Proposed 5 Star Hotel at Tajganj ward on Khasra No.

32, Mauza Budhera , Tehsil and


District –Agra, Uttar Pradesh by M/s Bloom Inn Pvt. Ltd.

APPENDIX -I
(See Paragraph – 6)
FORM-1
(I) Basic Information
S. No. Item Details
Name of the project Proposed 5 Star Hotel at Tajganj ward on Khasra
1. No. 32, Mauza Budhera , Tehsil and District –Agra,
Uttar Pradesh by M/s Bloom Inn Pvt. Ltd.
2. S.No. in the Schedule 8 (a)
Proposed capacity/area/length/tonnage Total Plot Area: 19,251.10 m2
3. to be handled/command area/lease Net Plot Area: 15,776.65 m2
area/ number of wells to be drilled. Built up Area(FAR + Non FAR): 27,422.40 m2
4. New/Expansion/Modernization New Project
5. Existing Capacity/Area etc. Not Applicable
6. Category of Project i.e. ‘A’ or ‘B’ B

7. Does it Attract the general condition? No


If yes, please specify.
8. Does it attract the specific condition? No
If yes, please specify.
9. Location
Plot/Survey/Khasra No Khasra No. 32

Village Mauza Budhera


Tehsil
District Agra
State Uttar Pradesh
10. Nearest railway station/airport along Nearest railway station is Agra City Railway
with distance in kms. Station at an aerial distance of 8.82 km towards
North-West.
Nearest Airport is Agra Airport Aka Kheria Air
Force Station at an aerial distance of 12.87 km
towards West.

11. Nearest Town, City, District District Headquarters: Agra approx. 5 km towards
Headquarters along with distance in North-West.
kms. Nearest Town: Tundla approx.20 km towards East
12. Village Panchayats, Zilla Parishad, Agra Development Authority
Municipal Corporation, Local body Near Sales Tax Office, Ratan Muni Rd, Jaipur
(Complete postal addresses with House Colony, Agra, Uttar Pradesh 282010
telephone nos. to be given) Tel. Nos. 0562 281 1009
Website: www.ada-agra.com
13. Name of the applicant M/s Bloom Inn Private Limited
14. Registered Address 201, CSC, Pocket-52, CR Park, Near Police

Consultant-Ascenso Enviro Pvt. Ltd. Page 1 of 19


Proposed 5 Star Hotel at Tajganj ward on Khasra No. 32, Mauza Budhera , Tehsil and
District –Agra, Uttar Pradesh by M/s Bloom Inn Pvt. Ltd.

Station, New Delhi -South Delhi - 110019

15. Address for correspondence:


Name Rahul Verma
Designation(Owner/Partner/CEO) President

Address 201, CSC, Pocket-52, CR Park, Near Police station,


New Delhi
Pin Code 110019
E-Mail rahul@springindia.in
Telephone No. 9650793399
Fax No. -
Board Resolution regarding Authorized signatory is
attached as Annexure-XIX.
16. Details of Alternative Sites Examined, The proposed site for Hotel falls under the
if any, Location of these sites should Commercial landuse as per the Master Plan of Agra
be shown on a topo sheet. 2021. The copy of a letter from Town Planning
Department, Agra Development Authority by vides
letter no. 32/D/Planning/17-18 Dated 02.01.2018
regarding confirmation of land use is attached as
Annexure-III.

So, there is no requirement to examine the


alternative site.
17. Interlinked Projects Not Applicable

18. Whether separate application of Not Applicable


interlinked project has been
submitted?
19. If yes, date of submission Not Applicable
20. If no, reason Not Applicable

Consultant-Ascenso Enviro Pvt. Ltd. Page 2 of 19


Proposed 5 Star Hotel at Tajganj ward on Khasra No. 32, Mauza Budhera , Tehsil and
District –Agra, Uttar Pradesh by M/s Bloom Inn Pvt. Ltd.

21. Whether the proposal involves


approval/clearance under: If yes, detail
of the same and their status to be
given
(a) The Forests (Conservation) a.) No, since no land protected under The Forests
Act, 1980? (Conservation) Act, 1980 is involved in the
project.

b.) No wild life sanctuaries lie within 10 km from


(b) The Wild Life (Protection)
the project site. So, The Wild Life (Protection)
Act, 1972?
Act, 1972 is not applicable.

c.) The C.R.Z. Notification, 1990 is not applicable


(c) The C.R.Z. Notification, 1990? as no coastal zone is coming within 10 km of the
project site.

22. Whether there is any Government Not Applicable


order/policy relevant/relating to the
site?
23. Forests Land Involved (Hectares) No Forest Land is involved and only 1 tree is
present at project site.
24. Whether there is any litigation No litigation is pending against the project and/or
pending against the project and/or land land in which the project is proposed.
in which the project is proposed to be
setup? Not Applicable.
(a) Name of the Court
(b) Case NO.
(c) Orders/ directions of the Court,
if any and its relevance with the
proposed project.

(II) Activity
1. Construction, operation or decommissioning of the Project involving actions,
which will cause physical changes in the locality (topography, land use, changes in water
bodies, etc.)
S.No. Information/Checklist Yes/No Details thereof (with approximate
confirmation quantities/rates, wherever possible)
with source of information data
1.1 Permanent or temporary change Yes The proposed site for Hotel falls under the
in land use, land cover or Commercial landuse as per the Master
topography including increase in Plan of Agra 2021. The copy of a letter
intensity of land use (with
from Town Planning Department, Agra
respect to local land use plan)
Development Authority by vides letter no.
32/D/Planning/17-18 Dated 02.01.2018
regarding confirmation of land use is

Consultant-Ascenso Enviro Pvt. Ltd. Page 3 of 19


Proposed 5 Star Hotel at Tajganj ward on Khasra No. 32, Mauza Budhera , Tehsil and
District –Agra, Uttar Pradesh by M/s Bloom Inn Pvt. Ltd.

attached as Annexure-III.
So, the land is being used for the
development of Hotel Project.

The land cover of project site is a fallow


land and depicts plain topography
(relative relief is less than 5m) the
construction activities of the project areas
per the Master plan of Agra 2021 and will
help in increasing the aesthetic beauty.

During the construction phase, land cover


of the project site has been altered to some
extent, which is temporarily in nature.
There are some small bushes present at
1.2 Clearance of existing land, site and only 1 tree is present at site in
Yes
vegetation and building? such a way that it will not affect the
building design.
The proposed site for Hotel falls under the
Commercial landuse as per the Master
Plan of Agra 2021. The copy of a letter
1.3 from Town Planning Department, Agra
Creation of new land uses? Yes
Development Authority by vides letter no.
32/D/Planning/17-18 Dated 02.01.2018
regarding confirmation of land use is
attached as Annexure-III.
1.4 Pre-construction investigations Yes Preliminary Geo-Technical investigation
e.g. bore houses, soil testing? already done at the proposed project site.
As per geo technical report the water table
is 44.45 mbgl.
Geo technical report is attached as
Annexure-XIV.
1.5 Construction Work? Yes The construction in the proposed Hotel
project involves the development of hotel
and Banquet hall having the total 204
guest rooms. The built up area of the
project is 27,422.40 m2 which includes
guest rooms, restaurant, spa, basements
and others services.
1.6 Demolition works? No The site is vacant land, so no demolition
will be involved.
1.7 Temporary sites used for Yes Site office will be provided for the
construction works or housing of Construction Management team during
construction workers? construction phase. Mostly local labours
will be hired and minimal temporary
labour sheds will provided to labour.

