Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
.1.I,It: :
1 1 .1. I .1. i
IlL 1 1.11.1 •
Recommended Practice
for
Glass Fiber Reinforced
Concrete Panels
Fourth Edition
prepared by
Substantial effort has been made to ensure that all data and
information in this Recommended Practice are accurate. However,
PCI cannot accept responsibility for any errors or oversights in the
use of material or in the preparation of engineering plans. This
publication is intended for use by professional personnel competent
to evaluate the significance and limitations of its contents and
able to accept responsibility for the application of the material it
contains. Special conditions on a project may require more specific
evaluation and practical engineering judgment.
ISBN 0-937040-67-3
Printed in U.S.A.
CONTENTS
3.6 Joint Sealants and Backer Rods 5.10 Facing / Backing Interaction
3.7 Coatings 5.11 Joints
5.12 Condensation Control
CHAPTER 4— PHYSICAL PROPERTIES 9
5.13 Architectural Details
4.1 Factors Affecting Physical Properties
4.2 Tensile and Flexural Strengths CHAPTER 6—TOLERANCES 35
4.3 Modulus of Elasticity 6.1 General
4.4 Compressive Strength 6.2 Product Tolerances
4.5 Impact Resistance 6.3 Erection Tolerances
4.6 Shear Strength 6.4 Interfacing Tolerances
4.7 Shrinkage and Other Moisture-Induced
Movement CHAPTER 7— MANUFACTURING 41
4.8 Thermal Movement 7.1 Panel Manufacture
4.9 Creep 7.2 Plant Facilities
4.10 Freeze-Thaw Resistance 7.3 Molds
4.11 Fire Endurance 7.4 Proportioning and Mixing
4.11 .1 Joint Treatments: One-Stage Butt Joints 7.4.1 Face Mix
4.11.2 Fire Safing 7.4.2 GFRC Backing Mix
I. 7.5 Spray Application of Mist Coat Appendix G — Facing I Backing Interaction
7.6 Placing and Consolidating of Face Mix Stress Analysis Ratio
- -
composites. No specific time interval is intended (unless fiber strands; it is chopped from roving in the spray-up
otherwise indicated). It is a general term associated with process.
GFRC composite properties after the time-dependent Cladding panel A light weight non-structural GFRC pre
-
changes discussed in Sections 4.2 and 5.2 (usually, but not fabricated building component produced by the spray-up
always, modified by F or T and Y or U). process for use as an exterior wall panel.
Admixture A material added to modify the properties of
-
Clearance Interface space (distance) between two items.
-
subjected in order to simulate their exposure to natural breaking the surface of a panel into areas of 1/4 to 6 in. (6
weathering; the intent is to accelerate any aging effects. to 152mm) across.
(See Ref. 1, Appendix F, Test 10). Creep The time dependent change in dimension or shape
-
Backing The GFRC mix deposited into the mold after the
- temperature of freshly placed face mix and backing during
face mix or veneer has been placed and consolidated. some definite period following placing, spray-up, or finish
Blocking Materials used for keeping GFRC elements
-
ing to assure satisfactory hydration of the cementitious ma
from touching each other or other materials during storage terials and proper hardening of the skin. When the curing
and transportation. temperature remains in the normal environmental range
Bondbreaker A substance placed on a material to pre
-
[generally between 60 and 90 deg. F (16 and 41 deg. C)] it
vent it from bonding to the GFRC, or between a face mate is considered normal curing; when the curing temperature
rial such as natural stone and the GFRC backing. is increased to a higher range [generally between 90 and
120 deg. F (41 and 50 deg. C)] it is considered accelerated
Bonding agent A substance used to increase the bond be
-
curing.
tween an existing piece of GFRC and a subsequent appli
cation of GFRC such as a patch. Draft The slope of the mold surface is relation to the di
-
insert can be embedded. specimen; commonly expressed in pounds per cubic foot
BOP Bend over point (tensile) in some literature; re
-
(pcf) (kg per m_).
placed herein by TY, tensile yield. Ductile Appearing or Pseudo-Ductile Large permanent
-
*The abbreviations A or E, F or T, and Y or U are used in this Recommended Practice in appropriate combinations to de
scribe particular conditions. For example, AFY indicates that state of material in the Aged Flexural Yield condition.
V
E (Early)* One of two general ages in the life of GFRC
- GRC Glass Reinforced Concrete or Glass Fiber Rein
-
composites. Often but not always associated with 28 days. forced Cement; intended to be synonymous with Glass
Specifically an age prior to the time-dependent property Fiber Reinforced Concrete.
changes (usually, but not always, modified by F or T and Y Gravity anchor Rods, bars or plates which transfer the
-
inforcement of plastics, but not recommended for use with connecting GFRC units or attaching or accommodating ad
portland cement. jacent materials or equipment. Hardware is normally di
Efflorescence A deposit of salts, usually white, formed
-
vided into three categories:
on the surface of the skin. It is a substance that has Contractor’s hardware Items to be placed on or in the
-
emerged in solution from within the GFRC backing or face structure in order to receive the GFRC units, e.g.,
mix and deposited by evaporation. anchor bolts, angles or plates with suitable anchors.
Erection drawings A set of instructions in the form of
-
Plant hardware Items to be part of the GFRC units
-
diagrams and text. The instructions typically describe the themselves, either for connections and GFRC erector’s
location and assembly details of each GRFC element at the work, or for other trades, such as mechanical, plumbing,
construction site. glazing, miscellaneous iron, masonry, or roofing trades.
timate (U). The apparent maximum stress when GFRC is the installation of the GFRC units.
subjected to flexural loading (Mdl). This is the most com Insert A threaded connecting or handling device cast into
-
monly determined measure of strength (herein usually, but a GFRC panel or the structure. Inserts are machine or coil-
not always, modified by A or E and Y or U). threaded to receive a bolt or slotted to receive a bolt head,
Face mix A proportined mix of unreinforced mortar, con
-
nut, strap anchor or threaded rod.
crete and admixtures at the exposed face of GFRC unit LOP Limit of proportionality (flexural) in some litera
-
used for specific appearance reasons.. ture; replaced herein by FY, flexural yield.
Facing aggregate An aggregrate complying with ASTM
- Matrix The cement paste into which various amounts of
-
C33 except for gradation, predominately retained on the aggregate particles and/or glass fibers are incorporated.
No. 20 (850 zm) sieve with a 1/4 inch (6mm) maximum Mist coat A thin [1/8 in. (3mm) nominal] coat of port
-
age, of the glass fiber to the total composite; can be by Modulus of Elasticity Ratio of normal stress to corre
-
to the panel frame. See illustration for parts of anchor. Moisture migration The movement of moisture through
-
the skin.
FRC Fiber Reinforced Concrete or Fiber Reinforced Ce
-
ment; concrete containing dispersed, randomly oriented Moisture-induced movement Volume change of the skin -
steel, plastic, natural or other fiber; not intended to by syn due to change in moisture content. Volume change may be
onymous with GFRC. contraction or expansion.
Form See Mold.
-
Mold The container or surface against which fresh GFRC
-
mended Practice, GFRC is a sprayed composite with an studs and track and/or structural shapes used to support and
absolute minimum of 4 percent by weight of total mix with stiffen the skin and provide a means for connecting the
a minimum design thickness of 1/2 in. (13 mm) as pro skin to the building frame.
duced by a PCI Certified Plant Group G. -
PEL Proportional elastic limit in some literature and used
-
vi
to apply to either flexural or tensile values; replaced herein members and such units and adjacent materials.
by FY, flexural yield and TY, tensile yield. Sealers Clear chemical compounds applied to the surface
-
Practice).
seismic load of the skin to the panel frame.
Plastic cracking Short cracks often varying in width
-
glass fiber and water together into a mortar and subse ing manufacture to facilitate and/or improve the processing
quently spraying or casting with vibration, press-molding,
and performance of the fiber.
extruding or slipforming the mortar into a product.
Skin The thin exterior section of a panel, including the
-
ment paste. —
panel separated by control joints.
the hardening of the cement paste on a GFRC surface cosity of a cement slurry.
within a time period and to a depth to facilitate removal of Slurry A mixture of water, portland cement, sand, and
-
this paste after the GFRC element is otherwise cured (a other additions or admixtures in suspension.
method of producing an exposed aggregate finish).
Spray-up process The simultaneous depositing of glass
-
ate a desired architectural effect; (2) The depth of exposure together by sizing. Typical AR glass fiber strands contain
of the facing aggregate of an exposed aggregate finish. 102,204, or 408 fibers.
Rib (1) A stiffening member backing the skin; (2) A pro
-
Stripping The process of removing a GFRC element
-
jection from the panel face. from the mold in which it was sprayed.
Roving A group of glass fiber strands gathered together
-
Stud frame See Panel Frame.
-
composite formed by attaching two skins separated by an Test board A test sample produced by spraying up simul
-
insulating core. taneously with and alongside the production panel from
which coupons are cut for testing.
Scrim A manufactured fabric having open area construc
-
) using AR
tion (windows) of over 0.062 sq. in., (0.40 cm
2 Thermal movement Volume change of the skin due to-
glass fiber strands. It is laid up by hand to reinforce an temperature change of the skin. Volume change may be
area of the GFRC backing. contraction or expansion.
Sealants (joint sealant)- Material used to exclude water
- Tolerance Specified permissible variation from stated re
-
and solid foreign materials from joints between GFRC quirements such as dimensions and strength.
vii
Trowel surface The surface of a panel away from the
-
Wythe Each continuous vertical section of a wall.
-
form or mold made by smoothing with a trowel or roller. Wythe Equivalent Thickness The thickness of a solid
-
viii
CHAPTER 1 — INTRODUCTION
1.1 —Scope
This Recommended Practice is intended to provide infor
mation relating to the planning, preparation of specifica
tions, design, manufacture and installation of glass fiber re
inforced concrete (GFRC) panels.
Data presented covers portland cement based composites
manufactured by the spray-up process using special alkali
resistant glass fibers that are chopped and sprayed onto a
form with an appropriate cement/aggregate slurry (see Sec
tion 7.7). The premix method of manufacturing concrete
composites is covered in Appendix J. Polymer modified E
glass fiber reinforced concrete (P-GFRC) that uses a mini
mum of 10 percent of a special polymer compound to pro
vide alkali protection for the E-glass is not covered in this
publication.
The primary concern of this publication is thin-walled ar
chitectural panels made of glass fiber reinforced concrete
by the spray-up process under controlled factory condi Fig. 1. In the spray-up process, a continuous strand of
tions. These cladding panels are capable of accepting and glass fiber is fed into the compressed-air-powered gun,
transferring wind and self-weight and their own inertial where the strand is chopped into predetermined
seismic loads to the building’s load-resisting system, but lengths and combined with a sand and cement slurry.
are not considered as vertical loadbearing components or as
part of the lateral load-resisting system. 1.3 — Historic Development
This Recommended Practice reflects the present state of The potential of using glass fiber reinforced concrete sys
the art. As significant changes in materials or process tech tems was recognized during the early development work on
nology occur, revisions to this document will be consid glass fiber reinforced plastics carried out in the 1940’s. A
ered. summary of Russian experience up to 1964 is given in Ref.
GFRC is recognized by the four US model codes. See 2. This early experience indicated that portland cement
Section 1.6 composites made with unprotected hE glass (conventional
glass fiber reinforcement used in plastics) were subject to
alkaline attack. Because of this fact, a special glass fiber
12 — General Description product was developed.
Glass fiber reinforced concrete (GFRC) is the term ap Following the successful development of AR (alkali re
plied to products manufactured using a cement/aggregate sistant) glass fibers in the late 1960’s, test programs were
slurry reinforced throughout with alkali resistant glass undertaken to determine the properties of portland cement
fibers. and AR glass fiber . 45 AR glass fibers have
’
3
composites
GFRC does not consist of a single composition, but can been used in the U.S. since early 1970’s.
be manufactured using different combinations of materials
to meet the required properties. Mix composition, degree of 1.4 — Plant Certification
compaction, type of cement, and the proportion, length, The GFRC manufacturing plants shall be certified by the
and orientation of glass fibers may all be varied to produce Precast/Prestressed Concrete Institute, Plant Certification
a specific product. Typically, a GFRC panel consists of 5 Program. Manufacturers shall be certified at time of bid
percent by weight (of total mix) of alkali resistant glass ding. Certification shall be in Product Group G.
fiber (absolute minimum of 4 percent) combined with a The certification of a GFRC producing plant by PCI en
portland cement/sand slurry. Methods of manufacture vary, sures that the plant has developed an in-depth quality sys
but spraying either by hand equipment onto a form of the tem that is based on time-tested industry standards. Every
desired shape and size, or mechanically on a production plant must document their specific practices in a Quality
line are most common (Fig. 1). System Manual. The QSM must be submitted to and ap
It is important to understand that the material is a compos proved by PCI; then updated at least annually. In addition,
ite with reinforcing elements randomly distributed through every company must have at least one year of production
out the matrix, unlike reinforced concrete where the rein experience prior to the initial audit. Participants may be ei
forcing steel is placed primarily in tensile stress areas. ther PCI producer members or non-members.
1
The glass fiber reinforced concrete products industry has weight and its own inertial seismic loads to the building’s
taken steps to publish standards for design, production, in load resisting system. GFRC panels are used primarily as
spection and testing. These are contained in PCI Manual cladding or fascia panels.
for Quality Control for Plants and Production of Glass In terms of creative architectural design, the possibilities
Fiber Reinforced Concrete Products, MNL-130. Audits and of shape variation inherent in the GFRC manufacturing
grading of GFRC products are based on MNL- 130. A plant process provide a wide range of opportunities. The de
is audited a minimum of twice each year. These are unan signer can choose from deep reveals to complex rectilinear
nounced audits. Auditors are independent, specially trained and curvilinear shapes, such as short radius curves, wide
engineers accredited by PCI. They are employed by a sin sweeping arcs or 90-degree angles. Properly designed pan
gle consulting engineering firm under contract to PCI els with appropriate configurations and multiple skin seg
which ensures consistency for every plant. ments on a single panel frame have been made up to 30 ft
The audit covers all aspects of production and quality (9 m) in length with 1/2 in. (13 mm) skin thickness.
control as well as engineering and general plant practices. GFRC systems can be designed to provide a 2-hour fire
During each audit, stored products are reviewed. Selected resistance rating using fire rated insulation and drywall. In
panels are measured and compared to shop drawings to addition, GFRC does not contribute to the fire load of the
verify conformance with tolerances. Product evaluations building.
performed by in-house quality control personnel are also GFRC is recognized by the four US model codes. See
reviewed to determine if regular plant quality control pro Section 1.6
cedures are correct and effective. GFRC panels can be produced with or without a face mix
PCI certification ensures adherence to a pre-approved, in with decorative aggregates. In either case, the cementitious
dustry endorsed, quality assurance program. It does not in material produces a durable, lightweight wall for the struc
volve inspection and/or judgment of product quality on ture. With a face mix, GFRC cladding panels are indistin
specific individual projects. A current listing of all PCI guishable in exterior appearance from traditional precast
Certified Plants is published quarterly in PCI’s ASCENT concrete panels.
magazine. A convenient searchable list is regularly updated A wide range of surface finishes may be achieved by us
on the Internet at: www.pci.org. ing exposed aggregate face mixes, integral color, white ce
ment, textured or featured finishes, or by using veneer-
faced panels; the designer has a wide latitude for free archi
1.5— Applications and Advantages
6 tectural expression.
GFRC cladding panels can be designed as wall units, win
Multiple integral colors and finishes can be achieved
dow wall units, spandrels, mullions and column covers.
within one panel, expanding design possibilities. Color
Custom designed in sizes to suit the modular planning of
transitions can occur in a greater variety of locations within
the building, their largest dimensions may be vertical or
the panel, and in more intricate detail as compared to other
horizontal. GFRC is also suitable for use as fascia panels,
materials.
soffits, sun screens, mansard roofs and interior feature pan
Exact replicas of original ornamental work, e.g., terra
els. GFRC architectural panels will generally weigh from cotta, from historic buildings can be made of GFRC.
10 to 25 pounds per square foot (0.5 to 1.2 kPa) depending
on surface finish, panel size and shape, and arrangement of
panel frame. 1.6— Building Codes
The lightweight GFRC panels are in general less costly to GFRC is covered in Section 1903.11 of the Uniform
transport because more panels can be carried per truckload. Building Code
; and in ICBO’s Evaluation Report ER-
49
435949; Section 1406.3 of the National Building Code
;
87
The light weight of GFRC panels allows the contractor to
quickly and efficiently erect panels even in hard-to-reach Section 1910 of the Standard Building Code
; and Table
88
areas with smaller, less expensive cranes. High early im 719.1(2) items 15-1.10 and 15-1.11 of the International
pact strength minimizes handling and erection damage. Building Code
96
The low weight of GFRC panels decreases superimposed
loads on the building’s structural framing and foundation, 1.7 —Types of GFRC Panels
usually providing savings in multistory construction and in Currently, the single skin GFRC panel is the predomi
areas with poor supporting soil. Its light weight also makes nantly used panel in the United States. These panels have a
it ideal for use on low-rise frame buildings where heavier typical GFRC backing thickness from 1/2 to 5/8 in. (13 to
cladding systems would increase the size of framing mem 16 mm), not including the exposed aggregate face mix or
bers required. In building rehabilitation or retrofit projects, veneer finish, when used. However, design requirements or
the use of GFRC panels for recladding minimizes the load panel size may call for a thicker backing or the use of stiff
added to the existing structure. eners. In no case should the minimum design thickness of
Currently, GFRC is not considered as a vertical loadbear the backing be less than 1/2 in. (13 mm).
ing component or as part of the lateral load-resisting sys Unless the panel has a functionally strengthening shape,
tem, although it can accept and transfer wind and self- GFRC properties dictate the use of stiffeners on panels of
2
Fig. 2. Typical panel frame, box, upstand GFRC skin stiffeners.
any appreciable size. Stiffeners commonly used include dition, the panel frame provides a support for attaching fur
prefabricated, plant attached, cold formed steel studs or ring elements for the interior finish, drywall, and window
structural tubes; upstanding, single skin ribs formed on the frame. Furthermore, this system provides a cavity for in
back of the panel; and integral ribs formed on the back of stalling insulation and electrical, mechanical and telephone
the panel by spraying over hidden rib formers, such as ex conduits.
panded polystyrene sthps (Fig. 2). Each of these methods Sandwich panels are usually constructed with two outer
reinforce and stiffen the GFRC skin and provide a means
skins of GFRC separated by a lightweight insulating core.
for connecting the panel to the supporting structure.
As with the single skin GFRC panel, this panel also has a
While each method of stiffening has advantages, use of
panel frames is the most economical and preferred method GFRC backing thickness for each wythe between 1/2 to 5/8
for stiffening panels in the United States. Sometimes, com in. (13 to 16 mm). Specific guidelines need to be developed
plex shapes or exposure of the steel panel frame to the to overcome thermal and moisture-induced bowing and
weather dictates the use of self formed ribs (Fig. 2). In ad- warping of sandwich panels which may cause cracking.
3
CHAPTER 2— PROJECT RESPONSIBILITIES
JJ
5
Table 1. Design Responsibilities.
Responsibility of the
Contract Information Supplied by Manufacturer of GFRC Units
Designer (ArchitectlEngineer)
Option I
(erection
detailing The manufacturer shall make shop drawings
Provide complete drawings and specifications and production draw ings ), as requ ired, with detai ls as
requ irem ents
all aesthetic, functional and structural shown by the desig ner. Mod ifica tions may be sug
plus dimensions, gested that, in manufacturer’s estim ation , wou ld im
s, struc tural soun dnes s or perfo rm
prove the economic
GFR C insta llatio n. The man ufac turer shall
ance of the
. Full re
obtain specific approval for such modifications
pane l desig n, inclu ding such
sponsibility for the GFRC
, shall rema in with the desig ners. Alte rna
modifications
mete rs estab
tive proposals remain within the para
sable to give
lished for the project. It is particularly advi
favorable considera tion to such prop osals if the modifi
are sugg ested so as to conf orm to the manu
cations
facturer’s normal and proven proc edur es.
Option II
but The manufacturer has two alternatives:
requ irem ents all neces
Detail all aesth etic and func tiona l (a) Submit erection and shape drawings with
ce of the approval
specify only the required structural performan sary detai ls and desig n infor mati on for the
rman ce shall inclu de all desig ner.
GFRC units. Specified perfo and ultimate responsibility of the
their points general ap
limiting combinations of loads together with (b) Submit erection and shape drawings for
icati on. This infor mati on shall be supp lied in me respo nsib ility for part of the struc
of appl proval and assu
unit can be desig ned but not their effect
such a way that all details of the tural design, i.e., the individual units
beha vior of othe r parts of the pting this prac tice may ei
without reference to the on the building. Firms acce
The divisio n of respo nsib ility for the design ) draw ings them selve s, or com miss ion
structure. ther stamp (seal
stamp the
shall be clearly stated in the contract. engineering firms to perform the design and
drawings.
shall be
The choice between alternatives (a) and (b)
een the desig ner and the man ufac turer
decided betw
clear ly state d in
prior to bidding with either approach
er alloc ation of desig n re
the specifications for prop
sponsibility.
responsibil
Experience has shown that divided design
lems . It is essen tial that
ity can create contractual prob
n respo nsib ility is unde rstood
the allocation of desig
ly expr essed in the cont ract docu men ts.
and clear
where the
The second alternative is normally adopted
desig n engi neer to assist
architect does not engage a
in the design.
Option III
e in the prelim
ce require- The GFRC Manufacturer shall participat
Cover general aesthetic and performan mary design stage and the deve lopm ent of the final de
prov ide enou gh detai l to define the and shall
ments only and tails and spec ifica tions for the GFR C units
of work. an effic ient de
scope work with the design team to provide
ides the engi neer ing de
sign. The manufacturer prov
units and their conn ectio ns to the
sign of the GFRC
shall work with the desig n profe ssion als
structure and
inter facin g work . The
on the team to coordinate the
at various
manufacturer shall submit shop drawings
pleti on for coor dina tion with othe r work.
stages of com
I-
CHAPTER 3— MATERIALS
3.2 — Reinforcement
3.2.1 — Alkali Resistant Glass Fiber
Only high zirconia (minimum 16 percent) alkali resistant
glass fibers specifically designed for alkali resistance and
use in concrete should be used (Fig. 3). (See Appendix K.)
Specifically, unprotected “E’ glass, the type designed for
use in reinforced plastic should not be used.
Alkali resistant glass fiber reinforcement is available in
roving, chopped strand and scrim forms. The use of roving
for spray-up and chopped strands for premix is most com
mon, with scrim being used for selective reinforcement in
areas of high stress concentrations.
Glass fiber lengths of 1 to 2 in. (25 to 51 mm) are most
common in GFRC production. Lengths less than 1 inch (25
mm) are used for special situations.
Fig. 3. Glass fiber roving
3.3 — Panel Frame and Hardware rosion resistant. Materials that are galvanized should con
3.3.1 — Panel Frame form to the requirements of ASTM A153 . Materials that
25
The panel frame for a GFRC panel may be fabricated are cadmium plated should conform to the requirements of
from light gage steel and/or structural steel shapes. Light ASTM B766 . Materials that are zinc plated should con
26
gage steel materials should be either painted or galvanized form to the requirements of ASTM B633 . Inserts should
27
to inhibit corrosion. Hot dip galvanizing of the frame after be compatible with or isolated from the other materials
fabrication is not recommended, as it can cause distortion. with which they will come in contact in order to avoid un
The necessity for corrosion protection of the panel frame wanted chemical or electrochemical reactions. Ductile ma
members depends on the thickness of the material and the terials should be used. Hardware, which is specified to be
aggressiveness of the atmosphere. Under normal circum protected with paint, galvanizing or plating should be
stances, structural steel sections equal to or greater than touched up if the coating is damaged. If welding is required
3/16 inch (5 mm) in thickness will not require corrosion as part of the field assembly, the welded area should be
protection. cleaned and touched up with zinc-rich paint if galvanized,
Light gage steel should conform to ASTM A1011 15 or or if painted, with matching paint.
