Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Certificate
This is to certify that this report, the design of Border hydropower development project, is an
authentic work prepared and submitted by:-
1. Abel Alemayehu
2. Blihan Haile
3. Chalie Agez
4. Dagnachew Dawit
5. Daniel Kebede
6. Eyoal Assefa
7. Mussie Kebede
8. Nebiyu Letefe
9. Yared Worku
In partial fulfillment of the requirements for the award of the degree of Bachelor of Science in
Hydraulic and Water Resources Engineering at Gondar university, under the guidance of
Wonwossen Beyene (Msc), and Getachew Smur, (Bsc).
Approved by
Advisors
Examiners
Acknowledgement
We are deeply grateful to so many who have helped us make this final year Project practical. We
feel humbled and blessed by others contributions and our sentiment towards other is aptly
expressed by Albert Einstein, who said: ‘’ Every day I remind myself that my inner and outer life
are based on the labors of other men, living and dead, and that I must exert myself in order to
give in the same measure as I have received and am still receiving”. So it is with this final
project. It could not have been successful without the help of many people for whom we are
genuinely thankful.
Special thanks to our Advisor, Ato Wondwossen Beyene, Msc for his very kind treatment
through the time he spent with us starting from the commencement. His motivation and
constructive comments rally round us to put our best effort on the work and encouraged us to
carry on long-sufferingly, even if we were in the middle of Deep Ocean.
Most importantly, we acknowledge and thank God for blessings, insights and support we have
felt throughout this Project. For us, He is the source of all principles that bring joy and success in
life.
Abstract
The Border hydropower development project site is located on the Abay River (Blue Nile) some
30km downstream of its confluence with the Beles River and 20km upstream of the Ethiopia-
Sudan border. The catchment area for the Border Project comprises some 172254km2 of the
Abay river basin. Since the hydrological data available is at Kessie river, gauged site, some
distant from the Border site, ungauged site, the flow series from the ungauged is transposed to
gauged site by Area-ratio method. The flow duration curve is drawn by total period method, by
using the entire average monthly flow of 600 values of 50 years. The design flood is determined
by using L-moment and Lognormal II is used for design estimation from moment ratio diagram
and the estimated value is 20500m3/sec.
Based on the selection criteria of the dam type, especial availability of construction material
nearby the site and suitability of the topography and geology of the area, RCC dam is proposed
with total height of 83m, from area-elevation curve, which store 42066.8Mm3, by Prismoidal
formula, with maximum installed capacity of 1882.25MW. The Spillway design flood is
computed by flood routing procedure and it is 5116.04m3/sec, at the middle of the dam, having
192m crest width and it is designed as ogee shaped crest profile. The gross head available at the
site is 60.73m with net head of 60.43m.The steel lined penstock of 120m length with diameter of
6m is designed to convey discharge directly from the reservoir to the units. Since there is a
desired head, generating coefficient and turbine speed Francis turbine is considered as the
appropriate turbine type with vertical alignment to reduce surface requirement in the surface
powerhouse.
Under Power house design detail dimension of the turbine runner, scroll casing and draft tube are
comprehensively included.
The positive and negative impact due to the power development is also identified and mitigation
measures endorsed and the economic feasibility of the project is assessed by benefit cost ratio
method, which is 1.3, and internal rate of interest (IRR) is found to be 6.045 %.
Contents
Acknowledgement ...........................................................................................................................iii
Abstract ............................................................................................................................................ iv
List of Figure...................................................................................................................................xii
Chapter 1 ........................................................................................................................................... 1
1 Introduction .................................................................................................................................... 1
1.1General ..................................................................................................................................... 1
1.3.1 Climate.............................................................................................................................. 5
Chapter 2 ........................................................................................................................................... 6
2.6.1 General............................................................................................................................ 12
Chapter 3 ......................................................................................................................................... 21
3.7.1 General............................................................................................................................ 27
Chapter 4 ......................................................................................................................................... 30
4.1 General............................................................................................................................... 30
Chapter 5 ......................................................................................................................................... 35
5. Dam work.................................................................................................................................... 35
5.5 Modes of failure and criteria for structural stability of dam ................................................. 38
Chapter 6 ......................................................................................................................................... 63
6. Spillway ...................................................................................................................................... 63
For Border hydropower project ogee spillway is provided as the dam is RCC gravity dam and
because it can be easily used on valleys, where the width of the river is sufficient to provide
the required crest length and the river bed below can be protected from scour at moderate cost.64
Chapter 7 ......................................................................................................................................... 76
7.3.1 General............................................................................................................................ 86
Chapter 8 ......................................................................................................................................... 96
10.3 Power developed versus operating and maintenance costs ............................................... 131
List of Table
Table 1 Gauging stations Abay at Kessie ....................................................................................... 7
Table 2 Guide lines for selecting the return period....................................................................... 12
Table 3 Elevation area storage curve data .................................................................................... 23
Table 4 coordinates (x,y) from x=0 to x=7.51 .............................................................................. 70
Table 5 Coordinates points for bell mouth entry .......................................................................... 78
Table 6 unsupported length of bar in cm for velocities (m/se) ..................................................... 79
Table 7 coordinates of pheratic line for different values x and y (Seepage line) ......................... 90
Table 8 Types of Runner and Its Specification ........................................................................... 103
Table 9 Summary of environmental impact of Border hydropower project ............................... 119
Table 10 preliminary Estimate Grand Summery in US$ ............................................................ 121
Table 11 Summary of bill of quantity for structures and electromechanical equipment ............ 122
Table 12 Summary of power intake structure ............................................................................. 122
Table 13 Power intake structure ................................................................................................. 123
Table 14 Summary of power house and control building ........................................................... 124
Table 15 Power house and control building ............................................................................... 124
Table 16 Summary of River Diversion Work ............................................................................. 125
Table 17 River diversion work ................................................................................................... 126
