation of relays with inrush
of 2115 A obtained by simulation presented in Fig. 4 in restrain feature may be required to avoid nuisance
Section IV–B. Such a difference between the actual peak inrush trips during transformer energization.
and the maximum simulated peak inrush can be expected since 3) When modifying power system configurations from their
the actual energization may occur on any point on the voltage original design, system studies, short circuit studies, pro-
waveform while the simulation is done for the worst-case tection settings, arc flash analysis need to be revalidated to
energization at the voltage zero crossing. confirm implementation of the scheme and identify power
The relay recorded a distorted current waveform with second system operating limits, if any.
harmonic content, which is expected during transformer ener- 4) When potential exists to interconnect the temporary and
gization. Since the inrush current is a nonsymmetrical event and permanent electrical systems in a bidirectional manner,
different inrush magnitudes occur in different phases, the relay such interconnection should be evaluated and, if deter-
recorded the presence of the zero-sequence current component. mined beneficial, incorporated in early stages of the design
Zero-sequence component of less than 10 A occurred for both, process. Considerations for the design of interconnected
residual element IGW2, and the direct measurement by IN1 systems are further explained in [7].
from the ground CT in the transformer neutral.
The voltage waveform presented in Fig. 10 shows the sag ACKNOWLEDGMENT
expected during transformer energization. The voltage peak The authors would like to thank A. Tiwari from Bechtel Oil,
dropped to 84.6% of the nominal value in the first cycle af- Gas, and Chemicals for his valuable comments. The authors
ter energization and recovered to 95% by the fifteenth cycle. would also like to thank T. Turner and K. Hackart from Pow-
Similar waveforms were captured on the 33 kV side where ertech Services for performing the transformer energization sim-
measured peak inrush was equal to 370 A, which is less than the ulation.
expected 798 A obtained by simulation for the worst-case ener-
gization scenario at voltage zero crossing simulation presented
in Fig. 5 in Section IV-B. REFERENCES
Due to modifications in protective relay settings explained in [1] D. Beeman, Ed., Industrial Power Systems Handbook, New York, NY, USA:
Section V and implemented prior to transformer energization, McGraw-Hill, 1955.
[2] J. E. Hobson and R. L. Witzke, Electrical Transmission and Distribution
the relays did not trip during the energization. Reference Book, L. Witzke and J. S. Williams, Ed., Raleigh, NC, USA:
ABB Power T&D, 1997.
[3] J. L. Blackburn, Applied Protective Relaying, Principles and Applications.
VIII. CONCLUSION New York, NY, USA: Taylor & Francis, 2006.
[4] B. Kasztenny, “Impact of transformer inrush currents on sensitive protection
The following conclusions can be made from this case study. functions,” in Proc. 32nd Annu. Protective Relay Conf., Oct. 25–27, 2005..
1) An ungrounded system can cause severe power system [5] M. M. Adibi and D. P. Milanicz, “Protective system issues during restora-
problems including overvoltage and stress on equipment tion,” IEEE Trans. Power Syst., vol. 10, no. 3, pp. 1492–1497, Aug. 1995.
BHATT et al.: TRANSFORMER ENERGIZATION FROM LOW-VOLTAGE SIDE WITH LIMITED GENERATION—POWER SYSTEM CONSTRAINTS 1869

[6] I. Hassan, H. V. Nguyen, and R. Jamison, “Analysis of energizing a large Terry Tadlock (M’92–SM’11) received the B.S. de-
transformer from a limited capacity engine generator,” in Proc. IEEE Power gree in electrical engineering from the University of
Eng. Soc. Winter Meeting, 2000, vol. 1, pp. 446–451. Washington, Seattle, WA, USA, in 1992, and the M.S.
[7] C. J. Mozina, “Interconnect protection of dispersed generators,” in Proc. degree in systems and engineering management from
IEEE/PES Trans. Distrib. Conf. Exp., vol. 2, 2001, pp. 709–723. Texas Tech University, Lubbock, TX, USA, 2013.
[8] G. Bhatt, T. Tadlock, and D. Ristanovic, “Transformer energization He joined Bechtel Oil, Gas, and Chemicals, Hous-
from low voltage side with limited generation—Power system con- ton, TX, in 1992, and has worked on various types of
straints and protection considerations—A case study,” in Proc. 2016 projects including power, telecommunications, min-
Petroleum Chem. Ind. Tech. Conf., Philadelphia, PA USA, pp. 1–9, doi: ing, petrochemical, coal gasification, and liquefied
10.1109/PCICON.2016.7589246. natural gas projects. He is currently an Electrical Prin-
cipal Engineer with Bechtel Oil, Gas, and Chemicals,
specializing in industrial power systems analysis, protection, and control appli-
cations.
Mr. Tadlock is a member of the Industry Applications Society. He is a regis-
tered Professional Engineer in the states of Texas and Washington.

Dragan Ristanovic (S’01–M’03–SM’12) received


the Dipl.Ing. degree in electrical engineering from
the University of Belgrade, Belgrade, Serbia, in 1996,
Gautami Bhatt (M’08–SM’18) received the B.Tech. and the M.Sc. degree in electrical engineering from
degree in electrical and electronics engineering from Texas A&M University, College Station, TX, USA,
Jawaharlal Nehru Technological University, Hyder- in 2003.
abad, India, in 2009, and the master’s degree in elec- He has 17 years of experience in the industry. For
trical engineering from the University of Houston, four years, he was an Electrical Engineering Con-
Houston, TX, USA, in 2010. sultant on power grid projects in the Middle East,
In 2011, she joined Bechtel Oil, Gas, and Chem- where he was engaged in performing substation de-
icals, Houston, as an Electrical Engineer, where she sign, relay coordination studies, and relay testing and
is involved in power system analysis and protective commissioning. In 2003, he joined Bechtel Oil, Gas, and Chemicals, Houston,
relaying studies. TX, where he is a Senior Electrical Engineer with responsibilities in power
Ms. Bhatt is the Co-Chair for the IEEE Industry system analysis and protective relaying studies.
Applications Society Houston Section. She is a registered Professional Engineer Mr. Ristanovic is a Professional Engineer in the state of Texas and registered
in the state of Texas. Professional Engineer in QLD, Australia.

Potrebbero piacerti anche