TOP RANKED EPC CONTRACTOR


- REFERENCE LIST -

STEEL PLANTS

AS OF MAY 2014
POSCO E&C AT A GLANCE

SOURCE: ENR 2013

ZPSS Hot Strip Mill


POSCO Guangdong CGL
POSCO Assan TST
Assan CCL
ESCO B/F, Sinter Plant
Asia Special Steel
HADEED CCL
POSCO-Mexico No.1&2 CGL
Formosa HRM
IISCO Blast Furnace POSCO CRM
POSCO Maharashtra CRM, CGL CSP Integrated Steelworks

PT.KP Integrated Steelworks


BSL Sinter Plant

• Quality ISO 9001


• Environment ISO 14001
• Safety OHSAS 18001, KOSHA 18001
• Energy KEPIC, ASME Section 1&3

Total Solution Provider


BUSINESS AREA

WORK P E P C O M
SCOPE
Planning Engineering Procurement Construction Operation Maintenance

Planning Project Execution Commercial Operation

MINING PLANTS
MINE PROCESS PLANT TRANSPORTATION PORT FACILITIES

STEEL PLANTS
IRON MAKING PLANT STEEL MAKING PLANT ROLLING MILL PLANT PROCESS LINE

• PICKLING LINE
PROCESS • ANNEALING LINE
• GALVANIZING LINE
• COLOR COATING LINE
• SLITTING LINE
• PACKING LINE

Total Solution Provider


OUR VALUABLE CLIENTS
DOMESTIC

OVERSEAS

Total Solution Provider


INTEGRATED STEEL WORKS
POSCO POHANG WORKS, KOREA POSCO GWANGYANG WORKS, KOREA

CAPACITY : 12.3MTPY (4 BF, 3 FINEX) CAPACITY : 20MTPY (5 BF)


PRODUCT : CR, HR, PLATE, WIRE ROD, STS, GO, ETC. PRODUCT : CR, HR, PLATE

PT.KP INTEGRATED STEELWORKS, INDONESIA CSP INTEGRATED STEELWORKS, BRAZIL

CAPACITY : 3MTPY (1 BF) CAPACITY : 3MTPY (1 BF)


PRODUCT : STEEL SLAB, HEAVY PLATE PRODUCT : STEEL SLAB

Total Solution Provider


IRON MAKING PLANT - RAW MATERIAL HANDLING
Raw material handling facilities including Ore and Coal
MAJOR PROJECTS *) ON-GOING PROJECT

handling with material treatment capacity of 68 and 35 PROJECT SCOPE CAPACITY COMPLETION
million tons respectively are in operation in POSCO steel
works. POSCO E&C has supplied Silos each of 50 thousand FORMOSA, RMHF, MAX 6,000 T/H
ECE 2016*
HA TINH, VIETNAM 220 BC LINE
tons of capacity in Gwangyang.
CSP, RMHF, MAX 2,400 T/H
EPC 2015*
PECEM, BRAZIL 50 BC LINE

SNG, SILO PLANT, 50,000 TON


EPC 2014
GWANGYANG, KOREA 4 SET

POSCO, SILO PLANT, 50,000 TON


EPC 2012
GWANGYANG, KOREA 15 SET

POSCO, RMHF (WHARF BELT 6,000 T/H


EPC 2012
CONVEYOR), POHANG, KOREA 2 SET
POSCO, RMHF (WHARF BELT
6,000 T/H
CONVEYOR) GWANGYANG, EPC 2012
PROJECT POSCO, NEW SILO PLANT 22 SET
KOREA
CAPACITY 50,000 TON, 15 SET
POSCO, RAW MATERIAL SILO, 60,000 TON
EPC 2011
STORAGE MATERIAL COAL POHANG, KOREA 6 SET
LOCATION GWANGYANG, KOREA INTERNATIONAL AIRPORT EPC, 4,000 T/H
2010
RECLAMATION, KOREA O&M 3 BC LINE
PERIOD DEC. 2010 ~ SEP. 2012
WORK SCOPE EPC SNNC, FE-NI RMHF, MAX 6,000 T/H
EPC 2010
GWANGYANG, KOREA 10 BC LINE

Total Solution Provider


IRON MAKING PLANT - RAW MATERIAL HANDLING
MAJOR PROJECTS
PROJECT SCOPE CAPACITY COMPLETION
MAX 6,000 T/H
POSCO, NO.2 FINEX RMHF, POHANG, KOREA EPC 2006
56 BC LINE

POSCO, FINEX RMHF, POHANG, KOREA EPC 4,000,000 T/Y 2006

MAX 6,000 T/H


POSCO, CTS RMHF, GWANGYANG, KOREA EPC 2005
18 BC LINE

POSVEN CA, RMHF(HBI PLANT), BOLIVAR, VENEZUELA EPC 1,500,000 T/Y 1999

CVRD, RMHF(PELLETIZING PLANT), TUBARAO, BRAZIL EPC 4,000,000 T/Y 1998

Total Solution Provider


IRON MAKING PLANT - COKE PLANT
The Coke Plant comprise 84 ovens (42 Chamber x 2 MAJOR PROJECTS *) ON-GOING PROJECT
Batteries) and is operated at 98% on the basis of annual
PROJECT SCOPE CAPACITY COMPLETION
average operating ratio. It consists of Coal Preparation
and Coke Treatment Plant , Coke Oven, Gas Treatment CSP, COKE PLANT,
EPC 1,320,000 T/Y 2015*
Plant, and Coke Moving Machine. PECEM, BRAZIL