Table 18 Summary of gravity dam ............................................................................................. 127
Table 19 Gravity dam and spillway ............................................................................................ 127
Table 20 Summary of waterway ................................................................................................. 128
Table 21 Waterways ................................................................................................................... 128
Table 22 Summary of access road and site compounds ............................................................. 129
Table 23 Access road and site compounds ................................................................................. 130
Table 24 Environmental and administration rough estimated cost ............................................. 131
Table 25 Detail calculation for internal rate of return ................................................................ 133
List of Figure
Figure 1 Location of Border dam site ............................................................................................. 4
Figure 2 Hydrograph of kessie and Border ..................................................................................... 9
Figure 3 Flow duration curve at Border dam site ......................................................................... 11
Figure 4 Moment ratio diagram of Border .................................................................................... 19
Figure 5 Elevation area storage curve ........................................................................................... 24
Figure 6 Flow mass curve ............................................................................................................. 26
Figure 7 Inflow hydrograph of Border.......................................................................................... 32
Figure 8 Reservoir routing of Border............................................................................................ 34
Figure 9 Gravity dam profile ........................................................................................................ 50
Figure 10 Forces act on the dam water pressure up to NPL ......................................................... 51
Figure 11 Forces act on the dam water pressure up to MPL ....................................................... 54
Figure 12 Forces act on the dam in extreme load combination .................................................... 57
Figure 13 Forces act on dam in empty case .................................................................................. 59
Figure 14 Spillway crest profile .................................................................................................... 71
Figure 15 Ogee spillway ............................................................................................................... 73
Figure 16 Solid roller bucket detail .............................................................................................. 75
Figure 17 Coffer dam layout ......................................................................................................... 91
Figure 18 Scroll case (spiral casing) detail ................................................................................. 106
Figure 19 Draft tube detail .......................................................................................................... 108
Abbreviation
Symbols/abbreviations Descriptions
B/C Benefit cost ratio
cm Centimeter
FDC Flow duration curve
GEV General extreme value
HFL High flood level
HRL High reservoir level
IRR Internal rate of return
kg Kilogram
KWh Kilo Watt-hour
M Million
MW Mega Watt
m meter
mm millimeter
Km Kilometer
MFL Maximum Flood Level
NPL Normal Pool Level
NPV Net Present Value
ICS Inter Connected System
SCS Self Contained System
Ton/yr tones per year
t tone
PMF Probable Maximum Flood
DF Design Flood
SPF Standard Project Flood
L-Moment Linear Moment
MRD Moment Ratio Diagram
RCC Roller Compacted Concrete
U/s Upstream
D/s Downstream
EIA Environmental Impact Assessment
NMSA National Metrological statistical Agency
Chapter 1
1 Introduction
1.1General
Energy is the lifeblood of development and development in its basic form of description is about
reducing poverty and about increasing access to basic needs to result in an improved standard of
living.
Industrial development, which is the key factor for the economic development, requires energy
as its main input. Development in the power sector will encourage industrial development that
will create employment opportunities for more people and this will result in improved standard
of living.
Ethiopia has significant energy resources that are enough to the present and long term energy
requirement of the country. But only some of these resources are presently being exploited. The
main indigenous sources of energy are biomass, hydropower, fossil (fuels), natural gas, coal,
geothermal, solar and wind.
Although the country is known to have the potential sources, currently most of the energy
consumed comes from biomass.
Studies conducted on the country’s energy consumption show that around 91% of the need is
covered from biomass. As a result of this there is increased soil degradation due to erosion and
deforestation. And also the climatic change is causing erratic rainfall both in amount and
distribution that result in the fluctuation of hydropower energy supply.
Hydropower has a great advantage as it is continuous source of energy while thermal power has
a depleted fossil fuel sources, besides hydropower doesn’t consume the water.In addition to this
hydropower development also provides secondary benefit such as recreation, fishing, flood
control etc. where storage is contemplated.
The hydro resources of the country is said to be an immense potential that can be utilized for any
water resources in the country. Due to the countries topography suitability and abundant river
flows, hydropower has been the cheapest and the main energy source in Ethiopia for supplying
energy for domestic, industrial and other energy consumption.
The gross hydropower potential of the countries is estimated at 650TWh/yr. More than three
quarter of which is available from mountain reservoirs with flow regulation. Generally, the
country has about 15000-30000MW hydroelectric potential that can be exploited to generate
electricity. However, only less than 3% of the country’s energy potential is known to have been
developed so far.
The total population of the country is estimated to be more than 77 Million of which about 85%
of the population lives in the rural areas and almost with no access to electricity, road, education
…etc.
In the near future sufficient energy and capacity appears to be available to satisfy the demand.
However a significant risk remains of continuing energy shortages depending on successful
completion of ongoing rehabilitation and construction project .It is clear that with the generation
project currently committed for implementation, the sustainability of electric demand of the
country will be guaranteed.
By this time inter connected system (ICS) consists of 8-hydro, 10-dieseal, and 1-geothermal
power plant with total installed capacity of 635.35MW, 22MW and 7.3MW respectively.
However due to aging of the plants the dependable total capacity is about 456.4MW excluding
the newly commissioned Gilgel-Gibe hydroelectric power plant and the peak demand is around
390MW. Over 98% of the total generation in the country comes from inter connected system
(ICS) and of the supply system 99% is from hydro.
The self-contained system (SCS) consists of three small hydro powers and several diesel power
plants. Generation in this system is mainly by diesel power plant having an aggregate capacity of
13.86MW. The contribution of the small hydropower plant is only 6.15MW.
Much of the upper part of the basin comprises the highland plateau with elevation generally
exceeding 2000m. The plateau exhibits extensive level areas with intensive agricultural divided
by incised valleys. Mountain peaks rises to over 4000m in North .The Abay flows generally
within a deeply incised gorge which has a relatively gentle gradient falling some 645m over 600
km from an elevation of El.1030m at Kessie bridg to El. 485m at the Sudan border.
The land around the Border dam site is mountainous having an elevation ranging from 490
meters above sea level (a.m.s.l) in the river bed at the dam site to locate peak of 1255 meters
a.m.s.l in hills on the right bank and 1241 a.m.s.l in hills on the left bank . Upstream of the
border dam site, the valley opens into a basin with low relief, typically surrounding land lying
between 500 and 600 a.m.s.l with a number of areas of high ground greater than 1000 a.m.s.l.
The Abay has confluences with two principal and perennial tributaries in this potential reservoir
area, Beles on the right bank and Debus on the left bank. Beles River joins Abay 30 km upstream
of the dam site. Other tributaries are shorter in length and are seasonal.
There are a series of rapids at the dam site, similar to cataracts on the main Nile in Sudan, but no
natural waterfall. The dam itself creates the head of the project for power generation.
