PHILIPPINE PRODUCTIVITY RATIOS

DESCRIPTION MANHOUR/UNIT UNIT

1.STRUCTURAL EXCAVATION

Common excavation

Hand 6 MH/M3

Machine 0.5 MH/M3

Rock excavation 8 MH/M3

Hauling of spoils 1 MH/M3

2.STRUCTURAL BACKFILL

By hand 5 MH/M3

By machine 2 MH/M3

3.TRENCHING

By hand 6 MH/M3

By machine 0.5 MH/M3

EXCAVATION- MANUAL

Common earth 8 MH/M3

Loam of sand 1.31 MH/M3

Clay or heavy soil 1.64 MH/M3

Rock 2.63 MH/M3

EXCAVATION- MECHANICAL

Common earth 6.67 MH/M3

Rock with jack hammer 16.67 MH/M3


BACKFILLING

Common manual 0.82 MH/M3

Gravel fill manual 5 MH/M3


TRENCHING & BACFILLING OF UNDERGROUND PIPING
USING EXCAVATION MATLS MANUAL FROM:
0 – 2m Depth 1.25 MH/LM

2 – 3m Depth 1.67 MH/LM

3 – 4m Depth 2.5 MH/LM

4 – 5m Depth 3.33 MH/LM

Placing binder gravel 0.11 MH/M3

Escombro backfilling 0.21 MH/M3

Spreading,tamping & grading 0.48 MH/M2


Mechanical compaction, plate
0.06 MH/M3
compaction
MANUAL CLEARING & GRUBBING

Clearing under growth & trees – 12″ 0.05 MH/M2

Clearing under growth & shrubs 0.03 MH/M2

Disposal of soil 1.69 MH/M3

Hauling of soil 1 MH/M3

Gravel fill 2.07 MH/M3

EXCAVATION – CRANE & CLAMPSHELL

With 8 men & 2 carpenters 1.07 MH/M3

5.ROOFING AND SIDING

Roofing
Metallic 0.97 MH/m2

Non-Metallic 1.51 MH/m2

Siding

Metallic 1.29 MH/m2

Non-Metallic 1.51 MH/m2

CONCRETE WORKS

4.CONCRETE WORKS

Grade members

Formworks 2.54 MH/M2

Concreting 8.54 MH/M3

Rebar 0.07 MH/kg

Finishing 0.4 MH/M2

Suspended members

Formworks 3.28 MH/M2

Concreting 16.7 MH/M3

Rebar 0.08 MH/kg

Finishing 0.8 MH/M2

Embeded metal 0.27 MH/kg

Water proofing 1.82 MH/M2

Joint filler 0.3 MH/lLm

PLACING CONCRETE

Slab on Fill 5 MH/M3


Slip Form 25 MH/M3

Floor Finish Unhardened 1 MH/M3

Concrete finished hardened 1.43 MH/M3

REBAR WORKS

Ground floor installation 0.07 MH/M3

Upper floor installation 0.08 MH/M3

Fabrication 0.1 MH/M3

Mixing manual 16 MH/M3

Mixing machine 1.8 MH/M3

MORE THAN 1.8 M3 POUR

Chute from truck 7 MH/M3

Crane & bucket 14 MH/M3

Wheeling 27 MH/M3

Finishing 2.8 MH/M3

FORMWORKS & CARPENTRY WORKS

FORM WORKS INSTALLATION

Wall on ground 2 MH/M2

Wall above ground 2.35 MH/M2

Beams 3.08 MH/M2

Columns 2.35 MH/M2

Suspended slab

Suspended slab 0 – 18″ 1.67 MH/M2


Suspended slab 10 – 36″ up 3.33 MH/M2

Elevated & shored slab forming

Forming only 8.6 MH/M2

Forming & Shoring 11 MH/M2

Wood wall & Partition 0.5 MH/M2

FORM WORKS FABRICATION

Form works fabrication 1 MH/M2

STRIPPING OF FORMS

Wall on ground 0.25 MH/M2

Wall above 10″ 1.29 MH/M2

Beams 1.03 MH/M2

Columns 0.85 MH/M2

Suspended slab

Suspended slab 0 – 18″ 0.83 MH/M2

Suspended slab 10 – 36″ up 1.08 MH/M2


Elevated & shored slab forming –
3.5 MH/M2
strip of forms
Floor slab at grade – strip of forms 2.8 MH/M2

INSTALLATION OF CARPENTRY WORKS

Plywood partition 1 MH/PC

T & G Flooring and Siding 0.14 MH/B.F.

Ceiling & frame work 0.36 MH/B.F.

Siding frame work 0.27 MH/B.F.


Flooring framing 0.97 MH/B.F.

Wooden post errection 0.43 MH/B.F.

Truss Fabrication 0.35 MH/B.F.

Truss Installation 0.8 MH/B.F.

Girt Installation 0.21 MH/B.F.

Plates Installation 0.13 MH/B.F.

Purlins Installation 0.27 MH/B.F.

Fascia board Installation 0.46 MH/B.F.

1/4″ or 3/4″ thk. plywood

Cutting by manual 1 MH/PC

Assembly 0.42 MH/M2

ARCHITECTURAL SPECIALTIES

DOORS

Wooden 2.37 MH/M2

Steel 7.64 MH/M2

Aluminum 8.07 MH/M2

Cyclone wire 7.64 MH/M2

WINDOWS

Glass 3.23 MH/M2

Louver 4.63 MH/M2

Steel 32.29 MH/M2

PARTITIONS
single wall 2.48 MH/M2

Wooden wall 3.44 MH/M2

Wooden Louver 3.44 MH/M2

cyclone Louver 5.38 MH/M2

PAINTING ( 3 coats )

Equipment 0.24 MH/f2

Pipes 0.3 MH/f2

Miscillaneous 0.24 MH/f2

STRUCTURAL STEEL WORKS

7. STRUCTURAL STEEL

Fabrication

Light 110-130 MH/MT

Heavy 60-90 MH/MT

Errection

Light 70-100 MH/MT

Heavy 40-60 MH/MT

WELDING ( one pass only )


1- Welder and 1- Helper ( 16 total
40-50 Lf/day
mh )
G.1 STRUCTURAL STEEL

Fabrication

Heavy weight 50-90 MH/MT

Light weight 100-125 MH/MT


Grating 1 1/4″ x 3/16″ 3.0 – 3.5 MH/SF

Star threat grating 4.0 – 5.0 MH/SF

Errection

Heavy Structural teel 30 – 60 MH/MT

Light Structural steel 60- 90 MH/MT

Stacks ( Inc. full welding ) 250 – 300 MH/MT

Tanks ( Inc. full welding ) 200 – 275 MH/MT

FINISHING AND MASONRY WORKS

H. CHB

4” CHB

Laying 8.0 – 10 m2/day

Tooling 11 – 14 m2/day

Plastering 8.0 – 10 m2/day

6” CHB

Laying 7.0 – 9.0 m2/day

Tooling 11 – 14 m2/day

Plastering 8.0 – 10 m2/day

8” CHB

Laying 6.0 – 8.0 m2/day

Tooling 11 – 14 m2/day

Plastering 8.0 – 10 m2/day