FORMOSA, BY-PRODUCT
C 175,000N㎥/H 2015*
PLANT, HA TINH, VIETNAM

PT.KP, COKE PLANT, CILEGON,


EPC 1,320,000 T/Y 2013
INDONESIA
NO.5 COKE PLANT,
GWANGYANG, KOREA EPC 2,850,000 T/Y 2011
(OVEN & BY-PRODUCT)
NO.5 COKE PLANT, 360 T/H
EPC 2011
GWANGYANG, KOREA (CDQ) (DRY COKE)
PROJECT PT.KP, COKE PLANT EXTENSION OF THE COKE
PLANT STAGE 5, POHANG, EPC 620,000 T/Y 2007
CAPACITY 1,320,000 T/Y
KOREA
CHAMBER HEIGHT 7.6 M
DESULFURIZATION PLANT FOR
LOCATION CILEGON, INDONESIA GAS REFINERY PLANT, EPC 6,800 N㎥/H 2007
POHANG, KOREA
PERIOD JUL. 2011 ~ DEC. 2013
COKE PLANT STAGE 4, 180 T/H
WORK SCOPE EPC EPC 2005
POHANG, KOREA (CDQ) (DRY COKE)

Total Solution Provider


IRON MAKING PLANT - SINTER PLANT
Specialized in technology of large-scale sinter plant
MAJOR PROJECTS *) ON-GOING PROJECT

which provides high productivity & availability with low PROJECT SCOPE CAPACITY COMPLETION
operating costs to client.
CSP, SINTER PLANT,
EPC 400 M2 2015*
Below is one of the largest sinter plant in the world. PECEM, BRAZIL

PT.KP, SINTER PLANT, CILEGON,


EPC 450 M2 2013
INDONESIA

POSCO, NO. 2 SINTERING PLANT


EPC 450 M2 2012
REVAMPING, GWANGYANG, KOREA

ESCO, TAVAZON SINTER PLANT,


EP 204 M2 2011
ESFAHAN, IRAN

NO.5 SINTER PLANT, GWANGYANG,


EPC 600 M2 2011
KOREA
PROJECT POSCO, NO.5 SINTER PLANT
NO.4 SINTER PLANT 2ND REVAMPING,
CAPACITY 600 M2 EPC 518 M2 2010
POHANG, KOREA
PRODUCTIVITY 40.3 T/D/M2 (8,825,700 T/Y)
NO. 3 & 4 SINTER PLANT 2ND 470 M2
LOCATION GWANGYANG, KOREA EPC 2009
REVAMPING, GWANGYANG, KOREA 497 M2
PERIOD AUG. 2009 ~ FEB. 2011
BSL, NO.3 SINTER PLANT
EP 420 M2 2009
WORK SCOPE EPC REVAMPING, AUSTRALIA

Total Solution Provider


IRON MAKING PLANT - SINTER PLANT
MAJOR PROJECTS
PROJECT SCOPE CAPACITY COMPLETION

NO.2 SINTER PLANT 2ND REVAMPING, GWANGYANG, KOREA EPC 450 M2 2007

POSCO, NO. 3 SINTERING PLANT REVAMPING, POHANG, KOREA EPC 504 M2 2006

POSCO, NO. 2&4 SINTERING PLANT REVAMPING PALLET WIDTH EXTENSION, NO.2: 450 M2
EPC 2004
GWANGYANG, KOREA NO.4: 477 M2

POSCO, NO. 1&3 SINTERING PLANT REVAMPING PALLET WIDTH EXTENSION,


EPC 400 M2 2002
GWANGYANG, KOREA

Total Solution Provider


IRON MAKING PLANT - BLAST FURNACE
Specialized in technology of large-scale blast furnace MAJOR PROJECTS *) ON-GOING PROJECT
which provides high productivity & availability with low INNER
operating costs to client. PROJECT SCOPE COMPLETION
VOLUME
Below is the first integrated steelworks in Southeast
Asia and its blast furnace that has officially begun CSP, BLAST FURNACE,
EPC 3,800 M3 2015*
operations. PECEM, BRAZIL

POSCO, NO.5 BF 2ND REVAMPING,


EPC 5,220 M3 2014
POHANG, KOREA

PT.KP, BLAST FURNACE,


EPC 3,800 M3 2013
CILEGON, INDONESIA

POSCO, NO.1 BF 2ND REVAMPING,


EPC 6,000 M3 2013
GWANGYANG, KOREA

POSCO, NO.4 BF 2ND REVAMPING,


EPC 5,600 M3 2011
POHANG, KOREA
PROJECT PT.KP, NEW BLAST FURNACE
SAIL-IISCO, BLAST FURNACE,
CAPACITY 3,000,000 T/Y EPC 4,150 M3 2010
BURNPUR, INDIA
INNER VOLUME 3,800 M3
POSCO, NO.4 BF 1ST REVAMPING,
EPC 5,500 M3 2009
LOCATION CILEGON, INDONESIA GWANGYANG, KOREA
PERIOD MAR. 2011 ~ DEC. 2013 ESCO, TAVAZON BLAST FURNACE,
EPC 2,020 M3 2009
WORK SCOPE EPC ESFAHAN, IRAN