A1008’ Grades A, B, C, or D, of
,
6 Sectio n A3.1 of the AISI The allowable load on any anchor or insert molded into
Specifications’ and should be prime-
7 painted with a rust-in the GFRC skin should be determined by the results of con
hibitive paint conforming to MPI 79 or SSCP- Paint 25 or trolled tests duplicating the loading condition in which it is
galvanized in accordance with ASTM A653’ 8 or 19
A924 used. Many inserts used in GFRC panels that have been de
with a minimum G-60 coating. Gage, yield strength and signed and tested by the insert manufacturer for use in pre
size of studs, tubes and tracks should be shown on the ap cast or cast-in-place concrete will develop different
proved shop drawings. strengths in GFRC. Anchors and inserts for use in GFRC
Structural steel tubes should conform to ASTM A500 .
20 require testing to determine their suitability, see Sections
Grade B or ASTM A5 1321. Other structu ral shapes should 5 .7.2.3 5 .8, and 8 .6.
,
confor m to ASTM .
22
A36 Memb er size and yield strengt h 3.3.3— Handling and Lifting Devices
should be shown on the approv ed shop drawin gs. Handling and lifting devices should be fabricated from
3.3.2 — Anchors and Inserts ductile material because they are subjected to dynamic
Steel bars for anchors should conform to the appropriate loads. They should be designed to lift and transport the
require ments of ASTM A29 23 or A108 . Yield strength
24 GFRC panel in its various positions considering special
should confor m to design minim um and maximum. loadings such as wind or impact with an appropriate factor
Anchors incorp orated into the GFRC skin should be cor of safety. When permanent connection hardware is used for
8
handling, it should be properly designed for such additional 3.6 — Joint Sealants and Backer Rods
service without any danger of subsequent damage to such The most commonly used sealants with GFRC wall panels
connections or their performance. are field molded sealants. For a complete reference to these
3.3.4 — Connection Hardware . The recommendations of
sealants refer to ASTM C1193
30
Miscellaneous structural shapes used to support or attach the sealant manufacturer should always be followed re
GFRC panels to the structure should be fabricated from garding mixing, surface preparation, priming, application
steel conforming to ASTM A36 or A500. Light gage shapes life and application procedure.
should conform to ASTM AlOll or A1008 and A653, Only high performance one- or two-part sealants meeting
A924, with MPI 79 or SSPC Paint 25. Under normal cir ASTM C920, such as polysufides, urethanes, silicones, or
3
cumstances, connection hardware equal to, or greater than other sealants that can meet Federal Specifications TT-S
3/16 inch (5 mm) thick wifi not require corrosion protec 00227e (polysulfides) Type II, non-sag: TT-S-00230c (ure
tion. thanes) Type II, non-sag: or TT-S-001543a (siicones) are
recommended for sealing joints in GFRC panels. Sealants
should withstand joint movements of at least ± 25 percent
3.4 — Integral Rib Farmers of specified joint width. Where greater movement capabil
Rib formers may be used to produce ribs, which provide ity may be required, manufactures of low modulus sealants
strength and stiffness for the GFRC panels. Expanded poly should be consulted.
styrene foam and polyurethane foam are the most common Joints are usually primed and primers require careful ap
materials used. Care should be exercised when these mate plications. Some will leave a stain on the face of the panel
rials are used where ambient service temperatures are if brushed along the joint edge.
greater than 140 deg. F (60 deg. C). Hollow sections can be The backup rod or bondbreaker should be as recom
made by using GFRC or cardboard shapes to form the void mended by the sealant manufacturer.
and then overspraying with GFRC backing mix. If GFRC The contractor responsible for sealing should test the
forms are to be incorporated into a panel they should be sealant for adhesion to on-site installed panels or to panels
prevented from drying prior to their incorporation to mini in the plant prior to proceeding with the whole job.
mize restraints due to differential drying shririlcage.
3.7 — Coatings
3.5 —Welding Coatings may be applied to GFRC panels. Latex masonry
The welding of panel frame members should be in accor paints and water-resistant stains in a methylmethacrylate
dance with the most recent AWS welding codes; AWS base offer a wide range of color choices. A clear coating of
for structural steel and AWS Dl 329 for sheet steel.
Dl .l
28 silane or siloxane may be applied to the face and back sur
Frames can be welded using the shielded metal arc welding faces of a panel to reduce moisture absorption (moisture
(SMAW), flux cored arc welding (FCAW) or gas metal arc movement) and efflorescence. It is important that the coat
welding (GMAW). ing be water vapor permeable to allow the panel to
Electrodes for SMAW should conform to the requirements “breathe. Manufacturers of coatings should be consulted
of AWS AS .1 or AS .5. Electrodes (wires) for FCAW should for details of application, performance and testing of coat
conform to the requirements of AWS AS .20. Electrodes ings prior to use on GFRC panels. In most cases, except for
(wires) for GMAW should conform to the requirements of the silanes or siloxanes, it will be necessary to adequately
AWS A5 .18. The type and grade of electrode should be as roughen the surface in order to obtain good adhesion of the
recommended by AWS for the grade of material being coating. One method is to lightly sandblast the surface to
welded be coated.
9
I
The physical properties of GFRC depend greatly on the cause problems with fiber and slurry laydown as well as
mix composition, glass fiber content and its length or on compaction and consolidation during rolling.
entation in the composite, polymer content, and the overall The orientation of reinforcing fibers also affects compos
ite physical ’
proper
3
32 3 ties 34 Sprayed-up GFRC composites
quality of workmanship incorporated during the manufac
turing process. Therefore physical properties of GFRC to are intended to have a two-dimensional random fiber orien
tation. However, if care is not taken during production,
be used in design must be determined for each individual
fibers can become unintentionally aligned parallel in one
manufacturer and each mix design used.
direction or another, resulting in a composite with sigriifi
Early (28-day) properties of GFRC are typically used to
cantly different properties when tested along different axes.
determine appropriate design parameters and to monitor
GFRC composites must also be compacted and consoli
quality control throughout manufacturing. Unaged GFRC
dated to achieve adequate fiber embedment and composite
is a relatively strong, tough, pseudo-ductile material. It
density, as well as the required design thickness. Failure to
must be anticipated that GFRC will exhibit gradual and
achieve adequate composite compaction and consolidation
permanent reductions in strength and strain capacity when
will have adverse affects on strength properties and can
exposed to an outdoor environment (natural aging). The
cause changes in the material response to both temperature
rate at which natural aging of GFRC occurs is environ
and moisture. GFRC skin permeability may also be ad
ment-dependent. GFRC products exposed to an outdoor en
versely affected. Flexural and tensile strength and modulus
vironment will, in most cases, reach a fully-aged condition . Poor consolidation can
of elasticity vary with density
35
within the intended life span of the product. Therefore, also lead to composite deterioration due to freeze/thaw cy
GFRC products must be designed to ensure that stresses re cles.
sulting from in-service conditions are kept within the The required (design) thickness for GFRC is determined
strength and strain limits of the fully-aged material. by the panel design engineer. Since GFRC is a relatively
thin material to begin with, even small thickness variations
4.1 — Factors Affecting Physical will have significant effects on skin stresses. Therefore
Properties GFRC thicknesses should always be within thickness toler
Variations in mix composition can result in variations in ances specified. In production, GFRC backing is often
composite physical properties. Cement/sand ratios ranging manufactured with a target thickness 1/8 in. greater than
from 1:1 to 3:1 have been used within the industry. Grada the design thickness in order to meet the specified thick
tion of the sand used for slurry mixes is also not standard ness tolerances.
ized. Performance of ordinary portland cements typically Proper curing results in adequate hydration of the cement
used can vary from one source of supply to another. Sev and is necessary to achieve desired fiber- and matrix-de
eral different polymer curing admixtures are currently pendent properties. Prior to the introduction of polymer
curing admixtures to the GFRC industry, adequate curing
available and in use. Therefore, composite mix proportions,
of GFRC composites was both time consuming and incon
constituents, and physical properties, can vary from one
venient. Today, curing of GFRC has become greatly simpli
manufacturer’s plant to another. Manufacturers should be
fied by using polymer admixtures in the cement matrix.
aware of the potential variations in the physical properties
Use of polymer admixtures, in appropriate amounts, has
of GFRC resulting from changes or modifications in mix
been shown to eliminate the need for the 7-day moist cure.
composition.
Sprayed up GFRC is a man-made material, which de
Fiber content, length, and orientation primarily affect the
strengths A glass fiber mands ongoing quality control and quality assurance moni
early tensile and flexural ultimate 4 .
is the optimum for GFRC toring. Therefore, an ongoing quality control and quality
conten t of 5 percen t by weight
I
ts in lower early ulti assurance program is recommended.
mix design s. Lower fiber conten result
mate strengths and higher fiber conten ts can lead to com
posite compaction and consol idation proble ms. Composite 4.2 —Tensile and Flexural Strengths
glass fiber content is contro lled and monito red during The primary properties of GFRC used to establish limiting
GFRC production by perform ing the bag, bucket and wash design stresses are the 28-day flexural yield and ultimate
out tests. strengths. As discussed in Chapter 5, the limiting design
Fiber length also affects composite ultimate strengths and stress in GFRC is based on an assumed aged flexural ulti
compaction and consolidation. For GFRC spray-up, the op mate strength. The assumed aged flexural ultimate strength
timum fiber length is 1 to 2 in. (25 to 51 mm). Shorter is determined based on the average 28-day flexural yield
lengths, although easier to spray, will not provide maxi and ultimate strength of 20 consecutive tests (6 specimens
mum reinforcement efficiency. Longer fiber lengths may each) performed by the manufacturer prior to design.
10
4000
3000
(0
0
0
0
0
0
ii
C,)
C,) 2000 AFU
AFY
1000 IATY=ATU
#
( I I
Aged
I I
I
0.5 1.0 0 0.1 0.2 0.3 0.4 0.5
Strain, %
Strain, %
2 hr
56 3/8 in. GFRC; 6 in. Returns 5 in. Ribs 24 in. (nominal) 5 in. TFB 5/8 in. GWB-C 7-3/8 in.
2 hr5
7 1/2 in. GFRC; 4 in. Studs 24 in. (nominal) 5 in. TFB 1/2 in. + 1/2 in. 6-1/2 in.
1-1/2 in. Returns GWB-C
2 hr 1/2 in. GFRC;** 6 in. Studs 24 in. (nominal) 5 in. TFB 1/2 in. + 1/2 in. 9 in.
1-1/2 in. Returns GWB-X
1 hr
59 1/2 in. GFRC; 5 in. Returns 4 in. Studs 24 in. (nominal) 5 in. TFB 5/8 in. GWB-C 6-1/8 in.
tected with a 5-in. (127 mm) initial depth of the same TFB sity offers good attenuation characteristics. A 3/8 in. (10
insulation as that used in the assemblies. mm) sheet of GFRC at 4 psf (0.2 kPa) provides a STC of
4.11.2 Fire Safing. Fire safing is used to close the gap be 34 (see Fig. 13)3233. However, a complete panel assembly
tween the edge of the floor slab and the GFRC skin. The will provide greater sound reduction conforming to most
gap varies due to the profile of the skin. The gap is filled code requirements.
with mineral wool batt insulation and a sealant is applied to
the top of the insulation. See Fig. 12. Table 3. Calculated depth of ceramic fiber felt
and joint width for various tire endurances.
4.12 — Acoustical Properties Depth (c)
GFRC follows the mass law for sound reduction. For Fire Joint of Ceramic
skins of similar design, but different weights, the sound Endurance Width Fiber Felt
transmission class (STC) increases approximately 6 units
1 hr 3/8 in. 1/2 in.
for each doubling of weight. GFRC’s relatively high den-
2hr 3/8 in. 3/4 in.
Band No.
lhr un. un.
2 hr 1 in. 2-1/4 in.
Ceramic
Fiber Felt
Joint Width
I
Frequency in Hertz
Fire Side
Fig. 13. Relationship of sound reduction and frequency.
15
GFRC Panel
i-Shaped Clips
:•.
Impaling Pins
;:t
1_____ Packing Material-Mm. 4
Pking MateriaMin. 4
Thickness Of 4 PCF Thickness Of 4 PCF
Mineral Wool BaIt Mineral Wool BaIt
Insulation Insulation
). A knowledge of the
is 120 to 140 pcf (1920 to 2240 kg/rn
3 Air permeability of GFRC ranges from 4.6 penn-in. (6.7 x
density gives information on the general quality of manu 10 gmlPa•s.m) for GFRC exposed to 40 percent relative
facture and is used as a measure of plant quality control humidity to 0.2 penn-in. (0.3 x 10 gmlPa•s•m) for GFRC
procedures. exposed to 90 percent relative humidity.
5
4.14 —Thermal Properties The air and water vapor permeances of GFRC decrease as
Thermal conductivity of the GFRC skin is dependent a function of time and storage under natural weather condi
5 The typical
upon composite density and moisture content. tions. These properties are largely those of the cement ma
range of thermal conductivity is 3.5 to 7.0 BTU/in ./ ft?/ trix and compare favorably with those of other building
hr./deg. F (0.5 to 1.0 WmIm
/deg. C).
2 materials ‘
The resistance, R value, per inch of skin thickness ranges
between 0.18 and 0.10 hr. ftZ deg. F/Btu (1.23 and 0.71 m 4.16 — Moisture Absorption
K/W). Moisture absorption varies according to the density and
polymer content of GFRC but will normally be in the range
4.15 — Permeability . Moisture content in an envi
of 8 to 16 percent by weight
52
The GFRC matrix tends to absorb and distribute water ronment of 65 deg. F and 60 percent relative humidity will
throughout the composite uniformly and rapidly but does reach equilibrium in the range of 4 to 8 percent by weight.
not seem to allow passage of water through the skin thick
ness. Laboratory tests have shown that no signs of moisture 4.17 — Property Summary
would appear on the inside of a 3/8 in. (10 mm) sheet of Different manufacturers may achieve different ranges of
GFRC with rain blown onto it by a 73 mph (117 km/h) values of physical properties of GFRC. Specific values of
50 Water vapor permeability of GFRC will range from
wind. properties should be supplied by the manufacturer to the
5 to 11 penn-in. (7.3 to 16 x l0 gm/Pa•s•m) for GFRC designer. For general information, Table 4 gives ranges of
materials made at 0.25 and 0.35 water-cement ratios, re material properties.
16
Table 4. Typical Range of GFRC Properties*
Property 28-day, (E) Aged, (A)
Density (dry) 120 to 140 (pcf) 120 to 140 (pcf)
Direct tension: Yield (TY) 700 to 1,000 (psi) 700 to 1,100 (psi)
Ultimate strength (TU) 1,000 to 1,600 (psi) 725 to 1,100 (psi)
Strain to failure 0.6 to 1.2 (percent) 0.03 to 0.08 (percent)
17
CHAPTER 5— DESIGN
The following notation is used in this Chapter: duction in strain to failure. There is also an associated de
f = limiting GFRC skin flexural stress for factored crease in tensile strength with time’
. This phenomenon
61
loads is called embrittlement. There is also a, not widely held,
= average 28 day flexural ultimate strength (EFU) theory, that chemical attack by hydroxyl ions on surface of
fyr = average 28 day flexural yield strength (EFY) the glass fiber may result in a reduction in the strength of
f’,,= maximum allowable designf’ the fiber”
. Researchers are not fully in agreement as to
62
design strength [f’J determinant if fur is less the mechanism responsible for the observed decrease in
f’ =
El
Even with special alkali-resistant glass compositions, if
moisture is present for cement hydration, the GFRC com
posite still loses significant strength and ductility with ‘ EFY Assumed AFUEFY
time. The leading theory to explain this phenomena is that
ongoing cement hydration results in products, primarily
calcium hydroxide, which penetrate the fiber bundles and
fill the interstitial spaces between the glass filaments. This
increases the bond of the glass fiber to the cement matrix
and leads to a reduction in fiber pull-out, and in turn a re
28 days Time —
Fig. 14. Long-term GFRC composite strength behavior
under typical weathering conditions.
18
5.2.1—Design Philosophy
The procedure for the design of GFRC panels is based on
both the assumption that the aged ultimate strength is at Maintain Frame
Clearance = 1/2 Mm.
least equivalent to the 28-day yield strength, to ensure that
in-service panel stresses are kept below the cracking
strength at all times. Demolding and other handling
stresses should also be kept as low as possible; and ideally,
below the yield strength of the material at all times.
Changes in GFRC properties with aging may affect con
Fig. 15. Reveal and frame clearance.
nections to a lesser degree, but must be considered when
designing connections and evaluating load tests, see Sec Presently, GFRC panels are usually made with a panel
tion 5.7.2.3. Aged properties of GFRC are usually deter frame stiffening system. Currently, there are two methods
mined in the laboratory by subjecting samples to a hot wa of attaching the skin to the panel frame, see Section 5.7.2.
ter bath, or some other regime that has been shown to sim One method uses flex anchors alone to transfer loads from
ulate, at an accelerated rate, the effects of real time in a nat the panel skin to the frame, which is described in Section
ural environment. It is generally impractical to test full 5.7.2. The second and preferred method, uses flex anchors,
sized panels that have been artificially aged. The following for wind load; but transfers the weight of the skin to the
minimum ratios of test load to service load have been sug frame with separate gravity anchors. The anchors are
gested for unaged panels: 1.5 to yield, and at least 4 to ulti welded to the panel frame, and bonded to the skin with ad
mate 65 ditional GFRC called a bonding pad.
The intent of the design procedures herein is to keep the When designing and detailing GFRC panels, it is impor
GFRC backing stresses below the cracking strength by an tant to keep the panel frame isolated from the skin, so that
adequate margin. This is done by keeping factored strength it does not create undue resistance to in-plane volume
greater than factored loads. Strength is assessed by com changes. The distance between the skin and the frame often
puting the stresses by the straight line theory- that is; flex varies due to the profile of the panel. The distance must be
ural stress and strain are both proportional to distance from adequate to permit unrestricted access by the workers for
the neutral axis. thorough integration of the bonding pad to the panel skin.
Structural performance is also a function of configuration. Panel edge returns and surface recesses (Figs. 15 and 38c)
Recognition should be given to the effects of shape, re often control the dimension from the panel skin to the
turns, recesses, plate action, and solid, hollow, or foam- panel frame, and in turn to the building frame.
filled stiffening ribs (Fig. 2) on structural performance.
It should be recognized that the design procedures in this 5.3—Design Loads
chapter primarily address panelized wall systems. As with GFRC panels are designed for stripping, handling, and in
many other materials, including precast concrete and terra stallation loads; usually by the panel manufacturer. Service
cotta, many applications, such as ornamental and historic loads are set by the governing building code, and are multi
replications, are designed and fabricated based on experi plied by the appropriate load factor. Minimum load factors
ence and previous successful use, rather than rigorous are set by the governing building code, but they should not
mathematical procedures. This practice has been followed be less than those in Section 5.3.2.
for centuries, particularly with developing materials, and is
not to be discouraged through rigid application of the pro 5.3.1—Panel Service Loads
cedures in this publication. Architects and engineers, how Panel design must consider dead, live, and environmental
loads; including wind, earthquake (if applicable), tempera
ever, should be aware of the material behavior related to
ture, and moisture effects
.Service loads set by the govern
68
aged strength, ductility, and volume change characteristics
ing building code should be considered only as minimum
discussed in this publication when considering these types
requirements. There may be situations where additional
of applications for GFRC.
considerations with respect to loads should be considered,
This chapter emphasizes those aspects of panel design re
such as:
lated to the panel skin and its anchorage to a panel frame.
Gravity Load Effects: Gravity loads associated with the
The design of the panel frame is treated in Section 5.7. For
weight of GFRC panels. Three-dimensional panels often do
more information on the connection of the panel frame to
not result in pure in-plane stresses. Skin bending stresseses
the structure see Refs. 66 and 67.
associated with gravity loads should be considered in de
5.2.2—Panel Stiffeners and Methods of Support sign. See Fig. 16.
It is not practical to make the panel skin very thick. To al Wind Load Effects: Variation in wind load due to sur
low larger panels, stiffening is used. This is usually accom rounding structures, or to the geometry of the structure
plished by anchoring the skin to a steel panel frame, by the should be considered in design. Since GFRC panels are
introduction of stiffening with panel shape, or with integral light in weight, wind load is a more significant part of the
ribs incorporated into the back of the panel. total design load than it is with heavier concrete panels.
19
Struts
a) b)
Earthquake Load Effects: Inertial forces developed in (b) Cyclic moisture changes in the panel skin.
panels during seismic events must be resisted. Special con (c) Differential shrinkage caused by unequal shrinkage
sideration should be given to three-dimensional panels coefficient between two different materials such as
where inertial forces can result in skin bending stresses. GFRC backing and architectural face mixes (if used),
Use of seismic anchors reduces load on flex anchors, see see Section 5.10.
Section 5.7.2.2 and Fig. 28.
5.3.2—Load Factors and Combinations
Volume Change Effects Thermal And Moisture: Ex
— GFRC uses strength design concepts where both the
--
pansion and contraction due to changes in temperature and material strength and the loads are factored. Minimum
moisture content are three dimensional or volumetric. In service loads stated in the governing building code, along
many respects their effects are the same and can be as with the additional load conditions and considerations
sessed similarly. Panels should be designed for horizontal stated in this Recommended Practice, should be considered
and vertical contraction and expansion without buckling, when assessing various load combinations. The following
opening of sealed joints, excessive stresses within panel load factor combinations should be considered as mini
components or fasteners, or other detrimental effects. Due mums:
to the thinness of the panel skin its response to temperature
or moisture change is usually faster, and the effect often 1.4 D 1.7 L
+ (5-1)
greater, than in thicker concrete panels. Volume change ef
fects are usually greater than wind load, and often control 0.75 [1.4D+ 1.7 L+ 1.7 (greater of Wor 1.1 E)j (5-2)
the design of the panel; especially if the panel has an archi 0.9D+1.3(greaterof Worl.1E) (5-3)
tectural face mix. Panels with architectural face mixes re
quire special considerations as described in Section 5.10. 1.4 D + 1.7 (greater of M or T) (5-4)
0.75 [1.4D+1.7(greaterof L,Worl.1E)
Temperature considerations should include:
+ 1.6 (greater of M or T)] (5-5)
(a) Gross thermal movement of panel for temperature
changes, consistent with geographical location. 1.1[1.2D + l.OE+0.5L] (56)*
Depending on weather, exposure, panel color, etc. (5.7)*
1.1[1.2D + 1.OE + 1.6(greater ofM or T)]
facade surface temperature can be 20 to 80 deg. F.
(11 to 45 deg. C.) greater than ambient temperature where:
due to solar heat gain.
(b) Differential thermal movement characteristics D = Dead Load
between the GFRC backing and architectural face E = Earthquake Load
mixes (if used), see Section 5.10. L = Live Load
Moisture considerations should include: *Note: Equations 5-6 and 5-7 apply only where 1997
(a) Initial drying shrinkage in the panel skin. Uniform Building Code is in effect.
20
M = Effects of Moisture Change dimensions; (2) to allow for variability in test methods; (3)
T = Effects of Temperature Change to allow for inaccuracies in the design equations; (4) to re
W = Wind Load flect the degree of ductility, and required reliability, of the
Depending on local conditions, where the International member under the load effects being considered; and (5) to
Building Code is in effect, if its provisions are more strin reflect the importance of the member in the structure.
gent they may govern the design. s = shape factor. The basic strength test for GFRC is a
The first four load factor combinations are the same as in flexure test on a solid rectangular specimen. Stress redistri
ACT 318. For cladding panels there is seldom a live load, bution occurs to different degrees in other cross sections, at
however window washing procedures may be a considera times approaching a tensile condition. To account for this,
tion, but would probably not occur with higher wind load. the following shape factors are suggested: solid rectangular
The factor for moisture and temperature is greater than in (including single skins with or without facing), 1; flange,
ACT 318 due to the uncertainties in values and calculation box, or I sections, 0.5. Other values may be used if sub
procedures, and the potential effect if underestimated. If stantiated by test.
there is a reasonable probability of a higher volume ‘change
effect due to a combination of the two, especially initial f’ = the lesser of:
drying shrinkage and temperature, that is greater than ei f’ =fyr (1t V) (5-9)
ther maximum alone, judgment may indicate that a combi f’uy = 113 fur (1t V) (5-10)
nation be used. In some circumstances, creep can reduce f’ max=
20 (5-11)
and:
these effects, but the rates at which moisture and tempera
f’ = assumed aged ultimate flexural strength for de
ture changes and creep occur are difficult to define, see
sign and quality control purposes. It is taken as
Section 5.10.
that value which, statistically, no more than 1%
of the tests will fall below. See Appendix B for
54—Limiting Stresses (Strength) a sample determination.