This contrast in morphology between the two differing rock formations ensures a relatively
narrow valley for the dam on granitic foundation, with a wide-open valley upstream of the dam,
ensuring high storage potential. This combination of morphological factors determines the
favorable characteristics of Border dam site.
Geological mapping at the site confirmed the existence of the two broad geological formations
divisions; namely the Granite /Granite Gneiss Formation and the Biotitic Schist / Marble
formations. The latte formation presents a significantly weaker rock mass than the former, and
needs to be avoided as a foundation rock for the dam.
The Border project area appears to be located in a relatively low seismic hazard zone. Mapping
of seismic activity in Ethiopia and the neighboring regions from 1906 until 2003 indicates that
Border dam site is 300km away from the nearest epicenter.
1.3.3 Temperature
Mean annual temperature in the border project area is between 25 and 300 c.
Chapter 2
2. Data analysis
2.1 General
The primary objectives of hydrological investigations are mainly in connection with the design,
construction and operation of hydraulic structures. The established river flow characteristics are:
mean daily and monthly flow, daily and monthly flow duration curves, firm flows and probable
maximum flood. Hydrology is required in the design stage to determine the maximum, minimum
and mean flow of the river at the proposed location of the structure. Design flood corresponding
to a certain return period is required to design efficiently and economically functioning hydraulic
structures. The maximum flow is used to predict the higher level over the structure, which occurs
on average once every T-years of return period.
The design of water resource project like Hydropower project, the peak magnitude of the flood
are of great important to design economical as well as structures with less probability of failure.
If the selected design flood is too high, it results in a conservative and unnecessary costly
structure while adoption of a low design flood can, if a higher than this occurs, results in the loss
of the structure itself causing there by untold misery to the people residing down steam, besides
damaging valuable immovable properties. It is because of this that a detailed study of hydrology
is very essential in practice.
The development of power from stream flow depends firstly on the volume of flow and secondly
on the differential head that could be available for power production.
Features to be considered for transposing hydrological data are soil type, land use, rainfall
distribution, evaporation rate, slope, catchment size, rainfall amounts, density and types of
natural vegetation cover.
The Nile at Border dam site has catchment area of 172,254 Km2 and at the Kessie Bridge
gauging station has catchment’s area of 65,784Km2. There are two methods to estimate the
weighted factor for transposing the flow data gauged site
i) Area ratio method
ii) Runoff coefficient method
i. Area ratio method is convenient when the ungauged and gauged sites have the same
stream (Upstream tributaries) and are hydro meteorologically the same. While runoff
coefficient method is used when there is multi gauged stations and the stations have
different features (density and type of vegetation).
For Border Hydropower Area ratio method is suitable as the stations are hydro-metrologically
the same and the only difference is area.
Qu W f * Qg
2000.00
1500.00
Q(m3/s)
1000.00
500.00
0.00
1950 1960 1970 1980 1990 2000 2010
Year
Yearly mean at Kessie Yearly mean at Border
It is useful for estimating available water resources for different uses like Hydropower project,
study of flood control, computing sediment load, design of drainage system and comparing the
adjacent catchments with a view to extend stream flow data. It also reflects the nature of the
stream and analyses the available flow records at the site.
There are methods in order to utilize the flow data available for the entire period, such as;
Total period method
Calendar year method
In Total period method, the entire available record is used for drawing the flow duration curve.
Thus the 50 year record would produce 600 values of monthly average flows. These are first
tabulated in the ascending order starting from the driest month period and ending with the
wettest month of the 50 years of duration or vice versa. The resulting flow duration curve would
then be drawn with the help of 600 values.
In Calendar year method, each year’s average monthly flow is first arranged in ascending order.
Then the average flow values corresponding to the driest month, second driest month and so on
up to the wettest months are found out by taking arithmetic mean of all values of the same rank.
These average values are then used for plotting flow duration curve. Such a curve would have 12
points.
The Total period method gives more accurate results than the calendar year method which
averages out extreme events. Therefore, for this particular project the total period method is
preferred.
Computation of flow duration curve using Total year method is tabulated in ANNEX-1.
The resulting flow duration curve would then be drawn with the help of 600 values and the
regulated flow is 31.702m3/s and average is 1341.972m3/s.
7000
6000
5000 FDC
4000
3000
2000
1000
0
0 20 40 60 80 100
Percentage of exceedance
Selecting higher return period means the corresponding flood magnitude also very high. Such a
very high flood may never occur during the life of the structure.
On the other hand, if a very low discharge corresponding to low return period is chosen for
design, it will result in the failure of the structure causing damage of the structure.
Subramania, (1994) has given better guide for selecting the return period.
For this particular project, it is expected that the total storage is greater than 60 Mm3 and it is
expected that the failure of the dam may cause hazard on property and lives of people in the area
as the dam is located in high flood area. Taking the reasons into consideration the return period
has been considered as 10,000 year.
So, depending up on the magnitude, the floods can be classified in to the following three classes:
i) Design Flood (DF)
This is a flood selected for the design of a structure. It is selected in such a way that it
accommodates any negative effects that are to be imposed on the structure intended. It is also
sometimes taken as a flood corresponding to a certain desired frequency of occurrence
depending up on economy and practical consideration.
At a given location in the stream, flood peaks enable one to assign a frequency to a given flood
peak value. In the design of all hydraulic structures, the peak flows that can be expected with an
assigned frequency are of primary importance to adequately proportion the structures to
accommodate its effect
The use of a particular method depends up on the preferred objective, the available data and the
importance of the project. The rational method is only applicable to small catchments (<70) and
the unit hydrograph method is restricted to moderate size of catchments area less than 500Km2.
The empirical formula is essentially regional formula based on statically correlation of the
observed peak and important catchments characteristics. Flood frequency analyses are the
statistics method of frequency studies. Therefore, based on the available data, project type and
the size of the catchment’s area (172,254 Km2) the frequency analysis method is selected for
Border Hydropower project.
Water resource projects must be planned for future events for which there is no exact time of
occurrence can be forecasted. Hence, probability that stream flow will be equaled or exceeded a
specified value must be estimated accurately.
To obtain the maximum daily discharge, it is required to have some conversion factor based on
regional and the catchment area.