Consultant-Ascenso Enviro Pvt. Ltd. Page 4 of 19


Proposed 5 Star Hotel at Tajganj ward on Khasra No. 32, Mauza Budhera , Tehsil and
District –Agra, Uttar Pradesh by M/s Bloom Inn Pvt. Ltd.

These labours camps will be removed on


completion of works. All the construction
activities including storage of raw
materials will confined to the project site
only.
1.8 Above ground building, Yes During Construction phase, excavation
structures or earthwork including will be carried out to provide foundations
linear structures, cut and fill or and basement. This excavated soil will be
excavations properly stacked within the site under
tarpaulin cover. The filling works will be
done by the excavated material and no
extra material will be used. All the topsoil
excavated during construction activities
shall be stored for use in
horticulture/landscape development
within the project site. The lower strata
earth is either used for filling the plinths,
road substructure and leveling low lying
areas. The quantum of Earth excavated
would be approximately around a 1.55
lakhs Cu. mts., considering the total
Basement extent of 10,410 sq.m. with one
levels.
1.9 Underground works including No As this is Hotel project, no mining or
mining or tunnelling? tunnelling would be required.
1.10 Reclamation works? No No reclamation work required.
1.11 Dredging? No No dredging required.
1.12 Offshore structures? No No offshore structures required.
1.13 Production and manufacturing No
processes? As it is a Hotel Project, so these activities
are not associated with the project.

1.14 Facilities for storage of goods or Yes During construction stage, the following
materials? raw material handling methods are being
adopted:
• Cement will separately stored
under cover in bales
• Sand & aggregates will stacked
neatly under tarpaulin cover
• Bricks and steel will laid in open
• Finishing materials like tiles,
sanitary fixtures, etc will stored in
closed rooms.

Material storage yard will be developed


for storage of construction materials and
RMC would be procured from legal
plants.

Consultant-Ascenso Enviro Pvt. Ltd. Page 5 of 19


Proposed 5 Star Hotel at Tajganj ward on Khasra No. 32, Mauza Budhera , Tehsil and
District –Agra, Uttar Pradesh by M/s Bloom Inn Pvt. Ltd.

1.15 Facilities for treatment or Yes 1.) Details regarding the Disposal and
disposal of solid waste or liquid treatment of Solid waste:
effluents?
i) Solid Waste generated during
construction phase: Details of
Construction waste is given below:
1. Soil, Sand and Gravel
2.Brick and Masonry
3. Concrete
4. Metal
5. Bitumen
6.Wood
7. Other (Glass, Plastic material, paper
etc.)
Reuse:
The construction waste will be used in
back filling, road making and pavement.
Metals, tin cans, glass will be sold to
local recyclers/kabadiwalas.
ii) Solid Waste generated during
operational phase:
Total quantity of the municipal solid
waste during the operational phase will be
around 211.2 kg/day. The municipal solid
waste will comprise of biodegradable
fraction, non-biodegradable fraction and
inert fraction.
Disposal:
The biodegradable waste will be collected
in green coloured bins/containers and will
be segregated in collection chamber and
will be disposed as per SWM Rules, 2016.
Non bio degradable waste will be
collected into white bins/containers and
will be segregated in collection chambers
and sold to kabadiwala or govt. approved
agency or recycling industry. Inert waste
will be separately collected and stored in
black containers and will be handed over
to municipal authority. E-waste generated
will be managed as per the E-Waste
(Management) Rules, 2016.

Sludge will be used for horticulture


Consultant-Ascenso Enviro Pvt. Ltd. Page 6 of 19
Proposed 5 Star Hotel at Tajganj ward on Khasra No. 32, Mauza Budhera , Tehsil and
District –Agra, Uttar Pradesh by M/s Bloom Inn Pvt. Ltd.

purposes.

Hazardous waste will be generated in


minimal amount which will be handover
to authorized recycler and management
will be done as per Hazardous and Other
Wastes (Management and Transboundary
Movement) Rules, 2016

Construction and Demolition waste


management:-
In one day, Construction waste will be
generated will be approx. 1 tonnes
As per the Construction and Demolition
Waste Management Rules, 2016,
construction waste will be segregate into
four streams such as concrete, soil, steel,
wood and plastics, bricks and mortar and
it will be disposed as per the same. Some
waste will be reused for backfilling and
recyclable material will be sent to local
recyclers.

2.)Details regarding the Disposal and


treatment of Liquid Effluent:
i) During the construction phase, approx.
24 KLD sewage will generate and it is
being disposed through mobile
toilets/septic tanks.
ii) During the operational phase, sewage
generated will be 182 KLD (including 17
KLD laundry waste) and it will be treated
in the STP installed of 220 KLD capacity
of MBBR technology. The treated water
will be recycled and reused for flushing,
horticulture, and cooling purposes.
1.16 Facilities for long term housing There will be no facility for long term
No
of operational workers? housing for operational workers.
1.17 New road, rail or sea traffic Existing roads will be used in construction
during construction or stage at the site for construction work and
No
operation? transport of construction materials.
During operational phase, traffic will

Consultant-Ascenso Enviro Pvt. Ltd. Page 7 of 19


Proposed 5 Star Hotel at Tajganj ward on Khasra No. 32, Mauza Budhera , Tehsil and
District –Agra, Uttar Pradesh by M/s Bloom Inn Pvt. Ltd.

increase to some extent. But there will be


no rail or sea traffic.
1.18 New road, rail, air waterborne or Existing transportation routes will be used
other transport infrastructure for transportation:
including new or altered routes Transportation sources exiting near the
and stations, ports, airports etc? project site:-

Nearest railway station is Agra City


Railway Station at an aerial distance of
No 8.82 km towards North-West.
Nearest Airport is Agra Airport aka
Kheria Air Force Station at an aerial
distance of 12.87 km towards North-West.

