L L
A B
A
B’
Concept in cranes
• In cranes, the force A is the load to be lifted.
(counterweight also contains fixed pulley block on which the cable is wrapped)
• The pulley system delivers a force to the load that is equal to the applied force multiplied by
the length of cable (boom) between the load lifted and counterweight.
• So we can say that, load lifting capacity of any crane depends on the length of the boom.
Specifications Extension boom
Cable
Counterweight
hydraulic
Cabin
Outrigger
Dimensions
Machinery
Operation cycle timing
• Boom Raising : 27 sec.
• Boom Lowering : 20 sec.
• Telescopic In : 8 sec.
• Telescopic Out : 14 sec.
• Hoist Line Speed : 52 m/min.
• Steering : 7 sec.
Economy
Before using or buying an equipment owner should answer two question??
2- what is the optimum economic life and the optimum manner to secure a machine ?
Rental Duration Rates Hours Rental Rate $/hr Operating hours Break Operating hour break
even 2166.32 point even point
6500/hr
14
Ownership cost
• Purchase expense
• salvage value
• tax saving from depreciation
• Major repairs and overhauls
• property taxes
• insurance
• Storage and miscellaneous
Operating cost
• Fuel
• Lubricant, filters and grease
• Repairs
• Tires
• Replacement of high-wear items
Thank you