Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
PROJECT
METHOD STATEMENT
ASSEMBLY AND INSTALLATION OF RTR PIPES
CONTENTS
TABLE OF CONTENTS
1. SCOPE
2. PURPOSE
3. REFERENCES
4. DEFINITIONS
5. PROCEDURE
5.1 RESPONSIBILITIES
5.6 FABRICATION
5.12 SAFETY
METHOD STATEMENT
ASSEMBLY AND INSTALLATION OF RTR PIPES
1. SCOPE
2. PURPOSE
This method statement is made to enumerate the procedure in the fabrication &
installation of Reinforced Thermosetting Epoxy-Resin pipes & fittings for Saudi
Aramco Jubail Export Refinery Project.
3. REFERENCES
3.1 SATORP STANDARDS
JERES-L-105 Piping Material Specification
JERES-S-070- Installation of Utility Piping Systems.
JERES-A-004- General Requirements for Pressure testing.
JERES-L-610- Non Metallic Piping
JERES-S-060- Plumbing Code
JERES-A-114- Specification for Excavation and Backfilling
JERES-S-020-Industrial Drainage And Sewers
JERMS-L-1029- RTR sewer Pipe and Fittings for gravity flow.
JERMS-L-1034- Unrestrained Gasket Joint RTR sewer Pipe and
Fittings.
METHOD STATEMENT
ASSEMBLY AND INSTALLATION OF RTR PIPES
4. DEFINITIONS
5. PROCEDURES
5.1 RESPONSIBILITIES
METHOD STATEMENT
ASSEMBLY AND INSTALLATION OF RTR PIPES
5.1.6 QC Inspector shall ensure that all works are carried out as per IFC
Drawings, project specifications and standards and he has to co-
ordinate with TRGC/SATORP QC Inspectors for inspection.
Powerpull (2X)
Joint Lubricant
Band Clamps (2X)
Pulling Rings (4X)
O -Ring
Bucket with Water
Screw Driver
Hammer
Key
It shall be as per manufacturer recommendations.
5.3.1 Pipes and Fittings shall conform to JERES-S-070 Para. 6.2 & 6.3 for
storage and preservations
5.3.15.3.2 The material handling, fabrication and installation of RTR Pipes
shall be followed as per vendor recommendations.
5.3.25.3.3 Incoming Inspection shall be carried out for shipments of Bond
strand Pipe and fittings for abuse in shipping. Broken Pipe bundles,
crushed fittings boxes, scratched and gouged pipe with crushed or spilt
ends are evidence of such abuse shall be checked.
5.3.35.3.4 Do not throw or drop pipe and fittings, protect from all types of
impact. Bond strand may be damaged by careless handling,
sometimes without exhibiting visible effects on the pipe surface.
SATORP JUBAIL EXPORT REFINERY
PROJECT
METHOD STATEMENT
ASSEMBLY AND INSTALLATION OF RTR PIPES
METHOD STATEMENT
ASSEMBLY AND INSTALLATION OF RTR PIPES
5.5.2 Small fittings and flanges that cannot be marked shall be tagged.
5.55.6 FABR
ICATION
5.5.1.1 Before joining pipe, end protection from both the male and
female pipe end must be removed.
5.5.1.2 Clean the grooves and sealing surface of both female and male
SATORP JUBAIL EXPORT REFINERY
PROJECT
METHOD STATEMENT
ASSEMBLY AND INSTALLATION OF RTR PIPES
METHOD STATEMENT
ASSEMBLY AND INSTALLATION OF RTR PIPES
band clamps, one may choose to use rubber pads under the
band clamp. Over tighten of band clamps are not allowed
otherwise it will crush the pipe.
5.5.2.8 After insertion check Pipe concentricity and uniformity of entry.
5.5.2.9 Keep keys ready for insertion when scribe mark is about 6 mm
away from the leading edge of the female pipe end.
5.5.2.10 Check the Pipe alignment again by looking along the pipe and
aligning the scribe mark on the male Pipe end with the edge of
the female end.
