Project objectives
To supply and install a total of 352 solar photovoltaic systems during the financial year
2019-2020 and 2020-2021 at 51 Primary Health Facilities located at Beau Bassin, Central
Flacq, Curepipe, Flic en Flac, Floreal, Grand Baie, Long Mountain, Mahebourg, Moka,
Pamplemousses, Pointe aux Cannoniers, Port Louis, Poudre D’Or, Quatre Bornes, Reduit,
Rose Belle, Rose Hill and Souillac in Mauritius. The project is set to be completed within
33 days at a cost not to exceed Rs 50 000 000.
Project deliverables
The project milestones comprise of only the major segments of the work with rough cut
estimates of time.
Milestone List
Milestone Milestone Mandatory/ Duration Stakeholder
.number Optional (Days) responsible
1 Site survey Mandatory 2 Structural
engineer
2 Notice to proceed Mandatory 10 Legal Advisor
3 Design phase Mandatory 2 Mechanical and
electrical
engineers
4 Labour procurement Mandatory 2 Project manager
5 Equipment Mandatory 2 Project manager
procurement
6 Equipment Mandatory 2 Project manager
delivery/Transportatio
n
7 Building solar Mandatory 1 Mechanical and
photovoltaic frames structural
engineers.
8 Solar PV system Mandatory 8 Electrical and
(including monitoring mechanical
system) installation engineers.
9 Testing of solar PV Mandatory 10 Electrical,
system mechanical
engineers and
technicians.
10 Commissioning of Mandatory 2 Project manager
solar PV systems.
Technical Requirement
Approval from Central Electricity Board to connect solar pv system to the grid.
Provide for at least metre squared of
The systems shall consist of
1. Solar PV 3000Wp
2. Battery 6KWh
3. Hybrid Inverter with MPPT Charge Controller: 3000-Watts or higher Rated
output power.
4. LED Bulb/Tube Light consuming less than 18-Watt power.
5. Fan consuming less than 75-Watt power.
6. A system
Proposed design
On roof design
On land design