DATE PERFORMANCE/
BASIC COMPETENCIES WEEK NO. OF DAYS
SUMMATIVE TEST
FIRST GRADING
THIRD GRADING
*
* Different types of forms 9 5
FIRST GRADING
NO. OF PERFORMANCE/
COMPETENCIES CODE DATE
HOURS SUMMATIVE TEST
FIRST GRADING
LO1 Prepare electrical materials and tools for the task TLE_IAEI7/8UT-0a-1
* Splicing of wires 10
1
* Making an extension cord 8
LO2 Request appropriate supplies, materials, and tools for a specific job. TLE_IAEI7/8UT-0a-2
* Different types of forms 10
LO3 Receive and inspect electrical supplies, materials, and tools TLE_IAEI7/8MT-0b-3 1
* Receiving and inspecting freight shipments 8
SECOND GRADING
* system of measurement 14 1
Second Summative Test
* Parts of a Multi-Tester 8
1
Third Summative Test
Lesson 3 Interpret Technical Drawings and Plan
THIRD GRADING
* Electrical Plans
20
* Parts of Electrical Plans 1
Second Summative Test
NO. OF
COMPETENCIES WEEK DATE NO. OF SUMMATIVE TEST
HOURS
FOURTH GRADING
* Types and kind of cleaning solvent 10
* Chemical hazards 8
1
* Physical hazards 10
* Biological hazards 10
* Emergency preparedness 6
Fourth Summative Test
FIRST GRADING
TLE_IAEL9EL-IIaIVJ-
1
Lesson 1 INSTALL ELECTRICAL LIGHTING SYSTEMs, AUXILLARY OUTLETS AND LIGHTING FIXTURES
LO1 Layout and install electrical wiring using knob and tube.
1.3 Safety reminders when installing knob and tube wiring. June 8, 2019 2
2.2 Install three bulb controlled by three single pole switch controlled in two different location using June 27 - 28, 2019 4
PVC raceway/molding.
2.2 Install three bulb controlled by three single pole switch controlled in three different location using June 29-30, 2017 4
PVC raceway/molding.
LO3 Layout and install rigid non-metallic conduit.
3.6 Install two bulbs connected in series controlled by one single pole switch and one bulb controlled by
July 19-21, 2017 6
another single pole switch in one location.
3.7 Install two bulbs connected in series controlled by one single pole switch and other two bulbs
July 24-26, 2017 6
controlled by another single pole switch in two locations.
Third Summative Test July 27, 2017 2
4.2 Install two bulbs connected in parallel controlled by one single pole switch and one bulb controlled
by another single pole switch in one location. Aug. 1-3, 2017 6
4.3 Install two bulbs connected in series controlled by one single pole switch and other two bulb
connected in parallel controlled by another single pole switch in two locations. Aug. 4-8, 2017 6
SECOND GRADING
CON724312
LO5 Assemble flourescent lighting fixtures
4
5.1 Types of Fluorescent lighting fixtures Aug. 14-15, 2017
4
5.2 Parts and functions of fluorescent lamp Aug. 16-17, 2017
8
5.3 Assembling open type 20 watts fluorescent lamp Aug. 18 & 24, 2017
8
5.4 Assembling of 40 watts box type fluorescent lamp. Aug. 25-31, 2017
2
First Summative Test Sept. 1, 2017
6.2 Install 3-Fluorescent lamp controlled by 3-SPST in one location with three gang convenience outlet.
(Safety Switch - line to ground connection) Sept. 7-11, 2017 6
6.3 Install 2-flourescent lamps controlled by two SPSTswitch in two locations using flexible non-metallic Sept. 12-14, 2017 6
conduit with two 3-gang outlet. (Circuit Breaker - line to line connection )
6.4 Install 3-flourescent lamps controlled by 3-SPST switch in two locations with two 3gang outlet. (CB -
Sept. 15-19, 2017 6
line to line connection)
6.5 Install 3-flourescent lamps controlled by 3-SPST in three locations with two 3-gang outlet. (Circuit
Sept. 20-22, 2017 6
Breaker - line to line connection)
Second Summative Test Sept. 25, 2017 2
THIRD GRADING
TLE_IAEI10WD-
IIIa-Ivj-1
Lesson 1 INSTALL WIRING DEVICES FOR FLOOR AND GROUND FAULT CURRENT INTERRUPTING OUTLETS
LO1 - Layout and install electrical boxes on wood, metal studs and concrete walls.