5.5.2.11 Drive the key by using wooden hammer only until you can see
its leading end through the insertion hole. Also remove power
pulls and band clamps
5.6.1 All pipes, joints, fittings, couplings, and spools, supplied under this
specification, shall be identified by cell classification system from the
standards listed in Section 6. Equivalent cell classifications by other ASTM
standards are also acceptable.
5.6.2 The product shall meet the performance requirements of Section 9
of this specification.
5.6.3 Pipe and couplings shall be filament-wound using polyester, vinyl
ester or epoxy resin and fiberglass reinforcement.
5.6.4 Resin System
Resin shall be suitable for the services specified, and shall be noted by the
vendor in his proposal. The resin system used for the interior liner, the
SATORP JUBAIL EXPORT REFINERY
PROJECT
METHOD STATEMENT
ASSEMBLY AND INSTALLATION OF RTR PIPES
structural wall, fittings, and adhesives, shall be polyester, vinyl ester or epoxy,
with suitable curing agents so that it meets the performance requirements and
temperature limits in this Specification.
5.6.5 Glass Reinforcement
The structural wall reinforcement shall be of commercial-grade glass fiber,
suitable for the services specified in the Purchase Order, treated with a
compatible binder and coupling agent.
5.6.6 Fillers
Siliceous sand may be used as filler as specified in cell classification.
Siliceous sand shall conform to ASTM C33, except that the requirements for
gradationneed not apply.
5.6.7 Additives
Resin additives such as pigments, dyes or coloring agents may be used,
provided they do not detrimentally affect the performance of the pipe. The
pipe shall contain a UV inhibitor if requested on the Purchase Order. Pipe and
fittings that will be exposed to sunlight when installed, shall contain UV
inhibitor.
5.6.8 Reinforcing Fiberglass Ribs
Pipe sizes 2600 mm (102 inch) and higher may be manufactured with
reinforcing fiberglass external ribs to achieve the required stiffness.
5.6.9 Joint Types
The pipe shall have one or a combination of the following joining systems that
shall provide for fluid tightness for the intended service condition.
a) Unrestrained Joints
1. Gasketed bell-and-spigot
2. Gasketed bell and bell coupling for use with spigot and pipe
b) Restrained joints
1. Bell-and-spigot, adhesive bonded
2. Butt-and-wrap, with reinforced overlays
SATORP JUBAIL EXPORT REFINERY
PROJECT
METHOD STATEMENT
ASSEMBLY AND INSTALLATION OF RTR PIPES
METHOD STATEMENT
ASSEMBLY AND INSTALLATION OF RTR PIPES
a thickness of 0.51 ± 0.13 mm (0.020 ± 0.005 in). The interior liner shall be
reinforced with either nonwoven polyester fibers or glass veil surfacing mat.
Polyester or glass veil liner reinforcement is not required on 100 mm (4 in)
and smaller fittings at the mitered joints, provided all gaps at the joints are
completely filled with epoxy resin to act as an effective corrosion barrier and
to prevent the presence of any exposed glass fibers.
5.6.14 All machined or cut surfaces shall be post-coated with catalyzed resin except
for bonding surfaces for field joints and mechanical fiberglass threads. Post-
coating shall be performed within four hours of machining or other surface
preparation.
5.6.15 Adhesive-bonded joints, if any, shall be bell and spigot type and shall not
require a field-applied overwrap to develop the required strength.
5.6.16 Flanges, if provided, shall be flat-faced, or flat-faced with a confined O-ring
gasket groove.
5.6.17 All pipe, fittings and flanges for a particular new installation shall be
manufactured or supplied by the same Vendor to avoid incompatibility due to
intermixing of products from different manufacturers.
5.6.18 Threads shall be per ASME B1.20.1 and shall conform to the requirements of
ASME B31.3, paragraph A 314.2.2. Threaded joints are not permitted in
piping manufactured using any kind of fillers, such as reinforced plastic mortar
piping (RPMP)
METHOD STATEMENT
ASSEMBLY AND INSTALLATION OF RTR PIPES
quarantine & the client shall be informed “ & after which this shall be disposed
as TRGC company procedure.