State Highway 62 (Agra- Fatehabad road)


(24 m. wide) is passing adjacent to the
project site.
1.19 Closure or diversion of existing No The project will not affect the existing
transport routes or infrastructure traffic status during the construction phase
leading to changes in traffic and the same will continue during the
movements? operational phase.
1.20 New or diverted transmission No No new or diversion of transmission lines
lines or pipelines? or pipelines will be done.
1.21 Impoundment, damming, No No impoundment, damming, culverting,
culverting, realignment or other realignment or other changes to the
changes to the hydrology of hydrology of surface watercourses is
proposed.
watercourses or aquifers?
1.22 Stream crossings? No No stream is crossing in the project site.
1.23 Abstraction or transfers of water No No ground water will be abstracted for
from ground or surface waters? any purpose during the construction
phase. Water requirement during the
operational phase will be met through
Municipal supply or by borewell or by
water tanker but after taking permission
from concerned authority.
1.24 Changes in water bodies or the No The sewage generated will be treated in
land surface affecting drainage the onsite STP and the treated water will
or run-off? be used for flushing, landscaping, &
Cooling purposes and no water will be
discharged. Hence, it is expected that
drainage or run off will not be affected
and change in water body or the land
surface will not occur.

Consultant-Ascenso Enviro Pvt. Ltd. Page 8 of 19


Proposed 5 Star Hotel at Tajganj ward on Khasra No. 32, Mauza Budhera , Tehsil and
District –Agra, Uttar Pradesh by M/s Bloom Inn Pvt. Ltd.

1.25 Transport of Personnel or Yes There is transport of construction


materials for construction, materials by trucks or trolleys etc.
operation or decommissioning? Precautions will be taken to reduce the
impact of the vehicular movement by
trying to avoid the vehicular trips during
peak hours.
1.26 Long-term dismantling or No Not Applicable
decommissioning or restoration
works?
1.27 Ongoing activity during No Not Applicable
decommissioning which could
have an impact on the
environment?
1.28 Influx of people to an area in Yes Construction phase:
either temporarily or Workers from nearby area will hire in the
permanently? construction phase. (Temporarily).

Operation Phase:
Guest and staff Persons will be main
population in Hotel complex during
operation phase.
1.29 Introduction of alien species? No Native/Local species will be planted.

1.30 Loss of native species or genetic


No No
diversity?
1.31 Any other actions? No No

2. Use of Natural resources for construction or operation of the Project (such as


land, water, materials or energy, especially any resources which are non-renewable or
in short supply):

S.No. Information/ Checklist Yes/No Details thereof (with approximate


confirmation quantities /rates, wherever possible
with source of information data)
2.1. Land especially Yes The proposed site for Hotel falls under the
undeveloped/agricultural Commercial landuse as per the Master
Plan of Agra 2021. The copy of a letter
from Town Planning Department, Agra
Development Authority by vides letter no.
32/D/Planning/17-18 Dated 02.01.2018
regarding confirmation of land use is
attached as Annexure-III.

Consultant-Ascenso Enviro Pvt. Ltd. Page 9 of 19


Proposed 5 Star Hotel at Tajganj ward on Khasra No. 32, Mauza Budhera , Tehsil and
District –Agra, Uttar Pradesh by M/s Bloom Inn Pvt. Ltd.

2.2. Water (expected source & Yes Total water requirement of the proposed
competing users) Unit: KLD project will be approximately 352 KLD.
Fresh Water Supply: 208 KLD
Flushing:35 KLD
Horticulture: 4 KLD
HVAC Cooling purposes: 102 KLD
Fire Water Tank: 3 KLD
Source of water would be municipal water
supply or by Ground water after prior
permission or by water tanker.
2.3. Minerals (MT) No Not Applicable
2.4. Construction material – stone, Yes List of building materials being used at
aggregates, sand/soil ( expected site:
source – MT) 1. Coarse sand
2. Fine sand
3. Stone aggregate
4. Stone for masonry work
5. Cement
6. Reinforcement steel
7. Plywood & steel shuttering
8. Pipe scaffolding (cup lock
system)
9. Bricks
10. Marble
11. P.V.C. conduit
12. MCBs/DBs
13. PVC overhead water tanks
14. Pave tiles
15. GI pipe
16. Wastewater lines
17. S.W. sewer line up to main
sewer
18. PVC rain water down take
19. Stainless steel sink in kitchen
20. Insulated glass
21. Joinery hardware
2.5. Forests and timber (source – Yes Minimum wood will be used in the
MT) project, mainly would be used for doors in
the Project. Aluminium frames and glass
doors and partitions will be used at most
of the places.
2.6. Energy including electricity and Yes 1. Electricity Source:
fuels (source, competing users) Power consumption during the operational
Unit: fuel (MT), energy (MW) phase will be 2.4 MVA and will be
supplied by Torrent Power Limited.

Consultant-Ascenso Enviro Pvt. Ltd. Page 10 of 19


Proposed 5 Star Hotel at Tajganj ward on Khasra No. 32, Mauza Budhera , Tehsil and
District –Agra, Uttar Pradesh by M/s Bloom Inn Pvt. Ltd.

2. Backup power source:


There will be 2 gas based gensets of total
capacity 3,000 KVA (2x1500 KVA) for
power back up for the project.
2.7 Any other natural resources (use No Not Applicable
appropriate standard units)

3. Use, storage, transport, handling or production of substances or materials, which


could be harmful to human health or the environment or raise concerns about actual or
perceived risks to human health.

S. Information/Checklist Yes/No Details there of (with approximate


No. Confirmation quantities/rates, wherever possible)
with source of information data
3.1 Use of substances or materials, No There will be no use of the substances or
which are hazardous (as per material which are hazardous, as per
MSIHC rules) to human health or Manufacture Storage and Import of
the environment (flora, fauna, and Hazardous Chemicals Rules, 1989 and its
water supplies) amendments 2000.
3.2 Changes in occurrence of disease of No The solid waste generated both during
disease or affect disease vectors construction phase is being properly
(e.g. insect or water borne diseases) managed and disposed off during the
construction phase and the same will be
followed during the operation phase. The
sewage generated from the project will be
treated in a STP. The cleanliness of the
project shall be maintained. Hence, it is
expected that there shall be reduction in
vectors as well as vector borne diseases.
3.3 Affect the welfare of people e.g. by Yes Due to the proposed project Socio-
changing living conditions? Economic condition due to increased
employment opportunities provided by the
project and aesthetic beauty of the area
will improve due to the development of
the landscape. The project shall not have
any adverse effect on the living condition
of the people.
3.4 Vulnerable groups of people who No The project shall not affect any vulnerable
could be affected by the project e.g. groups of people in the vicinity.
hospital patients, children, the
elderly etc.,
3.5 Any other causes No Not Applicable

Consultant-Ascenso Enviro Pvt. Ltd. Page 11 of 19


Proposed 5 Star Hotel at Tajganj ward on Khasra No. 32, Mauza Budhera , Tehsil and
District –Agra, Uttar Pradesh by M/s Bloom Inn Pvt. Ltd.