Total Solution Provider


IRON MAKING PLANT - BLAST FURNACE
MAJOR PROJECTS
PROJECT SCOPE CAPACITY COMPLETION

POSCO, NO.2 & 3 BF GRANULATION, GWANGYANG, KOREA EPC - 2008

POSCO, NO.3 BF 1ST REVAMPING, GWANGYANG, KOREA EPC 4,600 M3 2007

POSCO, NO.3 BF 2ND REVAMPING, POHANG, KOREA EPC 4,350 M3 2006

POSCO, NO.2 BF 1ST REVAMPING, GWANGYANG, KOREA EPC 4,350 M3 2005

POSCO, NO.1 BF 1ST REVAMPING, GWANGYANG, KOREA EPC 3,820 M3 2002

POSCO, NO. 5 BF, GWANGYANG, KOREA EPC 4,020 M3 1999

POSCO, NO.2 BF 2ND REVAMPING, POHANG, KOREA EPC 2,550 M3 1997

POSCO, NO.4 BF 1ST REVAMPING, POHANG, KOREA EPC 3,000 M3 1994

Total Solution Provider


STEEL MAKING PLANT - BOF
By increasing the annual capacity to 4.65 million tons at MAJOR PROJECTS *) ON-GOING PROJECT
Pohang Steel Works, the compatibility, competitiveness
and the quality of the converter furnace operation was PROJECT SCOPE CAPACITY COMPLETION
enhanced. CSP, SMP BOF, 300 TON/CH
EPC 2015*
PECEM, BRAZIL KR (2)/BOF (2)
POSCO, NO.4 HRM BOF, 280 TON/CH
EPC 2014
GWANGYANG, KOREA BOF(1)
PT.KP, SMP BOF, CILEGON, 300 TON/CH
EPC 2013
KOREA KR(1) / BOF(1)
POSCO, STS BOF, 100 TON/CH
EPC 2013
POHANG, KOREA BOF(2) K-OBM
POSCO, ALLOTHERMAL 100 TON/CH
EPC 2013
CONVERTER, POHANG, KOREA BOF(1) OBM
POSCO, NEW SMP BOF, 330 TON/CH
EPC 2011
POHANG, KOREA KR(2) / BOF(2)
PROJECT POSCO, NEW SMP BOF POSCO, PLATE MILL BOF, 280 TON/CH
EPC 2010
GWANGYANG, KOREA KR(2) / BOF(1)
CAPACITY 330 TON/CH (KR(2), BOF(2), RH(1), LF(2))
POSCO, NO.2 SMP DE-P
LOCATION POHANG, KOREA 280 TON/CH
CONVERTER , GWANGYANG, EPC 2007
KR(3) / BOF(1)
KOREA
PERIOD DEC.2007 ~ MAR 2011
POSCO, NO.2 SMP DE-P
WORK SCOPE EPC EPC BOF(1) 2007
CONVERTER , POHANG, KOREA

Total Solution Provider


STEEL MAKING PLANT - EAF
Specialized in standardized operation with easy MAJOR PROJECTS
maintenance and low project cost, POSCO E&C can
PROJECT SCOPE CAPACITY COMPLETION
provide total solution from process engineering to
commissioning based on experiences in Korea and POSCO SS, SCRAP MINI MILL,
EPC 120 TON/CH 2014
Vietnam. VIETNAM

POSCO STS STEEL MAKING


EPC 065 TON/CH 2012
PLANT, POHANG, KOREA

POSCO SS, EAF OFF-GAS


EPC 100 TON/CH 2009
SYSTEM, CHANGWON, KOREA

ASIA SPECIAL STEEL, MELT SHOP,


EPC 060 TON/CH 2009
JAPAN

POSCO SS, EAF OFF-GAS


EPC 150 TON/CH 2009
SYSTEM, CHANGWON, KOREA

POSCO SS, STS STEEL MAKING


POSCO SPECIALTY STEEL EPC 065 TON/CH 2006
PROJECT PLANT, CHANGWON, KOREA
STEEL MELTSHOP PLANT
POSCO, NO.3 STS SMP,
CAPACITY 447,000 T/Y EPC 090 TON/CH 2003
POHANG, KOREA
LOCATION CHANGWON, KOREA ARAB STEEL, ARCO SPECIAL
EPC 040 TON/CH 2003
STEEL-MILL, EGYPT
PERIOD JUN. 2010 ~ MAR 2013
POSCO, NO. 1 MINI MILL,
WORK SCOPE EPC EPC 130 TON/CH 1996
GWANGYANG, KOREA

Total Solution Provider


STEEL MAKING PLANT - SECONDARY REFINERY
Secondary refining facilities consisting RH and LF
MAJOR PROJECTS *) ON-GOING PROJECT

