Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
(Exercises)
Question – 1: You have reviewed the schedule of the project and realized it is
going to be slipped when finally delivered. There is no way to cut-down on the
schedule. You talked with you supervisor and he also agrees that it can't be
reduced. However, he told that this should not be informed with the
customer. What should you do?
Question – 4: You have been assigned to a project which you believe will not
succeed. You have made those feelings known to your organization, but they
wish that you work anyway. What should you do?
Question – 6: You are working on a project where you need one of the
components is needed from the Government. You realize in the typical case it
will take at least 2 months to get. However, the officials inform that there is a
concept of rush fee and if you pay, it can be done in 2 weeks. What should you
do?
A) Resolved quickly
B) Monitored carefully
C) Disclosed openly
D) Ignored
Question – 8: During a make or buy analysis, you found out that if it is built
internally it can save your organization a lot of money. There is a 3rd party
software available, which is of very good quality and of good reputation. You
are undecided on what to do. What should be the correct approach?
Question – 1: You are working as a project manager for a solar power vehicle
project. For some of your components you decided to contact a few
commercial auto-component developers, who are 3rd party developers to
develop the needed specialized components. You contacted prospective
sellers and informed that your organization will be providing the material for
development as well as the services plus a fixed fee for profit.
(D) Proprietary.
Question – 2: Your project is reaching the end stage of one of your phases. A
number of quality related testing has been done. You have documented these
quality control results in a format specified during quality planning. Now you
want to validate them and evaluate the quality processes which created these
measurements.
(A) You should go back to quality planning as process standards are defined there.
(B) You should go back to managing quality as quality control measurements process
is validated in this process.
(C) You should go back to managing quality as quality audit is performed there.
(D) You should use another quality control tool and stay in the current process to
check the process validity.
Question – 3: Initial scope of the project is present from the very beginning
with chartering of the project. However, detailed scope planning happens in
planning process group. One of processes in this process group documents
how the scope will be defined, broken down to manageable chunks, validated
and controlled. What can be the output(s) of this process?
(D) Project Scope Statement, Work Breakdown Structure, Work Breakdown Structure
Dictionary.
(A) 0.5
(B) 1.5
(C) 0.6
(D) 1.2
Question – 5: In one of the sub-phases for your project you found out the
activities, which are listed in the below table. The activities are important for
your deliverables and hence you are analysing them.
(A) The critical path in this activity is Start – A2 – A3 – A4 – End; Total float of A2 is
zero.
(B) Total float for A5, A3, and A4 is zero and they all are on the critical path.
(C) If you increase the duration of A5 to 5 days, then there will be more risks for the
project.
(A) 0
(B) 10
(C) 9
(D) 11
(A) Even through projects and programs aren’t interrelated, a set of projects can be
put under a program and collectively they can be linked to the strategic objectives.
(B) The portfolio created will link the projects to the strategic plan and hence
objectives.
(C) As the projects and program aren’t related or interdependent, organization project
management (OPM) is needed to link the project to the strategic objectives.
(D) The business goals of the organization will link the projects to the strategic
objectives as business goals finally translates to strategic objectives.
Question – 8: You project has a schedule of 6 months and 12 days. The end
date has been fixed. This will be considered as a:
(A) Constraint.
(B) Assumption.
(C) Risk.
(D) Functional.
Question – 11: You are in charge of building a shopping portal. You are fairly
confident as you have a team experienced in doing such work. As per the
agreement at the end of the first month you organize a demonstration of the
software. You invite the sponsor and key stakeholders. Later the sponsor
informs you that she is not very happy with the progress indicating that one
of the clients who would be using this software is not satisfied as her needs
are not being met. To satisfy this client's needs would mean some radical
changes, which will impact both cost and schedule. What could be the root
cause of this issue?
Question – 12: You are working as a project manager for a large, cross-
continental project. You are preparing the work breakdown structure (WBS)
with your team members. However, your senior management team believes a
lot of time is being spent creating the breakdown structure. But you know
good planning for scope is essential and the WBS is a very important element
of the scope baseline. Also, good planning can save a lot of churn later on in
the project. You, along with your team members, have broken down the
scope statement into deliverables, which has further been broken down. As
you explain the importance of the WBS and time consumed to create it to the
senior management team, all of the following are correct about the work
packages in a WBS, EXCEPT:
(A) The cost can be reliably estimated for the work packages.