5.7.2 Upon receipt of the pipe shall be subjected to visual inspection for any damage
during transit, and if defects are found the same shall be intimated to TRGC.
5.7.3 Pipes shall be placed near the excavated trench leaving a minimum safe
distance from the top edge of it as per JERES-S-070.
5.7.4 As RTR Design, support from surrounding soil shall be provided in
accordance with JERMS-L-1029, JERMS-L-1034 & JERES-S-070.
5.7.5 Pipe joined into longer lengths or pipe and fittings in subassemblies should be
lifted with web slings with enough lift points to avoid excessive bending and
dynamic flexing as per JERES-S-070.
5.7.6 Position the pipe on timbers across ditch. Block into position to hold alignment
and prevent lateral movement. For larger diameters, the use of a winch is
recommended to assemble and hold joint as per JERES-S-070.
5.7.7 Joint the pipe sufficiently in advance of the pipe lowering operation, so that no
movement of the pipe will take place at location where joints are being cured.
Pipe spools will be fabricated at above ground to a maximum length by
considering the erection feasibility and the same will be lowered on sand bags
having 150mm height in to the trench, placed at equal intervals as per
JERES-S-070.
5.7.8 With crane or manpower, raise the pipe slightly to remove the timber support
placed below the pipe. While lowering the pipe into the ditch, do not drop or
lower suddenly. Repeat the above operation for each support. Use rope or
webbed sling for lifting pipe as per JERES-S-070.
5.7.9 Suitable foundation support or padding extending shall be provided from the
end the end of encasement and also adequate protection shall be provided in
the road crossing as per project documents/vendor recommendation & as per
JERES-S-070.
SATORP JUBAIL EXPORT REFINERY
PROJECT
METHOD STATEMENT
ASSEMBLY AND INSTALLATION OF RTR PIPES
5.8.1 Thrust and Anchor Block shall be installed as per the engineering standard
and drawings.
5.8.2 The structural concrete for the thrust and anchor block shall be used as per
approved for the underground foundation.
5.8.3 The pipe shall be tested or placed in service when concrete is fully cured.
5.8.4 Thrust blocks (Company Library Drawing JERSD-S-1004, for reference only)
shall be placed at every change in direction for thermoplastic and RTR piping
with the following exceptions:
Exceptions:
a) Thrust blocks may not be necessary for piping in gravity flow systems.
b) Thrust blocks may not be required for 100 mm nominal pipe size and
smaller piping with restrained joints, as defined in Sections 11 and 12 of
this Standard.
5.8.5 If thrust block is required for RTR piping and thermoplastic piping in
accordance with paragraph 18.1 of this Standard, a thrust resistance shall be
provided prior to hydrostatic testing by temporary wooden supports.
Alternatively, the Contractor may choose to place concrete thrust blocks
before hydrotest at the risk of having to remove and replace any thrust blocks
on leaking components.
5.8.6 Thrust blocks shall not cover thermoplastic and RTR piping joints.
SATORP JUBAIL EXPORT REFINERY
PROJECT
METHOD STATEMENT
ASSEMBLY AND INSTALLATION OF RTR PIPES
5.8.7 Plastic pipes such as PVC, UPVC, CPVC, RTRP, HDPE, PP etc shall be
protected from contact with concrete by tape wrapping. Use JERMS stock
number for tape wrap 09-966-251/254/257 or equivalent.
5.8.8 At the edges where a thermoplastic or an RTR pipe or fitting enters or leaves
a thrust block, it shall be wrapped with neoprene wrapping that will protrude
slightly from the block. The thickness and the width of wrap shall comply with
Table 4 of this Standard, unless the manufacturer requires more than one
piece of wrapping.
5.9.1 Bedding, backfilling and concrete supports shall be done as per the civil
drawing.
5.9.2 Bedding in the pipe zone should be sand and must not include rocks larger
than 3/8” or sharp rocks of any size in direct contact with the pipe.
5.9.3 Sand bedding under the pipe should be a minimum of 25% of dia of pipe or
150 mm; sand shall pass a 3/8” screen and not more that 15% shall pass a
#200 sieve.