(Ladle Furnace) in PT.KP Integrated steelworks, PROJECT SCOPE CAPACITY COMPLETION


can refine 300 tons of hot metal per charge respectively.
CSP, SMP RH,LF, 300 TON/CH
EPC 2015*
PECEM, BRAZIL RH (1)/LF (1)

NO.4 HRM RH,LF, 280 TON/CH


EPC 2014
GWANGYANG, KOREA RH (1)/LF (1)

PT.KP, SMP RH,LF, 300 TON/CH


EPC 2013
CILEGON, INDONESIA RH (1)/LF (1)

POSCO, NEW STS VOD(2), 100 TON/CH


EPC 2013
POHANG, KOREA VOD(2)

POSCO,NO.1 SMP RH, LF, 100 TON/CH


EPC 2013
POHANG, KOREA RH(1)/LF(1)

POSCO, NEW SMP RH,LF, 330 TON/CH


EPC 2011
POHANG, KOREA RH (1)/LF (2)
PROJECT PT.KP, STEEL MAKING PLANT
POSCO, PLATE MILL RH, 280 TON/CH
CAPACITY 300 TON/CH EPC 2010
VTD GWANGYANG, KOREA RH (1)/ VTD (1)
LOCATION CILEGON, INDONESIA POSCO, NO.1 SMP RH, 275 TON/CH
EPC 2009
GWANGYANG, KOREA RH(1)
PERIOD 2011.03 ~ 2013.12
POSCO, NO.2 SMP RH, 280 TON/CH
WORK SCOPE EPC EPC 2007
POHANG, KOREA RH(1)

Total Solution Provider


CONTINUOUS CASTING MACHINE - SLAB
POSCO E&C recently designed No.4 Continuous Casting in MAJOR PROJECTS *) ON-GOING PROJECT
Gwangyang steelworks with its accumulated know-how
PROJECT SCOPE CAPACITY COMPLETION
and technology inherited from POSCO.
This, as a result, reduced costs and enabled POSCO E&C CSP, SLAB CASTER,
EPC 3,000,000 T/Y 2015*
to successfully enter into the continuous casting market. PECEM, BRAZIL

NO.4 HRM SLAB CASTER,


EPC 3,400,000 T/Y 2014*
GWANGYANG, KOREA

NO.4 SMP STS SLAB CASTER,


EPC 3,400,000 T/Y 2013
POHANG, KOREA

PT.KP, SLAB CASTER,


EPC 3,000,000 T/Y 2013
CILEGON, INDONESIA

NO.2 SMP SLAB CASTER


MODERNIZATION, EPC 2,800,000 T/Y 2010
POHANG, KOREA
NO.4 HRM SLAB CASTER
PROJECT
(NO.3 SMP IN GWANGYANG STEELWORKS) SMP PLANT SLAB CASTER,
EPC 1,300,000 T/Y 2010
CAPACITY 3,400,000 T/Y POHANG, KOREA

PRODUCT SLAB FOR HR COIL NO.3 SLAB CASTER,


EPC 3,200,000 T/Y 2010
GWANGYANG, KOREA
LOCATION GWANGYANG, KOREA
PERIOD JUN.2011 ~ JUN. 2014 PLATE MILL PLANT SLAB
EPC 3,200,000 T/Y 2009
CASTER, GWANGYANG, KOREA
WORK SCOPE EPC

Total Solution Provider


CONTINUOUS CASTING MACHINE - SLAB
MAJOR PROJECTS
PROJECT SCOPE CAPACITY COMPLETION

POSCO, NO.2,3 CONTINUOUS CASTING MACHINE, GWANGYANG, KOREA EPC 3,500,000 T/Y 2007

POSCO, POSTRIP DEMO PLANT, POHANG, KOREA EPC 00,600,000 T/Y 2006

POSCO, NO.3 CONTINUOUS CASTING MACHINE, GWANGYANG, KOREA EPC 2,500,000 T/Y 2003

POSCO, NO.2 CONTINUOUS CASTING MACHINE REVAMPING,


PC 1,500,000 T/Y 1999
GWANGYANG, KOREA

POSCO, NO.1 CONTINUOUS CASTING MACHINE REVAMPING,


EPC 2,200,000 T/Y 1997
GWANGYANG, KOREA

Total Solution Provider


CONTINUOUS CASTING MACHINE - BLOOM / BILLET
POSCO E&C offers advanced technology for bloom and MAJOR PROJECTS
billet continuous casting machines. Based on
experience and technical expertise we are ready to PROJECT SCOPE CAPACITY COMPLETION
supply to the clients the best bloom & billet caster with
maximized performance, highest operational flexibility NO.2 BILLET CASTER
and lowest operational and maintenance costs. REVAMPING IN NO.1 EPC 0,750,000 T/Y 2013
CONTINUOUS CASTING, POHANG

