Bevan Mace
April 13, 2017
1. At the end of this presentation, participants will understand what owners value in
design and construction and will be able to analyze and discuss how designers and
constructors can close the gap between owner expectation and typical project delivery.
2. At the end of this presentation, participants will be able to identify Lean process
innovations and tools that are flexible and positively change project team collaboration.
3. At the end of this presentation, participants will understand how the adoption of Lean
impacts the architect's role in design and construction.
4. At the end of this presentation, participants will know when to strike down Lean and
IPD myths with empirical data when they hear myths in the field.
Industrial
15%
Institutions Government
46% 15%
Developer
12%
24%
6% 10%
-17%
-21%
56%
37%
Ahead of Schedule Behind Schedule
33%
22%
14% 14%
5% 6%
1% 4%
6%
3%
26% to 11% to 1% to 10% No 1% to 10% 11% to 26% to More Than
35% of 25% of of schedule Variance of schedule 25% of 35% of 35% of
schedule schedule schedule schedule schedule
Typical Best Performing
37%
Under Budget Over Budget
20% 20%
14%
6% 10% 7% 6% 6%
4%
3% 7% 3%
4% 4% 3%
3% 5%
More 11% to 7% to 3% to Less No Less 3% to 7% to 11% to More
than 20% 10% 6% than 3% Variance than 3% 6% 10% 20% than
20% 20%
Typical Best Performing
83% 84%
69%
56%
-17% -16%
-31%
-44%
Rated 1 or 2 Rated 1 or 2
for Quality for Safety
68%
61%
54%
40%
10% 9% 11%
5%
25% Typical
22% Best Performing
17% 16%
15%
11%
9% 9% 9%
7%
3% 3% 4%
Pre-business Business case During During schematic During design During construction End of construction
case validation conceptualization design development documents documents or later
(pre-design) (0-15% design) (15-30%) (30-60%) (60-90%) (100% CD)
22% 23%
20% 19%
14%
11%
1% 1%
Construction Design-bid- Integrated Design-Build Lump Sum Guaranteed Cost
Management build Project Maximum Reimbursable
at Risk Delivery Price (with or With Target
without and Shared
shared Risk/Reward
savings)
Part-time co-lo
more common
than full time
2X
3X
65%
IPD (Best)
0%
5%
CM at Risk (Best)
39%
5%
Design-Bid-Build (Best)
21%
2. IPD contracts are too complicated, Lean tools are too rigid
2. Build the team: Contract (using best value) key stakeholders prior
to/ during concept design to validate targets & unify the team