In determining design conditions, service and environ f’ = design strength [f’ul determinant if ur is less
mental loads (or stresses) should be factored and combined than 3 times fyr
to establish the highest applicable value, see Appendix H. f’, = design strength [f’i determinant if fyr is more
In addition, panel geometry should be considered when de than 1/3 of fur
termining the effects of gravity, wind, earthquake, tempera fur = 28-day flexural ultimate strength
ture, and moisture induced stresses. Three dimensional (EFU).
fyr = average* 28-day flexural yield strength (EFY).
panel configurations can cause differential conditions with
respect to temperature, moisture, and wind effects, as well t = students t, a statistical value to allow for the
as gravity induced bending conditions in the skin. Changes number of tests expected to fall belowf’. See
in panel geometry, especially thickened sections, ribs, stiff Appendix A.
eners, returns and architectural face mixes can cause in V.,, ,V = coefficient of variation of the yield, ultimate
creased stiffness that may restrain the panel skin and create flexural test values.
VyUy/fyr and Vu=Uu/fur
additional stress.
°y’ u = sample standard deviation (n-i) of the yield,
Stresses imposed on the panel skin during stripping of the
ultimate flexural test values.
panel from the mold, handling, transporting, or erecting
should be kept as low as possible; and ideally, below the A maximum effective flange width of 24 times design
yield strength of the material at all times. thickness beyond corners or intersections may be used for
It is the intent of this procedure that skin forces be resisted stress calculations, as in Appendix C.
only by the glass fiber reinforced portion (backing) of the 5.4.2—Shear and Tension
skin. For design purposes, mist coat or architectural finish Direct shear seldom controls the design of GFRC panels.
layers of a two material skin are not considered as adding Interlaminar shear, likewise, seldom controls the design of
to the strength; nor included in test specimens for strength flat GFRC elements unless the span-depth ratio is less than
determination or quality control. 16. However, interlaminar shear may control design of con
nections. While in-plane shear occurring in the diaphragms
5.4.1—Flexure
and webs seldom controls design, it should be considered
Stresses due to factored loads, computed by the straight
and the principal tension stresses limited. Diligence is re
line theory of stress and strain, should be limited to:
quired to maintain the continuity of webs at intersecting
f = 4)5f’ (5-8)
box ribs. The tensile strength of GFRC is less than the flex-
where:
4) = 0.75, strength reduction factor. The derivation of this *
Note: ‘Average’ strength test values should be based on
factor is based on experience and judgment and is not in a minimum of twenty tests of six specimens each; half of
tended to be precise. The purpose of the strength reduction which are tested with the mold side in tension and half of
factor, 4) is: (1) to allow for the probability of under which are tested with the mold side in compression. All
strength members due variations in material strengths and tests shall conform to Appendix F of Ref. 1.
21
Small Openings Large Openings
*(a)
Poor Panel
TI T (b)
Good Panel
(C)
Poor Panel
Layout
(d)
Poor Panel
Layout
(e)
Good Panel
Layout Options
Layout Layout
Jambs too Narrow
ural strength. Due to impracticality of tests to determine umn covers are vertical panels covering columns. Some
tensile strength on a specific job basis, it should be limited times column cover type panels are used where columns do
to 40 percent of the flexural strength or 0.4 not actually occur, to achieve an effect. They may be con
tinuous or interrupted by spandrels. All three types may be
5.5—Deflection flat or have returns. Column covers, particularly at lower
Panels should have adequate stiffness to limit deflections floors, may be in sets to completely surround a column.
or any deformations that may affect serviceability or cause Beams are often similarly covered.
cracking. 5.6.1—Panel Layouts
Deflections due to service loads are sometimes limited to When possible, it is preferable to have small windows, or
L/240 but may need to be less in some conditions. The in
, other openings, occur entirely within one panel to mini
terior finish systems or windows that are attached to the mize fit and joint sealing concerns. For large openings,
panel frame should be compatible with this deflection. panels should be configured so that openings are least af
fected by movement of the structure. The panel configura
tions in Figs. I 7a, 1 7c, and 1 7d are poor layouts for open
5.6—Panel Types
ings. Figs. 17b and 17e show good layouts for openings.
Three types of panels (panel frame, integral rib, and sand
Panel layouts must be coordinated with the connections to
wich) based on their internal makeup are discussed in Sec
the structure, so story drift is not in conflict with panel
tion 1.6. These are essentially different in their stiffening
jointing. Generally, this is best facilitated if horizontal
systems. By far, the predominant system now used in the
joints are continuous, as in Fig. 17e, not interrupted as in
United States is the panel frame. The integral rib is used in
Fig. 17d. If a continuous column cover effect is desired, it
smaller panels; or where space limitations do not allow for
may be advisable to simulate it with panel shape and false
a panel frame, such as in column covers. The integral rib
joints.
can take a variety of shapes depending on space available
The panel manufacturer should be consulted for panel
and extent of stiffening required. It can approach a sand
size. For long panels, over 20 ft (6 m), it is usually neces
wich panel in appearance. However, in a sandwich panel,
sary to segment the skin with control joints, as in Fig. 18,
internal forces are transmitted between the two faces by the
to minimize restraint of the skin. Sometimes panel returns,
filler between them, so the properties of the filler, and its
or other shapes, are detached from the main skin as in Fig.
installation, are critical. With a box rib the filler’s only
19 to limit differential volume change stresses. Each skin
function is to form the desired shape. It should be noted
segment usually requires its own gravity anchors. Often
that it is difficult to resolve the high calculated stresses in
more than one skin segment is attached to a single large
integral rib and sandwich panels and panels with returns,
panel frame.
when rigorous mathematical modeling is carried out for
Due to the spray up methods used to manufacture GFRC
significant differential volume changes.
panels, integral returns are usually vertical in the mold, so
Panels can also be categorized by application. Terminol
should generally be less than one foot to prevent the fresh
ogy varies to some extent throughout the country, with
GFRC from sagging, see Fig. 19. Since circumstances vary,
‘panel’. ‘cladding’, ‘wall’, or ‘curtain wall’ being applied as a
the manufacturer should be consulted for the maximum di
general term to all types. Wall generally applies to panels
mension of returns.
that extend from one floor to the next. They may be solid,
or have ‘punched’ window openings. The horizontal joints
need not occur at the floor line, and the panels may even be 5.7—Panel Frame System
more than one story high. Spandrels are horizontal band The panel frame system is by far the most common type
panels, less than story height, separated by windows. They of panel in use today in the US. It is also gaining in popu
may be continuous or interrupted by column covers. Col larity world wide, even where light gage steel members are
22
a)
F
0 Q) (0
VI ,L1..
b)
Fig. 18. Skin segments separated with sealed control
joint.
not as common. Because of its popular appeal and ability
to adapt to many conditions it is given greater coverage in [LF
this publication.
The system consists of four distinct parts: the panel skin
(which may include an architectural face mix), the anchors
that attach the skin to the panel frame, the panel frame it
self, and the connectors that attach the panel frame to the
structure. The anchors are intended to be flexible in the
plane of the panel (except as required to carry gravity or
seismic load) so that they provide minimum in plane re
straint against the volume change of the skin. They must,
[LJ C)
shown in these figures; but the concepts apply to other ap Fig. 19. Corner panel skin joint and frame options.
plications as well, even though the details may differ. In all
(or tubes), the rest of the frame has little participation in the
cases, the wind load is transferred from the skin to the
gravity load transfer.
studs (or other frame members) by the flex anchors, by the
studs to the upper and lower tracks, by the tracks to the 5.7.1—Skin Design
connector studs (or tubes) and then to the connectors. If the skin has an architectural facing that has volume
There are two methods of transferring the gravity load of change characteristics that are not equal to the GFRC back
the skin to the frame. Fig. 20 is only for small panels where ing, the differential stress must be considered. If the panel
the flex anchors can be stiff enough to carry the gravity skin includes an architectural face mix, see Section 5.10 for
load without being so rigid that they unduly restrain the additional considerations.
skin against in-plane volume changes. Figs. 20 and 21b Typically, face mixes are not reinforced with glass fiber
have the gravity loads distributed to the panel frame uni so, for design purposes, they are not considered as con
formly along its length. This requires the frame to have suf tributing to the strength of the skin. The design of the skin
ficient in-plane rigidity to pick up the load and transfer it to for wind load is straight forward. The panel skin spans be
the connection system. In Fig. 21a the gravity anchors tween the anchors. It can be modeled as a beam on a row of
transfer the weight of the skin to the panel frame at two flex anchors, or as a two-way slab system, with the bond
discreet points. If these points are at the connector studs ing pads acting similar to a column capital, as in Appendix
23
Wind Load from Window
(Top & Bottom)
or Structural Tube
Tie-Back Connection
• Track Carries Wind Load
to Connector Studs
Stud Carries Load to This system is the same as (a) except that the
Top & Bottom Tracks top and bottom tracks are heavier members that
are designed to support the panel for vertical
a) • Diagonal Brace Transfers
Gravity Load to Connector ‘ dead load and eliminate the diagonal braces.
Studs
Fig. 20. Optional methods of stiffening frame for panels without gravity anchors for small panels only.
to Connector Studs
b) Braces or Heavier
Track (Alternates)
Restrains Skin
Movement
Skin Length of Flex-Anchor for
Horizontal Movement
from Neutral Point
(also must carry wind load)
I Frame
I Member
A
Length of Flex-Anchor for
b) Vertical Movement from
a) --
Neutral Point C)
(also must carry wind load)
Side
Return
Length of Flex-Anchor
Better for Horizontal Movement from
Neutral Point
(also must carry wind load)
Length of Flex-Anchor
for Vertical Movement
d) e) from Neutral Point
(also must carry wind load)
L rKL-1l
Studs Connector Studs at
Add Stud or Conn. to Bldg. Studs
Rolled Structural Welded Together or
Shape When Rolled Structural Shape
Required for
Greater Strength
Skin
Slots to Reduce
Restraint Optional
Fig. 26. Trussed rod gravity anchor. Fig. 27. Plate gravity anchor.
27
percent, with the failure in the bonding pads.
Tests have indicated the following unaged ultimate
strength ranges for various types of anchors.
Type of Anchor and Load Ultimate Load unaged
--
TENSION
Flex Anchor (Fig. 24) . .500 1200 lbs. (2 5 kN)
. - -
SHEAR
Trussed Rod Gravity Anchor (Fig. 26)
1000-2000lbs. (4-8kN)
Flat Plate Gravity Anchor (Fig. 27)
2000 4000 lbs. (8 -16 kN)
-
Threaded
Rod
ELEVATION
Fig. 31. Tie-back connections. Fig. 32. Bearing connections (combined with tie-back).
31
— Tie-back
if Rigid Panels rotates as in (a)
if Flexible Panels Translates as in (b)
— Bearing
a) Rotating b) Translating
Fig. 33. Alignment connections. Fig. 35. Story drift of tall narrow panels.
Consideration should also be given to environmental con more fully in Section 5.10. Also, see Sections 3.1 and 7.8
ditions, such as corrosive atmosphere, as well as to fire for other considerations.
protection requirements. Corrosion protection of connec Panel skins are considered one material if they consist en
tion elements should be provided to prevent loss of move tirely of glass reinforced material or have only a thin mist
ment. One technique to avoid a corrosion-fused connection coat. If it has a facing (tile, stone, concrete face mix, etc.),
is the use of plastic or fiber washers. Dissimilar metals that it is considered a two material skin.
The fine particle sizes in a cement-sand slurry mist coat
could lead to galvanic corrosion should be avoided.
can accurately reproduce the textural characteristics of the
5.9—Finishes — One and Two Material mold surface. However, the extent to which the glass fibers
Skins are able to penetrate surface detail depends on the scale of
GFRC has been made with all the traditional concrete fin the detail and the length of the fiber. The surface layer of a
ishes: paint, sandblasted, exposed aggregate, stone, and ce panel is usually unreinforced and such layers are not to be
ramic veneer. There are limitations, which are discussed included in the effective thickness when determining panel
Ii
Embedment Depth
Rear Surface of /
/
I
Surface Type Insert
sible, it has the best prospects for compatible properties, al
though larger aggregate mixes can tolerate less cement than
smaller aggregate facing mixes. Sealing the surface or us
ing a polymer curing admixture will also be of benefit by
OFRC Skin L GFRC Bonding Pad reducing water absorption, and its associated expansion
—,
Panel
Skin
11
Rounded
Galvanized Or Painted
Sheet Metal Cap By
)uirk Miter
Others (no attachment ci,
C
tOGFRC)_NS__ a
Sealant
Sealant
c) Optional Edge or Control Joint
Sheathing And/ Or
Roofing By Others
Galvanized Or Painted
Sheet Metal Cap By
Others (no attachment
Slope toGFRC)—
Slope Shim Equal
Sealant
to Joint
Sealant Width
Sealant
Flashing By Others
Sheathing And/ Or
‘—Sealant Roofing By Others
joints and interfacing materials in the finished struc length of the structure. Tolerances must relate to unit
ture. size and increase as unit dimensions increase.
3 .Visual— To ensure that the variations will be control 2. Panels that are out-of-tolerance can cause tapered
lable and result in an aesthetically acceptable looking joints and make alignment of adjacent panels
structure. extremely difficult.
4 Economic — To ensure ease and speed of production 3. Thickness variation of the GFRC panels requires the
and erection by having a known degree of accuracy in use of shimmed furring channels when interior fin
the dimensions of products. ishes are attached to the panel frame.
5 .Legal— To avoid encroaching on property lines and to Warping and bowing tolerances have an important effect
establish a standard against which the work can be on the edge match up during erection and on the visual ap
compared in the event of a dispute. pearance of the erected panels, both individually and when
6.Contractual — To establish a known acceptability viewed together.
range, and also to establish responsibility for develop Warping is generally an overall variation from planeness
ing, achieving and maintaining mutually agreed upon in which the corners of the panel do not all fall within the
tolerances. same plane. Warping tolerances are stated in terms of the
The architect should be primarily responsible for coordi magnitude of the corner variation, as shown in Fig. 39.
nating the tolerances for all work with the requirements of Bowing is an overall out-of-planeness condition that dif
other trades whose work adjoins the GFRC units. fers from warping in that while the corners of the panel
It should be understood by those involved in the design may fall in the same plane, the portion of the panel be
and construction process that tolerances shown in this Rec tween two parallel edges is out of plane, as shown in Fig.
ommended Practice must be considered as guidelines for 40. Differential temperature effects and differential mois
an acceptability range and not limits for rejection. If these ture absorption between the inside and outside faces of a
tolerances are met, the member should be accepted. If these panel should be considered in design to both minimize
tolerances are exceeded, the member may still be accept
able if it meets any of the following criteria:
1. Exceeding the tolerances does not affect the structural
integrity or architectural performance of the member.
2. The member can be brought within tolerance by struc
turally and architecturally satisfactory means.
3. The total erected assembly can be modified economi
cally to meet all structural and architectural require
ments.
The enforcement of tolerances should be based on the
technical judgment of the designer. In so doing, the design
professional should decide whether a deviation from the al
lowable tolerances affects safety, appearance, performance
or other trades. In construction very little work is rejected
and removed solely because it is out of T tolerance.’ Fig. 39. Warping definition for panels.
36
b. Edge return +1/2 in., 0 in. (+13 mm, 0mm)
- -
c. Thickness:
LEEEE 1. Architectural face mix thickness +1/8 in., -0 in.
(+3 mm, -0 mm.)
2. GFRC backing +1/4in.,-Oin.
Fig. 40. Possible bowing condition. (+ mm, 0 mm)
6 -
Cross Section of Facade ±1/16 in.(± 1.5 mm) total, whichever is greater.
e. Variation from square or designated skew (difference
Fig. 41. Differential bowing of panels. in length of two diagonal measurements)
1/8 in. per 6 ft (3 mm per 2 m) or 1/4 in. (6 mm) total,
bowing and warping and ensure that the resulting stresses whichever is greater.
are kept within acceptable limits. f. Local smoothness 1/4 in. per 10 ft
Bowing and warping tolerances are of primary interest at (6 mm per3 m)
the time the panel is erected and should be checked prior to g. Bowing: Bowing shall not exceed L/240 unless it can
panel delivery. Careful attention to pre-erection storage of be shown that the member can meet erection toler
panels is necessary since storage conditions can be an im ances using connection adjustments.
portant factor in achieving and maintaining panel bowing h. Length and width of blockouts and openings within
and warping tolerances. one unit ± 1/4 in. (± 6 mm)
Differential bowing is a consideration for panels that are i Location of window opening within panel .± 1/4 in.
..
— =11_IF—
lIII
2
L
t
Fig. 42. Tolerance locations.
(± 3 mm per 3 m); 1/4 in. (6 mm) maximum Fig. 43. Location of panel frame tolerances.
37
1. Panel frame and track
2. Flashing reglets at edge of panel
3. Inserts
4. Special handling devices
5. Location of bearing devices
1/4 in. (6 mm)
.±
± 1/4 in.
(±6 mm)
± 1/2 in. (± 12 mm)
± 3 in. (± 75 mm)
± 1/4 in.
tolerances. Lack of attention to these matters often necessi
tates changes and adjustments in the field, not only delay
ing the work but usually resulting in unnecessary extra
cost, and sometimes impairing the appearance of the units
and the completed structure.
Tolerances of the building frame must be adequate to pre
I
(± 6 mm) vent obstructions that may impact the panel installation
6. Blockouts ± 3/8 in. (± 10 mm) procedure. The building frame should also provide for the
1. Panel frames shall be fabricated within the follow use of standardized connections, i.e. beam elevations and
ing tolerances shown in Fig. 43. column locations should be uniform in relation to the
1. Vertical and horizontal alignment.. 1/4 in. in 10 ft. GFRC units with a constant clear distance between the
(6 mm in 3 m) GFRC units and the support elements.
2. Spacing of framing members . .± 3/8 in.
. .
Tolerances for structural steel framing should be specified
(± 10 nun) . Particular atten
to conform to the AISC Code of Practice
73
3. Squareness of frame (difference in diagonals) tion is directed to the “Commentary” included with this
3/8 in. (10 mm) Code, which provides a detailed explanation of the speci
4. Overall size of frame ± 3/8 in. (± 10 mm) fied erection tolerances. The combination of milling, fabri
cation, and erection tolerances result in the final dimen
sional accuracy of the structural steel frame.
6.3 — ERECTION TOLERANCES The allowable tolerances for steel frame structures can
Manufacturing and erection tolerances and the interface make it impractical, on tall structures, to maintain GFRC
with adjoining trades must be taken into account during the panels in a true vertical plane. Based on the allowable steel
design phase of each project to assure satisfactory panel in frame tolerances, it would be necessary to provide for a 3
stallation. Erection tolerances are those required for proper in. (76 mm) adjustment in connections up to the 20th story
fit with the building structure. Erection tolerances are de and a 5 in. (127 mm) adjustment in connections above the
termined by the characteristics of the building structure and 20th story if the architectlengineer insists on a true vertical
are provided to achieve uniform joints and plane wall con plane. These adjustments in connections are not economi
ditions. They should be determined on the basis of individ cally feasible. Therefore, walls should follow the steel
ual unit design, shape, thickness, composition of materials, frame.
and overall scale of the unit in relation to the building. The For a cast-in-place concrete frame, the maximum toler
specified erection tolerances affect the work of adjoining ances that should be permitted, unless otherwise stated in
trades and must be consistent with the tolerances as speci the contract documents, are those given in ACT 117 These
.
fied for those trades. Where GFRC units connect to site tolerances are not realistic for tall buildings when com
work, such as footings or foundation walls, sufficient erec pared to AISC Code tolerances and to tolerances actually
tion tolerances are required. obtained on concrete buildings. Also, greater variations in
Erection tolerances are by necessity largely determined by heights of floors are more prevalent in cast-in-place frames
the actual alignment and dimensional accuracy of the than in other types of building frames. This will affect loca
building foundation and frame. The general contractor is tion or mating of the connector in the panel with the cast-in
responsible for the plumbness, level and alignment of the connection devices. Tolerances for cast-in-place structures
foundation and building frame including the location of all may need to be increased further to account for local trade
bearing surfaces and anchorage points for the GFRC units. practices, the complexity of the structure, and climatic con
The architect should recognize the critical importance of ditions. As a result, it is recommended that walls should
controffing foundation and building frame alignment toler follow concrete frames in the same manner as for steel
ances and should include, in the contract documents, clear frames.
ance dimensions that allow for building frame tolerances. It should also be noted that ACT 117 standard tolerances
If the GFRC units are to be installed reasonably “plumb, for concrete construction and material applies only to cast-
level, square, and true,” the “as-built” location of all ele in-place reinforced concrete buildings, and the AISC Code
ments affecting their alignment, including the levels of only to steel building frames. Neither of these standards ap
floor slabs and beams, the vertical alignment of floor slab ply to buildings of composite construction (i.e. concrete
edges and the plumbness of columns or walls must be floor slabs carried by steel columns or concrete encased
known before erection begins. structural steel members). It should also be noted that fire-
The architect/engineer should clearly define in the con proofing and masonry are not controlled by referencing
tract documents the maximum tolerances to be permitted in these standards and the architect/engineer should require
the building frame alignment, and require verification by the location of all such materials adjacent to the GFRC
the general contractor that these tolerances are being held. units be within tolerances which are, at most, no more than
In addition, the architect/engineer should ensure that the those specified in ACT 117. Should there be any doubt as to
details in the contract documents allow for the specified what these tolerances should be the GFRC manufacturer
38
should be consulted for his recommendation. control points and bench marks in an undisturbed condition
In the determination of erection tolerances, attention until final completion and acceptance of the project.
should also be given to possible deflection and/or rotation Non-cumulative tolerances for the location of GFRC units
of structural members supporting GFRC panels. This is are as shown in Fig. 44.
particularly important for bearing on flexible members, a = Plan location from building grid datum*
such as open web joists, or cantilevered structural mem ± 1/2 in. (± 13 mm)
bers. If the deflection of the building frame is sensitive to 1 = Plan location from centerline of steel+
a
the location or eccentricity of the connection, limits should ± l/2in.(± 13mm)
be provided on the erection drawings. Consideration should b = Top elevation from nominal top elevation
be given to both initial deflection and to long-term deflec Exposed individual panel ± 1/4 in. (± 6 mm)
tion caused by creep of the supporting structural members. Nonexposed individual panel ± 1/2 in.
A structural steel building frame presents different erec
(± 13 mm)
tion and connection problems from a cast-in-place concrete Exposed relative to adjacent panel ± 1/4 in.
building frame. For example, structural steel beams, being (6 mm)
relatively flexible in torsion, compared to concrete, may re Nonexposed relative to adjacent panel. .± 1/2 in.
. .
quire that the load be applied directly over the web or that (13 mm)
additional bracing be provided to resist the effects of tor c = Support elevation from nominal elevation
sion. Problems during erection with rolling of steel beams 1/2 in. (13 mm)
Maximum low
may occur if they are not adequately braced. Also, al
Maximum high 1/4 in. (6 mm)
lowances must be made when detailing connections of
d = Maximum variation from plumb over height of
GFRC panels to steel structures for sway in tall, slender
structure or 100 ft. (30 m) whichever is less*
steel structures with uneven loading, and movements due
1 in. (25 mm)
to sun or wind on one side or seasonal thermal expansions
e = Plumb in any 10 ft. (3 m) of element height
and contractions.
1/4 in. (6 mm)
Final erection tolerances should be verified and agreed to
f = Maximum jog in alignment of matching edges
prior to the beginning of erection and, if different from
1/4in.(6mm)
those originally specified, stated in writing or noted in the
contract documents. g = Joint width (governs over joint taper) (See Section
10.5.1)
Appropriate procedures should be followed to ensure ap
propriate and accurate application of tolerances. The gen Panel dimension less than 20 ft. (6 m)
± 1/4 in.(± 6 mm)
eral contractor should be required to establish and maintain
Panel dimension over 20 ft. (6 m) ± 3/8 in.