(B) The effort can be reliably estimated for the work packages.
Question – 13: Mike has been assigned as the project manager on a large
project for a telecommunication company. He will be replacing another
manager who has quit in the middle of the work due to certain family
emergencies. Unfortunately, Mike couldn’t have knowledge transition from
the manager on leave. Certain deliverables in the project is being supplied by
contractors at Mike’s organisation. Mike would like to know what
performance metrics are going to be tracked for the contract workers.
Where could Mike find this information?
Question – 15: Two team members are fighting and it has been escalated to
you. As you intervened and tried to resolve the conflict, you realized that no
one is ready to concede. But you know this conflict if not addressed now will
crop up quite quickly. Hence, you want temporarily resolve the conflict,
which keep the situation calm for a few days. Which conflict resolution
technique should be applied?
(A) Direct.
(B) Withdraw.
(C) Reconcile.
(D) Accommodate.
(A) 1, 2, and 3.
(B) 2, 3, and 4.
(C) 1, 3, and 4.
(D) 1, 2, and 4.
Question – 18: You are working on a mission critical project for one of your
key customers. During on your status meeting, the customer informed about
a change request with respect to your project. The customer believes it is
highly important and should be delivered with highest priority. What should
be your FIRST step in this case?
(A) Discuss with the subject matter experts in your team and find out the impact of
this possible change.
(B) Start the change control process and direct your team to implement it.
(C) Talk to the sponsor and inform about this change request, as the sponsor is a key
stakeholder and should be immediately notified.
(D) Take it to the change control board (CCB) for immediate approval.
(B) Project X.
(C) Project Y.
(D) Project Z.
Question – 21: John is well respected and liked as a project manager by his
team members. The team members love to spend time with him and in fact
many times go out with him dinner. What kind of power John has over his
team members?
(A) Expert.
(B) Legitimate.
(C) Charm.
(D) Personal.
(A) Provide the basis for which the product configuration is defining.
Question – 23: Your team has decided to use Bluetooth technology for your
smartwatch project. With this technology, the smartwatch can connect to
smartphones, tablets and even hand-held devices. However, the team
members don’t have the domain expertise on it and hence you decide to form a
forum on this technology. Here team members can participate in the
discussion, raise questions, fix issues which are technologically unique and
also can share information on the latest standards and practices. What kind of
communication dimension is considered by you while creating this forum?
(B) Formal.
(C) Horizontal.
(D) Downward.
Question – 24: You have planned for the risks in your project by creating a
risk management plan, which has the information about the probability and
impact scales, the probability and impact matrix, the risk audit timings,
among others. Next, you identified all possible risks with the help of
stakeholders in your project. You have created the risk register, identified
and assigned the possible owners for the risks and further elaborated on the
risk breakdown structure. What should you do NEXT?
(A) Analyze the risks qualitatively to find the probability and impact of each risk.
(D) Analyze the risks quantitatively to quantity with respect to schedule and cost
impact for each risk.
Question – 25: Out of the following qualities, which one is MOST important
for a project manager?
Question – 26: You are working on a construction project. You, your team,
and your senior manager all feel that the work is complete. Your
stakeholders have communicated their final acceptance of the project. You
are now meeting with your team to update the organizational process assets
with a record of knowledge gained about the project to help future project
managers with their projects.
Question - 27: You have created all the subsidiary plans of the consolidated
project management plan. One of the subsidiary plan describes when and
how project team members as well as physical resources will be acquired,
and how the organization chart will be. It also has recognitions and rewards
will be given to the team members. It will have all of the following EXCEPT:
Question – 28: A project life cycle is the series of phases that a project passes
through from its initiation to its closure. The life cycle provides the basic
framework for managing the project, regardless of the specific work
involved. However, among the following which is not true for project life
cycle?
(A) The phases in the project life cycle are generally sequential.
(B) In the life of the project, the level of risk remains high in the beginning, but goes
down gradually.
(C) The stakeholder influence for an adaptive life cycle remains constant throughout.
(D) The cost of making changes typically decreases substantially as the project
approaches completion.
(B) Take the new feature request through change control steps
(C) Speak with the sponsor about the inclusion of the feature and decide
(D) Tell the customer politely that at this stage it can't be taken up