Sei sulla pagina 1di 3

[03.

1] SECRETARY OF THE DERPARTMENT OF PUBLIC WORKS AND 1940 without the owners’ consent and without the necessary expropriation
HIGHWAYS v SPS. TECSON proceedings and used for the construction of the MacArthur Highway.
G.R. No. 179334 | July 1, 2013 | Justice Peralta | Freya Patron  In a letter, Sps. Tecson demanded the payment of the FMV of the land.
Contreras, then District Engineer of the First Bulacan Engineering District of
PETITIONERS: Secretary of the Department of Public Works and Highways and DPWH, offered to pay the land at P0.70/sq. m. per Resolution of the
District Engineer Celestino Contreras Provincial Appraisal Committee of Bulacan. Unsatisfied with the offer,
RESPONDENTS: Sps. Heracleo and Ramona Tecson respondents demanded for the return of their property or the payment of
compensation at the current FMV.
TOPIC: Eminent Domain  Their demand remained unheeded. Respondents filed a Complaint for
recovery of possession with damages against petitioners, praying that they
CASE SUMMARY: Sps. Tecson are co-owners of a parcel of land in Maloloas, be restored to the possession of the land + attorney’s fees. Respondents
Bulacan. This was among the properties taken by the government sometime in claimed that the land was assessed at P2,543,800.
1940 without the owners’ consent and without the necessary expropriation  Instead of filing their Answer, petitioners moved for the dismissal of the
proceedings and used for the construction of the MacArthur Highway. The complaint on the ff. grounds:
spouses demanded payment of the FMV of the land, but was offered another o The suit is against the State which may not be sued without its consent
amount which the spouses did not approve of. Their demand went unheeded, so o The case has already prescribed
they filed a complaint for recovery of possession with damages against o Respondents have no COA for failure to exhaust administrative
petitioners. Instead of filing an answer, they moved for dismissal of the complaint. remedies
Among the grounds is prescription. The amount of the compensation owed them o Respondents are entitled to compensation. They should be paid only the
was also disputed. value of the property in 1940 or 1941.
The Court held that the issues of prescription and laches are not proper issues  The RTC issued an Order granting respondents’ MTD based on the doctrine
for resolution because they were not part of the pre-trial brief. But even if they of state immunity from suit. Upon appeal to the CA, the CA found that the
were, the action would still not barred because where private property is taken for doctrine did not apply because the recovery of compensation is the only
public use without first acquiring title thereto either through expropriation or relief available to the landowner. Contreras also earlier offered the payment
negotiated sale, the owner’s action to recover the land or the value does not of compensation to which respondents are entitled to recover for the
prescribe. As to the issue on just compensation, the Court held that it should be government. The decision became final and trial proceeded in the RTC.
fixed at the time of the actual taking by the government. Therefore, the just  The Branch COC was initially appointed as the Commissioner and
compensation should be based on the value in 1940. Even if the amount is little designated as the Chairman of the Committee that would determine just
compared to the value at present, that is what the rule says. Nevertheless, they compensation, but the case was referred to the Provincial Appraisal
are entitled to damages since their property was taken without the benefit of Committee (PAC). The PAC recommended the amount of P1,500 per sq.m
expropriation proceedings. as just compensation.
 RTC rendered a Decision – DPWH directed to pay P1,500/sq.m.
DOCTRINE: Just compensation is “the fair value of the property as between  On appeal, CA affirmed with modification that the just compensation stated
one who receives, and one who desires to sell, x x x fixed at the time of the should earn 6% interest from filing of action until full payment. In its appeal
actual taking by the government.” This rule holds true when the property is before the CA, petitioners raised the issues of prescription and laches, but
taken before the filing of an expropriation suit, and even if it is the property CA brushed these issues aside.
owner who brings the action for compensation.
 Before the SC, the petitioners insist that the action is barred by prescription
since it had been filed 54 years after the accrual of the action in 1940. They
FACTS:
also allege that just compensation should be based on the value of the
 Spouses Tecson are co-owners of a parcel of land with an area of 7,268 sq. property at the time of taking in 1940 and not at the time of payment.
m. located in San Pablo, Malolos, Bulacan and covered by TCT. The parcel
of land was among the properties taken by the government sometime in
ISSUE and RULING: WON the action is barred by prescription or laches. is taken before the filing of an expropriation suit, and even if it is the property
(NO) owner who brings the action for compensation.
 The case stemmed from an action for recovery of possession with damages  The RTC and CA found that the FMV of the property in 1940 was P0.70/sq.m.
filed by respondents against petitioners. But it revolves around the taking of Therefore it should be used in determining the amount due respondents
the lot by petitioners for the construction of the MacArthur Highway. There is instead of the higher value which is P1,500. While disparity in the amounts is
taking when the expropriator enters private property not only for a momentary obvious and may appear inequitable to respondents as they would be
period but for a permanent duration, or for the purpose of devoting the receiving such outdated valuation after a very long period. It is equally true
property to public use in such a manner as to oust the owner and deprive him that they are also remiss in guarding against the cruel effects of belated claim.
of all beneficial employment thereof. The concept of just compensation DOES NOT imply fairness to the
 The property was taken by petitioners without the benefit of expropriation property owner alone. Compensation must be just not only to the
proceedings for the construction of the MacArthur Highway. After the lapse of property owner, but also to the public which ultimately bears the cost of
more than 50 years, the property owners sought recovery of possession of expropriation.
their property.  Petitioners had been occupying the property for more than 50 years without
 But the issues of prescription and laches are NOT proper issues for resolution the benefit of expropriation proceedings. In taking respondents’ property
because they were not included in the pre-trial order. However, even if these without the benefit of expropriation proceedings and without payment of just
issues were dealt with, they will still fail. Laches is principally a doctrine of compensation, petitioners acted in disregard of respondents’ proprietary rights
equity which is applied to avoid recognizing a right when to do so would result which cannot be allowed by the Court. For this they are entitled to
in a clearly inequitable situation or an injustice. There is nothing inequitable compensation in the form of actual/compensatory damages (6% on value of
in giving due course to respondents’ claim. Both equity and law direct land at the time of taking in 1940 until full payment).
that a property owner should be compensated if his property is taken for
public use. Neither shall prescription bar respondents’ claim following DISPOSITIVE: WHEREFORE, the petition is PARTIALLY GRANTED. The CA
the long-standing rule “that where private property is taken by the Decision is MODIFIED, in that the valuation of the subject property owned
Government for public use without first acquiring title thereto either by respondents shall be P0.70 instead of P1,500 per sq.m. with interest at
through expropriation or negotiated sale, the owner’s action to recover 6% per annum from date of taking in 1940 instead of March 17, 1995 until
the land or the value thereof does not prescribe” full payment.