BLOOM CASTER IN NEW SMP,


EPC 2,400,000 T/Y 2011
POHANG, KOREA

NO.2 BLOOM CASTER


REVAMPING IN NO.1 EPC 1,100,000 T/Y 2008
CONTINUOUS CASTING, POHANG

PROJECT NEW SMP BLOOM CASTER


NO.1 BLOOM CASTER
CAPACITY 2,400,000 T/Y REVAMPING IN NO.3 EPC 0,800,000 T/Y 2002
CONTINUOUS CASTING, POHANG
PRODUCT BLOOM : 400 X 500MM
LOCATION POHANG, KOREA
PERIOD JAN.2008 ~ MAR.2011 NO.1 BLOOM CASTER IN NO.1
EPC 0,800,000 T/Y 2002
CONTINUOUS CASTING, POHANG
WORK SCOPE EPC

Total Solution Provider


HOT ROLLING MILL - HOT COIL
POSCO E&C demonstrates its own technology by
MAJOR PROJECTS *) ON-GOING PROJECT

performing No.4 HRM project with capacity of 3.3 PROJECT SCOPE CAPACITY COMPLETION
million tons per annum including Roughing Mill and 4
Hi-7stands work roll shifting type Finishing Mill.
CSS, NO.1 HRM, BRAZIL EPC 800,000 T/Y 2017*

FORMOSA NO.1 HRM,


C 5,300,000 T/Y 2015*
HA TINH, VIETNAM

POSCO, NO.4 HRM.


EPC 3,300,000 T/Y 2014*
GWANGYANG, KOREA

ZPSS, STAINLESS STECKEL MILL,


EP 800,000 T/Y 2006
CHINA

PROJECT POSCO-NO.4 HRM


POSCO, NO.2 HRM
CAPACITY 3,300,000 T/Y EPC 4,700,000 T/Y 2005
REVAMPING, POHANG, KOREA
THICKNESS : 1.2 MM ~ 25.4 MM
PRODUCT
WIDTH : 700 MM ~ 1950 MM POSCO, NO.3 HRM
EPC 1,674,000 T/Y 2003
REVAMPING, POHANG, KOREA
LOCATION GWANGYANG, KOREA
PERIOD DEC. 2010 ~ JUL. 2014
POSCO, NO.3 STS HRM,
EPC 1,674,000 T/Y 2003
WORK SCOPE EPC POHANG, KOREA

Total Solution Provider


HOT ROLLING MILL - HOT COIL
MAJOR PROJECTS
PROJECT SCOPE CAPACITY COMPLETION

POSCO NO.1 HRM (COIL CONVEYOR), GWANGYANG, KOREA EPC - 2009

POSCO NO.1 HRM (DOWN COILER), GWANGYANG, KOREA EPC - 2009

POSCO NO.1 HRM REVAMPING, POHANG, KOREA EPC 3,240,000 T/Y 2003

POSCO NO.2 HRM REVAMPING, GWANGYANG, KOREA EPC 4,050,000 T/Y 2001

POSCO NO.1 HRM REVAMPING, POHANG, KOREA EPC 2,640,000 T/Y 2000

POSCO NO.1 HRM REVAMPING, GWANGYANG, KOREA EPC 4,800,000 T/Y 1999

POSCO NO.1 HRM REVAMPING, POHANG, KOREA EPC 2,400,000 T/Y 1997

Total Solution Provider


HOT ROLLING MILL - PLATE
PT. KP Plate Mill project with capacity of 1.5 million
MAJOR PROJECTS *) ON-GOING PROJECT

tons per annum comprised with 4 Hi-1 stands work roll PROJECT SCOPE CAPACITY COMPLETION
type Finishing Mill. Accelerated cooling and heat
treatment are core technologies applied to the plate PT.KP, PLATE MILL
EPC 1,500,000 T/Y 2013
mills engineered by POSCO E&C. CILEGON, INDONESIA

POSCO NO.1 PLATE MILL,


EPC 2,000,000 T/Y 2010
GWANGYANG, KOREA

POSCO NO.2 PLATE MILL,


EPC 1,800,000 T/Y 2005
REVAMPING, POHANG, KOREA

POSCO NO.3 PLATE MILL


EPC 1,674,000 T/Y 2003
REVAMPING, POHANG, KOREA

PROJECT PT.KP - PLATE MILL POSCO NO.2 PLATE MILL


EPC 1,674,000 T/Y 2001
CAPACITY 1,500,000 T/Y REVAMPING, POHANG, KOREA
THICKNESS : 6MM ~ 120MM
PRODUCT
WIDTH : 1,250MM ~ 4,500MM POSCO NO.3 PLATE MILL,
EPC 2,400,000 T/Y 1997
POHANG, KOREA
LOCATION CILEGON, INDONESIA
PERIOD JUL. 2011 ~ DEC. 2013
POSCO NO.1 PLATE MILL
EPC 1,674,000 T/Y 1996
WORK SCOPE EPC REVAMPING, POHANG, KOREA