5.9.4 Accurately grade the trench bottom and sand bed to provide uniform bearing
support for each section of pipe along its entire length, a shallow depression
for
bells and couplings are required. The grade shall have no abrupt changes in
direction or slope except at fittings.
5.9.5 Do not cover the pipe joints until all required pressure tests are performed.
5.9.6 Initial back filling zone extended from the bedding to a minimum of 150 and
above this the crown of pipe shall be achieved.
5.9.7 Sand shall be uniformly compacted around the pipe with special care given
to the bedding beneath the haunches of the pipe. Sand bedding and backfill
should extend a minimum of 200mm above the pipe or clean / sweet sand
SATORP JUBAIL EXPORT REFINERY
PROJECT
METHOD STATEMENT
ASSEMBLY AND INSTALLATION OF RTR PIPES
bedding of 300mm thick above pipe, which will be compacted using water
compaction.
5.9.8 Backfill shall be deposited in 200mm maximum layers to a point at least two
feet above the top of the pipe, each layer being compacted with suitable
tamper.
5.9.9 Mechanical compactors may be used for compaction, provided the harmful
shock loads are not transmitted to the pipe wall.
5.9.1 The clean sand bedding shall be compacted per Section 10.7.2 of this
standard.
5.9.2 Within 300 mm of the top of the pipe, backfill shall be hand tamped, or a
board shall be used to protect the pipe from damage from vibratory plate
compactors.
5.9.3 Backfill above 300 mm sand cover in Non-Traffic area shall be on site
excavation or borrowed materials that meet the following conditions:
a) Not more than 3% organic or decomposable material.
b) No debris.
c) A maximum particle size of 150 mm or one-half the lift thickness, whichever
is smaller.
d) Minimum compaction shall be per down Table of this Standard.
Minimum Compaction
Non-traffic Areas Traffic Areas
65% relative density 85% relative density
per ASTM D4253/ASTM D4254 per ASTM D4253/ASTM D4254
or or
90% of maximum 95% of maximum
density per ASTM D698 density per ASTM D1557
SATORP JUBAIL EXPORT REFINERY
PROJECT
METHOD STATEMENT
ASSEMBLY AND INSTALLATION OF RTR PIPES
5.9.4 Backfill above the 300 mm sand cover in Traffic Area shall meet the
requirements of Section 22.3 of this Standard, except in the final 300 mm of
the backfill. This part of the backfill that is the base of the asphalt pavement
shall meet Class B base material as defined in JERES-Q-006, Table A.
5.9.5 Any sheeting and shoring shall be gradually removed as the backfill
is placed. All voids under and behind sheeting shall be filled as sheeting is
withdrawn.
5.9.6 Sheeting shall be cut and left in place where damage to the pipe may
occur or failure of the trench walls may cause damage or failure of
adjoining buildings or structures.
5.9.7 The pavement base course shall be of the same depth and material as the
original base course. The edge of existing pavement and the base course
shall be primed. The surface course shall be identical to the original
surface course. The patch shall be rolled in both directions with a 5-ton
roller so it is compacted to 96% of Marshall density in accordance with
ASTM D1559.
5.9.8 A bedding layer of clean sand 150 mm in depth is required for all trenches.
The sand shall be free of debris and rocks and compacted to at least 70%
relative density in accordance with ASTM D4253 and ASTM D4254.
Compaction by water flooding is allowed for clean, freely-draining sand
provided the excess water is continuously collected in sumps and pumped
out of the trench. Maximum and minimum densities of a representative
bedding sample shall be determined in accordance with ASTM
D4253 and ASTM D4254 for all locations. In-place density and moisture
content methods and frequency of testing shall be in accordance with
JERES-A-114.
METHOD STATEMENT
ASSEMBLY AND INSTALLATION OF RTR PIPES
METHOD STATEMENT
ASSEMBLY AND INSTALLATION OF RTR PIPES
longer.
5.10.15 The remaining bolts will be installed. All bolts shall extend completely through
their nuts.
5.10.16 At least one (1) complete thread or 3mm which ever is greater shall be visible
from the back side of each nut.
