COTIZACION MURO TIPO 1 LONG.

24 m

CONCRETO SOLADO LIMPIEZA

LONGITUD MURO = 24.0 m


ANCHO ZARPA = 3.80 m
EXPESOR SOLADO =0.05 m

=24.0m*3.8m*0.05m = 4.56 m3 en el solado de limpieza

CONCRETO ZARPA

LONGITUD MURO = 24.0 m


ANCHO ZARPA = 3.80 m
EXPESOR ZARPA =0.50 m

=24.0m*3.8m*0.5m = 45.60 m3 en la zarpa

CONCRETO ELEVACION MURO

LONGITUD MURO =24.0 m


ALTURA MURO =2.90 m
EXPESOR MURO =0.35 m promedio

=24.0m*2.90m*0.35m = 24.36 m3 en la elevación

=74.52 m3 TOTAL CONCRETO MURO TIPO 1 LONG. = 24.0 m

AGREGADOS PARA 1 m3 CONCRETO DE 3000 PSI (75% arena, 80% triturado, 7 bultos cemento)

ARENA = 74.52 m3 x 80% = 59.62 m3 incluye desperdicio (5%)


TRITURADO =74.52 m3 x 85% = 63.34 m3 incluye desperdicio (5%)
CEMENTO =74.52 m3 x 7 bul. = 521.64 bul.

ACERO REFUERZO MURO TIPO 1 LONG. = 24.0 m

ACERO REFUERZO ZARPA


LONGITUD MURO = 24.0 m
ANCHO ZARPA =3.80 m
SEPARACION HIERRO TRANSV. = 0.15 m
SEPARACION HIERRO LONG. = 0.18 m

24.0 m/0.15= 161 varillas 5/8 long. 4.15 m X 2 parrillas = 322varillas 5/8
3.80/0.18 = 22 varillas 1/2 long. 27.0 m incluye traslapo X 2 parrillas = 198 varillas 1/2
ACERO VASTAGO

LONGITUD MURO = 24.0 m


ALTURA MURO =2.90 m
SEPARACION HIERRO TRANSV. = 0.20 m
SEPARACION HIERRO LONG. = 0.18 m

24.0 m/0.20= 120 varillas 3/4 long. 2.60 m = 60 varillas 3/4


120 varillas 3/4 long. 2.10 m
120 varillas 3/4 long. 3.80 m = 120 varillas 3/4
120 varillas 3/4 long. 2.14 m = 60 varillas 3/4

2.90/0.18 = 16 varillas 1/2 long. 27.0 m incluye traslapo X 2 parrillas = 144 varillas 1/2

TOTAL HIERRO PARA MURO TIPO 1 LONG. 24.0 m

322 VARILLAS 5/8


342 VARILLAS 1/2
240 VARILLAS 3/4
100 kg alambre de amarre
70 kg alambre galvanizado
8 kg puntilla ( si la formaleta es de madera)

MANO DE OBRA

CANTIDAD CONCRETO = 74.52 M3

PRECIO POR M3 =$210.000 (EL PRECIO NO INCLUYE EXCAVACION, FORMALETA, SEGURIDAD SOCIAL, FILTROS Y
RELLENOS)

=74.52 M3 X $210.000 = $15´649.200


COTIZACION MURO TIPO 2 LONG. 12 m

CONCRETO SOLADO LIMPIEZA

LONGITUD MURO = 12.0 m


ANCHO ZARPA = 3.40 m
EXPESOR SOLADO =0.05 m

=12.0m*3.4m*0.05m = 2.04 m3 en el solado de limpieza

CONCRETO ZARPA

LONGITUD MURO = 12.0 m


ANCHO ZARPA = 3.40 m
EXPESOR ZARPA =0.40 m

=12.0m*3.4m*0.4m = 16.32 m3 en la zarpa

CONCRETO ELEVACION MURO

LONGITUD MURO =12.0 m


ALTURA MURO =2.60 m
EXPESOR MURO =0.35 m promedio

=12.0m*2.60m*0.35m = 10.92 m3 en la elevación

=29.28 m3 TOTAL CONCRETO MURO TIPO 2 LONG. = 12.0 m

AGREGADOS PARA 1 m3 CONCRETO DE 3000 PSI (75% arena, 80% triturado, 7 bultos cemento)

ARENA = 29.28 m3 x 80% = 23.42 m3 incluye desperdicio (5%)


TRITURADO =29.28 m3 x 85% = 24.88 m3 incluye desperdicio (5%)
CEMENTO =29.28 m3 x 7 bul. = 204.96 bul.

