The base plate and column can be connected together by using cleats or
by fillet welding.
A machined interface between column and base plate will enable all the
components to work in conjunction with another.
Column steel wedges are inserted between the underside of the base
plate and the top of the foundation.
iii Type of demolition at congested area and what shall he do
The best type of demolition method to be used at congested area is a top-down method which is by
using pusher arm. The other methods are not suitable mainly due to time consumption and also the
impact that will happen during demolition works. For example, using hand demolition will be time
consuming, wrecking ball uses a lot of working space due to the uncontrollable debris and explosive is
also risky due to the vibration it will cause during demolition works that might affect the structure of
buildings close by.
In order to ensure the