Bldg. Y Grid Datum (± 10 mm)
h = Joint taper maximum 3/8 in. (9 mm)
GFRC Panel 10 Joint taper in 10 ft.(3 m)
h 1/4 in. (6 mm)
i = Maximum jog in alignment of matching faces
1/4 in. (6 mm)
j = Differential bowing as erected between adjacent
XGrid Datum member of the same design 1/4 in. (6mm)
These tolerances are intended as guidelines only. Consid
eration should be given to the stated tolerances to ensure
PLAN that they are applicable to a given project. Upon comple
tion of GFRC panel alignment and before other trades in
terface any materials with the GFRC units, it should be
verified that the GFRC panels are erected within the speci
fied tolerances.
A nominal amount of bowing and warpage can often be
removed during panel alignment. Care shall be taken to en
ioj sure that neither the GFRC skin or the panel frame is over-
Building stressed when attempting to remove bowing and warpage.
Elevation
Datum *
For precast buildings in excess of 100 ft. (30 m) tall, tol
-naI erances a and ‘d’ can increase at the rate of 1/8 in. (3
ELEVATION mm) per story over 100 ft. (30 m) to a maximum of 2 in.
Fig. 44. Tolerance locations for GFRC elements to pre
(50 mm).
cast or cast-in-place concrete, masonry, or structural + For GFRC elements erected on a steel frame, this toler
steel. ance takes precedence over tolerance on dimension ‘a.’
39
Limits on the amount of bowing or warping which can be ances are realistically assessed, they will prevent many tol
removed during alignment should be established by the erance problems. Where large tolerances have been al
panel design engineer. Maximum permissible warpage of lowed for a supporting structure, or where no tolerances are
one corner out of plane of the other three corners shall be given, the clearance must be increased.
1/16 in. per ft. (5 mm per m) of distance from the nearest The maximum variation from the specified clearance be
adjacent corner, or 1/4 in. (6 mm) total after installation. tween adjacent independent members of separate building
Bowing shall not be over L/360 with a maximum of 1 in. parts or components should be ± 1/4 in. (± 6 mm). Adjacent
(25 mm), where L is the panel length in the direction of the independent members are members that are close together
bow. but are not connected structurally. These members may be
Clearance is the space provided between adjacent materi GFRC and cast-in-place concrete, masonry, or steel. Typi
als. It is one of the most important factors to consider in cally, this clearance situation develops at an expansion joint
erection. The clearance should provide a buffer area where or at the interface between a stair tower and a larger struc
frame, erection and manufacturing tolerance variatiois can ture when the two are joined only by an expansion joint.
be absorbed. All connections should be designed with the maximum
The designer should provide adequate clearance space be adjustability in all directions that is structurally and archi
tween the theoretical face of the structure and the back face tecturally feasible. To accommodate any misalignment of
of the GFRC panel frame in detailing the wall and its rela the building frame, connections should provide for vertical,
tionship to the building structure. Adjacent materials may horizontal, and lateral adjustments of at least 1 in. (25
include products such as glass or subframes that are in mm). Tolerance of hardware items cast into, or fastened to
stalled after the GFRC panels are in place. If sufficient the structure should be ± 1/4 in. (± 6 mm) in all directions.
clearance is not provided, alignment of the wall as speci Connection details should consider the possibility of bear
fied will likely cause delays and extra costs, and may be ing surfaces being sloped or warped from the desired plane,
impossible. which would necessitate field adjustments.
The failure to provide adequate clearances is an all-too- The minimum shim space between various connection el
common deficiency of cladding designs. They are ab ements should be 1 in. (25 mm) for steel structures or 1- 1/2
solutely essential for any of several reasons: in. (38 mm) for cast-in-place concrete structures.
1. To accommodate movement between adjacent mem Where a unit is not erected within the tolerances of the
bers. connection design, the structural adequacy of the installa
2. To provide for possible size variation or misalignment. tion should be checked and the connection design modi
3. To provide working space to make the connections, suf fied, if required.
ficient room for welding or adequate space to place a No unit should be left in an unsafe support condition. Any
wrench to tighten bolts.
adjustments affecting structural performance, other than
The clearance between the structure and the GFRC panel adjustments within the prescribed tolerances, should only
is an important detail and impacts the final appearance of
be made after approval by the connection design engineer.
the structure. Clearances should be reviewed during the de
Units should not be forced into place or installed by any
sign stages of the project to assure they are appropriate
method that would impose undue stress on the unit or the
from both erection and aesthetic points of view.
connections.
The clearance necessary for erection of the GFRC panels
The GFRC panels should be located in the center of their
will depend on their design, the dimensional accuracy of
theoretical location on the structure and adjusted to accom
the building frame or other construction to which the
modate adjacent materials, proper joint width, and align
GFRC panels are connected and the limits of adjustment
ment with adjacent GFRC panels. Width variations be
permitted by the connection details.
A good rule of thumb is that at least 1-1/2 in. (38 mm) tween adjacent joints can be minimized by laying out joint
clearance be required between GFRC panels and precast centerlines along an elevation and centering the units be
concrete members; 2 in. (51 mm) is the minimum clearance tween them. Variations from true length or width dimen
between the GFRC panels and cast-in-place concrete, For sions of the overall structure are normally accommodated
steel structures, 1-1/2 in. (38 mm) is the minimum clear in the joints or, where this is not feasible or desirable, at the
ance between the back of the GFRC panel frame and the corner units, in expansion joints, or in joints adjacent to
surface of the fireproofing. If there is no fireproofing re other wall materials.
quired on the steel, then 1-1/2 in. (38 mm) minimum clear During panel installation, priority is given to aligning the
ance should be maintained. At least 2 in. (51 mm) clearance exterior face of the panels to meet aesthetic requirements.
should be allowed in tall, irregular structures regardless of This will result in the interior panel frame face not being in
the structural framing materials. The minimum clearance a true plane. Panel design usually prevents spacing of the
between column covers and column should be 2 in. (51 panel frame members from being coordinated with interior
mm), with 3 in. (76 mm) preferred because of the possibil drywall modules. If the panel frame is to receive interior
ity of columns being out of plumb or a column dimension drywall or similar treatment, the interior finish should be
interfering with the completion of the connection. If clear- mounted on a separate stud system or on shimmed
40
transverse furring elements rather than directly to the panel
frame.
A liberal joint width should be allowed if variations in
overall building dimensions are to be absorbed in the
Theoretical
joints. This may be coupled with a closer tolerance for vari Location (±1/4”)
ations from one joint to the next for uniformity of appear
ance purposes. The individual joint width tolerance should
relate to the number of joints over a given building dimen
sion. For example, to accommodate reasonable variations
in actual site dimensions, a 3/4 in. (19 mm) joint may be
specified with a tolerance of ± 1/4 in. (± 6 mm) but with
only a 3/16 in. (5 mm) differential variation allowed be
tween joint widths on any one floor, or between adjacent
floors. Alternatively, the jog in alignment of edge my be Theoretical
Location (±1I4)
specified.
The performance characteristics of the joint sealant should
also be taken into account when selecting a joint size.
Joints between GFRC units should be wide enough to ac
commodate anticipated wall movements.
In a situation where a joint has to match an architectural Fig. 45. Spandrel (window) rough opening.
feature (such as a false joint), a large variation from the ance) for differential volume changes between the materi
theoretical joint width may not be acceptable and tolerance als. A case in point would be the glazing of an opening
for building lengths will have to be accommodated else completely formed within a GFRC panel. Such openings
where. -
can be made to normal manufacturing tolerances. However,
openings for aluminum windows should allow room for
6.4 — Interfacing Tolerances some temperature expansion of the sash.
Interfacing tolerances and clearances are those required A critical interface area is between the GFRC spandrel
for joining of different materials in contact with or in close panel and the spandrel glazing system. Vertical dimensions
proximity to GFRC panels and for accommodating the rel between spandrels should be checked with a story polel or
ative movements expected between such materials during similar device to ensure that opening size is within allow
the life of the building. Typical examples include toler able tolerances. The interface tolerance between these two
ances for window and door openings, joints, flashing and systems is as shown in Fig. 45. Windows between open
reglets. shape units where they will intersect a joint between units
Where matching of the different materials is dependent on also require interface erection tolerances.
work executed at the construction site, interface tolerances Fabrication and erection tolerances of other materials
should be related to erection tolerances. Consideration must be considered in design as the GFRC panels must be
should also be given to provision for adjustment of the ma coordinated with, and must accommodate the other struc
terials after installation. Where tolerances are independent tural and functional elements comprising the total structure.
of site conditions, they will depend solely on normal manu Unusual requirements or allowances for interfacing should
facturing tolerances plus an appropriate allowance (clear- be stated in the contract documents.
41
CHAPTER 7— MANUFACTURING
Demarcation
Between Finishes
and/or Colors
Fig. 46. Roller compaction of sprayed-up GFRC. Fig. 47. Demarcation groove between finishes.
44
late design concepts into realistic production requirements. It is advisable to vary the color or tone of the matrix to
With any integral or attached finish material, and its attach match or blend in with the color of the aggregate. This
ment, consideration must be given to the thermal and mois match can be achieved by careful selection of cement and
ture-induced volume changes and the compatibility of the sand colors, and the use of coloring agents. Good matrix to
volume changes or stresses with the aged properties of the aggregate match will minimize “patchy” effects (minor
GFRC. segregation of aggregate) from being noticeable.
The fine particle size of the cement-sand slurry matrix al 7.8.3 — Veneers
lows it to closely follow the surface texture or pattern of Materials such as natural cut stone, (granite, limestone,
the mold. However, the extent to which the glass fibers are marble,) thin brick, ceramic or quarry tile, and architectural
able to penetrate surface detail depends on the scale of the terra cotta, provide a great variety of textures for GFRC
detail. The surface layer of a heavily textured panel may units. Quality requirements (design and production proce
consist of unreinforced cement/sand mortar or it may be dures) for these finishes should be based on previous
exposed aggregate concrete. records with the identical materials, or sufficient testing of
sample and mockup units to establish performance criteria
7.8.1 — Mist Coats under the service conditions. Particular attention should be
A smooth or light textured off-the-form finish, using a paid to compatibility of materials with respect to differen
mist coat, may be one of the most economical, but is diffi tial expansion and contraction caused by thermal and mois
cult to produce, as color uniformity of gray, buff, or pig ture changes. It is necessary to consider the differential vol
mented surfaces may be difficult to achieve. Some produc ume change of veneer facings and GFRC backing.
ers have achieved acceptable uniformity in form finishes A complete bondbreaker between natural stone veneer and
that are white or other pale colors. The cement exerts the GFRC should be used. Bondbreakers may be a polyethyl
primary color influence on a smooth finish because it coats ene sheet or a polyethylene foam pad or sheet. Connection
the exposed GFRC surface. Many of the aesthetic limita of the natural stone to the GFRC should be with mechani
tions of smooth GFRC may be minimized by the shading
and depth provided by profiled surfaces (fluted, sculptured,
board finishes, etc.), subdividing the panel into smaller sur
face areas, using white cement, or by use of applied coat
ings.
The smooth cement film on the GFRC may be susceptible
to surface crazing, i.e. fine and random hairline cracks.
a)
This is, in most cases, a surface phenomenon and will not 1/16” Oversize Typ.
affect structural properties or durability. In some environ 5/32ø or 3/I 6ø
ments, crazing will be accentuated by dirt collecting in Stainless Steel
Spring Clip
these minute cracks. This will be more apparent in white
than gray finishes and in horizontal more than in vertical
surfaces. The use of polymer curing admixtures in the mist
Rubber Sleeve
coat or face mix may minimize crazing. 1/2 Mm.
r
— ..:
Generally GFRC panels are produced with a face mix that
. :. :
consists of sands, aggregates or color pigments specifically b)
the operator spraying the GFRC composite into a suitable mer curing admixture in the mix creates a film in the back
container or premixing the composite. The material is then ing and on the air exposed surfaces which holds the mois
deposited (by hand) over the flex anchor foot and the oper tire in the panel and eliminates the need for 7 days moist
ators knead them into the GFRC backing. Time delay be- ’ 79 All polymer curing admixtures have a mini
7778
curing
mum film formation temperature (MFT) below which the
Effective Width polymer spheres will not coalesce to form a tough, durable
film. Initial curing temperatures must be maintained above
the MFT until the film formation process is complete. The
recommended minimum panel curing temperature is 60
deg. F (16 deg. C) which should be maintained for 12 to 16
hours. The GFRC temperature should not exceed 120 deg.
F (50 deg. C).
After the GFRC backing has been sprayed, compacted,
the panel frame set and the bonding pads applied, the panel
should be covered with plastic or tarpaulin until stripping.
This will maintain at least a 65 percent RH environment
during initial cure and protect the panel from excessive air
movement. The film formation process is not disturbed by
-
Effective Length covering since the cement hydration and moisture evapora
3Mm.
tion into the space between the backing and the covering is
:
ongoing. Covering of the panel may also accelerate initial
1/8 Heel strength development of the GFRC backing.
to 3/8 Cover
— GFRC Care must be used when using overhead heaters in cold
Backing climate production. Excessive heat or hot molds coupled
* with low relative humidity can create situations where the
panels are subjected to rapid moisture loss which can lead
to drying shrinkage cracks. This can be eliminated by cov
ering the panels with plastic or tarpaulins as soon as possi
Facing Material ble after production.
Fig. 50. Bonding pad details. Moist Curing — Proper curing of fresh GFRC without
-“....--
polymer curing admixtures requires moist atmosphere so sonal protective equipment should be worn to avoid respi
that moisture is retained to assure adequate hydration of ce ration of fine silica dust.
ment and to prevent formation of cracks due to rapid loss
of water. Curing procedures should be well established and 7.13 — Handling
properly controlled to develop the required GFRC quality Each manufacturer should develop specific panel handling
and strength, as well as to minimize any surface blemishes, procedures. These procedures should include
such as non-uniformity of color, staining or cracking. demolding/lifting, storage, preparing panels for transport
Immediately after spray-up operations are completed or• and tie-down of panels during transportation. When panels
panel frame has been installed, the panel should be covered are handled and/or shipped in orientations other than their
with a polyethylene sheet. It should remain covered final orientation on the building, special considerations
overnight to avoid drying and to achieve adequate strength may be required for frame and flex-anchor design.
for stripping. During this period, the temperature of the Panels should be handled to avoid structural damage,
GFRC should be maintained above 60 deg. F (16 deg. C) to cracking, architectural impairment or permanent distortion.
aid early strength development. The number and location of lifting points for handling of
After initial overnight curing, the panel should be re elements and details of lifting devices should be considered
moved from the mold and placed in a controlled curing en integral parts of the design of GFRC units and should be
vironment. Panels should be kept in a surface-damp condi shown on the shop drawings. Lifting points may also serve
tion at a temperature above 60 deg. F (16 deg. C) in a mini as fastening points for connection to the building structure,
mum of 95% relative humidity for a period of 7 days. Con provided they are designed for that application also.
sistent and uniform curing conditions should be provided.
GFRC units should be cured as long as possible with a
minimum of seven days. At no time after spray-up and be 7.14 —Yard Storage
fore the end of the minimum seven days wet cure should A general rule of thumb regarding panel storage and trans
any portion of the unit be allowed to dry. GFRC panels are port preparation procedures is to not subject the panel skin
usually thin and are susceptible to rapid drying. Curing ma to any loads. Panels should be supported and tied down by
terials or methods that allow one portion of a unit to cure or the panel frame and should not be stacked without special
dry out faster than other portions may produce color varia precautions.
tions in the finished product and differential shrinkage GFRC panels should be stored on unyielding supports at
which can lead to warping or cracking of the unit. designated locations on a firm, level and smooth surface
Accelerated curing systems with temperatures over 120 with identification marks visible. Dunnage and storage
deg. F (50 deg. C) are not recommended and may be detri racks, such as A-frames and vertical racks, should be well
mental to strength. constructed and aligned to minimize warping, bowing,
chipping or cracking of the GFRC panels. Protective mate
7.11 — Stripping rial should be provided at points of contact with exposed
The panel does not achieve its fully cured properties at the surfaces. All blocking, packing, and protective materials
time of stripping. Therefore, panel and mold design should should be of a type that will not cause damage, staining, or
allow sufficient lifting points and easy release from the objectionable disfigurement of the panels. Staggered or un
mold without overstressing. even blocking should be avoided. When setting one panel
Stresses imposed on the panel skin during stripping of the against another, non-staining protective blocks should be
panel from the mold, handling, transporting or erecting
placed immediately in line with the supports of the first
should remain as low as possible, and ideally below the
panel.
yield strength at the specific time of that operation.
When long panels are stored vertically, horizontal support
The panel frame usually acts as a lifting frame for the
should be provided at each end.
panel during stripping, handling and erection. Depending
on the weight of the panel and the location of the pickup The GFRC panels should be protected from contact with
points, the panel may be sthpped with or without an auxil earth, oil, gas, tar or smoke. Any soiling or weathering of
iary spreader beam. units, which would result in a pattern different from the
Localized panel frame deformations due to lift cable or normal weathering as finally installed, shall be avoided by
hook attachment are usually of negligible significance. storing in a manner similar to their final position, or by
suitable protection from such soiling or weathering. Em
7.12 — Cutting and Grinding bedded items should be protected from penetration of water
When cutting or grinding GFRC panels, appropriate per- or snow during cold weather.
48
CHAPTER 8— QUALITY CONTROL
8.1 — General are supplied with each shipment. Instructions for admixture
The manufacture of GFRC products requires a greater de use should be kept on file at the plant with the mill certifi
gree of craftsmanship than conventional precast concrete. cates.
Therefore, it is important for manufacturers to implement Curing Agent. Plant testing of curing agents is not re
an active Quality Control program that conforms to recog quired if curing agents are certified to conform to specifi
nized standards. Ref. I is a comprehensive manual includ cation requirements in Appendix L. Curing agents are sen
ing both a standard and commentary covering all aspects of sitive to freezing and should be visually inspected for color
Quality Control. changes and/or coagulation upon delivery and prior to use.
The Quality Control program should include inspections, Certificates of Compliance should be maintained on file.
tests of raw materials and tests of the cured GFRC. These Form Release Agents, Surface Retarders, and Sealers. In
tests are required to ensure a consistent and uniform manu structions for proper use and application should be ob
facturing process. Properties of all materials used in the tained from suppliers and kept on file at the plant for all
manufacture of GFRC panels should be verified by appro such materials.
priate tests performed by either the material supplier or the Structural Shapes, Cold-Formed Steel, Hardware, and
panel manufacturer. Inserts. Mill certificates for all of these items should be
In order to establish evidence of proper manufacture and obtained from the manufacturers and maintained at the
conformance with plant standards and project specifica plant.
tions, a system of records should be kept to provide full in
formation on material tests, mix designs, GFRC tests, in 8.3 — Preproduction Testing
spections, and any other information specified for the proj Face Mixes. All face mixes should be developed using the
ect. brand and type of cement, the type and gradation of aggre
Each GFRC panel should be marked with an identification gates, and the type of admixtures proposed for use in pro
number referenced to the production and erection drawings
duction mixes. Face mixes should be tested to determine
and testing records. The date of manufacture should be in
volumetric changes due to moisture variation.
cluded. In the absence of specification requirements,
In addition, acceptance tests for face mixes should also in
records should be kept for a minimum of two years after
clude compressive strength, absorption, unit weight, and air
acceptance of the structure.
content, as described in Ref. 1.
GFRC Backing. Prior to design and production, a mini
8.2 — Acceptance Testing of Materials mum of twenty unaged flexural strength tests (of six speci
Cement. Plant testing of cement is not required if mill mens each) produced on twenty separate days should be
certificates are supplied with each shipment. All cement conducted.
should meet the requirements of the specified type in Flex Anchor and Gravity Anchor Pull-off and Shear
ASTM C 150. Mill certificates should be kept on file. Tests. Prior to design and production, a minimum of
Glass Fiber. Plant testing of glass fiber is not required if twenty unaged strength tests of each type and size of an
the glass fiber strand is certified as being manufactured chor should be conducted. The specimens and test proce
with an alkali-resistant glass produced using a minimum of dures should accurately simulate the various service condi
16% Zirconia and conforms to the specification require tions that are expected to be encountered during the life of
ments contained in Appendix K. Certificates should be kept the project.
on file.
Sand. Sieve analyses (ASTM C l36’) should be con
ducted on samples taken from each shipment received at 8.4 — Production Testing of Aggregates
the plant. A sieve analysis (ASTM C 136) should be conducted in
Facing Aggregates. Fine and coarse aggregates should be the plant with test samples taken at any point between
regarded as separate ingredients and each should conform stockpiling and batching. If material is stored in bulk, a
to the requirements for facing aggregates specified in Ref. sieve analysis should be conducted at least monthly during
1. the period of time the material is being used or more fre
Water. Water should be chemically analyzed when a pri quently if necessary. Each shipment of aggregate should be
vate well or nonpotable water is used. Except for water visually compared with the approved aggregate sample.
from a municipal supply, an analysis of the water should be Moisture tests are not required for bagged aggregates
on file at the plant, be updated annually, and be clearly re stored indoors. Surface moisture in bulk aggregates should
lated to the water in use. be evaluated and compensated for in all face mix and back
Admixtures. Plant testing of admixtures is not required if ing slurry proportioning. If moisture meters are not used to
Certificates of Compliance with appropriate requirements continuously monitor moisture, the free moisture should be
49
determined any time a change in moisture content becom
obvious.
es The test board for a panel having a surface finish such as a
mist coat or exposed aggregate should be made without
that surface finish but should in all other respects duplicate
122883.
I
the production panel. Also see ASTM C
8.5 Production Testing Wet
Wash-out Tests. The wash-out test is used to determine
—
—
For details of test procedures, see Appendix F of Refer the glass fiber content of the backing.
ence 1. The average glass content determined by the wash-out test
Slurry Consistency Slump Test. Slurry consistency should be recorded and be within the control limits of —
slump tests for each mixer should be performed at the be 0.5, + 1.0% by weight of the mix. If either the spray gun
re
ginning of each shift. With the use of high range water calibration or spraying technique is modified, an additional
, slump test may not be approp ri
ducers in a mix design the wash-out test should be performed.
mixer should be equipp ed with an ss
ate. As an alternate, each The uniformity of glass distribution through the thickne
ammeter that indicates the relative resistance of the mixer (top to bottom) is important and can be checked by means
motor. This is an advisory test performed at the discretion of the wash-out test with split samples. This is an adviso
ry
of the manufacturer. test performed at the discret ion of the manuf acturer . If a
Slurry Unit Weight. The unit weight test (ASTM C dual head (rather than a concen tric) spray gun is used
138) should be performed once per day before starting (where the glass is sprayed into the slurry stream from
one
3
production. The unit weight should not vary more than side) this test should be perform ed weekly . Also see ASTM
) from the established unit weight for the par
pcf (48 kg/rn
3 C 122883 and C 122984.
ticular mix design in use. This is an advisory test per Thickness. The skin thickness specified is the minimum
formed at the discretion of the manufacturer. for all points on the skin. Thickness of both the face
mix
red
Slurry Temperature. Temperature should be measu and GFRC backing should be checke d with a suitabl e
nt in
and recorded when test specimens are made, at freque depth/thickness gage. This is best done using a simple pen
ons
tervals in hot or cold weather, and at start of operati etration gage.