ACERO REFUERZO MURO TIPO 2 LONG. = 12.0 m

ACERO REFUERZO ZARPA


LONGITUD MURO = 12.0 m
ANCHO ZARPA =3.40 m
SEPARACION HIERRO TRANSV. = 0.19 m
SEPARACION HIERRO LONG. = 0.18 m

12.0 m/0.19= 64 varillas 5/8 long. 3.75 m X 2 parrillas = 128 varillas 5/8
3.40/0.18 = 20 varillas 1/2 long. 14.0 m incluye traslapo X 2 parrillas = 94 varillas 1/2
ACERO VASTAGO

LONGITUD MURO = 12.0 m


ALTURA MURO =2.60 m
SEPARACION HIERRO TRANSV. = 0.20 m
SEPARACION HIERRO LONG. = 0.18 m

12.0 m/0.20 = 61 varillas 3/4 long. 2.20 m = 30 varillas 3/4


61 varillas 3/4 long. 1.82 m = 20 varillas 3/4
61 varillas 3/4 long. 3.31 m = 61 varillas 3/4
61 varillas 3/4 long. 1.84 m
2.60/0.18 = 14 varillas 1/2 long. 14.0 m incluye traslapo X 2 parrillas = 67 varillas 1/2

TOTAL HIERRO PARA MURO TIPO 2 LONG. 12.0 m

128 VARILLAS 5/8


161 VARILLAS 1/2
111 VARILLAS 3/4
50 kg alambre de amarre
30 kg alambre galvanizado
4 kg puntilla ( si la formaleta es de madera)

MANO DE OBRA

CANTIDAD CONCRETO = 29.28 M3

PRECIO POR M3 =$210.000 (EL PRECIO NO INCLUYE EXCAVACION, FORMALETA, SEGURIDAD SOCIAL, FILTROS Y
RELLENOS)

=29.28 M3 X $210.000 = $6´148.800


COTIZACION MURO TIPO 3 LONG. 17.80 m

CONCRETO SOLADO LIMPIEZA

LONGITUD MURO = 17.80 m


ANCHO ZARPA = 3.10 m
EXPESOR SOLADO =0.05 m

=17.80m*3.1m*0.05m = 2.76 m3 en el solado de limpieza

CONCRETO ZARPA

LONGITUD MURO = 17.80 m


ANCHO ZARPA = 3.10 m
EXPESOR ZARPA =0.40 m

=17.80m*3.1m*0.4m = 22.07 m3 en la zarpa

CONCRETO ELEVACION MURO

LONGITUD MURO =17.80 m


ALTURA MURO =2.20 m
EXPESOR MURO =0.35 m promedio

=17.80m*2.20m*0.35m = 13.70 m3 en la elevación

=38.53 m3 TOTAL CONCRETO MURO TIPO 3 LONG. = 17.80 m

AGREGADOS PARA 1 m3 CONCRETO DE 3000 PSI (75% arena, 80% triturado, 7 bultos cemento)

ARENA = 38.53 m3 x 80% = 30.82 m3 incluye desperdicio (5%)


TRITURADO =38.53 m3 x 85% = 32.75 m3 incluye desperdicio (5%)
CEMENTO =38.53 m3 x 7 bul. = 269.71 bul.

ACERO REFUERZO MURO TIPO 3 LONG. = 17.80 m

ACERO REFUERZO ZARPA


LONGITUD MURO = 17.80 m
ANCHO ZARPA =3.10 m
SEPARACION HIERRO TRANSV. = 0.19 m
SEPARACION HIERRO LONG. = 0.20 m

17.80 m/0.19= 95 varillas 5/8 long. 3.45 m X 2 parrillas = 190 varillas 5/8
3.10/0.2 = 17 varillas 1/2 long. 20.0 m incluye traslapo X 2 parrillas = 114 varillas 1/2
ACERO VASTAGO

LONGITUD MURO = 17.80 m


ALTURA MURO =2.20 m
SEPARACION HIERRO TRANSV. = 0.20 m
SEPARACION HIERRO LONG. = 0.20 m

17.80 m/0.20= 90 varillas 5/8 long. 2.00 m = 30 varillas 5/8


90 varillas 5/8 long. 1.62 m = 30 varillas 5/8
90 varillas 5/8 long. 2.91 m = 45 varillas 5/8
90 varillas 5/8 long. 1.63 m = 30 varillas 5/8

2.20/0.20 = 12 varillas 1/2 long. 20.0 m incluye traslapo X 2 parrillas = 80 varillas 1/2

TOTAL HIERRO PARA MURO TIPO 3 LONG. 17.80 m

325 VARILLAS 5/8


194 VARILLAS 1/2

60 kg alambre de amarre
40 kg alambre galvanizado
5 kg puntilla ( si la formaleta es de madera)

MANO DE OBRA

CANTIDAD CONCRETO = 38.53 M3

PRECIO POR M3 =$210.000 (EL PRECIO NO INCLUYE EXCAVACION, FORMALETA, SEGURIDAD SOCIAL, FILTROS Y
RELLENOS)