4. Production of solid wastes during construction or operation or operation or


decommissioning (MT/month)

S.No. Information/Checklist Yes/No Details thereof (With approximate


confirmation quantities/rates, wherever possible)
with source of information data
4.1 Spoil, overburden or mine wastes No As this project is the Hotel project, so no
mine spoil and overburden waste will be
generated
4.2 Municipal wastes (domestic and or Yes Total municipal waste generated from the
commercial wastes) project will be 211.2 kg/day.
4.3 Hazardous wastes (as per No There will be no major Hazardous waste
Hazardous Waste Management generation. But if some amount of
Rules) hazardous will generate that will be
manage as per Hazardous and other waste
(Management and Transboundry
Movement) Rules, 2016
4.4 Other industrial process wastes No Not Applicable
4.5 Surplus product No Not Applicable
4.6 Sewage sludge or other sludge Yes The sludge (on wet basis) generated from
from effluent treatment STP is 133.224 kg/day and it will be dried
and used for horticulture purposes.
4.7 Construction or demolition wastes Yes Details of Construction waste is given
below:
1. Soil, Sand and Gravel
2.Brick and Masonry
3. Concrete
4. Metal
5. Bitumen
6.Wood
7. Other (Glass, Plastic material, paper
etc.)
Construction waste shall be used for back
filling, road making and pavements.
Unusable steel scrap is also collected to
site and sold off to recyclers.
No demolition activities will be required.
In one day, Construction waste will be
generated will be approx. 1 tonnes
As per the Construction and Demolition
Waste Management Rules, 2016,
construction waste will be segregate into
four streams such as concrete, soil, steel,
wood and plastics, bricks and mortar and
Consultant-Ascenso Enviro Pvt. Ltd. Page 12 of 19
Proposed 5 Star Hotel at Tajganj ward on Khasra No. 32, Mauza Budhera , Tehsil and
District –Agra, Uttar Pradesh by M/s Bloom Inn Pvt. Ltd.

it will be disposed as per the same. Some


waste will be reused for backfilling and
recyclable material will be sent to local
recyclers.
4.8 Redundant machinery or equipment No Not Applicable
4.9 Contaminated soils or other No Not Applicable
materials
4.10 Agricultural wastes No Negligible waste will be generated from
landscape, which will be the bio-
degradable waste.
4.11 Other solid wastes No Not Applicable

5. Release of pollutant or any hazardous, toxic or noxious substances to air (kg/hr)


S.No. Information/Checklist Yes/No Details thereof (with approximate
confirmation quantities/rates, wherever possible)
with source of information data
5.1 Emissions from combustion of Yes The operation of proposed project does
fossil fuels from stationary or not envisage any major air pollutant
mobile sources. generating sources.
5.2 Emissions from production No Not applicable as it is a Hotel project.
processes
5.3 Emissions from materials handling Yes Fugitive emissions are envisaged only
including storage or transport from material handling and transporting
areas, loading/unloading the construction
material, transportation and earthwork
(levelling etc.) during the construction
period.
5.4 Emissions from construction Yes As most of the construction equipment are
activities including construction mobile, the emissions are fugitive in
materials, sewage and waste nature. The dust generated is also fugitive
in nature, which will be controlled by
suitable mitigation measures like
sprinkling of water.
Sewage generated from labours shed it is
being disposed off by mobile toilets/septic
tanks.

The impacts will be localized in nature


and the areas outside the project boundary
would not have any adverse impact with
respect to ambient air quality.
5.5 Dust of odours from handling of Yes Dust will be generated during the
materials including construction construction phase, water sprinkling and
materials, sewage and waste tarpaulin will be provided over stored raw
Consultant-Ascenso Enviro Pvt. Ltd. Page 13 of 19
Proposed 5 Star Hotel at Tajganj ward on Khasra No. 32, Mauza Budhera , Tehsil and
District –Agra, Uttar Pradesh by M/s Bloom Inn Pvt. Ltd.

material to reduce dust emission.


5.6 Emissions from incineration of No Not Applicable
waste
5.7 Emissions from burning of waste in No Burning of waste will not be done and the
open air (e.g. slash materials, waste generated shall be managed as per
construction debris) the SWM Rules 2016. Construction debris
will be used in internal road construction.
5.8 Emissions from any other sources No Not Applicable

6. Generation of Noise and Vibration, and Emissions of Light and Heat:


S.No Information/Checklist Yes/No Details thereof (with approximate
confirmation quantities/rates, wherever possible)
with source of information data

6.1 From operation of equipment e.g. Yes During construction the machinery
engines, ventilation plant, crushers used for construction are of highest
standard of reputed make and are
adhering to international standard.
These standards itself take care of
noise pollution control/vibration
control and air emission control. Hence
insignificant impacts due to
construction machinery are envisaged.
Apart for this the construction
activities are being restricted to day
time only. Moderate noise being
generated from Construction
Machineries such as Concrete mixer
with hopper, JCB/Pockline, Road
roller. To avoid this, ear muffs have
been provided to the construction
worker
6.2 From industrial or similar No Not Applicable
processes
6.3 From construction or demolition Yes Moderate noise during construction
6.4 From blasting or piling No No blasting or mechanized piling will
be done in the construction phase.
6.5 From construction or operational Yes Noise generated due to traffic
traffic movement will be further minimized
by plantation on the sides of internal
roads, on the open spaces inside the
and around the periphery.
Informatory signboards shall be
provided to encourage vehicle owners
to maintain their vehicle, not to blow
horns.

Consultant-Ascenso Enviro Pvt. Ltd. Page 14 of 19


Proposed 5 Star Hotel at Tajganj ward on Khasra No. 32, Mauza Budhera , Tehsil and
District –Agra, Uttar Pradesh by M/s Bloom Inn Pvt. Ltd.

6.6 From lighting or cooling systems No Not Applicable


6.7 From Any other sources No Not Applicable

7. Risks of contamination of land or water from releases of pollutants into the ground or into
sewers, surface waters, groundwater, coastal waters or the sea:

S.No. Information/Checklist Yes/No Details thereof (with approximate


confirmation quantities/rates, wherever possible)
with source of information data.
7.1 From handling, storage, use or No No major hazardous material will be
spillage of hazardous materials stored at the project site. If any
hazardous waste will generate that will
be managed as per Hazardous and
other wastes (Management and
Transboundry Movement) Rules,
2016.
7.2 From discharge of sewage or other No Treated sewage from STP will be
effluents to water or the land reused for flushing, landscaping,
(expected mode and place of cooling purposes and no discharged
discharge) will be done to sewer.
7.3 By deposition of pollutants No Not Applicable
emitted to air into the land or into
water
7.4 From any other sources No Not Applicable

7.5 Is there a risk of long term build- No There is no such risk.


up of pollutants in the environment
form these sources?

8. Risk of accidents during construction or operation of the Project, which could affect
human health or the environment
S. No. Information/Checklist Yes/No Details thereof (with approximate
confirmation quantities/rates, wherever
possible) with source of
information data
8.1 From explosions, spillages, fires etc No This is basically a construction
from storage, handling, use or project and does not involve major
production of hazardous substances hazardous construction activity.
Hence, chances of explosions,
spillages, fires are minimal.