2.3 Install incandescent 4-lamps controlled by two 2-SPST two bulb connected in series and the other 2 Nov. 27-29, 2017 6
bulb connected in parallel with 1 convenience outlet (line to line connection)
Second Summative Test Dec. 1, 2017 2
2.7 Install incandescent 4-lamps controlled by two 2-SPST two bulb connected in series and the other 2
bulb connected in parallel with 2 convenience outlet (line to ground connection) Dec. 12-14, 2017 6
3.2 Installation of wiring devices for floor and ground fault current interrupting outlet. Dec. 20, 2017 & Jan. 3, 2018 4
3.3 Layout and install 1 bulb controlled by 2-3way switch Jan. 4-5, 2018 4
3.4 Layout and install 2 bulbs controlled by individual switch and 1 bulb controlled by 2-3way switch in
Jan. 8-9, 2018 4
two locations
Fouth Summative Test Jan. 10, 2018 2
FOURTH GRADING
CON724311
Lesson 1 INSTALL ELECTRICAL PROTECTION SYSTEM FOR LIGHTING AND GROUNDING.
LO1 - Layout and install fuse panel.
1.1 Philippine Electrical Code (PEC) provision for circuit protection (Fuse Panel) Jan. 15-17, 2018 6
1.2 Principles and operation of different type of fuses Jan. 18-22, 2018 6
1.5 Planning and preparing for installing Fuse Panel Feb. 1-5, 2018 6
1.6 Layout and install 2 bulbs controlled by individual SPST switch and 1 bulb controlled by 2-3way
Feb. 6-8, 2018 6
switches in two locations with 1 convenience outlet.
Second Summative Test Feb. 9, 2018 2
2.1 Philippine Electrical Code (PEC) provision for circuit protection. (Panel Board) Feb. 12-14, 2018 6
2.6 Installing wire receptacle circuit to a load center March 2-5, 2018 4
2.7 Load center accessories and their uses March 6-7, 2018 4
2.8 Layout and install 3 bulbs controlled by individual SPST switch and 2 bulbs controlled by 2-3way March 8-12, 2018 6
switches in two locations with 2 convenience outlet (line to line connections)
2.9 Layout and install 3 bulbs controlled by individual SPST switch and 2 bulbs controlled by 2-3way March 13-15, 2018 6
switches in two locations with 2 convenience outlet (line to ground connections)
Fourth Summative Test March 16, 2018 2
Prepared by:
FIRST GRADING
SECOND GRADING
Lesson 1: Performing Roughing-in Activities for Communications and Distribution System m Using Metallic Conduit
* Layout and install one bulb controlled by two three way switch with one convenience outlet using circuit breaker for concealed wiring
August 23-25, 29, 2017
* Layout and install one bulb controlled by two three way switch and one SPST as master switch with one convenience outlet and one
special purpose outlet using circuit breaker for concealed wiring Sept. 4-7, 2017
1.5 Perform Bending Metallic Tubing (Elbow Bend) Sept. 13-14, 2017
1.6 Perform Bending Metallic Tubing (Offset Bend) Sept. 15 & 18, 2017
2.1 PEC Provision on Rigid Metallic Conduit (RMC) Sept. 25, 2017
* Layout and install one bulb controlled by two three way switch and two bulbs controlled by individual single pole switch with one
Sept. 28-29 & Oct. 2, 2017
convenience outlet and special purpose outlet using circuit breaker for concealed wiring
3.3 Draw a wiring Diagram Based on the Given Plan/Working Drawing Oct. 9-10, 2017
4.3 Draw a Wiring Diagram Based on the Given Plan/Working Drawing Oct. 17-18, 2019
THIRD GRADING
1.1 Ohm's Law Statement and Ohm's Law Fromula Nov. 2-3, 2019
2.2 Parallel Circuit and Its Characteistics Nov. 17, 20-21, 2019
2.3 Draw a wiring diagram of 4 bulbs connected in series controlled by two single pole switch
Nov. 22-23, 2019
2.3 Draw a wiring diagram of 4 bulbs connected in parallel controlled by two single pole switch
Nov. 24 & 27, 2019
* Layout and install 1 bulb controlled by two 3-way switch and one 4-way switch in three locations
Jan. 3-4, 2020