=38.53 M3 X $210.000 = $8´091.300


COTIZACION MURO TIPO 4 LONG. 22.70 m

CONCRETO SOLADO LIMPIEZA

LONGITUD MURO = 22.70 m


ANCHO ZARPA = 4.20 m
EXPESOR SOLADO =0.05 m

=22.70m*4.2m*0.05m = 4.76 m3 en el solado de limpieza

CONCRETO ZARPA

LONGITUD MURO = 22.70 m


ANCHO ZARPA = 4.20 m
EXPESOR ZARPA =0.50 m

=22.70m*4.2m*0.5m = 47.67 m3 en la zarpa

CONCRETO ELEVACION MURO

LONGITUD MURO =22.70 m


ALTURA MURO =3.40 m
EXPESOR MURO =0.35 m promedio

=22.70m*3.40m*0.35m = 27.01 m3 en la elevación

=79.44 m3 TOTAL CONCRETO MURO TIPO 4 LONG. = 22.70 m

AGREGADOS PARA 1 m3 CONCRETO DE 3000 PSI (75% arena, 80% triturado, 7 bultos cemento)

ARENA = 79.44 m3 x 80% = 63.55 m3 incluye desperdicio (5%)


TRITURADO =79.44 m3 x 85% = 67.52 m3 incluye desperdicio (5%)
CEMENTO =79.44 m3 x 7 bul. = 556.08 bul.

ACERO REFUERZO MURO TIPO 3 LONG. = 22.70 m

ACERO REFUERZO ZARPA


LONGITUD MURO = 22.70 m
ANCHO ZARPA =4.20 m
SEPARACION HIERRO TRANSV. = 0.15 m
SEPARACION HIERRO LONG. = 0.18 m

22.70 m/0.15= 152 varillas 5/8 long. 4.65 m X 2 parrillas = 304 varillas 5/8
4.20/0.18 = 24 varillas 1/2 long. 27.0 m incluye traslapo X 2 parrillas = 216 varillas 1/2
ACERO VASTAGO

LONGITUD MURO = 22.70 m


ALTURA MURO =3.40 m
SEPARACION HIERRO TRANSV. = 0.12 m
SEPARACION HIERRO LONG. = 0.18m

22.70 m/0.12= 190 varillas 3/4 long. 2.60 m = 95 varillas 3/4


190 varillas 3/4 long. 2.62 m = 95 varillas 3/4
190 varillas 3/4 long. 4.31 m = 190 varillas 3/4
190 varillas 3/4 long. 2.14 m = 95 varillas 3/4

3.40/0.18 = 19 varillas 1/2 long. 27.0 m incluye traslapo X 2 parrillas = 171 varillas 1/2

TOTAL HIERRO PARA MURO TIPO 4 LONG. 22.70 m

304 VARILLAS 5/8


387 VARILLAS 1/2
475 VARILLAS 3/4
120 kg alambre de amarre
80 kg alambre galvanizado
12 kg puntilla ( si la formaleta es de madera)

MANO DE OBRA

CANTIDAD CONCRETO = 79.44 M3

PRECIO POR M3 =$210.000 (EL PRECIO NO INCLUYE EXCAVACION, FORMALETA, SEGURIDAD SOCIAL, FILTROS Y
RELLENOS)

=79.44 M3 X $210.000 = $16´682.400


TOTAL MATERIALES PARA LOS 4 MUROS CON LONG. = 76.50 m

ARENA 177.41 m3
TRITURADO 188.50 m3
CEMENTO 1552.39 bultos cemento

ACERO REFUERZO

HIERRO 1/2 1084 VARILLAS 6.0 m


HIERRO 5/8 1079 VARILLAS 6.0 m
HIERRO 3/4 826 VARILLAS 6.0 m

ALAMBRE NEGRO 330 KG


ALAM. GALVANIZADO N. 12 220 KG
PUNTILLA 29 KG

TOTAL CONCRETO MUROS=221.77 m3

PRECIO MANO DE OBRA


221.77 m3 x $210.000 = $46´571.700

EN LA MANO DE OBRA ESTA INCLUIDA HERRAMIENTA MENOR, DOTACION OBREROS, EQUIPO COMO LO
ES MEZCLADORA Y VIBRADOR DE CONCRETO CORTE FIGURADO Y AMARRADO DE HIERRO.

NO SE TIENE ENCUENTA LA EXCAVACION, SEGURIDAD SOCIAL, ALQUILER DE FORMALETA, FILTROS Y


RELLENOS QUE HAYA QUE HACER POR CONSIGUIENTE SERIAN COSTOS ADICIONALES EN LA MANO DE
OBRA.