For Border Hydropower project, the peaking factor is given as 1.3, since the catchment area is
65,784Km2.The daily maximum discharge at the dam site is obtained by multiplying the
maximum monthly discharge by the peaking factor, since the monthly data couldn’t consider the
fluctuation’s daily precipitation. Hence, the data multiplied by the factor in order to get accurate
result. The factored data tabulated in ANNEX of plotting position, ANNEX-3.
P=1/T
The most commonly used formula for determining Plotting position used for PWMs is APL
method.
i 0.35
Fi Where; Fi= plotting position
N
n= number of years record and
i= the rank of the events in order of magnitude
The computation of plotting position is tabulated in ANNEX-3.
In wide range of hydrologic application L-moments provide simple and reasonable efficient
estimators at the characteristic of hydrology data and of a distribution.
Let X (i/n) be the ith largest observation in the sample size of n and (i=1 correspond to the largest).
Then for any distribution the second L-Moments is a description of scale based on the expected
difference between to randomly selected observation:
2=1/2 E X(1/2) –X(2/2)-----------------------------------(2)
Similarly, the third and the fourth L-moments measures of Skewness and Kurtosis respectively
as:
3 = 1/3 EX (1/3) -2X (2/3) + X (3/3)-----------------------(3)
4= 1/4 EX (1/4) -3X (2/4) + 3X (3/4) - X (4/4)--------------(4)
L-Moment can be written as a function probability weighted moment (PWM s) which can be
defined as:
βr =E {X [F(X)] r} -------------------------------------------(5)
b0 X m 8030.265
n 1
n j X
j 1
j
b1 4755.695 -------(6)
nn 1
n 2
n j n j 1X
j 1
j
b2 3434.157
nn 1n 2
n 3
b3 2710.024
nn 1n 2n 3
According to the given data the values of L-Moment parameters are computed below:
1=bo=8030.265
2=2b1-bo=1481.125
3=6b2- 6b1+bo= 101.036
4=20b3- 30b2+12b1 – b0=213.855
LCV=τ= 2/1= 0.184
LCS=τ3= 3/2=0.068
LCK=τ4= 4/2= 0.144
To select the type of distribution which fit to the given data are computed as follows:
a) Uniform Distribution
Z3=0 Z4=0
b) Exponential Distribution
Z3=1/3 Z4=1/6
c) Normal Distribution
Z3=0 Z4=0.1226
d) Gumbel distribution
Z3=0.1699 Z4=0.1504
e) Log Normal Distribution
Z4=0.12282+0.77578 (τ3) 2 +0.12279 (τ3) 4 -0.13638(τ3) 6 +0.113638(τ3) 8
=0.12641
f) General Extreme Value (GEV)
Z4=0.1070+0.1109 (τ3) 2 -0.0669 (τ3) 3 + 0.60567(τ3)4 - 0.04208(τ3) 5 +0.03763(τ3) 6
=0.1075
g) Pearson Distribution
Z4=0.1224+0.30115 (τ3) 2 +0.95812 (τ3)4 -0.57488(τ3)6 + 0.19383(τ3) 8
= 0.123813
Based on the L-Moment estimator, the value of sample Z4 is close to the value of Z computed
using Log Normal II distribution. To get the most fitted probable distribution for this specific
project, the graphical representation of the relationship between L-Skewness (Z3) and Kurtosis
(Z4) and the values of Z3 and Z4 of the dam site is given below.
0.8
Moment ratio diagram
GPAR
0.6
GLOG
0.4
Kurtosis(LCk)
GEV
0.2
P-III
0 LOGN2
-0.4 -0.2 0 0.2 0.4 0.6 0.8 1 1.2
WKB
-0.2
OVB
-0.4
Skewness(LCs)
Lognormal II distribution
The Lognormal distribution can be written as X t exp y u * y
Therefore, the design flood for Border hydropower project for 10000 year design period is
20500m3/s.
Risk (R) is the probability of occurrence of an event (X≥ XT) at least once of over a period of n
years, where n is the useful life of the reservoir (1000 years).
Reliability (Re) is the probability of non-occurrence of the events (X≤ XT) in n years.
n
1
R 1 1 P 1 1
n
T
n
1
Re 1 R 1 Where; P =probability of event (X>XT) =1/T
T
Re= reliability
R= risk
n= expected life of the structure
T = return period
Since a useful life of 100 and a return period of 10000 years are considered.
100
1
R 1 1 P 1 1 1%
n
10000
Re 1 R 99 %
Thus the possible risk of flood damage by a flood magnitude exceeding the 10,000 years
frequency in the assumed life of the reservoir is about 1 % with the reliability of confidence of
99%.
Chapter 3
3.1 Reservoir planning
3.1 General
Reservoirs are manmade lakes aimed to store water during the time of day to day load
fluctuation, for balancing such fluctuations small amount of storage is required and met through
pondage or reservoir. A reservoir is created behind a dam built across a river or stream to
impound part of the runoff from the catchment upstream of the dam site. Storage is done during
wet season when flow is in excess of the demand to maintain continues hydropower generation
in addition to meet up the requirements for the various purposes such as irrigation, public water
supply and hydropower. The demand is met from the runoff of the river when the flow is in
excess and from the reservoir storage during load period. When a barrier is constructed across
some river in the form of dam, water gets stored on upstream side of the barrier forming pool of
water called dam reservoir.
Depending upon the purpose served by a given reservoir, the reservoir may be divided in to the
following three types:
1, Storage or conservation reservoirs
2, Flood control reservoir
3, multipurpose reservoirs
Volume determination
Volume of storage (V) or capacity of the reservoir at equal intervals (H) is calculated as under
i) Trapezoidal formula
V H * A1 A2
3
A1 A2 Where A1 and A2 are areas of succeeding contours and
H– Is the vertical distance between two alternative
contours
iii) Prismodal Formula
For this particular project from all the above methods prismodal formula is adopted since
our site condition is characterized by concave slope extending down to the river from
dome shaped mountainous.
25000 100
cummulative volume(m3)
200
20000
Area (m2)
300
15000
400
10000
500
5000 600
0 700
480 500 520 540 560 580 600
Elevation (m)
The slope of the tangent to the mass curve at any time is measure of inflow at that time. The
Mass Curve thus gives the relationship between the accumulated inflow and outflow and the
available for the storage at any given time from the beginning of the year, demand line is the
straight line rising from the origin for a uniform rate of demand.