WON the just compensation should be fixed at the time of the actual taking DISSENTING AND CONCURRING OPINION – JUSTICE VELASCO
by the government. (YES)  Expropriation is an exercise of the government’s power of eminent domain. As
 When a property is taken by the government for public use, jurisprudence an inherent attribute of the government, this power is fundamentally limitless if
provides for the remedies available to a landowner. The owner may recover not restrained by the Bill of Rights. Without the limitations thus imposed, the
his property if its return is feasible or, if it is not, the aggrieved owner may exercise of the power of eminent domain can become repressive. Thus, the
demand payment of just compensation for the land taken. For failure of Bill of Rights should always be a measure and guarantee of protecting certain
respondents to question the lack of expropriation proceedings for a long areas of a person’s life, liberty, and property against the government’s abuse
period of time, they are deemed to have waived and are estopped form of power.
assailing the power of the government to expropriate or the public use for  In the instant case, it is not disputed that DPWH illegally took the subject lot
which the power was exercised. What is left to respondents is the right of without the consent of respondents and the necessary expropriation
compensation. The RTC and CA found that respondents are entitled to proceedings. To make matters worse, almost 55 years have already passed
compensation. The only issue left is the propriety of the amount awarded to from the time of taking, yet DPWH still failed to institute condemnation
respondents. Just compensation is the fair value of the property as proceedings. This is clearly indicative of DPWH’s lack of intention to formally
between one who receives, and one who desires to sell, fixed at the time expropriate the subject property and consequently deny respondents of the
of the actual taking by the government. This rule is true when the property elementary due process of law. Thus, when respondents were constrained to
file a complaint before the trial court, they were the ones who, in effect,
commenced the inverse condemnation proceedings, which is ironic. The usually summarized this way: Money received today is more valuable than the
prevalence of the taking of a subject property without the owner’s consent and same amount of money tomorrow. By applying this concept, we are able to
the necessary expropriation proceedings does not, and should not, cure its capture just compensation in a more holistic manner. We take into
illegality. consideration the potential of money to increase (or decrease) in value across
 If the Court is to peg the reckoning value of the just compensation to PhP time. If the parties in an expropriation case would have perfect foresight, they
0.70, it would, in effect, be condoning the wrongful act of DPWH in taking the would have known the amount of FMV at the time of taking.
subject property in utter disregard of respondents’ property rights and violation  If this amount of money was deposited in a bank pending expropriation
of the due process of laws. Thus, while this Court has previously ruled, in proceedings, by the time proceedings are over, the property owner would be
a number of cases, that the value of the property at the time of the able to withdraw the principal (fair market value at the time of taking) and the
taking which is controlling in the determination of the value of just interest earnings it has accumulated over the time of the proceedings.
compensation, it is my submission that an exception to the foregoing Economists have devised a simple method to compute for the value of money
ruling must be made in cases where no condemnation proceedings were in consideration of this future interest earnings.
instituted after a substantial period of time from the time of illegal
taking. Pertinently, there is “illegal taking” when there is taking of a property
without the benefit of expropriation proceedings and without payment of just
compensation, as in the instant case. When the illegal taking is compounded
with the failure of the condemnor to institute condemnation proceedings after
a substantial period of time, i.e., 55 years from the time of taking, then it is not
really hard to grasp why pegging the basis for valuation of just compensation
at the time of illegal taking is erroneous, if not utterly reprehensible.
 The Court cannot reluctantly close its eyes to the likelihood that the invariable
application of the determination of just compensation at the time of the actual
taking, as in the cases cited in the ponencia, will grant government agencies
and instrumentalities the license to disregard the property rights of
landowners, violate the Constitution’s proviso on due process of laws, and
render nugatory statutory and procedural laws on expropriation proceedings
of private properties for public use. Both the RTC of Malolos City and the CA
were, therefore, correct in granting just compensation to respondents in the
amount of PhP 1,500 per square meter, as recommended by the PAC. This
way, government agencies and instrumentalities would think twice before
taking any unwarranted short cuts in condemning private properties that
violate the owners’ right to due process of laws as enshrined in the Bill of
Rights.

SEPARATE OPINION – JUSTICE LEONEN


 Gross injustice will result if the amount that will be awarded today will
be based simply on the value of the property at the time of the actual
taking. Should the value of the property been awarded to the owners at the
time of the taking, they would have used it for other profitable uses. Hence,
the failure of the State to have paid at the proper time deprives the owners of
the true value of the property that they had. The proper way to resolve this
would be to use the economic concept of present value. This concept is

Potrebbero piacerti anche