F
each day. An armored thermometer accurate to ± 2 deg. A minimum of one thickness measurement should
be
sample until the reading
(± 1 deg. C) should remain in the made per 5 sq. ft. (0.5 m2) of panel surface with at least six
adviso ry test performed at the
becomes stable. This is an measurements per panel. Bonding pad size, thickness and
acturer . d.
discretion of the manuf compaction over anchors should be visually checke
Spray Rate. The slurry flow rate (bucket test) and the Bonding pad thickness over gravity anchors should be
fiber roving chopping rate (bag test) should be used to de checked with a penetration gage at 50% of the anchor loca
termine if the fiber content being delivered by the spray tions.
equipment is within limits. The ratio of the fiber roving Additional thickness measurements should be made at
chopping rate to the slurry flow rate gives an indication of sensitive areas of the panel such as at corners, reveals
the fiber content. These tests should be performed for each (false joints) and other breaks in plane surfaces, and attach
spray machine before starting production each day and af ment inserts. Inside corners require special attention to en
ter any extended shut-down. After final setting of the fiber sure that thin areas, voids, and non-reinforced areas are not
roving chopping rate, the length of any three fibers from incorporated into the panel. Thin areas should be built-u
p
the bag test should be measured and should be within 15% by spraying fresh material into the area concer ned and not
of the required length. mold
by transferring sprayed material from one part of the
Test Boards. Test boards should be sprayed alongside of to another.
and in exactly the same way as the panel (i.e., distance of Face Mix. Air content tests should be conducted daily
on
test
spray gun to surface, rolling, troweling, etc.). The mixes containing air-entraining admix tures.
board should be lightly trowelled and should be appropri
ately sized to provide two wash-out test specimens, six Production Testing After Curing
8.6 —
51
CHAPTER 9— LOADING AND DELIVERY
GFRC products are usually transported by tractors and
semi-trailers, but rail or barge transportation may be more
feasible over long distances. The normal highway restric
tions on weight and size will have to be observed. Because
of their thin wall construction, which reduces weight,
GFRC panels can offer a cost savings in delivery. Support Top Return
The manufacturer should ensure that panels are ready for (remove after
installation)
delivery before loading. This may necessitate a lead time
for final checking, possible cleaning and minor repairing Frame
that may be required as a result of damage or accumulation
of dirt in storage. Panels should not be shipped to josites
until they have reached sufficient strength to withstand the
effects of the particular shipping and handling methods Fig. 51. Recommended strapping (blocking) procedure.
used.
Factors such as the size, shape, type of finish, method of the strapping points to avoid cracking of the GFRC skin
transportation, type of vehicle, weather and road condi (see Fig. 51).
tions, and distance of haul enter into determining the neces The erection supervisor should coordinate the arrival of
sity of wrapping or protecting the GFRC panels during the panels at the jobsite for erection in a safe and proper
shipment. manner.
Panels should be loaded as necessary: All GFRC panels should be clearly piece marked as indi
1. To permit their removal for erection from the load in cated on the erection drawings. Any panels that require se
proper sequence to minimize handling. quential erection should be so marked. Weight of the units
2. With proper supports, blocking, cushioning, and tie- should be communicated to transport and erection person
downs to prevent or minimize in-transit damage. nel.
3. With proper padding between GFRC and chains or Corners and panels with returns of unusual length are of
straps to preclude chipping of the GFRC. ten shipped with edge-to-edge bracing, that should not be
4. To support the panels in a manner to minimize relative removed until just prior to erection.
movement between the panel frame and the skin.
There are a variety of ways by which a panel may be
The blocking points and orientation of the panels on the
hoisted into position. The type of erecting equipment is de
shipping equipment should be determined by manufacturer.
termined by the weight of the product and reach distance to
GFRC panels should be loaded so the GFRC skin does not
support the weight of the unit. This is generally achieved set the panel. If possible, panels should be unloaded by
by blocking between the trailer bed and the panel frame. To handling in a vertical position. All chains, binders, straps,
minimize cyclic loading of the skin anchors, it may be ad bracing, packing and edge protection of the panels should
visable to provide additional blocking to the skin, after the be carefully removed prior to unloading.
panel weight is supported on the panel frame. Since the Panels should be lifted slowly from the transport vehicle.
trailer bed is flexible, two-point support is recommended. If any binding occurs during lifting, the panels should be
Blocking, packing and other protective materials should lowered and the obstruction removed. Panels should be
not cause damage, staining or other disfigurement of the handled to prevent structural damage, cracking or chipping.
panels. Groups of panels should not be removed with one lift un
Suitable materials that will cushion and protect the panel less designed accordingly.
edges during shipment should be used. When tying down Adjacent panels remaining on the trailer should be tied or
the GFRC panels to the trailers, it is preferable to use nylon blocked to prevent tipping.
straps rather than chains. Special care is required to protect
Balance of the trailer should be maintained by unloading
the panels at the binding points of the straps, and to protect
alternate sides of the vehicle or by blocking the trailer. The
against the “slap’ of a long reach strap. Over tightening of
exterior panel should be unloaded first from a stack to min
straps must be avoided as this may result in cracking and
permanent deformation of the panels. If panels are nested imize chipping and scraping; panels should not be slid out
or stacked, consideration should be given to transfer of ver from the middle of a stack.
tical load to prevent progressive crushing or other damage. Site conditions should allow erection equipment and
This can be prevented by blocking the panels from panel transportation units to proceed under their own power to a
frame to panel frame. Special support frames may also be location where GFRC panels can be handled by the erec
used to prevent damage from occurring. Attention should tion equipment directly from the transportation units. Site
be given to adequately support any top or bottom returns at storage, other than on trailers, should be avoided, as it is
52
expensive and can result in damage to the product, If tem If required, rotation of panels should be done while sup
porary job storage of panels is required, storage areas ported by the crane in the air and not by resting the panels
should be relatively level and firm, well-drained, and lo on the truck or ground unless the panels are specifically de
cated where there is little chance of damage due to other signed for such stresses.
construction activity. In addition, site conditions, season of Wall panels which are shipped flat should be picked up in
the same position and tilted to a vertical position by using
the year, and length of storage at the jobsite should be con
two crane lines, carefully avoiding tipping or twisting dur
sidered in detennining the necessity of protection to pre
ing this operation.
vent accumulation of dust, dirt or other staining material
For unusually shaped panels, special erection rigs, such as
from discoloring the panels. If a loaded trailer is stored at rotating sheaves, spreader beams or specially designed lift
the jobsite, the shipper should carefully block the trailer to ing brackets should be used to avoid damaging the panels
prevent damage to panels or accidental overturning. Block during hoisting and installation.
ing of trailers is necessary on sites that are frozen, and sub
ject to thawing. The stored trailer should be parked on firm
level ground.
53
CHAPTER 10—INSTALLATION
101 — Coordination
An efficient jobsite operation is the result of planning be
tween the manufacturer, trucker, erector, and the general
contractor. The following items should be reviewed prior to
installation:
1. Check jobsite access for all necessary equipment.
2. Check building frame tolerances and supporting sur
faces to minimize delays.
3. A sequence that will best utilize the available trucking
equipment.
4. A steady delivery of panels to the jobsite will ensure
efficiency and panel installation.
10.2 — 80
Erection
Erection supervision requires knowledge about handling
and positioning panels on the building. Advance planning
will ensure the presence of all necessary tools, equipment
and loose connection hardware. Jobsite conditions must
properly accommodate the erector’s equipment operating
under its own power.
A satisfactory installation results if the erector under
stands product manufacturing and erection tolerances cou
pled with permitted variations in building frame construc
tion. Panels that are to be installed in a special sequence
should be so noted on the erection drawings.
Prior to the start of erection and scheduling of delivery Fig. 52. Lightweight hydraulic crane used to erect
spandrel panels.
equipment, the jobsite should be inspected to determine ac
cessibility for the erection and delivery equipment. Sched that the connection system functions in the manner in
uling and coordination of erection with other trades is nec tended. Shims should be placed at panel frames not under
-
essary. The position and elevation of connections integral the GFRC skin.
with the building frame or foundation shall be verified be The installation or prewelding of miscellaneous steel
fore the GFRC units are erected. hardware should be performed prior to the start of erection,
The GFRC erector shall establish joint locations prior to whenever possible, to minimize the cost of crew and equip
actual panel installation. This will minimize the variation ment standby.
in joint widths, as well as identify problems caused by the The supply of loose erection hardware needed for the con
building being out of dimensional or alignment tolerance. nection of GFRC members is normally the responsibility of
In general, panels should move directly from truck to the GFRC manufacturer.
building to minimize the hazards and costs of extra han The responsibility for supply of contractor’s hardware to
dling. Should jobsite storage be necessary, the erector be placed on or in the structure to receive the GFRC units
should observe proper yard storage practices. The erector varies with local practice and should be clearly defined in
should confer with the manufacturer on proper storage the contract documents. Hardware should be incorporated
methods if they are not shown on the erection drawings. in the structure, within the specified tolerance, according to
The low weight of GFRC panels permits lighter and less a predetermined and agreed upon schedule.
expensive handling equipment. A simple hoist, mounted on Each GFRC unit should be securely fastened in place as
the roof, or a small crane may be sufficient (Figs. 52 and indicated on the erection drawings. Field checks should be
53). Care is required during lifting since the lightweight performed to ensure that panels have been installed in ac
GFRC panels are susceptible to movement due to wind. cordance with the drawings.
The erector should understand the function and perform During installation, priority is given to aligning the exte
ance of each connection detail to ensure that panels are in rior face of the panels because of aesthetics. This may re
stalled in keeping with the design concept. Field modifica sult in the interior frame faces not being in a true plane.
tions to the panel frame or connection system should be Where necessary, the erector should correct misalignment
made only with the approval of the engineer responsible of the units resulting from minor deflection and/or rotation
for the design. If connections require temporary support, of the supporting structure due to the weight of the GFRC
such as shims, they must be removed as soon as possible so units.
54
Fig. 55. Conduit, and insulation, or fire sating placed in
Fig. 53. Truck crane used to erect window wall panel. wall cavity.
Units may be erected with a predetermined allowance for 10.3 — Connections
such movements or, following field installation, adjust All connections that serve similar functions should be
ments may be made to connections which have been standardized as much as possible. As workers become fa
specifically designed for such movements. miliar with the procedures required to make the connec
Window frames should be attached directly to the head tion, productivity is enhanced and the potential for errors is
and sill tracks of the panel frame (or a separate framing reduced. Standardization of details facilitates selection and
system). The window loads, both dead load and wind pres shipment of connection items to the project with fewer de
sure, are to be supported by the panel frame and transferred lays and added economies.
through the frame to the panel connections attached to the Standardization also applies to the dimensioning of con
structure. The window frame is shimmed by the glazier to nection details. Little is gained by slight changes in dimen
its proper location and then screw attached to the panel sions, since the savings and materials maybe more than off
frame (see Fig. 54). set by the extra labor involved in developing the modifica
The only contact between the window frame and the skin tions. Furthermore, if different connections vary only
is the joint sealant, allowing the skin to move and prevent slightly in dimensions, there is a greater chance that an im
ing undue restraint of the skin. The skin can be expected to proper connection may be used at a given location.
expand and contract up to 1/8 in. per 10 ft. (3 mm per 3 m) It is desirable to have connections that are designed to en
as a result of moisture and thermal effects. Restraint due to able the erector to safely secure the member to the structure
improper installation of the window frame may result in in a minimum amount of time without totally completing
excessive restraint of the skin, thus creating a possible fu the connections. Often temporary connections are used
ture cracking problem. The sealant joint between the win with final adjustment and alignment capability. The con
dow frame and skin also keeps the wall system weather- nection is then completed later without tying up the crane.
tight. This allows the crane to begin placing the next unit while
Insulation, fire safing, electrical and telephone conduits connections on the first are being completed. Temporary
may be placed in the wall cavity created by the panel frame connections should not interfere with, or delay the place
(Fig. 55). Insulation, safing and other trade items are in ment of, subsequent members. Temporary connections may
stalled at the jobsite by other subcontractors. have to be relieved or cut loose prior to completion of the
permanent connections.
Where welded connections are used, welding shall be per
formed by certified welders in accordance with the erection
drawings which shall clearly specify the type, size, length,
Screws sequence if critical, and location of welds. Field welding
shall be inspected as per contract documents. Welding shall
Shim by Glazier
be in accordance with AWS Dl. 1 and 1.3. The temperature
of the environment as well as materials to be welded shall
be taken into consideration prior to the start of welding.
Sealant
Surfaces to be welded shall be clean and meet AWS re
quirements. Painted or galvanized components shall be
Panel touched up after cutting or welding, if required, with a rust
Skin
inhibitive or zinc rich paint.
With welded connections, units may be temporarily
shimmed while initial tack welding is accomplished. Provi
Fig. 54. Attachment of window frame to panel frame. sions shall be made to hold the unit safely in place while
55
adjacent units are placed and final adjustments are made. protect the erected panels from damage or staining by other
Before shims are removed, the final welds shall be com trades. Any cleaning or repair of the GFRC work subse
pleted quent to installation and/or acceptance should be done by
Bolting shall be in accordance with the erection drawings. the erector or manufacturer but under the responsibility of
Following erection, a check of bolt size, position, and tight the general contractor. Specifications should clearly state
ness shall be made. For sliding connections, the nut shall this responsibility.
be prevented from turning but not tightened so that it can
not move within the connection’s slot. Roughness at 10.5 — Acceptance
sheared or flame cut edges of slots or holes may have to be One person should have final and undisputed authority for
removed. When direct bolting through the panel skin is acceptance of the work. Contract documents should iden
used, over-sized washers, at least three times the bolt diam tify this person.
eter should be used. The manufacturer, if responsible for erection, should
Bolting generally permits an initial connection to be made make a thorough inspection of the installation after erection
with final alignment done later. Often, a bolted connection and arrange for final repairs, and cleaning, if required, to
is used for initial installation and alignment even if the fi ensure readiness for other trades such as joint sealing, win
nal connection is to be welded. dow installation, etc., and final acceptance.
Usually integral rib panels are fixed at one point while the The erector/GFRC manufacturer should periodically re
other connections have freedom to move. For integral rib quest approval and acceptance for all GFRC work com
panels, it is preferable in connection design to have; (1) the pleted, as deemed necessary in order to adequately protect
main support at the bottom of the panel so that the panel is the interests of everyone involved. In most cases the size
in compression under its own weight the connections are
-
and nature of the project will dictate the proper intervals
only required to restrain the panel, (2) the fastening system for securing approval and acceptance. Periodic approval in
must allow movement between the panel and the structure writing should be considered when it appears that such ac
to avoid overstress. tion will minimize possible problems, which could seri
If the panels are restrained, such as by over-tightening of ously affect the progress of the project.
nuts or bolts, large or sharp changes in section thickness, or Upon notification by the erector/GFRC manufacturer, the
by attachment of adjacent building components (e.g. win contractor and architect and/or engineer should promptly
dow frames), movement of the panel skin due to tempera make arrangements for final inspection of the erected por
ture or moisture changes is restricted. As the panel skin tion of the work to determine if it is plumb, level, aligned
ages, any unrelieved strains could exceed the strain capac within tolerances and that proper connections have been
ity of the aged GFRC, resulting in cracking. Low friction made.
washers (Teflon or nylon) may be desirable to ensure abil
ity for movement of bolts. 10.6 — Patching and Repair
Connection details should provide sufficient three direc
GFRC panels may be superficially damaged (minor chip
tional allowance to accommodate creep, thermal and mois
ping or spalling) during transport or erection. A certain
ture induced panel movements, field tolerances, and di
amount of repair of product is to be expected as a routine
mensional changes in the building frame. Slotted and/or procedure. Production blemishes should have been cor
oversized holes in connections or special fasteners are the rected at the plant. Since patching and repair of GFRC is a
usual means to achieve this. specialized activity, it is recommended that the manufac
Connections may have to be protected from corrosion de turer’s personnel be used for repair work. They understand
pending on exposure conditions. Protection may be: the use of bonding agents and shading or texturing tech
1. Painting with shop primer niques. It may even be necessary to prepare a composite
2. Coating with the zinc rich paint patching mix reinforced with glass fibers. Damage that af
3. Epoxy paint fects the structural integrity should be discussed with the
4. Hot dip galvanizing design engineer. In general, the extent of patching and re
5. Zinc or cadmium plating pairing required should be minor. It is important that all re
pairs be performed in advance of final cleaning and joint
10.4— Protection of Work sealing. The repair work must be fully cured, clean, and dry
All GFRC units should be furnished to the jobsite in a prior to sealing joints.
clean and acceptable condition.
The GFRC erector should protect the unit and adjacent 10.7 — Cleaning
material such as glass and aluminum from damage by field Dirt and stains that occurred during yard storage, ship
welding or cutting operations and provide noncombustible ping, or erection shall be cleaned. Many panels will require
shields, as necessary. To minimize staining, all loose slag only spot cleaning and with soap and water while some
and debris should be removed immediately after welding is may require a general cleaning. Cleaning should be pre
complete. The general contractor should be responsible to formed no earlier than three days after any GFRC skin re
56
pairs have been completed and after all joints are sealed. design development phase. Items affected by joint design
The manufacturer should be consulted regarding cleaning are: panel size, weathering, tolerances, transition between
procedures. Prior to preceding with general cleaning, a adjacent materials, and location of openings.
small [at least one square yard (0.8 square meters)] incon Characteristics that should be considered when making
spicuous area should be cleaned and checked to be certain the final selection of sealants from those with suitable
that the procedures are not detrimental to the GFRC or ad physical (durability) and mechanical (movement capabil
jacent materials. The effectiveness of the cleaning on the ity) properties are: adhesion to different surfaces, surface
sample area should be judged after the surface has been al preparation necessary to ensure satisfactory performance,
lowed to dry for it least one-week. Cleaning should be serviceable temperature range, curing characteristics (dirt
done when the temperature and humidity allow rapid dry pickup, susceptibility to damage due to movement of joint
ing. Slow drying increases the possibility of efflorescence while sealant is curing), puncture, tear and abrasion resist
and discoloration. ance, color desired and color retention, ease of application
A suggested order for testing procedures for removal of and compatibility with other sealants to be used on the job.
dirt, stains, and efflorescence is: 10.8.1 —Width of Joints
l.Dry scrubbing with a stiff fiber brush. Sealant life and performance are greatly influenced by
2.Abrasive blasting with industrial baking soda. joint width. Joints between GFRC panels must be wide
3. Wetting the surface with water and vigorous scrubbing enough to accommodate anticipated wall movements. Joint
with a stiff fiber brush followed by a thorough rinsing tolerances must be carefully evaluated and followed if the
with clean water. High-pressure water or steam clean joint sealant system is to perform within its design capabil
ing may also be thed. ities.
4. Chemical cleaning compounds such as detergents, When joints are too narrow, bond or tensile failure of the
muriatic acid, phosphoric acid, or other commercial joint sealant will occur, and/or adjacent units may come in
cleaners used in accordance with the manufacturer’s contact and be subjected to unanticipated loading, distor
recommendations. tion, cracking and local crushing (spalling).
5. Sand blasting may be considered if this method was Joint widths should not be chosen for reason of appear
originally used in exposing the surface. ance alone, but must relate to panel size, anticipated move
For information on removing specific stains from GFRC ment, building tolerances, joint sealant materials and adja
reference should be made to “Removing Stains and Clean cent surfaces. The required width of the joint is determined
ing Concrete Surfaces,” IS 214, published by the Portland by the temperature extremes anticipated, the movement ca
Cement Association, Skokie, IL. pability of the sealant to be used, the temperature at which
For information on efflorescence that may occur to vari the sealant is initially applied, panel size and fabrication
ous degrees on panel surfaces, reference should be made to tolerance of the GFRC units. The following factors take
“Efflorescence of Precast Concrete,” TN-3, published by precedence over appearance requirements:
the Precast/Prestressed Concrete Institute, Chicago, IL. 1. Temperature Extremes: The temperature range used
must reflect the differential between seasonal extremes of
10.8— Joint Sealing temperature and temperature at the time of sealant applica
One-stage joints are most commonly used in the United tion. Although affected by ambient temperature, joint
States, normally in the form of an elastomeric sealant close movement must be determined from panel temperature
to the exterior surface. A minimum GFRC panel return of rather than ambient temperature. Consideration should be
1-1/2 in. (38 mm) at the joints is recommended with 2 in. given to the orientation of the wall surface in relation to the
(51 mm) preferred. The following are general guidelines sun. South walls will experience significantly higher tem
for the use of joint sealants. For a comprehensive discus peratures, while north walls may experience lower.
sion of joint sealants used between wall panels, refer to 2. Sealant Movement Capability: The minimum design
ASTM Cl 193° and consult with sealant manufacturers and width of a panel joint must take into account the total antic
installers. ipated movement of the joint (i.e., the GFRC panels) and
A joint will provide a degree of watertightness consistent the movement capability of the sealant. All GFRC is sub
with its design and exposure. In addition the intended use ject to volume changes from creep, shrinkage, and temper
and size of the building will also determine design require ature variations.
ments for the joint. Design criteria for joints include; 3. Application Temperature: A practical range of instal
amount of movement to be accommodated, architectural lation temperatures considering moisture condensation at
appearance, function of the building, exposure (orientation low temperatures and reduced working life at high temper
and climatic conditions) and economics. The following de atures, is from 40 to 90 deg. F (5 to 35 deg. C). This tem
cisions must be made in response to the design criteria: perature range should be assumed in determining the antic
width and depth, type, location, number, architectural treat ipated amount of joint movement.
ment and materials selection. Many factors may be involved in actual joint movement.
Ideally, joint locations should be determined during the These include, but are not limited to: mass of material,
57
lion, building settlement, method of fastening
color, insul of fasteners, differential heating due to van- Tooled Exterior Face
and locatio’ , thermal conductivity, differential thermal Surface
able shadirg), building sway, and seismic effects. Larger
stress (bowje wider joints in order to accommodate realis
panels reqU in straightness of panel edge, edge taper, and
tic toleranc Material and construction tolerances that can
panel W1dtt1ler joints than anticipated are of particular im
produce Smch tolerances should be considered in the de
portance. S jjons and considerations. Skin
sign calcu1’ also accommodate variations in building and
Backer Rod
Joints musions so a liberal tolerance should be allowed
panel dime’s widths. For example a 3/4 in. (19 mm) joint
Fig. 56. Joint with field-molded sealant.
for the Ofl/_jfie(J with a ± 1/4 in. (± 6 mm) tolerance.
may be spe’ calculation of panel joint size can be made as on the ideal proportion, however, generally accepted guide
A practic lines are:
1. For joints from 1/2 in. to 1 in. (13 to 25 mm) wide: The
followLc + B + C
sealant depth should be 1/2 the width.
2. For joints in excess of 1 in. (25 mm) wide: Sealant
where: um joint width, in. depth should be 1/2 in. (13 mm) maximum.
J = mini movement capability of the sealant in percent.
The depth of the sealant should be controlled by using a
X = stattd movement of panel from thermal changes
suitable backup material. To obtain the full benefit of a
A = calcjcjent of thermal expansion) (change in tern-
well designed shape factor, the backup materials must have
e) (panel length)
= (coe3-
1 a bondbreaker surface or be flexible enough that it doesn’t
perat .jal construction tolerances.
limit shape change of the sealant, Fig. 56. (Note sealant
B = matj or other considerations as appropriate.
shape: wide edges for bond, narrow center for flexibility.)
C = seis ,4ng example will illustrate the use of the equa
The follo” of 15 ft. (4.57 m) length, expecting a maxi 10.8.2 — Sealant Installation
tiOn. PaneJramre change in the concrete of 60 deg. F (33 The sealants used for specific purposes are often installed
mum temp by different subcontractors. For example, the window sub
sealant installation temperature, with a mate
deg. C) 0 contractor normally installs sealants around windows,
tj-uction tolerance of 0.25 in. (6 mm), are to be whereas a second subcontractor typically installs sealants
rial or con a sealant having ± 25% movement capability
sealed W1tl’jned by ASTM C7 1 9)B1 If the coefficient of between panels. The designer must select and coordinate
(as deteril
1 nsion of the GFRC is assumed to be 12 x l0 all of the sealants used on a project for chemical compati
thermal e?(
j2, the calculated movement of the panel from
9 bility and adhesion to each other. In general, contact be
iniinideg’ ge is as follows: tween different sealant types should be minimized.
thermal cl1 iinJdeg. F) (60 deg. F) (180 in.) = 0.130 in. The recommendations of the sealant manufacturer should
(l2xl06 always be followed regarding mixing, surface preparation,
X = 25’on tolerance =0.25 in. (6 mm) priming, application life, and application procedure. Good
Construct considerations workmanship by qualified sealant applicators is the most
c important factor required for satisfactory performance.