For this particular project, reservoir capacity is determined by Mass Curve method by taking two
consecutive driest years (1983 and 1984). Mass Flow calculation is tabulated in ANNEX-6.
40000
35000
30000
25000
20000
S
15000
10000
5000
0
0 5 10 15 20 25 30
Time (month)
comm vol
Then the vertical intercept between these two straight lines (S) represents the minimum storage
volume required to permit continuous release (yield) of water at this average discharge rates for
the entire period.
From the above analysis the minimum live storage required is 23000Mm3. So lives storage
capacity of 23000Mm3 is taken.
The bed load and part of suspended sediment is deposited in the reservoir bed if the reservoir
discharges the surplus freely for long time which is the case when runoff the river is large in
comparison to reservoir capacity that is small capacity inflow ratio.
However if the capacity inflow ratio is large i.e the reservoir is large in comparison to the annual
runoff, all the water borne sediment brought by runoff is deposited in the reservoir bed.
The specific weight of settled sediment seems to vary with the age of the sediment samples from
reservoir range from about 650kg/m3 to 1800kg/m3 with an average of 1000kg/m3 for fresh
3
sediments and 1300 kg/m for old sediments.
The amount of sediment deposition depends on the extent of erosion in the catchment area which
depends on the following factors:
1. Nature of soil in the catchment area
2. Topography of the catchments
3. Vegetation covers
4. Intensity of Rainfall
From most reservoirs the useful life is assumed as 100 years. For Border hydropower project
monthly sediment inflow from the local area (i.e. 172254km2) is given at the dam site. The
inflow at 31.7m3/s from the regulated flow of Border is without bed load(i.e. desilted water).The
mean annual suspended load entered into the reservoir is calculated as below.
Annual inflow=318Mtone/yr
Old sediment density=1.55Mtone/m3
318M t
yr 3
Annual sediment inflow 205.16M m
1.55M t yr
m3
3
The dead storage 205.16M m *100 yr 20516Mm3
yr
Total reservoir = dead load + live load
Total reservoir = 20516Mm3 2300Mm3 43516Mm3
Therefore, from area elevation curve area of reservoir at normal pool level is 597.6Km2.
Annual average evaporation depth(Et)=1639mm/yr
Pmean=1236mm/yr
Total volume of evaporation = A mean * Et * K
Where K is pan evaporation coefficient from 0.6-0.8 hence, 0.7 is mostly recommended by
K.Subramanya (1994).
Total storage capacity = dead storage + live storage + net evaporation volume
Total storage capacity 20516 23000 160.56
Total storage capacity 43676.56Mm3
Chapter 4
4. Flood routing
4.1 General
The extent by which the inflow hydrograph gets modified, due to the reservoir storage can be
computed by a process known as reservoir routing.
Reservoir routing is a process of computing water level in the reservoir and out flow rates
corresponding to a particular inflow hydrograph at various instant of time. It is carried out to
determine the maximum water level and the corresponding out flow rates when the maximum
flow passes over the spillway. The maximum water level is required for fixing the height of the
dam while the maximum out flow rate is required for the design of spillway.
The unit hydrograph derived from such relationships are known as synthetic unit hydrographs.
Synthetic unit hydrograph is one of the Snyder’s methods that are based on the study of large
catchments in United States. The basin characteristics considered by Snyder’s synthetic unit
hydrograph are the area and shapes of the catchments.
The basin lag time tp is given by
But Linsley suggested that the basin lag tp is better correlated with the following catchment’s
parameters.
n
L * Lc
t p ct*
s
L c = Distances along the main water course from the gauging station to a point opposite to
A typical dimensionless unit hydrograph developed by the US soil conservation services (SCS)
has its ordinate expressed by the ratio of (Q/Qpk) and the abscissa is expressed as a ratio of time
to peak (t/tpk). This dimensionless unit hydrograph provides a shape to the unit hydrograph and
these leads to a better result than the synthetic unit hydrograph.
And the shape of the dimensionless unit hydrograph is more agreed with the unit hydrograph that
is likely to occur in nature.
'
tr
t pk t P
'
2
21 t
tp *tp r , So for our given data the values are as follows
22 4
n=0.38 constant adopted from…………………. K. SUBARMANYA (1994)
c t = 1.6 Interval between 1.36-1.65 from….…... K. SUBARMANYA (1994)
645m
Slope(s) = 0.0011 L=580Km Lc=60%L=0.6*580=348Km
600km
n 0.38
L * LC 580 * 348
But, t p ct 1.6 47hr
s 0.0011
tp 47
tr 8.5177hrs Take tr = 9hr
5.5 5.5
The inflow hydrograph is calculated by multiplying t pk and QPK with the ratio given by USCS.
For QP =20500m3/s (design flood obtained from flood frequency analysis) and time to peak t pk
calculated above; tpk=51.4hr the following inflow hydrograph table is formulated in ANNEX-8.
20000
Q (m3/s)
15000
10000
5000
0
0 50 100 150 200 250 300
Time(hr)
Inflow hydrograph
I1 I 2
There fore I avg
2
Q1 Q2
Qavg
2
S S 2 S1
Where the suffixes 1 and 2 denote the beginning and the end of the time interval ∆t,
The above equation can be written as:
I I2 Q Q2
t 1 t 1 S 2 S1
2 2
I I 2 S1 Q1 S 2 Q2
1
2 t 2 t 2
In order to determine the out flow hydrograph first the inflow hydrograph is divided in to a
number of small intervals; for this project ∆t=9hrs. Then calculate the average inflow for the
time interval. As the second term in the bracket is known, at the first time interval, the value in
the right hand side is obtained. The next head is determined by adopting computer (excel spread
sheet).
For the computation of the above steps the storage is determined by assuming a constant increase
in height for the horizontal surface area (normal pool level) at the top, which is assumed in the
routing technique.
Therefore; S=A*H
Where A=the surface area at normal pool level = 37Km2
H= head of water measured above the crest (normal pool level)
And the routing process is done for overflow spillway and discharge over it is computed
by the general equation.
Q C * L * H 1.5 ) where C is
From pre-feasibility study effective length of spillway is 192m.
