Sei sulla pagina 1di 2

CONTRACT NO

PETROJET

Dahshour /Abo El-Gharadig 24''/262.5 KM Gas PL REV 0


DOC NO. PTJ-KPC-DA-019-PROC
Concrete work procedure DATE 22/10/2012

INSPECTION AND TEST PLAN


Concrete work procedure
Document No.PTJ-KPC-DA-019-PROC
Sl. Character Responsible Acceptance Verifying
Activities PTJ KPC
No. to be Checked Person Criteria Document

Approved procedure & Approved for construction Work procedure for


1 Document review Procedure approval QC CiviI Inspector ,QA Engineer R R
drawings concreteing work

Material
Material mill certificates
2 selection,approval&review QC CiviI Inspector ,QA Engineer As per AFC drawing. Sample approval report H W
and test certificates
of test certificates

1-CONCRETE POURING
the testing results of
REPORT 2-
3 Mix design and trial mixes concrete strength to be CIVIL QC Inspector As per AFC drawing. H W
COMPRESSION TEST ON
checked
CONCRETE CUBES

Legend: H = Hold Point, R = Review, W = Witness, S = Surveillance / Monitor


CONTRACT NO
PETROJET

Dahshour /Abo El-Gharadig 24''/262.5 KM Gas PL REV 0


DOC NO.PTJ-KPC-DA-019-PROC
Concrete work procedure DATE 22/10/2012

INSPECTION AND TEST PLAN


Concrete work procedure
Document No.PTJ-KPC-DA-019-PROC
Sl. Character Responsible Acceptance Verifying
Activities PTJ KPC
No. to be Checked Person Criteria Document

1- All formwork shall be made from clean marine


waterproof plywood with white wood used for the frame of
formworks.
2- Formwork shall be sufficiently tight to prevent leakage
of cement slurry while concreting.
3- Form work will be adequately propped, braced and tied
Dimentions,tightness,
in position to ensure that it retains its shape and position INSPECTION RECORD
4 Formwork and spacers location,orientation and QC Civil inspector H S
before, during and after concreting. FOR CONCRETE WORKS
cleaness 4- Formwork will remain in place until the concrete has
hardened sufficiently to resist damages from the removal
operation which in this case in a minimum of 24 hours after
placing of concrete.
5- as per requirments of project specs and approved
procedure

1- Fabrication & Deformation of steel will be done at


Reinforcement steel fabrication shop at site or at external
factories approved by KPC.
2- Assembled reinforcement will be erected manually or
Steel reinforcement wire wire mesh type , cover , INSPECTION RECORD
5 QC Civil inspector using crane / suitable lifting equipment (If necessary). H S
mesh lap distance and fixation. 3- The spacer blocks will be prepared near Reinforcement
FOR CONCRETE WORKS
yard at site and casted from the same mix as the
surrounding concrete.

1- INSPECTION RECORD
Inspection prior to concrete Formwork , reinforcement FOR CONCRETE WORKS
6 QC Civil inspector approved for construction work procedure 2- POST – POUR H W
pouring and spacers final check
INSPECTION RECORD FORM

Concrete will be placed as nearly as practicable to its final


position and care taken to avoid segregation of concrete,
concrete pouring & displacement of reinforcement, formwork or embedded CONCRETE POURING
7 Concrete QC Civil inspector Items, maxi free fall for concrete shall not exceed 1.5m.
H W
compaction and curing REPORT
Temperature of concrete at the time of placement shall be
measured and recorded each pour card.

1-COMPRESSION TEST ON
CONCRETE CUBES 2-
8 Concrete test Tests for concrete QC Civil inspector AFC drawing. H S
CONCRETE POURING
REPORT

Prepared by: Approved by :

Petrojet KPC
QC Engineer Ref. Indicator

Legend: H = Hold Point, R = Review, W = Witness, S = Surveillance / Monitor

Potrebbero piacerti anche