Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Managing projects
Outcome
The underpinning detail for this Chapter in your Notes can be found in
Chapter 14 of your Study Text
175
Managing projects
What is a project?
A project has resources, like staff and funding allocated specifically for the
length of the project.
The project will also have stakeholders, i.e. all those who are interested in the
progress and final outcome of the project.
Once completed, it should then become integrated into the normal day-to-day
activities of the business.
177
Chapter 14
Project constraints
Every project has constraints. Constraints are anything which restricts, limits,
prevents or regulates activities being carried out. When running a project it is critical
that the constraints are known, so they can be taken account of throughout the
project.
The primary constraints are time, cost and quality. These are often referred to as the
“project triangle”:
TIME
CONSTRAINTS
COST QUALITY
In additional to these three main constraints, there are a number of other constraints
which will affect the project’s delivery, such as legal, technological, political,
environmental and ethical.
178
Managing projects
Project lifecycle
TIME
An alternative five stage project life cycle based on the Project Management
Institute's 5 Project Management Process Areas identifies the stages as IPECC.
INITIATION PLANNING
CONTROLLING EXECUTING
CLOSING
179
Chapter 14
Initiation
Process/service enhancement.
Statutory/legal requirement.
4.2 Feasibility
Feasibility studies may be carried out on a number of potential strategies and the aim
of the study is to decide on which proposal to choose.
There are a number of types of feasibility which could be considered, including the
following:
180
Managing projects
PLANNING TARA
MONITORING
181
Managing projects
cost and time estimates – it is a good idea for the project team to have some
feel for the organisation’s expectations in terms of the project budget
stakeholders – a list of the major stakeholders in the project and their interest
in the project
183
Chapter 14
Planning
ake clear the commitment of time, resources (people and equipment), and
money required for the project
Time
Cost
Quality
Resources
Contingency
Communication
Deliverables
184
Managing projects
Execution
Once the project plan has been developed and agreed by the customer and project
team, the project can commence. This stage can be weeks, months or years long.
Change may arise from internal or external factors, and can often change
the outcome of the project. It is therefore important to have an agreed
change management process in place so that everyone involved in the
project is aware of how change will be managed.
Team members may be working to the old plans which do not incorporate the
changes.
185
Chapter 14
Change process
Recording of changes.
Communication of changes.
The change control process discussed above will be part of the configuration
management system.
186
Managing projects
Control
Throughout the execution stage of the project the project manager is responsible for
monitoring and controlling its progress towards successful completion. The most
important aspect of project control is ensuring that monitoring progress is carried out
on a regular basis.
Prevention of deviations.
Correction of deviations.
187
Chapter 14
functional quality
inspection
quality control
quality assurance
188
Managing projects
The two most important elements used in the control of projects are reports and
meetings.
Exception reports
This is when everything is in accordance with the plan. Only exceptions are reported.
Progress reports
Both formal and regular, these note what has happened in the report period and the
project status to date.
The main meetings which should be held throughout the project are as follows.
Team meetings
The project manager should hold regular meetings with the members of the project
team.
These are regular, formal meetings involving the project manager, team members,
and the customer or steering committee.
These would be held on an ad hoc basis as required to deal with specific problems.
The project manager will also have to arrange meetings with external resource
providers such as suppliers and sub-contractors.
189
Chapter 14
Closing
The final stage of the project life cycle is the closure of the project once the project
work is finished. A number of activities must be undertaken at this stage.
to ensure that the project is finally completed and conforms to the latest
definition of what was to be achieved and formally agreeing with the customer
that all agreed deliverables have been provided successfully
formal comparison between PID and project outcomes. Review of time, cost
and quality aspects of the project will be reviewed
190
Managing projects
This is carried out a few months after the project has been completed.
It may also highlight specific issues with the project and the review meeting may
organise a set of actions to deal with these issues.
It should also establish whether the project has helped the business to deliver the
benefits defined in the original business case.
The primary benefit derived from the post-completion audit is to augment the
organisations experience and knowledge. Other benefits of PCAs include more
realistic forecasting of a project's costs and revenues, enhanced understanding of
project failures, and improved future decision making and project management
performance.
191
-
Chapter 15
Project management tools and
techniques
Outcome
The underpinning detail for this Chapter in your Notes can be found in
Chapter 15 of your Study Text
193
Project management tools and techniques
Breakdown structures
195
Chapter 15
This major document details the standards that must be adhered to in order to
ensure a successful development process. It will provide a clear indication of
procedures and policies that must be followed to maintain quality within the work
carried out. It generally includes:
risk assessment – possible internal and external risks which could affect the
project
key development stages and processes – the activities that will need to be
completed during the life cycle
key standards to be used in the project (quality assurance) – this will help to
ensure quality outputs
testing strategy – this will identify the stages of development where testing is
to be carried out, by whom and of what
configuration management – how this will be dealt with should be set out so
that each version of the deliverables is identified.
196
Project management tools and techniques
A Critical Path Analysis (CPA) or network diagram can be drawn to show these inter-
relationships and dependencies.
NAME OF ACTIVITY
Activity lines:
DURATION OF ACTIVITY
The activity name and the duration of the activity are written on the arrow.
Nodes:
197
Chapter 15
The nodes also contain information on two times: The earliest event time (EET)
and the latest event time (LET).
EARLIEST EVENT
TIME (EET)
NODE
IDENTIFIER
LATEST EVENT
TIME (LET)
The activities on the critical path are identified with a double line.
Once the network has been drawn, calculate the EET and LET for each node.
To calculate the EET, work left to right. Take the EET from the previous node
and add this to the duration of the activity. Where you have a choice of EETs,
always select the highest.