No seisn3ted minimum joint width is as follows:
The0.13j) +0.25 in.=0.77 in. The edges of the GFRC units and the adjacent materials
must be sound, smooth, clean, and dry. They must also be
.th determined is too wide, another sealant hay- free of frost, dust, loose mortar or other contaminants that
If joint movement capability should be selected. For may affect adhesion such as form release agents, retarders,
rug a gre movement capability is ± 50%, the joint width or sealers. Sometimes, smooth GFRC has a ‘skin” on the
example, ple becomes 0.51 in. (13 mm). surface, which may peel off leaving a gap between it, and
in the exaió optimum quality for the installation and per- the GFRC after the joint sealant has been applied. It may
To provi 0 field-molded sealants, the architect should be more economical and effective to prepare joint surfaces
formancet widths not less than 3/4 in. (19 mm). Corner prior to erection, if required. It may be desirable to conduct
specify j0 j be 1 in. (25 mm) wide to accommodate the
1 adhesion or peel tests to determine the compatibility of the
joints shOnent and bowing often experienced at this loca sealant with the contact surfaces.
extra moV v joints are a high risk for any joint sealant in Backup materials help to shape sealants. When selecting a
tion. Naii
0 backup material andlor bond breaker, the recommendations
stallation ed sealant depth is dependent on the sealant of the sealant manufacturer should be followed to insure
The req1) time of application. The optimum sealant compatibility. The backup should not stain the sealant, as
width at this may bleed through and cause discoloration of the joint.
th relationships are best determined by the
width/d@Vjjfacturer Since all manufacturers do not agree Backup materials, should be of suitable size and shape so
sealant nV
58
that, after installation, they are compressed 30 to 50 per reduce water absorption and dirt accumulation.
cent. Principal functions of backup materials are: control Sealers or clear surface coatings should be tested on rea
ling the depth and shape of the sealant in the joint (provide sonably sized samples of varying ages, and their perform
proper sealant dimensions and shape), serving as a bond ance verified over a suitable period of exposure, or use
breaker, assisting in tooling of the joint and protecting the based on prior experience under similar conditions. Sealers
back side of the sealant from attack by moisture vapors try should be applied in accordance with the manufacturers
ing to escape from the building. written recommendations. Some sealers may stain, soil,
Primers may be recommended by the sealant manufac darken, or discolor the finish. Also, some sealers may af
turer. Special care should be exercised to avoid staining the fect the bond of joint sealants or cause the joint sealants to
outside face of the GFRC unit since some primers will stain the panel. The manufacturer of both the sealer and the
leave an amber colored stain if brushed along the surface. joint sealant should be consulted or the specified materials
This stain will have to be mechanically removed which should be pre-tested before application.
will be expensive. The primer should be allowed to cure Jobsite applied coatings should not be applied until all re
before application of the sealant. The sealant and primer pairs and cleaning have been completed. In cases where the
panels have been coated at the manufacturing plant, and
should always be supplied by the same manufacturer.
additional cleaning is required; it may be necessary to re
coat those particular panels.
10.9 — Sealers Clear Surface Coatings
-
Low-pressure, airless spray equipment is commonly used
Due to its density, even with the minimum practical thick to apply sealers. This results in a uniform application while
ness, GFRC does not require sealing for waterproofing. avoiding excessive rundown. Care must be taken to keep
Sealers or clear surface coatings may be considered for the sealers off of glass or metal surfaces unless testing shows
possible improvement of weathering characteristics or to no detrimental effect.
59
REFERENCES bon Steel Structural Tubing in Rounds and Shapes ASTM
A500, ASTM, West Conshohocken, PA.
I. “Manual of Quality Control for Plants and Production of 21. Specification for Electric Resistance Welded Carbon and
Glass Fiber Reinforced Concrete Products” MNL- 130-91, Alloy Steel Mechanical Tubing, ASTM AS 13, ASTM, West
Precast/Prestressed Concrete Institute, Chicago, IL, 1991, Conshohocken, PA.
184 pp. 22. Specification for Carbon Structural Steel, ASTM
2. Biryukovich, K. L., Biryukovich, Yu. L., and Biryukovich. A36/A36M, ASTM, West Conshohocken, PA.
D.L., “Glass-Fiber-Reinforced Cement”, Published by Bu 23. Specification for General Requirements for Steel Bars Car
divel’nik, Kiev, 1964, Civil Engineering Research Associa bon and Alloy Hot-Wrought and Cold-Finishes, ASTM
tion Translation No.12, London, November 1965.
A29/A29M, ASTM, West Conshohocken, PA.
3. Majumdar, A. J., and Nurse, R. W., “Glass-Fibre-Rein
24. Specification for Steel Bars, Cold-Finished, Standard Qual
forced Cement,” Building Research Establishment Current
Paper, CP 79/74, Building Research Establishment, ity, ASTM A108, ASTM, West Conshohocken, PA.
Garston, Watford, England, August 1974. 25. Specification for Zinc Coating (Hot-Dip) on Iron and Steel
4. Ah, M. A., Majumdar, A. I., and Singh, B., “Properties of Hardware, ASTM A153, ASTM, West Conshohocken, PA.
Glass-Fibre-Cement The Effect of Fibre Length and Con 26. Specification for Electrodeposited Coatings of Cadmium,
tent,” Building Research Establishment Current Paper, CP ASTM B766, ASTM, West Conshohocken, PA.
94/75, October 1975. 27. Specification for Electrodeposited Coatings of Zinc on Iron
5. “A Study of the Properties of Cem-FIL/OPC and Steel, ASTM B633, ASTM, West Conshohocken, PA.
Composites, “Building Research Establishment Current Pa
28. Structural Welding Code Steel, AWS Dl .1, American Weld
per CP 38/76, June 1976, 14 pp.
ing Society, Miami, FL.
6. “Innovation by Design: Glass Fiber Reinforced Concrete
Cladding,” GFRC 3-93, Precast!Prestressed Concrete Insti 29. Structural Welding Code Sheet Steel, AWS Dl .3, American
tute, Chicago, IL, 1993, 16 pp. Welding Society, Miami, FL.
7. “Code of Standard Practice for Precast Concrete,” PCi 30. Guide for Use of Joint Sealants, ASTM C1l93, ASTM,
Design Handbook for Precast and Prestressed Concrete - West Conshohocken, PA.
Fifth Edition, Precast/Prestressed Concrete Institute, 31. Specification for Elastomeric Joint Sealants, ASTM C920
Chicago, IL, 1999, pp.
32 to 10-42.
-
10 ASTM, West Conshohocken, PA.
8. Specfication for Portland Cement, ASTM C 150, ASTM, 32. Design Guide: Glassfibre Reinforced Cement (Second Edi
West Conshohocken, PA. tion) Pilkington Brothers Ltd., St. Helens, England, 1979.
9. Specification for Concrete Aggregates, ASTM C33, ASTM,
33. Cem-FIL GFRC Technical Data Manual, Pilkington Rein
West Conshohocken, PA.
forcements Limited, St. Helens, England, 1985.
10. Specification for Aggregate, for Masonry Mortar, ASTM
34. Oakley, D. R. and Proctor, B. A “Tensile-Stress-Strain of
C144, ASTM, West Conshohocken, PA.
11. Specification for Chemical Admixtures for Concrete ASTM Glassfibre Reinforced Cement Composites” Proceedings,
C494, ASTM, West Conshohocken, PA. RILEM Symposium on Fibre Reinforced Cement and Con
12. Specification for Air--Entraining Admixtures for Concrete, crete, The Construction Press Limited, 1975, pp. 347-359.
ASTM C260, ASTM, West Conshohocken, PA. 35. Proctor, B. A., “Glass-Fibre Reinforced Cement-- Princi
13. Specfication for Coal Fly Ash and Raw or Calcined Nat ples and Practices”, Proceedings, International Congress
ural Pozzolan for Use as a Mineral Admixture in Concrete, on Glassfibre Reinforced Cement, The Glassfibre Rein
ASTM C618, ASTM, West Conshohocken, PA. forced Cement Association, Wigan, United Kingdom, 1977.
14. Specification for Pigments for Integrally Colored Concrete, 36. Mindess, S. and Young, F. J., “Concrete,” Prentice-Hall
ASTM C979, ASTM, West Conshohocken, PA. Inc., Englewood Cliffs, NJ, 1981, pp. 496-498.
15. Specification for Steel, Sheet and Strip, Hot-Rolled, Car
37. Oakley, D. R., and Unsworth, M. A., “Shear Testing for
bon, Structural, High-Strength Low-Alloy and High-
Glass Reinforced Cement,” Proceedings, RILEM Sympo
Strength Low-Alloy with Improved Formability, ASTM
AlOll ASTM, West Conshohocken, PA.
,
sium on Testing and Test Methods of Fibre Cement Com
16. Specification for Steel, Sheet, Cold-Rolled, Carbon, Struc posites, Edited by R. N. Swamy, The Construction Press
tural, High-Strength Low-Alloy and High-Strength Low-Al Limited, 1978, pp. 233-241.
loy with Improved Formability, ASTM A1008, ASTM, West 38. Langley, A. A., “The Dimensional Stability of Glass-Fibre
Conshohocken, PA. Reinforced Cement,” Magazine of Concrete Research, Vol.
17. Specification, for the Design of Cold-Formed Steel Struc 33,No. 117,pp. 221-226, December 1981.
tural Members, 1996 Edition with the July 30, 1999 Sup 39. “Shrinkage of GRC Composites,” Cem-FIL Bulletin No.
plement, “Cold-Formed Steel Design Manual,” American 51, Pilkington Reinforcements Ltd., St. Helens, England,
Iron and Steel Institute, Washington, DC. May 1986, 8 pp.
18 Specification for Steel Sheet, Zinc-Coated (Galvanized) or
40. Test Method for Resistance of Concrete to Rapid Freezing
Zinc-Iron Alloy-Coated (Galvanealed) by the Hot-Dip
Process ASTM A653/A653M, ASTM, West Conshohocken,
and Thawing, ASTM C666, ASTM, West Conshohocken,
PA. PA.
19. Specification for General Requirements for Steel Sheet, 41. Daniel, J. I., and Schultz, D. M., “Long-Term Strength
Metallic-Coated by the Hot-Dip Process, ASTM Durability of Glass Fiber Reinforced Concrete,” Portland
A924/924M, ASTM, West Conshohocken, PA. Cement Association, Skokie, IL, PCA RID Serial No. 1780,
20. Specification for Cold-Formed Welded and Seamless Car- April 1985,48 pp.
60
42. Daniel, J. I., and Schultz, D. M., “Durability of Glass Fiber 1979, pp. 17-27.
Reinforced Concrete Systems,” Proceedings Durability of
63. “Properties of GRC: Ten-Year Results,” Building Research
Glass Fiber Reinforced Concrete Symposium, November
12-15, 1985, Precast/Prestressed Concrete Institute, Establishment Information Paper, IP 36/79, November
Chicago, IL, pp.174-198. 1979,4 pp.
43. Behavior of GRC in Freeze/Thaw Conditions, Cem-FIL 64. Proctor, B. A., “Past Development and Future Prospects
Corporation, Nashville, TN, October 1975,5 pp. for GRC Materials,” Proceedings of the International Con
44. Ward, D., “The Effect of Freeze/Thaw and Low Tempera
gress on Glass Fibre Reinforced Cement, The Glassfibre
ture Conditions on GRC,” Piflcington Brothers Ltd., Eng
land, October 1978. Reinforced Cement Association, Wigan, United Kingdom,
45. Test Method for Behavior of Materials in a Vertical Tube November l98l,pp. 50-67.
Furnace at 750 deg. C., ASTM E136, ASTM, West Con 65. “Application Data for Use with Cem-FIL Fiber, Guidelines
shohocken, PA. for Testing,” Pilkington Brothers Ltd., England, 1978.
46. Test Method for Surface Burning Characteristics of Build
66. “Architectural Precast Concrete,” MNL 122-89,
ing Materials, ASTM E84, ASTM, West Conshohocken,
PA. Precast/Prestressed Concrete Institute, Chicago, IL, 1989,
47. “Flame Spread Classification and Smoke Density Devel 352 pp.
oped--Glass Fiber Reinforced Concrete Panels,” United 67. “Design and Typical Details of Connections for Precast
States Testing Company, Inc., Los Angeles, CA, December and Prestressed Concrete” MNL 123-88, Precast/Pre
1, 1989,6 pp.
stressed Concrete Institute, Chicago, IL, 1988, 270 pp. And
48. Method for Fire Tests of-Building Construction and Materi
als, ASTM El 19, ASTM, West Conshohocken, PA. Addenda to Design and Typical Details of Connections for
49. 1997 Uniform Building Code, International Conference of Precast and Prestressed Concrete, PCI Journal Vol. 4 No. 5,
Building Officials (ICBO), Whittier, CA.. Sept.-Oct. 1995
50. Elkalite Fiber Reinforced Cement, Product Brochure, Elka 68. Schultz, D. M., Daniel, J. I., and Oesterle, R. G., “Design
lite Limited, Sussex, England, 1973.
Considerations for GFRC Facade Panels Incorporating the
51. Langley, A. A., “The Air and Water-Vapor Permeance of
Glass-Fibre Reinforced Cement” Magazine of Concrete Steel Stud/Flex Anchor Connection,” Proceedings of the
Research,Vol.33,No. 114,March 198l,pp. 18-26 6th Biennial Congress, October 20-23, 1987, pp. 241-247,
52. Correspondence from: Ward, D., Pilldngton Brothers Ltd., The Glassfibre Reinforced Cement Association, Wigan,
England, January 22, 1980. United Kingdom.
53. Litherland, K. L., Oakley, D. R., and Proctor, B. A., “The 69. Daniel, J. I., Roller, J. J., Weinmann, T. L., Oesterle, R. G.,
Use of Accelerated Aging Procedures to Predict the Long
Strength of GRC Composites” Cement and Concrete Re and Schultz, D. M., “Quality Control and Quality Assur
search,Vol. ll,No. 3, 1981,pp.455-466. ance for the Manufacture and Installation of GFRC Fa
54. Oakley, D. R., Litherland, K. L., and Proctor, B. A., “The cades,” Proceedings of the 7th Biennial Congress, Septem
Development of a Method of Predicting the Weathering Be ber 26-28,1989, Maastricht, The Netherlands, pp. 243-266,
havior of Glass Reinforced Cement Composites,” Proceed The Glassfibre Reinforced Cement Association, Wigan,
ings of the Second International Conference on the Durabil
ity of Building Materials and Components, Gaithersburg, United Kingdom.
MD, September 1981. 70. Oesterle, R. G., Schultz, D. M., and Glikin, J. D., “Design
55. Proctor, B. A., Oakley, D. R., and Litherland, K. L., “De Considerations for GFRC Facades,” Thin-Section Fiber
velopment on the Assessment and Performance of GRC Reinforced Concrete and Ferrocement, SP-124, American
over 10 years, Composites”, April 1982, pp. 173-179. Concrete Institute, Detroit, MI, 1990, pp.- 157-182.
56. Gustaferro, A. H., “Fire Test of a Glass Fiber Reinforced
Concrete Wall Panel Produced by the Cem-FIL Corpora 71. Hanson, N. W., Roller, J. J., Daniel, J. I., and Weinmann, T.
tion with Thermafiber Insulation and Sheetrock Firecode L., “Manufacture and Installation of GFRC
C,” July 1, 1979, Cem-FIL Corporation, Nashville, TN. Facades, “Thin-Section Fiber Reinforced Concrete and Fer
57. Gustaferro, A. H., “Two-Hour Fire Tests of Glass Fiber Re rocement, SP-124, American Concrete Institute, Detroit,
inforced Concrete Wall Panels with Thermaflber Insulation MI., 1990, pp. 183-213.
and Sheetrock Firecode C Gypsum Panels,” April 1982,
72. “PCI Design Handbook Precast and Prestressed Con
Precast/Prestressed Concrete Institute, Chicago, IL. -
58. “Report of Non-Load Bearing Fire Resistance Tests of crete, 5th Edition,” MNL 120-99, Precast/Prestressed Con
Non-Symmetrical 9” Thick PGFRC Exterior Curtain Wall crete Institute, Chicago, IL, 1999, 690 pp.,
Fired on the PGFRC Exterior Side Only,” Warnock Hersey 73. “Code of Standard Practice for Steel Buildings and
International, Inc., Antioch, CA, November 1983. Bridges,” American Institute of Steel Construction,
59. Gustaferro, A. H., “Fire Tests of Glass Fiber Reinforced
Chicago, IL, March 2000, 90 pp.
Concrete Wall Panels with Thermafiber Insulation Firecode
C Gypsum Panels,” February 1982, Precast/Prestressed 74. Pfeifer, D. W., Rogalla, E. A., and Nugent, W. J., “Aging
Concrete Institute, ,Chicago, IL. and Cracking of Composite GFRC Wall Panel Skins on
60. Stucke, M. S., and Majumdar, A. J., “Microstructure of Metal Stud Frames in the United States,” Proceedings 4th
Glass Fibre-Reinforced Cement Composites,” Journal of Rilem International Symposium on Fibre Reinforced Ce
Materials Science, Vol. ll,l976,pp.1019-103O.
ment and Concrete, July 20-23,1992, pp. 933-953, Univer
61. Proceedings--Durability of Glass Fiber Reinforced Con
crete Symposium, November 12-15, 1985, Precast/Pre sity of Sheffield, Sheffield, England.
stressed Concrete Institute, Chicago, IL, 356 pp. 75. “ASHRAE Handbook of Fundamentals,” American Society
62. Majumdar, A J., and Laws, V., “Fibre Cement Fibre Ce of Heating, Refrigerating, and Air-Conditioning Engineers,
ment Composites: Research at BRE, “Composites”, January Inc., New York, NY, 1997.
61
76. “Standard Tolerances for Concrete Construction and Mate ings 10th Biennial Congress of the GRCA, Strasbourg, The
rials,” ACI 117-90, American Concrete Institute, Detroit, Glassfibre Reinforced Cement Association, Wigan, United
MI, 1990, 22 pp. Kingdom, 1995.
77. Ball, H. P., Jr., and Wackers, M., “Performance of Polymer 94. Ball, Hiram P. Jr. “Polymer modified glass fiber reinforced
Modified GFRC,” Proceedings of the 9th Biennial Con concrete composites- a 20 year review”, Proceedings 11th
gress, June 13-17, 1993, Copenhagen, Denmark, 16 pp., Biennial Congress of the GRCA, Cambridge, The Glassfi
The Glassfibre Reinforced Cement Association, Wigan, bre Reinforced Cement Association, Wigan, United King
United Kingdom. dom, 1998.
78. Daniel, J. I., and Pecoraro, M. B., “Effects of Forton Poly 95. Firestop Systems Inc., 1412 Derwent Way, Delta, B. C.,
mer on Curing Requirements on AR Glass Fiber Reinforced Canada V3M 6H9.
Cement Composites”, Report to Forton, Inc., Sewickley, 96. International Building Code, International Code Council,
PA, Submitted by Construction Technology Laboratories, A Inc., Falls Church, VA., 2000.
Division of the Portland Cement Association, Skokie, IL, 97. Test Method for Dry and Wet Bulk Density, Water Absorp
October 1982,48 pp. tion and Apparent Porosity of Thin Sections of Glass Fiber
79. Knowles, R. P., and Proctor, B. A., “The Properties and Reinforced Concrete ASTM C948, ASTM, West Con
Performance of Polymer modified GRC” Proceedings of shohocken, PA
the 6th Biennial Congress of the GRCA, 20-23 October,
1987, Edinburgh, Scotland, pp. 79-89, The Glassfibre Rein
Supplementary References
forced Cement Association, Wigan, United Kingdom.
5-1. “International Congress on Glass Fibre Reinforced Ce
80. “Erectors’ Manual Standards and Guidelines for the
-
63
APPENDIX A - STUDENTS t
In order to maintain the required reliability it is important mended, more are better. Students t values listed below
that an adequate number of tests be made under production with the procedures in Section 5.4.1 and 5.7.2.3 account
conditions by each manufacturer on the specific mix to be for the actual number of tests. A wide range of Students
used for a job. Each flexure test is the average of three values are presented so that equivalent reliability can be
specimens loaded with the mold side in tension and three obtained while taking advantage of a greater number of
with it in compression to account for thickness, and surface tests or if circumstances dictate, proceeding with a smaller
variations. A minimum of twenty tests (120 flexure speci number of tests.
mens or twenty anchor specimens of a type) are recom
um value.
Table Al. Students t for the required 99% of tests to be above the assumed minim
Number Degrees Students Number Degrees Students
Number Degrees Students
of of t of of t
of of t
Tests Freedom Tests Freedom
Tests Freedom
14 13 2.650 26 25 2.485
2 1 31.821
15 14 2.624 27 26 2.479
3 2 6.965
16 15 2.602 28 27 2.473
4 3 4.541
17 16 2.583 29 28 2.467
5 4 3.747
18 17 2.567 30 29 2.462
6 5 3.365
19 18 2.552 31 30 2.457
7 6 3.143
20 19 5.539 41 40 2.423
8 7 2.998
21 20 2.528 61 60 2.390
9 8 2.896
22 21 2.518 121 120 2.358
10 9 2.821
23 22 2.508 00 00 2.326
11 10 2.764
12 11 2.718 24 23 2.500
13 12 2.681 25 24 2.492
The variation of test values is as important as high average both the number of tests and their coefficient of variation
values. Small variation indicates more uniformity and a on the ratio of assumed ultimate strength for design to the
higher reliability. Fig. Al shows the effect of variation in average test value.
(1)
E
D
0
E
D
C’)
Table Bi. Data from 20 consecutive 28-day andf’ = 1/3 fur (1t V) (540)
unaged production flexural tests (stresses in psi). = 1/3 {2703 [1-(2.539)(0.090)J}
= 694 psi
Yield Ultimate controllingf’ is smallest of: [f’] 876, V’taIl 694, and
842 1210 2269 2665 [f’maxl 1200 (5-9,5-10,&5 11)
1282 1322 2961 2792 = 694 psi
65
Appendix C — Integral Rib Wall Panel Wind Stress Analysis
-
Design Criteria
Assume a single skin GFRC panel (see Figs. Cl to C5)
Since self loads are essentially in the plane of the panel
and, even when the panel is in the horizontal attitude, are
less than wind loads they can be ignored except for con
nections.
Lf)
Connections
Connection design is typical, taking dead load on bottom
pair, wind on all four, and in-plane seismic on either the
bottom pair or a side pair.
Connections and joints must allow for a GFRC length
change between them of not less than 1/8 in. per 10 ft. This
usually results in fixing one corner and using slotted or
oversized holes in the others.
Design Considerations
This example is only for purpose of investigating stresses
8-2”
due to wind. It does not consider effects of thermal or
moisture movements or restraints. These are often additive
Fig. Cl. Elevation of panel.
to wind stresses and may control design.
3
bd = 3
12C/2)
W
J s (12)(12)(12t
)
2 2
288t — =0.125 in.
/ft of width
4
/288f I 0.125
S=—= /ftofwidth
3
=0.5Oin.
t
__yI
w C /4
Then, if f = 600 and w, = 26, and both ends are fixed, the
span/depth ratio can be expressed as:
28” ‘
82
= 20(28)2
M = =131 in.-lb.
ore =41 in. fora 1/2 in. skin. 10 10(12)
2
M 131
When one end is fixed and the other end is pinned or f =—-- =•öj =262 psi
when both ends are pinned:
£ /192f Interior spans:
T/WU -
66
or £ = 33 in. for a 1/2 in. skin whenf = 600 and w = 26. 33”
Cantilevered member:
23
z=w /(96t
4
£
E )
67
1/2” Skin
1/2’TYP.-
$f!
[4I
I 12” (24t) 3/4 5 39.5” I
i—
Fig. C4. Rib section.
Assumed Effective
L__L== 12” (24t) 9”
Assumed Effective
Horizontal Rib
Fig. C5. Edge beams.
Maximum tributary width on box rib:
33+ 14=47in.=3.92ft.
Deflections at Service Load
The section properties are: Skin interior span:
4
wçe — 20(33)
1= 96.6 • 5 = 19.5 in. 92.9 in.