20000
Q(m3/s)
15000
10000
5000
0
0 5 10 15 20 25 30 35
Time(hr)
Chapter 5
5. Dam work
5.1 General
Dam is a solid barrier generally impervious in nature constructed at the narrow out let of a
catchments area in a valley .It holds up the flow of water to raise the water level to a fixed level
to form a reservoir on the upstream side .Generally dam fulfills two fundamentals functions:
A) It develops a reservoir which has a capacity to store water and
B) Builds up head and thus potential for the river water
In most of the high head and medium head hydroelectric projects, a dam across the river is an
important component.
I. Topography: topography dictates the first choice of the type of dam. The dam site of Border
Hydropower project is mountainous having the topographic expression of a complex intrusion of
granite, granitic gneiss, and granodiorite gneiss and dome shaped with concave slopes extending
down to the river.
II. Geology and foundation condition: - A dam is a very large structure in which all the loads
acting on it including its own weight is ultimately transferred to the foundation. The geological
mapping of the Border Hydropower project confirmed the existence of the two broad geological
formations divisions; namely the Granite/Granite Gneiss formation and the Biotite Schist/Marble
formations. The latter formation presents a significantly weaker rock mass than the former, and
needs to be avoided as a foundation bed rock for the dam.
III. Availability of materials: - in order to achieve economy in the dam, the materials required
for its construction must be available locally or at a short distance from the dam site. For border
hydropower project dam site there is sand cover and a large amount of rock material available for
the purpose of aggregate, which means that gravity dam, is suitable for the area.
IV. Earthquake zone: - If the dam site is located in seismic zone, the most suitable type of dam
is one, which can resist the earthquake shake without much damage. Therefore the Border
Project area appears to be located in a relatively low seismic hazard zone. Mapping of seismic
activity in Ethiopia and the neighboring regions from 1906 until 2003 indicates that Border dam
site is 300 Km away from the nearest epicenter. Therefore the effect of earthquake for the dam is
neglected as it is not that much significant.
V. Spillway size and location: - the selection of the most suitable type of a dam for a particular
site is sometimes governed by the size and location of spillway.
VI. Economy: - Roller compacted concrete (RCC) gravity dam is constructed in much the same
way as an embankment dam. Because the RCC gravity dam construction method is quicker and
requires less labor, it is most cost effective than conventionally placed mass concrete. The RCC
approach is best suited to wide valley giving scope for unobstructed end-to-end continuous
placing. The construction saving realized are at maximum for high volume dams and align from
a 30% reduction in construction time as well as from reducing unit cost for the RCC. The vertical
rates of the raising of (2-2.5) m/week are attainable for RCC gravity dams, which can also lead
to be more economical.
Therefore considering all the above points and specially its technological acceptance, a roller
compacted concrete gravity dam (RCC) is selected for Border hydropower project.
The failure may occur at the foundation plane (i.e. at the base of the dam) or at any other plane at
higher level.
A. Overturning stability: - If the resultant of all the forces acting on a dam at any of its
sections, passes outside the toe, the dam shall rotate and over turn about the toe.
M ve
FO M ve Inclusive of moment generated by up lift
M ve
H
Fss , if it has a horizontal plane F SS > , where = 0.75
V
Fss
H
V
tan
1 H
V
tan
F SS Should not be permitted to exceed , (where = 0.75) But under (extreme load
combination) ELC it can be up to 0.9, which is acceptable.
II. Shear friction factor (SFF) – is defined as the ratio of total resistance to shear and sliding
which can be mobilized on a plane to the total horizontal load.
V * q
SFF
H
Where, B = width of the dam at the joint.
q = average shear strength of the joint which varies from about 1400 km/m2 for poor
rocks to about 4000 km/m2 for good rocks.
- The Value of generally varies from 0.65 to 0.75
SFF > 3 (for normal load combination) (NLC)
SFF>2 (unusual load combination) (ULC)
SFF>1 (ELC)(extreme load combination)
f
FLE Where -the shear stress generated under the applied loading.
f -the shear strength available and expressed by Mohr coulomb
failure criteria.
C. By development of tension
Masonry and concrete gravity dams are usually designed in such a way that no tension is
developed anywhere, because these materials cannot with stand sustained tensile stresses.
The maximum permissible tensile stress for high concrete gravity dams, under worst
loadings, may be taken as 500kN/m2. Therefore, in order to ensure that no tension is
developed anywhere in the dam, it must be proved that P min is at most equal to zero.
Hence, the maximum value of eccentricity that can be permitted on either side of the center is
equal to B/6 i.e. the resultant must be with in the middle third of the base.
D. Cracking or compression
A dam may fail by failure of its materials, i.e. the compressive stresses produced may exceed
the allowable stresses, may get crushed.
V 6e
P max/min =
B 1 B where e = eccentricity of resultants from the center of base.
V 6e
Pmin 1 B , Pmin=0
B
V 6e
=
B 1 B =0
6e B
0 1 e
B 6
Hence maximum value of eccentricity that can be permitted on either side of the
B
center is equal to , which leads to the famous statements that the resultant must lay
6
within the middle third of the base.
At the heel,
o heel Pv heel P tan
A. Primary loads
1. Water pressure
When the upstream face is vertical, the intensity is zero at the water surface and equal to
w * H at the base, where W the unit weight of water and H is the depth of water. The
H
resultant force due to this external water is 0.5 * w * H 2 and acting at from the base.
3
When the upstream face is partly inclined, the resulting water force can be resolved in to
H
two components. The horizontal component Ph 0.5 * W * H 2 acts at from the base
3
and vertical component, is equal to the weight of water stored in the upper inclined
portion of the dam and acts at the center of gravity of the area.
For this particular project, as there is no tail water condition given, its value is neglected
for the designing analysis at normal pool level.
2. Up lift pressure
The pressure variation along the base of the dam is assumed to be linear between the
upstream and the downstream faces.
Total upstream force on the base of the dam
u Average pressure intensity* area
Pu w * H H ' *
L*B
And
2
5* H 2* H '
z , From the base. When drainage galleries are provided to relieve the
3( H H ' )
uplift, the recommended up lift at the face of gallery u
Pu w H ' 1 w H w H '
3
3. Weight of the dam
The weight of the dam body and its foundation is the major resisting force. In two-
dimensional analysis of gravity dam, a unit length of the dam is considered. The cross –
section can then be divided in to rectangles and triangles. The weight of each along with
their center of gravities can be determined. The resultant of all these down ward forces
will represent the total weight of the dam.
w c. Where, c unit weight of concrete
2) Ice pressure
The ice that may be formed on the water surface of the reservoir in cold countries may
sometimes melt and expand. For this particular project as Ethiopia is in tropical zone, this
force is not considered for design.