To calculate the LET, work right to left. Take the LET from the previous node
and deduct the duration of the activity. Where you have a choice of LETs,
always select the lowest.
198
Project management tools and techniques
The EET and LET of the final node will always be the same and this will equal
the overall duration of the project.
We can also identify the critical path, i.e. the activities where any delay will
lead to a delay in the overall project. These are the activities for which EET =
LET.
Some activities could increase in duration and yet the project could still be
completed by the target date. Such activities are said to exhibit 'float'. Float can
generally be calculated as the difference between the LET and the EET.
3.5 Illustration
A 8 –
B 10 A
C 6 –
D 4 C
E 8 B,D
199
Chapter 15
Draw the basic shape and add the durations for each activity:
B
A
8 10
E
8
D
C
4
6
Note: the network can be drawn in different ways. The following diagram would also
correctly represent this project:
B E
10 8
A
8
C
D
6
4
200
Project management tools and techniques
Work left to right. Start at the first node: the EET of the first node must always be
zero. You then look at each activity in turn.
Take the EET from the node at the beginning of the activity line, and add it to the
duration of the activity, the answer gives you the EET for the node at the end of the
activity line.
B
A
8 10
E 26
18
0
8
D
C
4
6
6
201
Chapter 15
Work right to left. Start at the last node: the LET of the last node must equal the EET
of the last node, so here the LET of the last node is 26. You then look at each activity
in turn.
Take the LET from the node at the end of the activity line, and deduct the duration of
the activity. The answer gives you the LET for the node at the beginning of the
activity line.
When you have a choice for the LET, you always use the lowest.
This completes the network diagram – now you can put in the node reference
numbers and identify the critical path.
8
2
8 B
A
8 10
E 26
18 5
0 4 26
1 18 8
0
D
C
4
6
6 3
14
202
Project management tools and techniques
Limitations Benefits
Time consuming for large Helps identify all required activities
projects
Identifies dependent activities and
Overly complex for small, short- those which can run in parallel
term projects
Identifies the activities on the
Difficult to use for less routine critical path
projects
Identifies activities with float
203
Chapter 15
4.1 Dealing with risk and uncertainty when planning for time
While risk is considered at the initiation stage of the project risk (and uncertainty)
must be considered again at the detailed planning stage when the project manager is
planning the time aspect of the project. There are a number of techniques which can
assist with this:
Scenario planning
Buffering
This involves adding artificial slack into risky activities. It adds padding to the
original estimates and allows for the fact that it can be very difficult to ensure
that all stages and activities are carried out exactly as planned.
204
Project management tools and techniques
A Gantt chart is a horizontal bar chart where the length of the bar represents the
duration of the activity. It is usual to use two bars, one showing the planned duration
and the second showing the actual duration.
Activity/Weeks 1 2 3 4 5 6 7 8
Actual Plan
205
Chapter 15
Gantt charts are very useful tools in project management, but they can be of less use
in large, complex projects.
Gantt charts share the same benefits as network analysis. In addition they have
additional benefits.
Milestones are important in assessing the status of the project and quality of the
work. Monitoring the milestones enables the project manager to keep control over the
projects progress, and allows any delays to be identified immediately.
Some milestones are key points in the project life cycle which give the project
sponsor or steering committee an opportunity to review project progress, and make a
decision whether to proceed further or to terminate the project. These milestones are
called ‘control gates’ and represent the significant completion of milestones. A gate
can only be ‘passed’ if the progress meets pre-defined performance standards. This
could take the form of technical reviews or completion of documents.
206
Project management tools and techniques
Resource Histogram
This is a graphical aid for determining the total requirement for a specific resource
during the project. The histogram identifies, in block graph form, the fluctuating need
for finance, staff, technology resources or vendor services at any stage in the project.
This can assist in planning. Reallocation of key tasks can reduce the excessive
requirement at certain periods, providing a smooth flow of resources throughout the
project.
$/People
14
12
10
1 2 3 4 5 6 7 8
Weeks
207
Chapter 15
Project management software can assist considerably at all stages of the project.
PLANNING REPORTING
ESTIMATING MONITORING
Improved communication.
Accuracy.
What if analysis.
Can help to ensure that all necessary tasks are carried out as
required.
208
Project management tools and techniques
7.2 PRINCE2
209
Project management tools and techniques
Controlling a stage – monitoring and control activities are carried out by the
project manager at each stage of the project. This process incorporates the
day-to-day management of the project.
211
Chapter 15
212
Chapter 16
People and projects
Outcome
The underpinning detail for this chapter in your Notes can be found in
Chapter 16 of your Study Text
215
People and projects
Project owner
Project brief
Project
Funds
Project customer proposals
Terms of
Schedules
reference
Status reports
Project manager
Project team
217
Chapter 16
Project Sponsor
Appoints the project manager and provides resources for the project.
Project Owner
Project customer/user
Project Team
Will carry out the work on the project under the leadership of the project
manager.
218
People and projects
Project manager
219
People and projects
The basic project team consists of the project manager (and possible team leaders),
and a group of specialists assigned or recruited for the project.
The ideal project team will achieve project completion on time, within budget and to
the required specifications. They will do all this with the minimum amount of direct
supervision from the project manager.
221
Chapter 16
Project structure
Project
Manager A
Project
Manager B
Project
Manager C
222
People and projects
The projects have different start and end dates, so the organisation is
continually reassigning resources from project to project.
The projects are complex, so staff benefit from also being assigned to a
technical function (such as finance of logistics) where they can share
knowledge with colleagues.
223