Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Presentation Overview
2. TREE OF LIFE
3. TIMELINES
The former IT mall, closed its doors on June 30 2016 after 31 years of trading, is
being redeveloped into a mixed-use complex
Redevelopment nearly double the old complex's floor area to 80,857.7m2 . Plot
Ratio 7.0
Funan set to be the first online-and-offline (O&O) shopping mall integrating online
and offline with technology and automation in Singapore
First commercial development to allow cycling through the building at Level 1,
Funan will bring to life cycling amenities and end-of-trip facilities such as cafés
and shower facilities
Live Performance Theatre & Cineplex
THE FUNAN REDEVELOPMENT
Retail Office
Serviced Residence
THE FUNAN REDEVELOPMENT
AMSL – 55.80m
Total Height Above Ground– 50.8m
Basement Depth – 17.85m Below Level 1
Serviced Residence Floor-to-Floor – 3150mm
Office Floor-to-Floor Height – 4200mm, 4450mm for Top
Most Floor
Basement Retail Floor-to-Floor – 5075mm & 5775mm
PERSPECTIVE Above Ground Retail Floor-to-Floor – 5250mm & 4725mm
THE TREASURY Retail & Office Transition at Level 4 Floor-to-Floor –
5175mm
THE FUNAN REDEVELOPMENT BASEMENT PLANS
Level 4 Level 4
Level 3M
Level 3 Level 3M Level 3
Level 2M Level 2M
Level 2 Level 2
Level 1 Level 1
A
B
View ‘A’ Across Retail Blocks View ‘B’ Across Retail Blocks
TREE OF LIFE
Link Bridge
Column A
Column A Inclined
Level 4
at 8 Degree & Stops
at Level 4
Platform
Column B Inclined
at 5 Degree & Stops
at Level 3M
Tie-Back to Main
Link Bridge Building
Structures
Column A
Level 3 Platform
Column B
Column A
Column C
Column D
Planter Supporting
Level 1 Cycling Path & Planters Structure Below Cycling
Path
FUNAN – TREE OF LIFE FINITE ELEMENT ANALYSIS FOR COMPLEX JOINT
Most Critical Column Head Connection at Level 4 Platform
3 4 5 6
FUNAN – TREE OF LIFE INSTALLATION SEQUENCE
7 8 9 10
Erection bracket
Erection bracket
details for columns.
details for braces
Tier 1 and Tier 2
connecting to
columns to be
column. Braces and
connected by full
column to be
penetration butt weld
connected by full
penetration butt weld
FUNAN – TREE OF LIFE SITE PHOTOS
FUNAN – TREE OF LIFE SITE PHOTOS
TIMELINES
TIMELINES CONSTRUCTION SEQUENCE AS PLANNED
+0 17.01.17 starts +02 demolition l1 +04 demolition l1/b1/b2, +06 demolition b2,
deck, piling/kingpost & cbp cbp & temp deck
+07 demolition b3, +09 b1, l1, l3, piling & +12 b2 raft, l1, l2, l5, l6 +13 demolition b1/b2,
cbp, piling, kingpost & l1 kingpost & demolition b1/b3 b1, l2, l3, l4 & l6
+17 b3, b2, pool, l7, +19 b3, l8, l11 & roof +21 b4 & roof
l10, l12 & roof
+22 b4, podium & +24 office & sr facade +25 dismantle tc3
office facade
The site is now racing ahead to open the Mall & Office by Q2 of 2019
instead of Q3 following the contract ….. and the serviced residence
by Q4 of next year
TIMELINES WORK IN PROGRESS
WHY COMPOSITE & HOW THE CONSTRUCTION HAS HIT AN IMPORTANT
MILESTONE AHEAD OF SCHEDULE
WHY COMPOSITE & HOW THE CONSTRUCTION HAS HIT AN IMPORTANT
MILESTONE AHEAD OF SCHEDULE
KEY DRIVERS
COMPLIANCE
URA’s Building Height Control – Retain A Lower Rise Character
Around Fort Canning Hill
HAPPY PROBLEM
More than 50% GFA available To Consume
Maximizing Floor Areas with More Floor Inserts – Floor to Floor
& Ceiling Height Requirement
OBSTACLE
Redevelop with Presence of Existing Basement - Construction of
New Basement Must go in Tandem with Demolition to the Old
MOTIVATION
Early Completion & Ready to Trade
WHY COMPOSITE & HOW THE CONSTRUCTION HAS HIT AN IMPORTANT
MILESTONE AHEAD OF SCHEDULE