5.10.17 All hydraulic torque wrenches shall have calibration stickers. Records
shall be If a tensioning device is to be used, the stud shall protrude 1 bolt
diameter longed the nut to allow attachment of tensioning device. The
other end of the stud shall extend three threads or 9mm (which ever is
greater) past the nut.
5.10.18 Prior to Hydro test NSH test Engineer/Inspector should identify the flanges
which require torque before test and it to be completed along with the
category ‘A’ items Punch.
5.10.19 Flanges which is marked in the test Packages should be torque except test
limit and those flanges where temporary gasket is installed. (control valve,
and other inline items)
5.10.20 After Hydro test torquing will be done at the test limits and to be inspected.
5.10.21 Copy of bolt torque sequential order and rotational order is attached along
with JERES-L-610.
5.10.22 The table of torque values and bolting category is attached along with
JERES-L-610.
5.10.23 Hand tightening of the bolts will be done. One full thread will be kept visible
beyond the nut.
5.10.24 The torque values of bolt tightening shall be done as per JERES-L-610.
5.10.25 Bolt torque will be done as per the sequential order mentioned in the
specification JERES-L-610 in three passes.25% of the target torque value
will be applied in the first pass, 50% of the second pass, and 100% in the
third pass.
5.10.26 Once the final torque value is reached, the bolts will be tightened in
SATORP JUBAIL EXPORT REFINERY
PROJECT
METHOD STATEMENT
ASSEMBLY AND INSTALLATION OF RTR PIPES
METHOD STATEMENT
ASSEMBLY AND INSTALLATION OF RTR PIPES
METHOD STATEMENT
ASSEMBLY AND INSTALLATION OF RTR PIPES
d) Sanitary sewer and storm water force mains: 1035 kPa (150 psig) or 345
kPa (50 psig) above the pump shut-off head, whichever is greater.
e) Gravity sanitary sewer pipe tested separately: a column of water equivalent
to the rim elevation of the upstream manhole.
g) Gravity storm water sewers and manholes not a part of an oily water sewer
system: none, unless called for in the project specifications.
h) Nonmetallic piping in non-hydrocarbon process applications: 1035 kPa
(150 psig) or 345 kPa (50 psig) above the maximum operating pressure,
whichever is greater.
5.11.9 Plumbing and utility systems within buildings shall be tested in accordance
with the Uniform Plumbing Code (UPC), with the exceptions as listed in
JERES-S-060.
5.11.10 Building firewater systems shall be tested in accordance with JERES-S-050.
5.12 SAFETY
5.12.1 NSH Safety Supervisor shall carry out the safety site inspections to ensure
that safety requirements laid out in the safe work plan are followed during the
testing.
5.12.2 NSH Safety Manager / Supervisor shall review Safety Action Plan and secure
work Permit if necessary prior to start of any activities Job safety analysis will
be strictly followed as per attachment.
5.12.3 Equipment, tools and materials inspection. All equipments for testing shall
have to be inspected by NSH Safety Manager / Supervisor prior to forwarding
to TR Safety Department inspection prior to use at site to ensure their safe
worthiness at work. The inspection reports shall be kept for record.
METHOD STATEMENT
ASSEMBLY AND INSTALLATION OF RTR PIPES
The requirements of the project helath and safety plan shall prevail in respect of
safety requirements for those involved in the Assembly and Installation of RTR
pipes.
The QAlQC manager will ensure that only persons competent to undertake
inspections shall be allowed to do so, having regard to the fact that some
inspections and maintenance activities may only to be undertaken by third
parties organization.
In particular, it is the responsibility of the Manager to consider the following:
Risks
Training and Information
5.13.1 The following risk assessments and does not take the place of the task risk
assessment for the activity concerned.
Risk Assesment
Task Hazard Person at Controls Person
Risk Responsible
METHOD STATEMENT
ASSEMBLY AND INSTALLATION OF RTR PIPES
METHOD STATEMENT
ASSEMBLY AND INSTALLATION OF RTR PIPES
METHOD STATEMENT
ASSEMBLY AND INSTALLATION OF RTR PIPES