3) Silt pressure
Silt is deposited in the reservoir on the upstream of the dam. Silt exerts the earth pressure on
the dam, similarly to that in case of an earth retaining wall. The generated horizontal thrust
Ps has vertical and horizontal component and it is a function of the sediment depth h s ,
a. s .hs
'
hs
Ps = = acts at above the base of the dam.
2 3
4) Wind load: - When the dam is full, wind acts only on the down streamside thus contribute to
stability.
C. Exceptional loads
1. Seismic load.
If the dam is to be located in a region, which is susceptible to earthquake allowance, must be
made for the stress generated by the earth. If the ground under the dam moves the dam must
also move with this to avoid rupture. Inertia force always acts opposite to the direction of
earthquake acceleration.
When the reservoir is full, the worst condition is if the earthquake acceleration moves
towards upward and corresponding inertia force acts on the down direction. And
when the reservoir is empty the worst case is if the acceleration moves towards the
downstream direction and corresponding inertia force moves to the upstream
direction.
2. Height of water above normal pool level up to the maximum flood level
HW = MFL- NPL
Where MFL is the maximum flood level and
NPL is normal pool level
Height of storage from reservoir routing= 560-480=80m
In a high dam the maximum permissible compressive stress is exceeded, if the resultant of all
forces were to pass thought the middle third. Approximate downstream slope in terms of its
angle to vertical d , required for no tension to occur at vertical up stream face is given by:
1/ 2
tand 1 ………… …………… P.NOVAK, (1996)
c
w
Where C - Density of concrete
w - Density of water
- An area reduction coefficient and ( =1) for analytical purpose…P.NOVAK, (1996)
C 24KN / m2 and w 10kN / m2 ………P.NOVAK, (1996)
1/ 2
tan d 1
c
w
1
tand [ ]1 / 2 0.845
24
( 1)
10
d 40 .2 0
Base width
The base width of the dam should be safe against overturning, sliding and no tension in the dam
body.
The base width is determined by taking trial values of the upstream slope and checking the
stability of the dam.
83 83
B AN * tan u 0
tan d tan(49.8)
B=0+70.14
=70.14m, Take B=71m
d ' 90 d
tand 0.845 And d 90 40.2
d ' 49.8
For this particular project the cross section is determined by using the recommendation given
by P.NOVAK, (1996).
The upstream face flare of a gravity profile is determined by changing the slope of the inclined
plane until it satisfies its stability. The face flare is advantageous in that it serves to lengthen the
base contact and hence stress can be distributed at the surface and it can resist against sliding.
From the above figure
tan d 49.8
'
5m
The limiting height
f
H Where f = allowable stress of dam material
( Sc C 1)
= Unit weighs of water
Sc Specific gravity of concrete
C When uplift is ignored (USBR)
Sc=2.4
f
H max =
w ( Sc 1)
H max = 3000KN/m2
9.81KN/m2 (2.4+ 1)
H max = 89.9 m
There are two approaches for profile selection of a dam to match the specific conditions
applicable; multi stage approach and single stage approach.
Single stage approach is based up on definition of suitable and uniform downstream
slope.
For Border Hydropower project two galleries are provided at a 15 m excavation difference and
the galleries are placed at 4m distances from the vertical face of the dam.
All loads acts on the dam and moments created by the load in each case tabulated in
ANNEX-11.
For this particular project since earthquake is neglected, some of the load combinations are
neglected in the stability check.
1) Water pressure up to the normal pool level (normal uplift), silt pressure.
All loads acts on the dam and moments created by the load tabulated in ANNEX-11.
V V 1 V 2
V 60889 .83KN
M 2163404.98
x 34.52
V 60889.83
Therefore B 71 B … Safe against tension
e X 34.52 0.98 11.83
2 2 6
FO
M 3365556 2.80 1.5..........Safe
M 1202151.24
Stress analysis
i. Average vertical stress
At the toe
60889.83 6(0.98)
Pvtoe [1 ] 928.63 3000KN / m2........OK
71 71
At the heel
Pvheel 857.60(1 0.08) 786.56 3000KN / m2.......OK
ii. Principal stresses
At the toe
1 Pvtoe * sec 2
1 928.63(1 0.852 )
1 1597.24 KN / m 2 3000KN / m 2 ........( ve...OK )
At the heel
2 Pvheel * sec2 Pw tan2 , but
2 786.56KN / m 2 3000KN / m 2 ..........OK
iii. Shear stresses
At the toe
o ( toe) Pvtoe * tan , tan 0.85 928 .63 * 0.85 789 .34 KN / m 2
At the heel
o ( heel ) [ Pvheel P tan ], p tan 0
o ( heel ) [1031.74 0] 786.56KN / m 2 30000KN / m 2 ..........OK
2. Water pressure up to maximum reservoir level (High flood condition) normal up lift, silt
pressure
All loads acts on the dam and moments created by the load tabulated in ANNEX-11.
∑M=1973517.77kNm
∑V=60180.47kN
∑H=33370.09KN
M ve 3365556
FO 2.41 1.5 (Safe)
M ve 1392038.23
Stress analysis
1. Average vertical stress
V 6e
PVtoe / heel 1 B
B
At the toe
60180.47 6 * 2.71
PVtoe 1 1041.72 KN / m 2 3000KN / m 2 ......OK
71 71
At the heel
60180.47 6 * 2.71
PVheel 1 71 652.66KN / m 3000KN / m ........OK
2 2
71
2. Principal stresses
At the toe
1 P' vtoe * sec2 ph tan2 , p' 0 (No tail water)
1 1041.72 * 1 0.852
1 1791.76KN / m 2 3000KN / m 2 ......OK
At the heel
2 PVheel * sec 2 PW tan 2 p w tan 2 0 & sec 2 1
2 652.66 *1
652.66KN / m 2 3000KN / m 2 .......OK
3. Shear stresses
At the toe
O toe PV toe tan
otoe 1041.72 * 0.85
otoe 885.46KN / m 2 3000KN / m 2
At the heel
oheel pvheel p * tan
oheel 652.66 0
oheel 652.66KN / m 2 3000KN / m 2 .......OK
All loads acts on the dam and moments created by the load tabulated in ANNEX-11.