During construction, all the


labourers are being provided with
suitable personal protective

Consultant-Ascenso Enviro Pvt. Ltd. Page 15 of 19


Proposed 5 Star Hotel at Tajganj ward on Khasra No. 32, Mauza Budhera , Tehsil and
District –Agra, Uttar Pradesh by M/s Bloom Inn Pvt. Ltd.

equipment (PPE) as required under


the health and safety norms.
Training and awareness about the
safety norms is being provided to
all supervisors and labourers
involved in construction activity.

An agreement will be signed with


the contractor, which will clearly
deal with the safety aspects during
construction.

No major hazardous waste shall be


stored within the project site. No
chemical industry or process
activity is involved in this project,
hence no chemical hazard and
accidents due to the envisaged.
8.2 From any other causes No Not Applicable.
8.3 Could the project be affected by No The project falls under seismic
natural disasters causing active Zone III indicating moderate
environmental damage (e.g. floods, damage risk zone, according to the
earthquakes, landslides, cloudburst Indian Standard Seismic Zoning
etc)? Map. The buildings will be
designed as earthquake resistant and
comply with the required IS
specifications.
There are no chances of floods and
landslide.

9. Factors which should be considered (such as consequential development) which could


lead to environmental effects or the potential for cumulative impacts with other existing or
planned activities in the locality

S.No. Information/Checklist Yes/No Details thereof (with approximate


confirmation quantities/rates, wherever possible)
with source of information data
9.1 Lead to development of Yes Appropriate infrastructure like roads,
supporting facilities, ancillary power supply, waste management
development or development and waste water treatment will be
stimulated by the project which developed within the project site.
could have impact on the There will be a cumulative positive
environment e.g.: impact on the environment in terms
• Supporting infrastructure of better infrastructure.
(roads, power supply, waste or

Consultant-Ascenso Enviro Pvt. Ltd. Page 16 of 19


Proposed 5 Star Hotel at Tajganj ward on Khasra No. 32, Mauza Budhera , Tehsil and
District –Agra, Uttar Pradesh by M/s Bloom Inn Pvt. Ltd.

waste water treatment, etc.) The project will lead to enhancement


in the infrastructure facilities of the
area. In due course of time, other
• Housing development similar projects are expected to come
• Extractive industries up and result in further enhancement
• Supply industries of the supporting infrastructure.
• Other
9.2 Lead to after-use of the site, No Not Applicable
which could have an impact on
the environment
9.3 Set a precedent for later Yes Infrastructure development of area.
development Socio Economic condition will
improve.
9.4 Have cumulative effects due to Yes It will improve the environment by
proximity to other existing or creating a more attractive and inter
planned projects with similar active environment for employment
effects generation and foreign exchange for
the country, leisure & recreation,
create an urban landmark.
(III) Environment Sensitivity
S.No. Area Name/ Identity Aerial distance (within
15km) Proposed project
location boundary
1. Areas protected under Taj Mahal 6.54 km towards NW
international conventions, Agra Reserved Forest 5.8 km towards NW
national or local legislation for Yamuna River 5.17 km towards NE
their ecological, landscape, Agra Fort 8.31 km towards NW
cultural or other related value Chini Ka Rauza 9.01 km towards NW
2. Areas which are important or Taj Mahal 6.54 km towards NW
sensitive for ecological reasons Agra Reserved Forest 5.8 km towards NW
–Wetlands, watercourses or Yamuna River 5.17 km towards NE
other water bodies, coastal Agra Fort 8.31 km towards NW
zone, biospheres, mountains, Chini Ka Rauza 9.01 km towards NW
forests
3. Area used by protected, Agra Reserved Forest 5.8 km towards NW
important or sensitive species of
flora or fauna for breeding,
nesting, foraging, resting, over
wintering, migration
4. Inland, coastal, marine or Yamuna River 5.17 km towards NE
underground waters Ground water Depth:-
Premonsoon-2.19-45.58
mbgl
Postmonsoon-1.10-246.34

Consultant-Ascenso Enviro Pvt. Ltd. Page 17 of 19


Proposed 5 Star Hotel at Tajganj ward on Khasra No. 32, Mauza Budhera , Tehsil and
District –Agra, Uttar Pradesh by M/s Bloom Inn Pvt. Ltd.

mbgl
Source:- District Boucher,
CGWB( 2012-2013)
As per geotechnical report
the water table is 40.45
mbgl.
5. State, National boundaries None No state and national
boundary is coming within
15 km of project site.
6. Routers or facilities used by the State Highway 62/ Agra- adjacent to the project site
public for access to recreation Fatehabad Road Taj in North East
or other tourist, pilgrim areas Express way( Proposed Adjacent to site in South
Agra Gwalior Ring Road)
East
7. Defence installations Agra Airport aka Kheria 12.87 km towards West
Air Force Station
8. Densely populated or built-up Lakavli 0.85 km towards SW
area Kundol 0.65 km towards North
9. Areas occupied by sensitive Hospital:
man-made land uses (hospitals, Jaypee Medical Center 3.11 km towards North
schools, places of worship, Dr. Aarti Manoj Hospital 5.81 km towards NW
community facilities) Upadhyay Hospital 5.83 km towards NW
Schools:
St Joseph International 440 m towards SE
School
Primary School Lakavli 990 m towards West

Balihari Temple
820 meter towards West
10. Areas containing important, Yamuna River 5.17 km towards NE
high quality or scarce resources Ground Water Depth:-
(ground water resources, Source:- District Boucher,
surface resources, forestry, CGWB( 2012-2013)
agriculture, fisheries, tourism,
As per geotechnical report
minerals) the water table is 40.45
mbgl.
11. Areas already subjected to Industrial area Approx. 7.5 Km in North
pollution or environmental West
damage. (those where existing
legal environmental standards
are exceeded)
12. Areas susceptible to natural Yes Area is susceptible to
hazard which could cause the Earthquake. Project area
project to present environmental falls in Zone-III as
problems (earthquakes, Moderate Damage Risk
subsidence, landslides, erosion, Zone. Area is not
flooding or extreme or adverse susceptible to natural
climatic conditions) hazard such as landslides,
Consultant-Ascenso Enviro Pvt. Ltd. Page 18 of 19
Proposed 5 Star Hotel at Tajganj ward on Khasra No. 32, Mauza Budhera , Tehsil and
District –Agra, Uttar Pradesh by M/s Bloom Inn Pvt. Ltd.

subsidence, erosion,
flooding or extreme or
adverse climatic condition.