Total Solution Provider


HOT ROLLING MILL - LONG PRODUCTS
POSCO E&C offers a single window solution from MAJOR PROJECTS
planning, engineering, procurement, construction,
PROJECT SCOPE CAPACITY COMPLETION
operation & maintenance of Mini-Mill process
consisting of EAF, casting machine and rolling mills POSCO NO.4 WIRE-ROD
keeping the project cost under budget while fulfilling EPC 700,000 T/Y 2013
MILL, POHANG, KOREA
the objectives of the project under secured and
environment friendly surroundings. POSCO NO.1 WIRE-ROD
MILL REVAMPING, POHANG, EPC 680,000 T/Y 2006
KOREA
BAR & WIRE-ROD MILL,
ARAB SPECIAL STEEL/SADAT EP 140,000 T/Y 2003
CITY, EGYPT
NO.3 WIRE-ROD MILL
(REVAMPING), EPC 820,000 T/Y 2002
POSCO/POHANG, KOREA
BAR & WIRE-ROD MILL,
EPC 200,000 T/Y 1995
VPS/HAIPHONG, VIETNAM
PROJECT POSCO NO.4 WIRE-ROD MILL
BAR & WIRE-ROD MILL,
CAPACITY 700,000 T/Y DAEKYOUNG/POHANG, EC 200,000 T/Y 1994
PRODUCT WIRE ROD KOREA

LOCATION POHANG, KOREA


HYUNDAI STEEL BAR &
PERIOD JUL. 2011 ~ MAY. 2013 SELECTION MILL, POHANG, EC 700,000 T/Y 1990
WORK SCOPE EPC KOREA

Total Solution Provider


PROCESS LINE - PICKLING LINE
POSCO E&C demonstrates its own technology by MAJOR PROJECTS *) ON-GOING PROJECT
performing POSCO-ASSAN TST STS CAPL project with PROJECT SCOPE CAPACITY COMPLETION
capacity of 300 thousand tons per annum including high
speed jet pickling technology reaching 120 mpm. POSCO NO.1 STAINLESS
HAPL, POHANG, KOREA EPC 600,000 T/Y 2014*
(REVAMPING)

POSCO NO.1 STAINLESS


CAPL, POHANG, KOREA EPC 175,000 T/Y 2014*
(REVAMPING)
POSCO-ASSAN TST,
STAINLESS CAPL, IZMIT, EP 300,000 T/Y 2013
TURKEY

POSCO VST, STAINLESS


EP 220,000 T/Y 2012
CAPL, HOCHIMIN, VIETNAM

PROJECT POSCO-ASSAN TST STS CAPL POSCO, STAINLESS CAPL,


EPC 400,000 T/Y 2009
CAPACITY 300,000 T/Y POHANG, KOREA

PRODUCT STAINLESS COLD COIL ZPSS, STAINLESS HAPL,


EPCM 695,000 T/Y 2006
LOCATION IZMIT, TURKEY ZHANGJIAGANG, CHINA
PERIOD SEP. 2011 ~ JUL. 2013
POSCO NO.3 STAINLESS
EPC 474,000 T/Y 2003
WORK SCOPE EP HAPL, POHANG, KOREA

Total Solution Provider


PROCESS LINE - ANNEALING LINE
POSCO E&C capable of providing high quality annealing MAJOR PROJECTS
line facility through it’s home grown technology PROJECT SCOPE CAPACITY COMPLETION
providing energy saving, efficiency , heat balance &
speed map advantages as value addition. POSCO MAHARASHTRA
NO.1 CAL, EPC 1,000,000 T/Y 2014
MAHARASHTRA, INDIA

POSCO-VIETNAM
NO.1 CAL, EPC 700,000 T/Y 2009
VUNGTAO, VIETNAM

POSCO NO.1 CAL


(REVAMPING), EPC 300,000 T/Y 2005
POHANG, KOREA

POSCO NO.2 CAL


(REVAMPING), EPC 300,000 T/Y 2005
PROJECT POSCO MAHARASHTR CAL POHANG, KOREA

CAPACITY 1,000,000 T/Y POSCO NO.3 CAL


PRODUCT ANNEALED COIL COIL (REVAMPING), EPC 1,000,000 T/Y 2003
POHANG, KOREA
LOCATION MAHARASHTRA, INDIA
PERIOD MAY. 2011 ~ FEB. 2014 POSCO NO.1,2 CAL
EPC 1,800,000 T/Y 1997
WORK SCOPE EPC KWANGYANG, KOREA

Total Solution Provider


PROCESS LINE - COLD ROLLING MILL
Successful experience from Cold Rolling Mill complex MAJOR PROJECTS *) ON-GOING PROJECT
project in Korea as well as Vietnam and India has PROJECT SCOPE CAPACITY COMPLETION
enhanced the reliability of its stable operation through
POSCO E&C’s optimized engineering. CSS, NO.1 CRM, BRAZIL EPC 600,000 T/Y 2017*

POSCO MAHARASHTRA,
EPC 1,800,000 T/Y 2014*
NO.1 CRM, INDIA

ASSAN TST, STAINLESS


EP 300,000 T/Y 2013
ZRM, TURKEY

POSCO VST,
EPC 100,000 T/Y 2012
STS CRM, VIETNAM

POSCO VIETNAM CRM,


EPC 1,200,000 T/Y 2009
VIETNAM

QPSS, STAINLESS ZRM,


EPCM 150,000 T/Y 2004
PROJECT POSCO MAHARASHTRA-NO.1 CRM QINGDAO, CHINA
CAPACITY 1,800,000 T/Y NO.2 STAINLESS ZRM,
PRODUCT COLD ROLLED PRODUCTS ZPSS ZHANGJIAGANG, EPCM 140,000 T/Y 2003
CHINA
LOCATION MAHARASHTRA, INDIA
PERIOD MAY. 2011 ~ JUN. 2014 POSCO NO.2 CRM
(CAL,CAL REVAMPING), EP 1,225,000 T/Y 2003
WORK SCOPE EPC POHANG, KOREA