3
,
T
4 SB =
E
3
384(12)t — 4608(0.5)31.5(106)
= 3.92(20X6.5)
(
3 12)
M = ± 5045 = 0.027 in. or Li 1200
Cross rib:
In this case the minimum section modulus controls since
4
L
5
5w 5(3.92)(20)(6.5)(l2)
wind load is stipulated as being equal in both directions. If
the outward load is greater (putting the outside skin in ten 384 El — 384(1.5)(106)(96.6)
sion) advantage could be taken of the greater outside sec =0.O2in.orL/3590
tion modulus (SB) since the 0.5 shape factor for boxes is set
in order to limit tensile stresses. The compressive stress Vertical member:
could go up to that allowed for single skin (shape factor =
4
L
5
5w 5(4.1)(20)( 1 2.33)( 12)
1.0).
—
1=760 m
ST= 103 in.
4 ,
Sb = 93 in.
3
M 18700
fw=_M =±200 psi
mm =
68
Appendix D — Frame Panel I Skin Wind Stress Analysis
-
Analyze GFRC skin as a two-way slab system using direct Maximum moment @ face of bonding pad
design method (ACT 318-99 Section 13.6) with bonding
pads acting as “support.’ If bonding pad is round, assume a = 0.65(0.75) w
L
2
(1/122)
square with the same area (square with a side of 0.89(diam-
eter).
Resisted by GFRC 2 /2 wide with a section modulus of:
2
(L2(t
where
t= thickness, in.
M o.65(0.75)we
L, (11122)/(
2 —
f)
S 8 j)
w
4
1 2 2
(
2
use
e.g. using 5 in. square pads (= 5.6 in. round with apprecia
ble thickness) at 2 ft on center each way (i.e., £ = 24 5
-
= 19 in.), 1/2 in. thick skin and 20 psf service wind load
Moments will be greatest in longest span direction so only 20 u192
the moments in this direction need to be examined, i.e., L fu=) =l44psi
and £,. Moment curve shape and sign are for any strip cut
anywhere along £2. Column and middle strips are both 1/2 Midspan moment and related stresses are 43% of negative
bay wide. moment.
=W
Lfl
L
2
Total moment/bay = Mo
where:
69
Appendix E In-Plane Anchor Restraint
— -
In-plane anchor restraint stress is the stress in panel skins If the unit volume change strain of the skin is, e, and the
anchored to panel frames that is due to the anchors acting distance from the panel center (or other neutral’ point
as springs which resist the volume changes of the skin. which is assumed to be stationary) is, X, the movement at
The changes are due to initial drying shrinkage, reversible an anchor is, s, and equal to the anchor deflection, D. So
shrinkage and thennal expansion or contraction. Often, the distance from the panel ‘neutral’ point, at which the an
initial drying shrinkage in GFRC is high enough that it is chor yields,
6
y—
never overcome by subsequent changes, so the skin re
mains in tension. = Z£
therefore: for anchors of diameter, d:
For two material skins the stress due to in-plane vQlume 6E1e
change should be assumed to be resisted entirely by the
backing. z=f andI=
To be conservative, the anchor is assumed fixed at one
end by welding it to a (assumed rigid) stud and at the other l6f 2
therefore: (E-l)
end (parallel to the foot) with the bonding pad: = 9 n- E dE
70
5 Flex Anchors
Each Stcle n = 5
: _ravAnc+s
: : : :
For horizontal volume change: so only the two anchors farthest from the center yield at an
=
With 5 flex anchors, 3/8 in. diameter x 2-12 in. effective
length, with 48,000 psi yield, s 24 in. and a 1/2 in. skin
)‘
— f
d
3
3
—
—
48000(0.375)
3(2.5)
—
—
338 lb
(E-2)
fa= = 3 5(48000)(0.375)
nfd
3(2.5)(24)(0.5)
=141 psi
based on taking
three anchors exert a smaller force, proportional to their
distance form the panel center.
Actually if = 0.0002:
338) =521b;338()= 156 ib; and 338 (= 260 lb
16f/
=
so the five anchors together exert a total of:
—
= 16(48000) (2.5)2
9t(29x 106)(0 .375)(0,0002)
= 78 in
SOfa= P5105
(
24
9
)
fa 4 (48000)(0.375)
3(2)(2.5)(24)(0.5)
=56 p51 (E-3)
71
Appendix F — Facing I Backing Interaction Stress Analysis -
The effect of differential volume change between the face of the coefficients (for the sample calculation in Appendix
mix and backing layers of a panel skin is very complex. A G) is in the last column, ‘F’, in the sample calculations at
brief discussion of the phenomenon is in Section 5.10. The the end of this appendix.
procedures in this and the next appendix can be used to es At the end of this appendix is a sample use of the spread
timate the stresses due to differences in characteristics be sheet procedure which has 6 investigations. Column F is
tween the two layers and to thermal and moisture changes. described above. Column A is for the long hand calcula
Two procedures are given, one in each appendix, both with tion earlier in this appendix. Its answers are slightly differ
sample calculations. They differ substantially in complex ent because the computer works with more significant fig
ity, but under the same conditions, the same stresses are ures than are practical in a long hand calculation. The ex
computed. amples herein are purely for illusfrative purposes. They
These procedures do not consider a thermal gradient are not intended to be representative of actual practice.
across the individual layers of the skin, so the stress in each The user must use values appropriate to their individual
layer is axial, but varies in a straight line across the layer circumstances.
and also along the span between anchors due to the fixity
Columns B through E are a sample of the kind of investi
of the assumed beam supportlcontinuity conditions. Theo
gation that can be rapidly made to see the effect of different
retically the fixity can vary from zero to one and one half.
variables for a given panel skin with an architectural facing
The first procedure shows the wide range of stress that oc
on a GFRC backing. Columns B and C both have the same
curs through the thickness of the skin, both at the anchors
and midway between them. The second procedure gives facing shrinkage and the same, but higher, backing shrink
only the maximum stress in each layer, without showing age. In column B both layers have a zero creep coefficient,
where it occurs. while column C has creep coefficients of two for each
The greatest benefit will be achieved if a short computer layer. Note that the resulting stresses are proportional to
program is written using the procedure in this appendix. A ‘one plus the coefficient’, so the stresses in column C are
sample spread sheet program follows to facilitate this. one third of those in column B. This applies as long as the
Once written, this procedure becomes easy to use, gives creep coefficients are the same for both layers.
more information, greater accuracy, and allows the investi Columns D and E have the no shrinkage. Column D has a
gation of a greater number of variables. temperature increase, while column E has a temperature
This procedure allows the simultaneous consideration in decrease. It is best to analyze shrinkage and temperature
each layer of any: thickness, modulus of elasticity, creep, changes separately, and add the resulting stresses, to allow
Poisson’s ratio, shrinkage (or moisture induced expansion), the use of different creep factors for temperature than for
coefficient of thermal expansion, and increase or decrease shrinkage. For seasonal temperature changes the creep
in temperature. Fixity can be varied from zero to one and might be less than it is for shrinkage, but for daily changes
one half. The latter is an extreme and unlikely to occur in a there would probably be no creep effect.
typical panel. A typical maximum design value of one and Column D has a creep coefficient of one and a tempera
one quarter has been suggested.
ture increase of 40 deg. F in both layers. As long as the
The values in the curves for the Ratio Coefficient proce
creep and temperature change are the same in both layers
dure in Appendix G are determined with this procedure by
the stresses are proportional to: 1+ creep, and to the tem
using appropriate values of face to back thickness ratio and
fixity. Namely both moduli of elasticity of one, both creep perature change. If there were a temperature decrease the
coefficients of zero, both Poisson’s ratios of two tenths, stresses would be the same magnitude but opposite sign.
both temperature changes and thermal coefficients of zero, Column E has a temperature decrease of 40 deg. F in the
facing shrinkage of zero, backing shrinkage of one, and facing and 30 deg. F in the backing. This column also has
fixity of one and one and a half. A sample of the derivation a creep coefficient of one and a half for both layers.
Reference:
Garlich, John D. and Tulin, Leonard G., “Modeling of GFRC/Tile Laminate Behavior,” University of Colorado, Boulder,
Colorado, Structural Research Series 8905,June, 1989, 76pp.
72
GFRC FACING AND BACKING STRESS: Equations
FACING & BACKING PROPS. & VOL. CHANGES Facing Backing
Thickness in. tb =
Modulus of elasticity psi =
Poisson’s ratio b
4
1
Shrinkage in. / in. f ——
b ——
i+Cb
1:’ ••3
-
3
Ebtb
Elf Elb=
— l2(l-u.) 12 (-i’,,)
FIXITY = 0 & N Note: Zero is automatically included in equations, a value (N) up to 1.5 must be input for the other limit
73
GFRC FACING AND BACKING STRESS: Sample long hand calculation
EAf= 6
1.5x10
x 0.2_ 0.385x 106 EAb= 6
1.5x10
x 0.6 = 1.lx 106
1-0.22 1-0.18
EIf= 1.5x10
1280
x
6 0.2’_ EIb= 6
1.5x10
x 0.6’.. 32900
12(1- 0.22) 12(1- 0.18)
(0.385 x 106 x 0.5 x 0.2 )+{1.1 x 106 [0.2 +(0.5 x 0.6)]} = 0.396
Yf=
(0.385 x 106) + (1.1 x 106)
The facing stresses at the indicated locations are: Note that this example has combined shrinkage and ther
50, 130, 230 and 250 psi compression. mal expansion for illustrative purposes. This is inadvis
The backing stresses at the indicated locations are: able in practice as they may have different creep and load
80 psi compression, and 50, 100, and 140 tension. factors. The values used here are chosen purely for il
lustration, and are not necessarily realistic.
74
GFRC FACING & BACKING STRESS: Spread Sheet Format
Note lines (cells) 23,24,46 and 47 can be omitted as they relate only to deflection, not stress
75
SPREAD SHEET Sample Calculations
A B C D E F
Sample Shr Shr+Crp Hot+Cip Cold+Crp App G
FACING PROPERTIES & VOLUME CHANGES
Thickness fl. tf 0.2 0.25 0.25 0.25 0.25 0.4
Modulus of elasticity psi Y1 3x10
6 3x10
6 3x10
6 3x10
6 3xl0
6 1
Creep coefficient 0=none 1 0 2 1 1.5 0
Poisson’s ratio 0.22 0.22 0.22 0.22 0.22 0.2
Shrinkage iniin. 800x10 800x10 6
400x10 0
Temp Change Incr. is +, Decr. is — deg. F Df 20 80 -60 0
Thermal coefficient of expansion inJinfdeg. F af 6
5x10 5x10
6 5x10 0
PLATE SIZE
Plate Height in. H 24 24 24 24 24
Plate Width in. W 24 24 24 24 24
The Ratio Coefficient procedure makes several simplify with the procedure in the preceding appendix by using ap
mg assumptions and has some limitations. It assumes all propriate values of face to back thickness ratio and fixities;
the properties, except volume change, are the same for both both moduli of elasticity of one, both creep coefficients of
the facing and the backing; namely the modulus of elastic zero, both Poisson’s ratios of two tenths, both temperature
ity, creep, and Poisson’s ratio. Poisson’s ratio is assumed to changes and thermal coefficients of zero, facing shrinkage
be 0.2 for both layers. Creep could be considered (with of zero, backing shrinkage of one. The coefficients plotted
both layers the same) by dividing the stresses by [1+C], are based on fixities of zero and an extreme of 1.5. A
where C is the creep coefficient (creep strain / initial strain) smaller maximum value could be input in the previous ap
from Chapter 4 for the GFRC and other sources for the pendix equations to develop other similar coefficient
face mix. curves. The example below is shown in column F of Ap
This procedure uses the unit volume change of the back pendix F.
ing with respect to the facing, with backing shrinkage
- With a facing thickness of 0.2 inches and a GFRC backing
taken as positive. If the backing expands (relative to the thickness of 0.5 inches the facing to backing ratio is 0.4.
facing), it would be taken as negative, so the resulting Reading from the curve the multipliers are +1.28 and -0.74.
stresses would reverse in sign. For a given ratio of facing If the moduli of elasticity (of both facing and backing) are
to backing thickness of the skin, the curves give two coeffi 2 x 106 and the backing shrinks by 200 x 10.6 (with respect
cients, which are the maximums determined with the other to or more than the facing) stresses would be:
procedure. These are to be multiplied by the modulus of
elasticity and the differential volume change strain between +1.28 (2) (106) (200) (10.6) = + 512 psi
the facing and backing to find the maximum stress in the
skin, with positive results indicating compression and neg and 0.74 (2) (106) (200) (106)
- = -296 psi
ative indicating tension. Proper attention must be given to
the signs of the volume change, the coefficient and the re Backing tension of 296 psi and facing compression of 512
sultant stress. For the plotted conditions, backing shrink psi. If the facing shortened more than the backing by the
age produces backing tension. same amount the stresses would be reversed, 512 psi facing
The curves for the Ratio Coefficients can be determined tension and 296 psi backing compression.
1.5 I
joacin
*CoIumn F
0.5 - Appendix F
m
0
:
:•
-1.5 -
77
Appendix H — Combining Load Factors and Limiting Stresses
Strength design procedures require that the sum of the If this skin was subject to the following stresses due to
factored loads be less than the factored member strength. service loads:
With GFRC, load effects and member strength are both
measured in terms of flexural and axial stress. Equations Single skin flexural stress
5-1 through 5-7 require consideration of different load fac
Dead Live Wind Erthq Moist Temp
tors for various load combinations. Sections 5.4.1 and
10 0 100 0 0 0
5.4.2 give different limiting stresses for various conditions.
Though the critical combination of these variations can be Box section flexural stress
determined in several ways; the easiest is to compute the 0 0 0 15 0 0
stresses due to service loads, multiply them by the appro
Tensile stress
priate load factors, and divide that product by the appropri
12 0 0 0 150 80
ate limiting stress. These ratios can then be added, using
traditional interaction methods for combining flexural and
For illustration the following example assumes only equa
axial stresses. i.e.:
tions 5-1 through 5-5 apply.
By inspection Equation 5-5 is more critical than 5-1
Single skin factored flexural stress
+ through 5-4, i.e.:
Single skin limiting flexural stress
0.75 [1.4D+1.7(greaterof L,Worl.1E)+
Box section factored flexural stress 1.6 (greater of M or T)j
+
Box section limiting flexural stress
Also by inspection, for all conditions: Live is less than
Factored tensile stress 1.0 Wind, and Temperature is less than Moisture so the L and T
Limiting tensile stress
terms drop out. 1 .1E is also less than W even considering
its lower limiting stress so it is not critical.
Stresses due to skin anchor restraint and to the interaction
between facing and backing with differential material prop
Equation 5-5 for this case simplifies to:
erties are tensile.
0.75 [1.4D+1.7W +1.6 M]
Particular caution must be exercised in determining the
but since stresses must be separated, to flexural + tensile,
appropriate limiting stress. The shape factor, s, is not the
equation becomes:
same for all sections as defined in Section 5.4.1 and the
tensile limit is different than the flexural limit.
0.75 [1.4 D + 1.7W] flexural + .75 [1.6 M] tensile
For example if a member had anf’ of 900 psi, the:
Single skin limiting flexural stress would be:
therefore:
0 sf’= 0.75 (1) (900) = 675 psi 0.75 [1.4(10) + 1.7 (100)1 0.75 [1.6(150)]
675 + 270
Box section limiting flexural stress would be:
78
.—-.:....
.
Appendix I — Alternate Cementitious Systems
for GFRC Panels
Three cementitious systems introduced into the United 1-3. Molloy, H. J., Jones, J., and Harmon, T., “Glass Fiber
States since 1993 appear to minimize the loss in ductility Reinforced Concrete with Improved Ductility and
of the GFRC. The approaches are different. Long Term Properties,” Proceedings 9th Biennial
One system uses a calcium suiphoaluminate rapid-harden Congress of the GRCA, 13-17 June, 1993, Copen
ing cement and an additive which is at least 5 percent of hagen, Denmark, 9 pp.. The Glassfibre Reinforced
cement weight (see Refs. I-i to 1-4). This system obtains Cement Association, Northway, Wigan, United King
80 percent of the 28 day strength in 24 hours with the 28 dom.
day strengths comparable to conventional GFRC. Panels 1-4. Molloy, H. J., and Jones, J., “Application and Produc
must be kept wet during initial set and while heat is being tion Using Rapid Hardening Hydraulic Cement Com
liberated during the initial cement hydration (exotherm), posites,” Proceedings 9th Biennial Congress of the
(typically lasting 15 to 30 minutes). No further curing GRCA, 13-17, June, 1993, Copenhagen, Denmark, 7
need be provided. Polymer curing admixtures must not be pp., The Glassfibre Reinforced Cement Association,
used because they can interfere with the curing of the ce Northway, Wigan, United Kingdom.
ment. I-S. Ambroise, I., Dejean, J., Foumbi, J., and Pera, J.,
The other system consists of modifying the cement matrix “Metakaoline Blended Cements: An Efficient Way to
by the addition of a synthetic pozzolanic material rich in Improve GRC Durability and Ductility,” Proceedings
metakaolinite 2 .A1 produced by the thermal acti
(2Si0
)
3
0 6th Biennial Congress of the GRCA, 20-23 October,
vation of kaolin in air at 1290 to 1650 deg. F (700 to 900 1987, Edinburgh, Scotland, p. 19-24, The Glassfibre
deg. C) (see Refs. I-S to 1-9). Generally, an attempt is Reinforced Cement Association, Northway, Wigan,
made to consume with the addition of 20 to 25 percent United Kingdom.
metakaolinite by weight of portland cement as much as 1-6. Soukatchoff, P., and Ridd, P. J., “High Durability
possible of the calcium hydroxide generated during the hy Glass-Fibre Reinforced Cement Using a Modified Ce
dration process. This prevents growth of the calcium hy mentitious Matrix,” Proceedings 8th Biennial Con
droxide crystals from filling the spaces between the fiber gress of the GRCA., 21-24, October. 1991, Maas
bundles. This system may be designed to use or not use tricht, Netherlands, p.45-60, The Glassfibre Rein
polymer curing admixture. Unlike most other pozzolans, forced Cement Association, Northway, Wigan, United
which develop strength slowly, the high reactivity of the Kingdom.
metakaolin results in high early strength enabling normal 1-7. Thiery, I., and Genis, A., “High Durability Glass Ce
stripping time. ment Composites: New Vetrotex System,” Proceed
A third system was introduced in 1999 which is based on
ings 7th, Biennial Congress of the GRCA, 26-28 Sep
a matrix of ordinary Portland cement, granulated blast fur
tember, 1989, Maastricht, Netherlands pp. 10, The
nace slag, and a super low shrinkage admixture (NSR).
Glassfibre Reinforced Cement Association, Northway,
NSR is an admixture consisting of calcium sulfate and cal
Wigan, United Kingdom.
cium fluoroaluminate. In addition to providing stable long
1-8. van der Plas, C., Yue, B., and Bijen, J., “Effect of Poz
term properties, it also confers very low shrinkage proper
zolans on the Durability of Polymer Modified Glass
ties on the composite. (see Refs. 1-10 and I-li). The system
Fibre Reinforced Cement,” Fly Ash. Silica Fume,
can be used with or without polymer curing admixture.
Slag and Natural Pozzolans in Concrete--Proceedings,
References Fourth International Conference, Istanbul, Turkey,
I-i. Tallentire, A. C., “New Developments in Rapid Hard American Concrete Institute, Detroit, Michigan. 1992,
ening and High Strength Cement Technology of Rele pp. 175-188.
vance to the GRC Industry,” Proceedings 6th Biennial 1-9. Marikunte, Aldea, and Shah “Durability of Glass
Congress of the GRCA, 20-23 October, 1987, Edin Fiber reinforced Cement Composites Effect of Silica
burgh, Scotland, p.53-58, The Glassfibre Reinforced Fume and Metakaolin” Advanced Cement Based Ma
Cement Association, Northway, Wigan, United King terials, 1997 5,100-108, Elsevier Science Ltd., NY.
dom. I-10.K. Imai, M. Hayashi, T. Tamaki, and H. Tanaka,
1-2. Gartshore, G. C., Kempster, B., and Tallentire, A. G., “Glass Fiber Reinforced Concrete using Super Low
“A New High Durability Cement for GRC Products,” Contractile Admixture,” Proceedings ACT 549 Com
Proceedings 8th Biennial Congress of the GRCA, 21- mittee Symposium on “High Performance Fiber Rein
24 October, 1991, Maastricht, Netherlands, p. 3-11, forced Thin Products”, ACT Convention, Chicago, IL
The Glassfibre Reinforced Cement Association, March 14-19, 1999
Northway, Wigan, United Kingdom. I-11.US Patent # 3,856,540, December 24, 1974.
79
Appendix J — Premix GFRC
J1.1- Scope
1
This Appendix is intended to provide information con CHAPTER J4 PHYSICAL PROPERTIES
-
cerning premix glass fiber reinforced concrete and indicate The physical properties of premix composites depend
where it differs from spray-up GFRC which is the primary heavily on the fiber content, fiber length and quality of
material discussed in the Recommended Practice. This Ap mixture. They are also greatly influenced by the type of
pendix covers only those sections presented within the manufacturing process.
body of the Recommended Practice that require revision to
address the difference between premix glass fiber rein J4.1 Factors Affecting Properties
-
forced concrete and spray-up GFRC. For sections not cov As with spray-up GFRC, strength properties, such as flex
ered, it is intended that the main body of the Recom ural, tensile and impact strengths increase with increased
mended Practice be referred to unless indicated otherwise fiber content and length. Fiber contents below 3 percent
in this Appendix. even at longer lengths of 1 in. and 1-1/2 in. (25 mm and 37
mm) can show a dramatic fall off in early strength.
Ji .2- General Description In theory the longer fiber length should produce a stronger
Premix glass fiber reinforced concrete is the term applied product. In practice there is often little difference, and the
to a cement/sand slurry and chopped strands of alkali-re 1/2 in. (12mm) strand length is preferable because it is eas
sistant glass fiber mixed together before transport to the ier to incorporate and the premix has better workability.
mold. The slurry is cast usually with vibration into a mold, As a general rule, premix with the same fiber content and
similar to precast concrete products, or may be sprayed. fiber length wifi have lower strengths than spray-up GFRC.
Typically, premix products contain less than 4 percent AR Reasons for this are:
glass fiber by weight of the total mix. a. Premixing may entrap more air, thereby reducing
Ji .5- Applications and Advantages the density of the composite. Strengths of premix-
Premix is used in products where strength is not the prime are density sensitive.
requirement. Premix is not recommended for the type of b. The mixing action may cause filamentizing and
thin wall architectural panels covered by the main body of reduce tensile strength of strand.
the Recommended Practice. It is used for smaller, highly c. The spray-up process lays the fibers down with
sculptured architectural units and mass produced standard almost perfect random planar orientation or two
products. dimensional orientation, whereas premix will have
Premix provides an efficient means of producing items a more three dimensional orientation. This
with good dimensional control, particularly thickness, and reduces the effective fiber content in the plane of
complex detail. Premix manufacturing processes usually the composite, thereby reducing the inherent
have low material losses and provide accurate and repro strength of those planar related strengths such as
ducible control of product weight. flexural and tensile strength.
J4.17 Property Summary
-
CHAPTER J3 MATERIALS-
Different manufacturers achieve different ranges of values
Materials for use in the manufacture of premix products of physical properties of premix. Specific values of prop
should conform to the requirements set forth in Chapter 3 erties should be supplied by the manufacturer to the de
of the Recommended Practice with the exception of the signers. For general information, Table 1.1 gives typical
following section. ranges of 28 day property levels using cement) sand ratios
J3.2 Glass Fibers
-
of between 3:2 to 1:1.
The range of pre-chopped fiber lengths is between 1/4 in.
to 1-1/2 in. (37mm), although special processes may use CHAPTER J7 MANUFACTURE
-
longer lengths. Fibers normally used for spray-up produc J7.2 Plant Facilities
-
tion are not normally suitable, being too soft and prone to These are the same as discussed in the Recommended
tangling. Practice except for the following:
In general 1 in. to 1-1/2 in. (25mm to 37mm) chopped 1. Equipment for mixing the cement/sand slurry at high
strands are suitable for simple flat or thick section products speed and the ability to blend the chopped strands on a
and 1/4 in.(6mm) to 1/2 in. (12mm) strands are more suit slower speed setting to avoid fiber damage. Alterna
Section numbers in Appendix I parallel those in the Rec
1 tively, proprietary mixers designed specifically for pre
ommended Practice. mix can be used.