* Layout and install 1 bulb controlled by two 3-way switch and one 4-way switch in three locations and other 2
bulbs controlled by individual SPST. Jan. 5, 8-9, 2020
FOURTH GRADING
Lesson 1: Installation of Communication, Signaling Devices and Remote Control Systems on Auxilliary Equipment
1.1 PEC Requirements in Installing Signal and Alarm Jan. 22-23, 2020
1.2 Check Condition of Buzzer, Chime and Bell Jan. 24-25, 2020
1.4 Draw a schematic and wiring diagram of annunciator system Feb. 1-2, 2020
* Testing the continuity in the circuit and reading of voltage Feb. 13-16, 2020
* Layout and install 1 bulb controlled by two 3-way switch and two 4-way switch in four locations and other 2
bulbs controlled by individual SPST. Feb. 21-23, 2020
Second Summative Test Feb. 27, 2020
4.3 Direct Online Control and Power Circuit March 6-7, 2020
Checked by:
Republic of the Philippines
Region IX, Zamboanga Peninsula
Department of Education
Division of Zamboanga del Sur
Toribio Minor National High School
Margos sa tubig Zamboanga del sur
BUDGET OF WORK IN ELECTRICAL INSTALLATION AND MAINTENANCE - GRADE 12
CONTENT CONTENT STANDARDS PERFORMANCE STANDARDS LEARNING COMPETENCIES NO. of HOURS ACTUAL DATE
Electrical tools, equipment and materials for specific job order The learner demonstrates an understanding The learner independently demonstrates the 2.1 Select appropriate electrical tools, June 5-6,2017
of the basic concepts and underlying theories common competencies in electrical equipment and materials for specific tasks.
Different types of wiring methods approved in the Philippine condition in electrical installation and maintenance. installation and maintenance as prescribed 2.2 Apply suitable wiring method for the job. June 7-8, 2017
Open wiring on insulator by TESDA Training Regulations. 2.3 Install electrical wiring systems using June 12-13, 2017
different types of wiring methods:
Concealed wiring installation Non-metallic sheathed cable June 14-15, 2017
2.3.1 Circuit with one bulb controlled by
Flexible conduit (metal & non-metal) surface or flush type single pole switch June 19-20, 2017
2.3.2 Circuit using two 3-way switches in
Surface raceway (metal & non-metal) two locations June 21-22, 2017
2.3.3 Circuit using 3-way and 4way
switches in 3 locations
2.3.4 Combination of lighting and
convenience outlets
Circuit with one bulb controlled by surface or flush type single pole switch June 27-July 4, 2017
Circuit with two 3-way and one 4-way switches July 13-20, 2017
The learner demonstrates an understanding the learner independently performs proper 1.1 Test wiring installations for defects such
Testing Wiring Installation for possible circuit defects; (Open/Loose wiring of the concepts and underlying principles in maintenance of electrical tools and as:
connections) the maintenance of electrical tools and equipment and troubleshooting based on 1.1.1. Open/Loose Circuit August 14, 2017
Testing Wiring Installation for possible circuit defects; (Short Circuit) equipment and troubleshooting work industry standards. 1.1.2. Short Circuit August 15, 2017
Testing Wiring Installation for possible circuit defects; (Grounded Circuit) 1.1.3. Grounded Circuit August 16, 2017
Install Wiring System for EIM NC II Assessment LO2. Maintain electrical System. August 28-31, 2017
2.1 Check wiring installations periodically 2.2
Connect Wiring system for EIM NC II Assessment September 4-7, 2017
perform Housekeeping
LO3. Troubleshoot Defects of an Electrical September 11-14,
Troubleshoot Wiring System Using Multitester System 8 201
3.1 Identify Defects of an electrical system
Perform Housekeeping 3.2 Repair Defects of an electrical System September 18, 2017
Industry Immersion Open Date