(IV) Proposed Terms of Reference for EIA studies–Not Applicable

Consultant-Ascenso Enviro Pvt. Ltd. Page 19 of 19


SHEET NO. 03

° RWH

94

90
°
RWH

CANOPY

CANOPY
TRUCK LOADING / UNLOADING STALL

50.800 [166'-8"]

6.500 [21'-4"] 2.400 [7'-10 1/2"] 4.050 [13'-3 1/2"] 14.300 [46'-11"] 5.700 [18'-8 1/2"]

2.500 [8'-2 1/2"]


SANITIZING/ SHAFT
UP
VEG WASHING

4.200 [13'-9 1/4"]


4.300 [14'-1 1/4"]
4.30 x 2.50 M
MEP DG AND ELECTRICAL PANEL ROOM

5.775 [18'-11 1/4"]


4.300 [14'-1 1/4"]
SECURITY + RECEIVING GOOD'S RECEIVING + MATERIAL

6.575 [21'-6 3/4"]

6.575 [21'-6 3/4"]


STAFF LOBBY OFFICES MANAGEMENT OFFICES
5.300 [17'-4 3/4"]

7.292 [23'-11"]
1.875 [6'-1 3/4"] 1.800 [5'-10 3/4"]
6.50 x 9.20 M 6.50 x 9.20 M 4.05 x 6.60 M 10.0 x 4.20 M 3.550 [11'-7 3/4"]
TRASH / GARBAGE / WASH-UP AREA + 1.95 x 1.175 M
DN
DE-BOXING RECYCLING STOREROOM

PANEL
DG SYN.
8.000 [26'-3"]

4.000 [13'-1 1/2"]

4.000 [13'-1 1/2"]


7.600 [24'-11 1/4"] 4.10 x 1.80 M 5.70 x 6.575 M

9.200 [30'-2 1/4"]

2.625 [8'-7 1/4"]


8.000 [26'-3"]

2.175 [7'-1 3/4"]


7.800 [25'-7"]
ELECT.ROOM
CCTV & FIRE CONTROL ROOM 3.55 x 4.0 M 3.0 x 4.0 M 1.9 x 2.625 M
8.0 x 2.175 M HYGIENE LAB
GENERATOR ROOM
4.10 x 1.875 M
3.000 [9'-10"] 1.900 [6'-2 3/4"] 5.5M CLEAR HEIGHT REQUIRED
4.100 [13'-5 1/2"]

4.700 [15'-5"]
AREA = 132 SQ M
7.80 x 4.7 M LT PANEL ROOM

LxBxH-13000x1600x2200
MAIN LT PANEL
3.6M CLEAR HEIGHT REQUIRED

2.425 [7'-11 1/2"]

2.416 [7'-11 1/4"]


AREA = 115.5 SQ M BUFFER
DN TANK

BANK-01
CAPACITOR
15500
2.425M WIDE BOH CORRIDOR FHC
ST-02

LxBxH-6200x2500x3200

LxBxH-6200x2500x3200
2000kVA, HEAT EXCHANGER
OPEN TYPE DG -01

2000kVA, HEAT EXCHANGER


OPEN TYPE DG -01
FIRE
STAIRCASE
STAIR
UP 1.5 M
11.000 [36'-1"] 4.900 [16'-1"] 8.100 [26'-7"]
PRS

11900
5.000 [16'-4 3/4"] 1.600 [5'-3"] 5.100 [16'-8 3/4"] WIDE

2.450 [8'-0 1/2"]


FLOWER

BANK-02
CAPACITOR
2.800 [9'-2 1/4"]
PREPARATION VEG.PREPARATION
PHE
1.6 x 3.0 M 4.90 x 2.45 M 8.10 x 2.80 M
SH 7.200 [23'-7 1/2"]
DAY STORAGE

3.300 [10'-10"]
BALL ROOM KITCHEN, ENGINEERING STORES TANK (Typ.)

6.350 [20'-10"]

6.350 [20'-10"]
6.350 [20'-10"]
FEMALE RESTROOM MALE RESTROOM DISH WASH & STORAGE 8.3 x 3.30 M LT PANEL
5.0 x 6.35 M 5.10 x 6.35 M 11.0 x 6.35 M 5.100 [16'-8 3/4"]
2.4M WIDE BOH
CORRIDOR DG ROOM

3.700 [12'-1 3/4"]


LL LINEN

3.500 [11'-5 3/4"]


PRESSCHUTE DRAINAGE SUMP
5.10 x 3.70 M LxBxH-1000x1000x1000

2.417 [7'-11 1/4"]


GARDE MANGER 8.300 [27'-2 3/4"] 19900
8.10 x 3.50 M
7950 11950
2.4M WIDE SERVICE LIFT LOBBY
8.3 x 2.4 M
2.400 [7'-10 1/2"]

4.500 [14'-9 1/4"]

2.000 [6'-6 3/4"]


RAMP EXIT HT PANEL TRANSFORMER

2.500 [8'-2 1/2"]


2.400 [7'-10 1/2"] SE-03 SE-02 SE-01
2.0M WIDE SERVICE CORRIDOR

2.500 [8'-2 1/2"]

2.500 [8'-2 1/2"]

2.500 [8'-2 1/2"]


FISH PREPARATION 1600 Kg 1600 Kg 1600 Kg
2.4MX2.5M 2.4MX2.5M 2.4MX2.5M HT
8.10 x 2.50 M
PANEL

4400
TRANSFORMER - 01 TRANSFORMER - 01
2.400 [7'-10 1/2"] DRY TYPE, STEP DOWN - DRY TYPE, STEP DOWN -

5650
6.850 [22'-5 3/4"] 21.800 [71'-6 1/4"] 2.500 [8'-2 1/2"] 2.500 [8'-2 1/2"] 2.500 [8'-2 1/2"] HT PANEL ROOM 11KV/0.433KV, 2000kVA, 11KV/0.433KV, 2000kVA,
2.000 [6'-6 3/4"]
4.4M CLEAR HEIGHT REQUIRED ON LOAD TAP CHANGER, ON LOAD TAP CHANGER,
AREA = 22 SQ M LxBxH-2950x2900x3150 LxBxH-2950x2900x3150

3.400 [11'-1 3/4"]


SHAFT
4895
MEAT PREPARATION TRANSFORMER ROOM
8.10 x 3.40 M 4.4M CLEAR HEIGHT REQUIRED
AREA = 56 SQ M 9895
8.900 [29'-2 1/2"]
1.8M WIDE BOH
CORRIDOR

3.850 [12'-7 1/2"]


HALL 01
BAKERY & PASTRY
8.9 x 3.85 M

4.750 [15'-7"]
OPERATING
EQUIPMENT STORE
8.10 x 4.75 M
8.950 [29'-4 1/4"]
RWH
IVED

DELI SEATING
ECE
EY R

19.250 [63'-1 3/4"]


V
SUR

REST ROOM
8.10 x 5.80 M
OAD
R
OP /

HALL 02

67.500 [221'-5 1/2"]

67.500 [221'-5 1/2"]


R LO
S PE

2.0M WIDE
SERVICE

21.650 [71'-0 1/4"]


CORRIDOR
A
ENT

42.795 [140'-4 3/4"]