80
Table J. 1. Typical Range of Premix Properties
These are typical values and are not to be used for design or control purposes. Each
manufacturer must test production composites to establish physical properties for de
sign. The values achieved in practice will be dependent on mix design, quality con
trol of materials, fabrication process and curing.
2. Means of vibrating the cast item at frequencies from contents than conventional mixers .A typical premix formu
3000 to 9000 vpm with a high amplitude or correct lation is:
equipment to spray the fibrous premix into a mold. Cement 100 lbs.
Sand 75 lbs.
J7.3 Molds
-
Water 29 lbs. (approx.)
Molds for premix manufacture are essentially the same as
Superplasticizer l6ozs.
for spray-up GFRC manufacture. The principal difference
Polymer curing admixture 10.6 to 12.6 lbs.
being that premix allows the use not only of open molds
Chopped 1/2 in. AR glass fiber 6.5 to 9 lbs.
but also back formed (inner core) molds, similar to precast
concrete molds, which cannot be used in spray-up.
Good premix properties require a water/cement ratio in
J7.4 Proportioning and Mixing
- the range 0.3-0.35. Workability adjustments should be
Each product has its own particular requirements and made with the use of water reducers or superplasticizers.
records should be kept enabling correlation between prop The mixing process should create a thoroughly mixed
erties of cured product to the specified requirements. slurry, while at the same time causing minimal strand
The majority of premix architectural products are based breakdown, fiber damage, or entangling of the strands
on 3 to 3-1/2 percent by weight of AR glass fiber on the to (fiber balling). This requires that the mixing process must
tal weight of the mix and 1/2 in. (12 mm) to 1 in. (25 mm) be capable of incorporating the fibers speedily and uni
fiber length. These parameters can be varied to produce formly.
many different combinations of materials giving different The mixing processes use either the special mixer de
end properties. The fiber content of premix is usually lim scribed above or a two stage process in which the slurry is
ited by the mixer and/or workability considerations. The prepared in a high shear mixer followed by a slow blending
fiber length may also affect the fiber content limit. phase in which the fibers are incorporated.
Increasing fiber content over four percent reduces the The fiber should be added last over a period not exceeding
workability of the mix and most conventional mixers can 2 minutes and the mixer should only be allowed to run for
not incorporate fiber contents much higher than four per a sufficient time to fully incorporate the fiber, normally
cent. Longer fibers will have a tendency to reduce the only a few seconds.
workability of the mix and make mixing difficult.
Higher fiber contents than four percent can be achieved J7.7- Placing
with special mixers. One such mixer has a flexible base, Placing or casting of the premix must be done in such a
which is undulated by the action of an eccentric shaft pro way that the glass fiber strands are not orientated in any
jecting into the center of the mixing vessel. This undulating particular direction, particularly with strand lengths over 1
action causes the material to be turned over on itself in. (25mm).
thereby mixing the fibers into the slurry. This mixing ac When casting, the molds should be filled in a way that
tion enables the mixer to be capable of mixing higher fiber avoids two or more material charges. Flow lines can be cre
81
ated where flows meet and the fibers may not bridge the control procedures recommended for spray-up GFRC are
flow lines. This will create a weak point in the product, applicable to premix. Premix properties are highly depend
which may result in a crack. ent on density and glass content and these should be
The mold must be filled in a manner that avoids pockets checked.
of air being trapped between the premix and the mold sur
face. Whenever possible, the mold should be filled from General References
one point only. J-l. Hills, D. L., “Premix glass fiber reinforced cement,”
If the premix is pumped from the mixer to the mold using Precast Concrete, May 1975, p.251.
a peristaltic action pump the mix must be designed to avoid J-2. True, C., “GRC Production and Uses,” Palladian
separation of the mix components. A thixotropic or pump Publications, London, 1986, 104 pp.
ing aid can help avoid separation. J-3. Smith, I. W., “A Review of GRC Production
Because it is not usually possible to build up cast premix Processes,” Glass Fibre Reinforced Cement Associa
in layers, as is done in spray-up, (the total thickness being tion, Northway, Wigan, United Kingdom, 1986, 16 pp.
placed in one casting), rolling out is usually not ‘effective J-4. Majumdar, A. J., and Laws, V., “Glass Fibre Rein
with premix. However, the mixing process inevitably in forced Cement,” BSP Professional Books, Blackwell
corporates some air into the mix and as the composite Scientific Publications, Inc., Oxford, United King
properties are density dependent, premix castings should dom, 1991, 197 pp.
involve vibration of the mix at some point, in order to ex J-5. “A Guide to Vibration Cast Premix GRC,” Cem-FIL
pel as much as possible of this entrapped air. The vibration International Limited, Merseyside, England, 1984.
can be applied either during the transfer of the premix to J-6. Ferry, R., Lowe, D., and Pickavance, A., “Premix
the mold and or when the material is filling the mold. Ex Methods of GRC Manufacture,” Proceedings 4th Bi
cessive vibration must be avoided as it can cause separa ennial Congress of GRCA, 5-4 October 1983, Strat
tion of the mix components. ford-Upon-Avon, England, p.66-76, The Glassfibre
J7.11 Stripping
-
Reinforced Cement Association, Northway, Wigan,
In the case of a mold with a back form, it is useful to re United Kingdom.
move the core as soon as possible after casting. This pre J-7. White, I. C., “The Economic Argument for the Use of
vents the premix from shrinking onto the core and making Appropriate Machinery in GRC Production,” Pro
demolding difficult. ceedings 6th Biennial Congress of the GRCA, 20-23
If a product is overstressed on demolding it may crack at a October, 1987, Edinburgh, Scotland. p 133-138, The
later date. Glassfibre Reinforced Cement Association, Northway,
Wigan, United Kingdom.
82
Appendix K — Specification for AR Glass Fiber
This document specifies requirements for glass fibers 1.2 The container shall be clearly labeled alkali resistant
made from alkali resistant glass compositions and in glass and indicate manufacturer, product code, filament
tended for use as reinforcement in portland cement con diameter and roving tex. The end count for roving prod
crete. Tests shall be carried out by the fiber supplier who ucts shall also be given.
shall certify compliance. 1.3 The roving shall be free from oil, grease, and other
visible contaminants.
1. Condition and Properties
1.4 The nominal filament diameter shall be as agreed be
1.1 The product shall be packed in containers in such a tween purchaser and manufacturer, or as specified.
manner as to give adequate protection in transport and
storage. A roving package shall be free from obvious 1.5 The properties of roving shall comply with the re
damage and should not be deformed. quirements given in Table K.1 below.
References
K-i Textile glass Determination of combustible-matter content, ISO 1887, International Organization for Standardization,
-
Geneva, Switzerland
K-2 Textile glass Staple fibres orfilaments Determination of average Diameter, ISO 1888, International Organization for
- -
Geneva, Switzerland
K-4 Reinforcement Products Determination of moisture content, ISO 3344, International Organization for Standardization,
-
Geneva, Switzerland
K-5 Testing Methods of Textile Glass Products, JIS R 3420, Japanese Industrial Standard, Japanese Standards Association,
Akasaka, Minato-ku, Japan
83
APPENDIX L — Specification for Polymer Curing Admixture
1. Property Requirements 2. Performance Requirements
1.1 Type compound To ensure GFRC product quality, curing compounds shall
aqueous thermoplastic copolymer dispersion be tested by an independent laboratory to demonstrate
that...
12 Type polymer
acrylic based .the recommended quantity of polymer curing admixture
in GFRC mix with no moist curing equals flexural proper
ties of GFRC cured 7 days moist when both are tested at 28
1.3 % Solids days.
45 to 55% by weight
...the long term durability of the dry cured polymer admix
1.4 Free monomer content ture modified composite, verified by aging tests, is equal to
maximum 0.2% by weight in dispersion or greater than the durability of GFRC cured 7 days moist.
1.13 Viscosity
100-300 cps
[Brookfield, spindle 2, 100 RPM, 70°F (21°C)
84
GUIDE SPECIFICATION FOR
GLASS FIBER REINFORCED
CONCRETE PANELS
85
Guide Specification
This Guide Specification is intended to be used as a basis for the development of an office master specification or in the
preparation of specifications for a particular project. In either case this Guide Specification must be edited to fit the condi
tions of use. Particular attention should be given to the deletion of inapplicable provisions or inclusion of appropriate re
quirements.
MASTERSPEC® Section 03491 Glass Fiber Reinforced Concrete (© 2001 The American Institute of Architects) is a prod
-
uct of the American Institute of Architects (AlA) and is used by permission of ARCOM, publishers of MASTERSPEC®.
SECTION 03491
GLASS FIBER REINFORCED CONCRETE
This Section uses the term “Architect. Change this term to match that used to identify the design professional as defined
in the General and Supplementary Conditions.
Verify that Section titles referenced in this Section are correct for this Project’s Specifications; Section titles may have
changed.
PART 1 - GENERAL
1.2 SUMMARY
A. This Section includes glass fiber reinforced concrete (GFRC) panels, consisting of GFRC, panel frames, anchors,
and connection hardware.
Retain subparagraph below if listing GFRC panel applications.
1. GFRC panels include [wall units] [window wall units] [mullions] [column covers] [fascia units] [cornices]
[soffits] <Insert applications>.
B. Related Sections include the following:
List below only products and construction that the reader might expect to find in this Section but are specified elsewhere.
1. Division 3 Section “Cast-in-Place Concrete” for placing connection anchors in concrete.
2. Division 3 Section “Plant-Precast Architectural Concrete.”
3. Division 5 Section “Structural Steel” for connection attachment to structural-steel framing.
4. Division 7 Section “Joint Sealants” for elastomeric joint sealants and sealant backings.
5. Division 8 Section “Aluminum Windows” for windows set into GFRC panels.
1.3 DEFIMTIONS
Retain paragraph below if a design reference sample has been preapproved.
A. Design Reference Sample: Sample of approved GFRC color, finish and texture, preapproved by Architect.
86
4. Wind Loads: <Insert loads or wind-loading criteria, positive and negative for various parts of the building.>
5. Earthquake Loads: <Insert applicable earthquake design data including seismic coefficient and importance
factor.>
Revise deflection limit in subparagraph below to suit Project.
6. Deflection: Design panel frames to withstand design loads without lateral deflections greater than 1/240 of wall
span.
Differential values in first subparagraph below are suitable for most of the U.S. Revise to suit local conditions.
7. Thennal Movements: Provide for thermal movements resulting from annual ambient temperature changes of
100 degF (56 degC) <Insert temperature>.
8. Design panel frames and connections to accommodate deflections and other building movements.
Retain below if window loads will be transmitted to structure through panel frames. Insert other performance and design
criteria here to suit Project or add to Drawings.
9. Design panel frames to transfer window loads to building structure.
1.5 SUBM1TTALS
A. Product Data: For each type of product indicated. Include GFRC design mixes.
B. Shop Drawings: Show fabrication and installation details for GFRC panels, including the following:
1. Structural analysis data signed and sealed by the qualified professional engineer responsible for their
preparation.
2. Panel elevations, sections, and dimensions.
3. Thickness of facing mix, GFRC backing, and bonding pads for typical panels.
4. Finishes.
5. Joint and connection details.
6. Erection details.
7. Panel frame details for typical panels, including sizes, spacings, thicknesses, and yield strengths of various members.
8. Locations and details of connection hardware attached to structure.
9. Sizes, locations, and details of flex, gravity, and seismic anchors for typical panels.
10. Other items sprayed into panels.
11. Erection sequence for special conditions.
12. Relationship to adjacent materials.
13. Descriptions of loose, cast-in, and field hardware.
C. Samples: Representative of finished exposed face of GFRC showing the full range of colors and textures expected,
16 by 16 inches (400 by 400 mm) and of actual thickness.
Retain paragraph below if procedures for welder certification are retained in “Quality Assurance” Article.
D. Welding certificates.
Retain paragraph below if steel sheet certification is retained in “Quality Assurance” Article.
E. Steel Sheet Certification. For steel sheet used in cold-formed steel panel framing.
Retain paragraph below if mill certificates are retained in “Quality Assurance” Article.
F. Mill Certificates: For structural-steel shapes and hollow structural sections used in panel framing.
Coordinate first paragraph below with qualification requirements in Division 1 Section “Quality Requirements” and as
supplemented in “Quality Assurance” Article.
G. Qualification Data: For GFRC manufacturer, including proof of current PCI Plant Certification.
H. Source Quality-Control Program: For GFRC manufacturer.
I. Source Quality-Control Test Reports: For GFRC, inserts, and anchors.
Insert specific model code organization below or revise if report must be from another source. PCI’s ICBO Evaluation Re- -
87
Retain option in first subparagraph below if requiring manufacturer to install GFRC.
1. Manufacturer’s responsibility includes fabricating [and installing] GFRC panels and providing professional
engineering services needed to assume engineering responsibility for GFRC panels.
2. Engineering responsibility includes preparation of Shop Drawings and comprehensive engineering analysis,
based on GFRC production test values, by a qualified professional engineer experienced in GFRC design.
Retain paragraph below if requiring mill certificates or test reports for cold-formed steel framing used in panel frames.
B. Steel Sheet Certifications: Obtain mill certificates, signed by manufacturers of steel sheet or test reports from a
qualified testing agency indicating that steel sheet used in cold-formed metal panel framing complies with require
ments, including uncoated steel thickness, yield strength, tensile strength, total elongation, chemical requirements,
and galvanized-coating thickness.
Retain first paragraph below if requiring mill certificates for structural-steel shapes and hollow structural sections used in
panel frames.
C. Mill Certificates: Obtain certified mill test report from manufacturer of structural-steel shapes and hollow structural
sections used in panel framing indicating compliance of these products with requirements.
D. Source Limitations: Obtain GFRC panels from a single manufacturer.
Retain “Welding certificates” Paragraph in “Submittals” Article with paragraph below.
E. Welding: Qualify procedures and personnel according to AWS Dl .1, “Structural Welding Code--Steel,” and AWS
Dl .3, “Structural Welding Code--Sheet Steel
F. PCI Manuals: Comply with requirements and recommendations in the following PCI manuals, unless more strin
gent requirements are indicated:
1. PCI MNL 128, “Recommended Practice for Glass Fiber Reinforced Concrete Panels.”
2. PCI MNL 130, “Manual for Quality Control for Plants and Production of Glass Fiber Reinforced Concrete
Products.”
Retain paragraph below if using cold-formed metal framing for panel frames.
G. AISI Specifications: Comply with AISI’s “Specification for the Design of Cold-Formed Steel Structural Members.”
Retain subparagraph below if using structural-steel shapes or hollow structural sections for panel frames. Retain one of
first two options if requiring ASD or LRFD calculations with submittals.
H. AISC Specifications: Comply with AISC’s [“Specification for Structural Steel Buildings--Allowable Stress
Design and Plastic Design”] [“Load and Resistance Factor Design Specification for Structural Steel Buildings ‘9
[and] [“Specification for the Design of Steel Hollow Structural Sections”].
Retain paragraph and subparagraphs below if required for GFRC. If retaining, indicate location, size, and other details of
mockups on Drawings or by inserts. Revise wording if only one mockup is required.
I. Mockups: Build mockups to demonstrate aesthetic effects and set quality standards for fabrication and installation.
1. Build mockup of typical wall area as shown on Drawings [as part of] [separately from] building.
2. In addition to GFRC panels, mockups include [architectural precast concrete] [unit masonry] [aluminum
windows] [joint sealants] [metal flashings] [and] [copings] <Insert construction>.
Retain subparagraph below if mockups are erected as part of building rather than separately and the intention is to make an
exception to the default requirement in Division 1 Section “Quality Requirements” for demolishing and removing mock
ups.
3. Approved mockups may become part of the completed Work if undamaged at time of Substantial Completion.
Delete below if Work of this Section is not extensive or complex enough to justify a preinstallation conference. If retain
ing, coordinate with Division 1.
J Preinstallation Conference Conduct conference at Project site to comply with requirements in Division 1 Section
‘Project Management and Coordination”
88
2. Store panels on firm, level, and smooth surfaces.
3. Place stored panels so identification marks are clearly visible.
PART 2-PRODUCTS
2.1 MANUFACTURERS
Delete this Article unless naming GFRC manufacturers. See PCI’s magazine “Ascent” or its Web site www.pci.org for cur
rent PCI-certified plant listings.
See Editing Instruction No. 1 in the Evaluations for cautions about naming manufacturers and products.
A. Available Manufacturers: Subject to compliance with requirements, manufacturers offering products that may be
incorporated into the Work include, but are not limited to, the following:
Retain above for nonproprietary or below for semiproprietary specification. Refer to Division 1 Section “Product Require
ments.”
B. Manufacturers: Subject to compliance with requirements, provide products by one of the following:
1. <Insert, in separate subparagraphs, manufacturer’s name>
91
- -
A. Construct molds that will result in finished GFRC complying with profiles, dimensions, and tolerances indicated,
without damaging GFRC during stripping. Construct molds to prevent water leakage and loss of cement paste.
1. Coat contact surfaces of molds with form-release agent.
Usually retain subparagraph above. Delete subparagraph below unless exposed-aggregate surfaces require surface retarder
to achieve desired finish.
2. Coat contact surfaces of molds with surface retarder.
Delete paragraph below if form liners are not used.
B. Place form liners accurately to provide finished surface texture indicated. Provide solid backing and supports to
maintain stability of liners during GFRC application. Coat form liner with form-release agent.
Delete below if flashing reglets are not used.
C. Locate, place and secure flashing reglets accurately.
92
2. Edge Return Thickness: Plus 1/2 inch (13 mm), minus 0 inch (0 mm).
3. Architectural Facing Thickness: Plus 1/8 inch (3 mm), minus 0 inch (0 mm).
4. Backing Thickness: Plus 1/4 inch (6 mm), minus 0 inch (0 nun).
5. Panel Depth from Face of Skin to Back of Panel Frame or Integral Rib: Plus 3/8 inch (10 mm), minus 1/4 inch
(6 mm).
6. Angular Variation of Plane of Side Mold: Plus or minus 1/32 inch per 3 inches (0.8 nmi per 75 mm) of depth or
plus or minus 1/16 inch (1.5 mm) total, whichever is greater.
7. Variation from Square or Designated Skew (Difference in Length of Two Diagonal Measurements): Plus or
minus 1/8 inch per 72 inches (3 mm per 1800 mm) or plus or minus 1/4 inch (6 mm) total, whichever is greater.
8. Local Smoothness: 1/4 inch per 10 feet (6 mm per 3 m).
9. Bowing: Not to exceed L/240 unless unit meets erection tolerances using connection adjustments.
10. Length and Width of Block Outs and Openings within One Unit: Plus or minus 1/4 inch (6 mm).
11. Location of Window Opening within Panel: Plus or minus 1/4 inch (6 mm).
12. Maximum Permissible Warpage of One Corner out of the Plane of the Other Three: 1/16 inch per 12 inches (1.5
mm per 300 mm) of distance from nearest adjacent corner.
C. Position Tolerances: Measured from datum line locations, as indicated on Shop Drawings.
1. Panel Frame and Track: Plus or minus 1/4 inch (6 mm).
2. Flashing Reglets at Edge of Panel: Plus or minus 1/4 inch (6 mm).
3. Inserts: Plus or minus 1/2 inch (13 mm).
4. Special Handling Devices: Plus or minus 3 inches (75 mm).
5. Location of Bearing Devices: Plus or minus 1/4 inch (6 mm).
6. Blockouts: Plus or minus 3/8 inch (10 mm).
D. Panel Frame Tolerances: As follows:
1. Vertical and Horizontal Alignment: 1/4 inch per 10 feet (6 mm per 3 m).
2. Spacing of Framing Member: Plus or minus 3/8 inch (10mm).
3. Squareness of Frame: Difference in length of diagonals of 3/8 inch (10 mm).
4. Overall Size of Frame: Plus or minus 3/8 inch (10 mm).
2.11 FiNISHES
This Article presumes Architect has preapproved one or more design reference samples. Include complete description of
design reference sample here. If preapproving manufacturers, coordinate with “Manufacturers” Article. Revise paragraph
below to add requirements if GFRC finish is to match another product such as architectural precast concrete.
A. Finish exposed-face surfaces of GFRC as follows to match approved [design reference sample] [and] [mockups].
Panel faces shall be free of joint marks, grain, or other obvious defects.
Delete subparagraph below if Architect’s design reference sample is not used. Revise if multiple samples are approved.
1. Design Reference Sample: <Insert description and identify manufacturer and code number of sample.>
Retain type of finish from subparagraphs below. If more than one frnish is required, add locations to fmish descriptions or
indicate on Drawings. Add more detailed descriptions of finishes outlined below when greater definition is required.
2. Smooth-Surface Finish: Provide free of sand streaks, honeycombs, and excessive air voids, with uniform color
and texture.
3. Textured-Surface Finish: Impart by form liners to provide surfaces free of sand streaks, honeycombs, and
excessive air voids, with uniform color and texture.
4. Retarded Finish: Use chemical-retarding agents applied to concrete forms and washing and brushing proce
dures to expose aggregate and surrounding matrix surfaces after form removal.
5. Sand- or Abrasive-Blast Finish: Use abrasive grit, equipment, application techniques, and cleaning procedures
to expose aggregate and surrounding matrix surfaces.
6. Acid-Etched Finish: Use acid and hot-water solution equipment, application techniques, and cleaning
procedures to expose aggregate and surrounding matrix surfaces.
PART 3- EXECUTION
3.1 EXAMINATION
A. Examine structure and conditions for compliance with requirements for installation tolerances, true and level
bearing surfaces, and other conditions affecting performance.
1. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 ERECTION
A. Install clips, hangers, and other accessories required for connecting GFRC panels to supporting members and
backup materials.
B. Lift GFRC panels and install without damage.
C. Install GFRC panels level, plumb, square, and in alignment. Provide temporary supports and bracing as required to
maintain position, stability, and alignment of panels until permanent connections are completed.
1. Maintain horizontal and vertical joint alignment and uniform joint width.
2. Remove projecting hoisting devices.
D. Connect GFRC panels in position by bolting or welding, or both, as indicated on Shop Drawings. Remove temporary
shims, wedges, and spacers as soon as possible after connecting is completed.
E. Welding: Comply with applicable AWS Dl .1 and AWS Dl .3 requirements for welding, appearance, quality of
welds, and methods used in correcting welding work.
1. Protect GFRC panels from damage by field welding or cutting operations, and provide noncombustible shields
as required.
F. At bolted connections, use lock washers or other acceptable means to prevent loosening of nuts.
94
3.4 REPAIRS
Production blemishes should have been corrected at manufacturer’s plant. Blemishes occurring after delivery are normally
repaired before final joint cleaning and sealing.
A. Repairs will be permitted provided structural adequacy of GFRC panel and appearance are not impaired, as
approved by Architect.
B. Mix patching materials and repair GFRC so cured patches blend with color, texture, and uniformity of adjacent
exposed surfaces.
C. Prepare and repair accessible damaged galvanized coatings with galvanizing repair paint according to ASTM A780.
Retain paragraph above if using galvanized framing, anchors, connections, and other items; retain first paragraph below if
items are prime painted.
D. Wire brush, clean, and paint accessible weld areas on prime-painted components with same type of shop primer.
E. Remove and replace damaged GFRC panels when repairs do not comply with requirements.
1 in. = 25.4 mm
1 ft = 0.3048 m
1 sq.ft= 2
O.0929m
1 cu.ft= 3
0.0283m
1 lb. = 4.448 N
1 psi = 0.006895 MPa
°F = (F-32) 5/9 °C
section modulus (in.
) =
3 16,387 mm
3
moment of inertia (in.
) =
4 416,231 mm
4
Coefficient of heat transfer
IhI°F) =
2
(BtuIft 5.678 W/(m
2 °C)
Thermal expansion (in./in.°F = 1.800 mm/(mm°C)
95