Total Solution Provider


PROCESS LINE - COLD ROLLING MILL
MAJOR PROJECTS
PROJECT SCOPE CAPACITY COMPLETION

ZPSS NO.1 STAINLESS CR PLANT, ZHANGJIAGANG, CHINA EPCM 140,000 T/Y 1999

POSCO NO.1 CR MILL (REVAMPING), POHANG, KOREA EPC 1,100,000 T/Y 1999

POSCO NO.2 CR MILL (POL), GWANGYANG, KOREA EPC 500,000 T/Y 1997

POSCO NO.4 CR MILL, GWANGYANG, KOREA EPC 1,800,000 T/Y 1997

Total Solution Provider


PROCESS LINE - GALVANIZING LINE
Our history of galvanizing in POSCO group and abroad, MAJOR PROJECTS
more than 20 hot dip galvanizing lines are operational PROJECT SCOPE CAPACITY COMPLETION
throughout the world with satisfied customers
successfully producing galvanized sheets, galvanneal POSCO NO.2 CGL,
EPC 500,000 T/Y 2013
sheets, 55%Al-Zn coated sheets and 90%Al coated sheets. ALTAMIRA, MEXICO

POSCO CGL,
EPC 450,000 T/Y 2012
GUANGDONG, CHINA

POSCO CGL,
EPC 450,000 T/Y 2012
MAHARASHTRA, INDIA

UNION STEEL, NO.5 CGL,


EP 370,000 T/Y 2009
BUSAN, KOREA

PROSPERITY PGL,
EP 500,000 T/Y 2009
KAOSHIUNG, TAIWAN
PROJECT POSCO MAHARASHTRA CGL
POSCO NO.2 CGL REVAMPING,
EPC 430,000 T/Y 2008
CAPACITY 450,000 T/Y GWANGYANG, KOREA
PRODUCT EXTERIOR PANEL OF HIGH END AUTOMOBILES
POSCO NO.6 CGL,
LOCATION MAHARASHTRA, INDIA EPC 400,000 T/Y 2006
GWANGYANG, KOREA
PERIOD JAN. 2010 ~ MAY. 2012
POSCO NO.1 CGL REVAMPING
WORK SCOPE EPC EPC 300,000 T/Y 2006
GWANGYANG, KOREA

Total Solution Provider


PROCESS LINE - GALVANIZING LINE
MAJOR PROJECTS
PROJECT SCOPE CAPACITY COMPLETION

GENERAL TRADE CGL, THAI BINH, VIETNAM EP 30,000 T/Y 2005

POSCO NO.5 CGL, GWANGYANG, KOREA EPC 450,000 T/Y 2005

PROSPERITY CGL, KAOSHIUNG, TAIWAN EP 200,000 T/Y 2005


250,000 T/Y
SINO LEADING NO.1&2 CGL, CHANGSHU, CHINA EP 2005
X 2 LINES
POSCO NO.2 CGL, POHANG, KOREA EPC 300,000 T/Y 2004

KISCO CGL, KUNMING, CHINA EP 150,000 T/Y 2004

NAKISCO CGL, HOCHIMINH, VIETNAM EP 30,000 T/Y 2004

PCCS CGL (REVAMPING), DALIAN, CHINA EP 150,000 T/Y 2004

POSCO PGL (REVAMPING), GWANGYANG, KOREA EPC 580,000 T/Y 2002

POSCO NO.1 CGL (REVAMPING), POHANG, KOREA EPC 200,000 T/Y 2000

POSCO NO.4 CGL, GWANGYANG, KOREA EPC 450,000 T/Y 2000

MPSC CGL, YANGON, MYANMAR EP 30,000 T/Y 1998

ZPSS CGL, ZHANGJIAGANG, CHINA EPCM 100,000 T/Y 1998

DONGKUK HGL, POHANG, KOREA EP 150,000 T/Y 1997

Total Solution Provider


PROCESS LINE - COLOR COATING LINE
POSCO E&C has rich technology and experiences on MAJOR PROJECTS
CCL, propose to provide highly efficient equipment and PROJECT SCOPE CAPACITY COMPLETION
services including design, manufacturing, supply and
test run. We can give you increasing of productivity by ASSAN GALVANIZ, CCL,
EP 120,000 T/Y 2014
eliminating time loss. ISTANBUL, TURKEY