PREFUNCTION BANQUETS
EXT

6.85 x 42.795 M 21.80 x 40.55 M

40.545 [133'-0 1/4"]


ELT

RECEPTION
EN B

FFL .+1.10M
GRE

HALL 03

8.400 [27'-6 3/4"]

3.100 [10'-2"]
GUEST ELEVATOR LOBBY

RWH 8.4 x 3.10 M

20PAX 20PAX 20PAX

2.500 [8'-2 1/2"]

2.500 [8'-2 1/2"]

2.500 [8'-2 1/2"]


HPE-01 HPE-02 HPE-03
2.4MX2.5M 2.4MX2.5M 2.4MX2.5M

2.500 [8'-2 1/2"] 2.500 [8'-2 1/2"] 2.500 [8'-2 1/2"]

7.200 [23'-7 1/2"]


PRS
HALL 04 DN
ST-01

4.000 [13'-1 1/2"]


ST-01
UP FIRE
4.250 [13'-11 1/4"]

STAIRCASE
STAIR

4.200 [13'-9 1/4"]


UP 1.8 M
WIDE

FHC
DN 2.0 x 4.20 M
7.249 [23'-9 1/2"]

2.000 [6'-6 3/4"]

4.500 [14'-9 1/4"]


9.500 [31'-2"] 20PAX
RAMP ENTRY

2.700 [8'-10 1/4"]


BPE-01
2.5MX2.7M

3.555 [11'-8"]
MALE RESTROOM FEMALE RESTROOM
ESCALATOR TO MEETING ROOMS
9.20 x 3.55 M 9.50 x 3.55 M

BANQUET DROP OFF PLAZA OPEN ON ALL SIDES


2.500 [8'-2 1/2"]

9.960 [32'-8"]
8.255 [27'-1"]

BAGGAGE
SCANNER

4.500 [14'-9 1/4"]

4.500 [14'-9 1/4"]

2.650 [8'-8 1/4"]


BANQUET RECEPTION WAITING LOUNGE
BANQUET LIFT LOBBY
ENTRANCE LOBBY
8.90 x 4.5 M
89

6.95 x 2.65 M
VALET DESK 25.300 [83'] 8.900 [29'-2 1/2"] 6.950 [22'-9 1/2"] 8.900 [29'-2 1/2"]
°

VALET DESK BAGGAGE


SCANNER

PLAZA - 4M WIDE
DROP OFF ZONE

PICK UP ZONE

DROP OFF ZONE


BYPASS
CANOPY
8
PICK UP ZONE

BYPASS
CANOPY

RWH

SECURITY CABIN
3.15 x 1.76 M

1.800 [5'-10 3/4"]


RWH

SECURITY CABIN
3.15 x 1.76 M

OWNER'S.

M/s BLOOM INN (P)LTD.


GROUND FLOOR
01.
1:200

NOTES. OWNER. ARCHITECT DRG NO :


A1102 SUBMISSION DRAWING

PROPOSED HOTEL PLAN SITUATED AT MAUZA BUDHERA, TAJGANJ WARD ON KHASARA NO. 32 DATE :
25SEP17
SCALE :
1:200
M/s BLOOM INN (P)LTD.
FOR OWNER : M/s BLOOM INN (P)LTD.
DRN BY :
BK
N
CHK BY :
KB
i`"B 33@93

3-4-5 10-5 eh-


eh- ls (I) 10-5 ehVj ls vf/kd m¡pkbZ ds Hkouksa gsrq lsV&cSd fuEuor~ gksx
a s %&
vf/kd ÅWpkbZ Hkou dh ÅapkbZ pkjksa vksj NksMs+ tkus okyk lsV
ds Hkou ¼ehVj½ cSd ¼ehVj½
10-5ls 15 rd 5-0
15 ls 18 rd 6-0
18 ls 21 rd 7-0
21 ls 24 rd 8-0
24 ls 27 rd 9-0
27 ls 30 rd 10-0
30 ls 35 rd 11-0
35 ls 40 rd 12-0
40 ls 45 rd 13-0
45 ls 50 rd 14-0
50 ls vf/kd 15-0
(II) fdlh Hkh Hkou dh vf/kdre Å¡pkbZ bl izfrcU/k ds v/khu gksxh fd 30
ehVj ls de pkSM+s ekxksaZ ij fLFkr Hkouksa dh vf/kdre ÅWp a kbZ ekxZ dh
fo|eku pkSM+kbZ rFkk QzUV lsV&cSd ds ;ksx ds Ms<+ xquk ls vf/kd ugh
gksxh] ijUrq 30 ehVj ,oa mlls vf/kd pkSM+s ekxksaZ ij fLFkr Hkouksa essa
;g izfrcU/k ykxw ugha gksxkA Hkou dh vf/kdre ÅWp a kbZ lajf{kr
Lekjd@gSfjVst+ LFky ls nwjh] ,;jiksVZ QUusy t+kus rFkk vU;
LVsV~;qVjh izfrcU/kksa ls Hkh fu;fU=r gksxhA
(III) ;fn Hkou nks ;k vf/kd fHkUu pkSM+kbZ dh lM+dksa ij fLFkr gks rc
vf/kd pkSM+h lM+d dh vksj Hkou dk vxz Hkkx ekuk tk,xk rFkk
mijksDr (II) ds vuqlkj Hkou dh Å¡pkbZ vis{kkd`r de pkSM+s ekxZ ds
lkFk 24 ehVj xgjkbZ rd vuqeU; gksxhA
(IV) mijksDr izLrj-(I) ds fodYi esa fuEu lSVs cSd vuqeU; fd;s tk
ldrs gaS%&
¼d½ 24 ehVj Å¡pkbZ rd vuqorhZ ryksa ij ,d lSV cSd ds lkFk
Hkwry ij pkjksa vksj dk U;wure lSV cSd 6 ehVj gksxkA
¼[k½ 24 eh-ls 37-5 eh- Å¡pkbZZ rd vuqorhZ ryksa ij ,d lSV cSd ds
lkFk Hkwry ij pkjksa vksj dk U;wure lSsV cSd 9 eh- gksxkA
¼x½ 37-5 ehVj ls vf/kd Å¡pkbZ ds Hkouksa esa vuqorhZ ryksa ij nks lSV
cSd ds lkFk Hkwry ij pkjksa vksj dk lSV cSd U;wure 12 ehVj
gksxkA
¼?k½ izLrj&3-4-5 dh rkfydk esa fn, x, lSV cSd dh deh dks Åijh
ryksa ij fn, x, lSV cSd ls iwjk fd;k tk,xk] ijUrq vuqorhZ
ryksa ij lSV cSd esa dejksa ;k Q~ySV ls dksbZ igqWap ugh gksxhA
(V) nks Cykdksa ds e/; ijLij nwjh mPpre Cykd dh ÅWp a kbZ ds vk/kkj ij
ml gsrq okafNr lsV&cSd vFkok 6 ehVj] tks Hkh vf/kd gks] gksxhA
IN PROGRESS
NOT FOR CONSTRUCTION

KEY PLAN

VALET
STATION

Entry Foyer / Reception Area /


Cloakroom 50/70sq.m

DECK

NOTES :-

Rev Date Issued to Description Dwn Chk by

The concepts and information contained in this document are the copyright of Think Bim
Technical Services Pvt. Ltd. . Use or copying of the document in whole or in part without the
written permission of Think Bim Technical Services Pvt. Ltd. constitutes an infringement of
copyright. Do not scale drawings. If in doubt, ask!

