CONTRACT NO

PETROJET

Dahshour /Abo El-Gharadig 24''/262.5 KM Gas PL REV 0


DOC NO. PTJ-KPC-DA-030-PROC
OPEN CUT CROSSING PROCEDURE DATE 22/10/2012

INSPECTION AND TEST PLAN


OPEN CUT CROSSING PROCEDURE
Document No. PTJ-KPC-DA-030-PROC
Sl. Character Responsible Acceptance Verifying
Activities PTJ KPC
No. to be Checked Person Criteria Document
Procedure approval and Road
Document Review QC Inspector Approved procedure
revision status Crossing Procedure
1 R R
QA Engineer

Installation of Road Signs, Const. Supervisor Proposed diversion of road to ensure safe
Diversion Road Approved by KPC
2 Diversions boards HSE Advisor passage of vechicles W S

Dimensions, Levels as per


Setting of Reference Const. Supervisor EXCAVATION / FILLS /
AFC Drawings
BACK FILLS -
Approved procedure
3 line and excavation CIVIL QC Inspector INSPECTION REPORT W S

Material size and type, Minimum padding layer thickness 150mm


Pre padding Const. Supervisor EXCAVATION / FILLS /
free from sharp edges in QC Inspector shall inspect and record
4 trench, levels BACK FILLS - H W
CIVILQC Inspector INSPECTION REPORT

Post padding Material size and type, Const. Supervisor 1000mm sand padding from crown of pipe
EXCAVATION / FILLS /
5 free from sharp edges in CIVIL QC Inspector no pipes shall be left over night in trench BACK FILLS - H W
INSPECTION REPORT
trench, levels without post padding covering the pipe.

Legend: H = Hold Point, R = Review, W = Witness, S = Surveillance / Monitor


PETROJET

Dahshour /Abo El-Gharadig 24''/262.5 KM Gas PL REV 0


DOC NO. PTJ-KPC-DA-030-PROC
OPEN CUT CROSSING PROCEDURE DATE 22/10/2012

INSPECTION AND TEST PLAN


OPEN CUT CROSSING PROCEDURE
Document No. PTJ-KPC-DA-030-PROC
Sl. Character Responsible Acceptance Verifying
Activities PTJ KPC
No. to be Checked Person Criteria Document
Backfilling & Thickness of layer & Filling thickness shall not be more than Lab Test Report
Const. Supervisor
compaction and compaction and dimantion 300mm in each layer, Degree of filling
concrete slabs of concrete slab material compaction shall be 95% of max.
CIVIL QC Inspector EXCAVATION / FILLS /
dry density of AASHTO compaction test
BACK FILLS -
controling authority
INSPECTION REPORT
Low density polystyrene foam (50mm thickness) shall
6 be laid below concrete slabs H W

Identification pre-cast concrete slabs (1000mm wide *


min 300mm THK) shall be placed on top of the pipe
crossing, Final layer of granular road base compacted to
min 95% MDD
Road Reinstatement Road top level Const. Supervisor Road must be remade to the same
7 W S
CIVIL QC Inspector standard as existing

Prepared by: Approved by :

Petrojet KPC
QC Engineer Ref. Indicator

Legend: H = Hold Point, R = Review, W = Witness, S = Surveillance / Monitor