PROSPERITY CCL, TAIWAN EP 200,000 T/Y 2009

HADEED CCL, KSA EPC 120,000 T/Y 2007

GENERAL TRADE CCL,


EP 50,000 T/Y 2005
VIETNAM

POSCO C&C NO.2 CCL


EPC 150,000 T/Y 2005
REVAMPING, KOREA

HANDAN NO.1, 2 CCL, 100,000 T/Y


PROJECT ASSAN COLOR COATING LINE EP 2005
CHINA X 2 LINE
CAPACITY 120,000 T/Y
KISCO CCL, CHINA EP 100,000 T/Y 2004
PRODUCT PCM (PRE-COATED METAL)
LOCATION TURKEY
NAKISCO CCL, VIETNAM EP 20,000 T/Y 2004
PERIOD DEC. 2009 ~ MAY. 2013
WORK SCOPE EP
PCCS NO.2 CCL, CHINA EP 100,000 T/Y 2003

Total Solution Provider


PROCESS LINE - COLOR COATING LINE
MAJOR PROJECTS
PROJECT SCOPE CAPACITY COMPLETION

NO: 100,000 T/Y


SHUNPO MULTI COATING LINE, SHUNDE, CHINA EP 2003
COLOR: 50,000 T/Y

POSVINA CCL, HOCHIMINH, VIETNAM EP 22,000 T/Y 2002

HAIER CCL, CHINA EP 70,000 T/Y 2001

POSCO C&C NO.1 CCL REVAMPING, POHANG, KOREA EPCM 100,000 T/Y 1999

PCCS NO.1 CCL, DALIAN, CHINA EPCM 50,000 T/Y 1998

Total Solution Provider


PROCESS LINE - ELECTRICAL STEEL LINE
POSCO E&C, having rich technology and experiences on MAJOR PROJECTS
ESL, propose to provide highly efficient equipment and
PROJECT SCOPE CAPACITY COMPLETION
services including design, manufacturing, supply and
test run. We can help you achieve higher productivity POSCO MAHARASHTRA
by eliminating time loss. ACL, EPC 300,000 T/Y 2013
MAHARASHTRA, INDIA
SHUNPO ACL,
EPC 1,500,000 T/Y 2010
SHUNDE, CHINA
POSCO NO.3 HCL,
EPC 850,000 T/Y 2009
POHANG, KOREA
POSCO NO.3 DCNL,
EPC 900,000 T/Y 2009
POHANG, KOREA
POSCO NO.3 COF,
EPC 1,000,000 T/Y 2009
POHANG, KOREA
POSCO NO.3 APL
PROJECT POSCO MAHARASHTRA ACL EPC 3,690,000 T/Y 2009
POHANG, KOREA
CAPACITY 300,000 T/Y
POSCO NO.2 COF
EPC 820,000 T/Y 2006
NO POHANG, KOREA
PRODUCT THICKNESS : 0.35MM ~ 0.70MM POSCO NO.2 HCL
WIDTH : 900MM ~ 1,280MM (REVAMPING), EPC 1,640,000 T/Y 2006
LOCATION MAHARASHTRA, INDIA POHANG, KOREA
PERIOD MAY. 2011 ~ AUG. 2013 POSCO NO.3 ACL
(REVAMPING) EPC 3,430,000 T/Y 2006
WORK SCOPE EP POHANG, KOREA

Total Solution Provider


PROCESS LINE - ELECTRICAL STEEL LINE
MAJOR PROJECTS
PROJECT SCOPE CAPACITY COMPLETION

POSCO, NO.2 DCNL REVAMPING, POHANG, KOREA EPC 18,000 T/Y 2006

POSCO, APL, POHANG, KOREA EPC 341,000 T/Y 2005

POSCO, NO.1 COF, POHANG, KOREA EPC 82,000 T/Y 2004

POSCO, NO.1 ETL REVAMPING, POHANG, KOREA EPC 250,000 T/Y 2002

POSCO, NO.2 ACL, POHANG, KOREA EPC 220,000 T/Y 1998

Total Solution Provider


NEW TECHNOLOGIES - FINEX & CEM
FINEX® (FINE ORE REDUCTION PROCESS)
FLUIDIZING FINEX, one of the most successful alternative iron-
BED REACTOR FINE ORE MELTING making technologies jointly developed with
NON-COKING
COAL FURNACE SIEMENS-VAI, is based on the direct use of ore fines
and non-coking coal. The key technologies of FINEX
are fluidized bed reduction of ore fines, hot DRI
fines compaction to HCI(Hot Compacted Iron),
COAL briquetting of coal fines, and melting of HCI into hot
BRIQUETTE metal. POSCO has been operating the world’s first
HCI commercial FINEX plant, with 1.5 MT of annual
MOLTEN
IRON capacity, since April 2007 and has added up a new
2.0 MT in January 2014.
No.3 FINEX Plant

CEM (COMPACT ENDLESS CASTING AND ROLLING MILL)


HIGH SPEED CASTING ENDLESS ROLLING LOWERED OPEX & CAPEX
In pursuit of eco-friendly and slim steelworks,
POSCO has developed CEM process, a new down
stream in the plant following successful
development of FINEX®. Large portion among CR
products can be replaced by thin HR products
utilizing the benefits of CEM coming from the direct
linking of the caster to the rolling mill.
Operational records of CEM will demonstrate its
superiority to conventional processes.

Total Solution Provider

Potrebbero piacerti anche