ARCHITECT :

MEP CONSULTANT :
Unit-228-236, 2nd floor, Tower-A
th ink BiM
Spaze I Tech Park, Sohna Road
DESIGN . CONSTRUCTION . FM
Sector-49, Gurgaon-122018
Haryana, India
PH-0124-4069379, 4145060

Project Name

PROPOSED 5 STAR HOTEL , AGRA

Title

SOIL & WASTE


SCHEMATIC

Discipline Status
PLUMBING SERVICES CONCEPT
Designed By Checked By Approved By
RAK AR DKT
Project No. Date Scale
17345 07/04/2017 NTS (at A1)
Drawing No. Revision
17345-P-A1-0401 R0

PLOT DATE:-21 December 2017 FILENAME:-T:\0345_Hyatt Agra\06_ThinkBiM Dwgs\PL\Working\Current Drawing only\21.12.2017 Report Schematic\17345-P-A1-0401.dwg
0 10 20 30 40 50
ENERGY SAVING CALCULATIONS

Solar Based LED Lighting will be done in the common areas, signages, entry gates and boundary walls etc.

S. Description Consumption Consumption Common area = Total Total Saving Saving (kVA)
No. with with solar light Total Plot area - consumption consumpti (Watts)
conventional (Watt/sqm.) ground with on
light coverage (sqm) conventional with solar
(Watt/sqm.) light (Watt) light
(Watt)

1. Solar Light 1 0 12558.65 12558.65 0 12558.65 15.6

LED Based Lighting will be done in the dwelling units


S. Description Consumption Consumption FAR (s.q.m) Total Total Saving Saving (kVA)
No. with with LED light consumption consumptio (Watts)
conventional (Watt/s.q.m.) with n
light conventional with LED
(Watt/sqm.) light (Watt) light
(Watt)

2. LED Light 1 0.4 22029.57 22029.57 8811 13218.57 16.5


Usage of energy efficient Lift (VVVF gearless lifts)
S. Description Consumption Consumption No. of Lift Total Total Saving Saving (kVA)
No. with with VVVF consumption consumption (KW)
conventional gearless lifts with with VVVF
lift (KW) conventional gearless lifts
(KW) lift (KW)
(KW)

3. Lifts 18 15 9 162 135 27 33.75

Usage of energy efficient Lift (VVVF gearless lifts)


S. Water Water required Water quantity Ambient water Temperature of Gain in Kilo Electricit
No. provided for (liter / person) (liters) temperature Water required temper calories y to heat
30% of total (˚C) (˚C) ature required 30400
population (˚C) to heat Liter of
184000 water
Liter of to 60˚C
water to (KW)
60˚C
(kcals/day)
4. 422 25 10560 20 60 40 422400 495
Considering 173
35%
use in a year
Considering 129.98
75%
diversity
factor
Total Energy Saved 129.88
Total Energy Saved
S. No. Description Saving in KVA
1 Solar Based Lighting will be done in the common areas, signages, entry gates and boundary walls etc. 15.6
2 LED Based Lighting will be done in the dwelling units 16.5
3 Usage of energy efficient Lift (VVVF non gear lifts) 33.75
4 Solar Hot Water Generation System will be provided to guest rooms 129.98
Total Energy Saved 195.83
Total Energy Consumption 2400
Total Energy Saving 8.15%
IN PROGRESS
NOT FOR CONSTRUCTION

KEY PLAN

NOTES :-

Rev Date Issued to Description Dwn Chk by

The concepts and information contained in this document are the copyright of Think Bim
Technical Services Pvt. Ltd. . Use or copying of the document in whole or in part without the
written permission of Think Bim Technical Services Pvt. Ltd. constitutes an infringement of
copyright. Do not scale drawings. If in doubt, ask!

ARCHITECT :

MEP CONSULTANT :
Unit-228-236, 2nd floor, Tower-A
th ink BiM
Spaze I Tech Park, Sohna Road
DESIGN . CONSTRUCTION . FM
Sector-49, Gurgaon-122018
Haryana, India
PH-0124-4069379, 4145060

Project Name

PROPOSED 5 STAR HOTEL , AGRA

Title

FIRE FIGHTING
SCHEMATIC

Discipline Status

FIRE FIGHTING SERVICES CONCEPT


Designed By Checked By Approved By
RAK AR DKT
Project No. Date Scale
17345 07/04/2017 NTS (at A1)
Drawing No. Revision

17345-F-A1-0403 R0
PLOT DATE:-Thursday, May 18, 2017 FILENAME:-T:\0345_Hyatt Agra\06_ThinkBiM Dwgs\PL\Working\Current Drawing only\18.05.2017 Report Schematic\17345-F-A1-0403.dwg
0 10 20 30 40 50
IN PROGRESS
NOT FOR CONSTRUCTION

KEY PLAN
M

NOTES :-
M

Rev Date Issued to Description Dwn Chk by

The concepts and information contained in this document are the copyright of Think Bim
Technical Services Pvt. Ltd. . Use or copying of the document in whole or in part without the
written permission of Think Bim Technical Services Pvt. Ltd. constitutes an infringement of
copyright. Do not scale drawings. If in doubt, ask!

ARCHITECT :

MEP CONSULTANT :
Unit-228-236, 2nd floor, Tower-A
th ink BiM
Spaze I Tech Park, Sohna Road
DESIGN . CONSTRUCTION . FM
Sector-49, Gurgaon-122018
Haryana, India
PH-0124-4069379, 4145060

Project Name
ADDRESSABLE MAIN FIRE ALARM
CONTROL PANEL FOR HOTEL (FACP)
PROPOSED 5 STAR HOTEL , AGRA

Title

FIRE ALARM SYSTEM BLOCK SCHEMATIC

Discipline Status
ELECTRICAL PRELIMINARY
Designed By Checked By Approved By
RKM GIS AKT
Project No. Date Scale
17345 18.05.17 NTS (at A3)
Drawing No. Revision

17345-E-A3-0002 R0
PLOT DATE:- Thursday, May 18, 2017 FILENAME:- T:\0345_Hyatt Agra\06_ThinkBiM Dwgs\Ele\Working\Current Drawing only\SCHEMATIC FOR DBR\R1\17345-E-A3-002_FIRE ALARM SYSTEM BLOCK SCHEMATIC.dwg
FULL SIZE ON ORIGINAL 0 10 20 30 40 50