M =1079472.24KNm
V =39020.4KN
H =-32408.71KN
Check for tension
M 1079472.24
X 27.66m
V 39020.40
......safe against tension failure
B 71 B
e X 27.66 7.84 11.83
2 2 6
FSF
Ca V tan 1200 * 71 39020.4 tan 59.5
h
H 32408.71
FSF 4.67 4..............OK
M VE 3373245.89
FO 1.47not 1.5but......acceptable
M VE 2293777.65
Stress analysis
I. Average vertical stress.
At the toe
39020.40 6 * 7.84
PVTOE 1 71
71
PVtoe 912.30KN / m 2 30000KN / m 2 ..........OK
At the heel
39020.40 6 * 7.84
PVheel 1 71
71
PVheel 186.86KN / m 2 3000KN / m 2 .............OK
II. Principal stresses
At the toe
1 PVtoe * sec 2 Ph tan2
1 1745.52 * 1 0.852 (9.81 * 14) tan2 40.2
1 1471.64 KN / m 2 3000KN / m 2 .............OK
At the heel
2 PVheel * sec2 PW tan2 , pw tan 0
2 186.86(1)
2 186.86KN / m 2 3000KN / m 2 ..........OK
III. Shear stresses
At the toe
o toe PVtoe * tan , tan 0.85
otoe 912.3 * 0.85 775.46KN / m 2 3000KN / m 2 .......OK
At the heel
oheel PVheel P * tan
oheel 186.86 0
oheel 186.86KN / m 2 3000KN / m 2 .........OK
All loads acts on the dam and moments created by the load tabulated in ANNEX-11.
Distance of resultant force from the toe
M 3365556
X 46.44
V 70944
B
e X , B 71
2
71
e 46.44 Since -10.94<11.83 no tension is developed.
2
B
e 10.94 11.83
6
Stress analysis
I. Average Vertical Stresses
At the toe
V 6e
PVtoe 1 b
B
70944 6 *10.94
PVtoe 1 +ve it is safe
71 71
PVtoe 79.94 KN / m 2 3000KN / m 2
At the heel
V 6e
PVheel 1 B
B
70944 6 *10.94
PVheel 1
71 71
PVheel 1918.48KN / m 2 3000KN / m 2 .....OK
The dam following this approach is therefore optimized for construction using a lower strength
and relative permeable RCC gravity profiles in conjunctions with horizontally slip formed high
quality upstream concrete membrane.
Chapter 6
6. Spillway
6.1 General
Spillways are structures constructed at a dam site for effective disposal of the surplus water from
the reservoir upstream to downstream. When the flood water enters the reservoir, the level of
water rises beyond the predetermined HRL, at the same time the excess water will be left out
over the spillway without causing any damages to the dam and its appurtenant structures.
Types of spillway
Depending up on the type of the structure constructed for disposing of the surplus water, the spill
way can be of the following major types:
1. Free over fall or straight drop spillway
2. Over flow or ogee spillway
3. Chute or open channel or trough spillway
An over flow spillway is an improvement up on the free over fall spillway. The essential
difference between the free over fall spillway and the over flow spillway is that in the case the
former the water flowing over the crest of the spill way drops as free jet clearly away from the
downstream face of the spillway, while in the case of later the water is guided smoothly over the
crest of the spillway and is made to glide over the downstream face of the spillway.
At the design head H H d the water flowing over the crest of the spillway will remain in
contact with the surface of spillway as it glides over it and optimum discharge will occur.
At a head greater than the design head (H>Hd) the nape trajectory is higher than the crest profile,
and the over flowing water tends to break contact with spill way surface and zone of separation
will be formed in which negative or suction pressure will be produced.
The values of X and Y are taken as positive towards the downstream and in the down direction
respectively. Hence the equation of downstream profile is applicable only for positive values
from the region of other coordinate.
The profile of the Spillway is reverse S-shaped and the curved profile of the crest section is
continued till it meet tangentially the straight sloping surface of the downstream face of the over
flow dam.
After having plotted most of the profile the Ogee spillway has a smooth gradual reverse
curvature is provided at the bottom of downstream face which turns the flow in to the apron of
stilling basin or in to the spillway discharge channel. Radius of about one-fourth of the spillway
height is satisfactory for this reverse bottom curve.
H
i.e. R Where H=height of spillway crest above the bed level.
4
The location of point of tangency of the dawn stream straight-line sloppy face of the over flow
dam and the curved profile is determined from the stability requirement of the over flow section,
and the type of stilling basin at the toe of Spillway.
The slope of the straight line portion of the downstream face of the over flow dam varies and
between (0.6H: 1V to 0.85H: 1V), S.K. GARG (2005)
The bucket like profile at the downstream end of the dam is also use full for the dissipation
energy and prevention of scour.
In the analysis of flood routing from the inflow and out flow rate effective length is selected as:
Le = spillway length = number of gates * width of gate = 12 *16 = 192m
Q peak (Peak out flow) = 5110m3/sec
H d = 5.27m (maximum water level above the crest level of the spillway)
Q
Velocity of approach, Va ( )
( Le N * t ) * ( P H d )
For round nose pier and 90o cut water nosed piers, thickness and the number of piers
was assumed to be 1m and 4 respectively
That is t = 1m, N= 4
3
5110 m
Va sec 0.33 m
(192 4 * 1) * (74.73 5.27) sec
va 0.33
Ha 0.017m
2 g 2 * 9.81
He P 5.27 74.73
15.18 1.7 So neglect the effect of downstream submergence
Hd 5.27
on the coefficient of discharge.
For flow at design head H d , the average value of K P and Ka, for piers and Rounded
abutment which is cut at 90o to the direction of flow, K P = 0.01 and K a = 0.1
respectively.
L Le 2NK P Ka H e
= 192 +2 (4* 0.01 + 0.1) 5.27
But length due to thickness of piers = 4* 1m = 4m, then the total length of the spilling crest is
equal to 194 + 4 = 198m
dy X 1 1.85 * X 0.85 1
d x 8.32 0.85 8.21 0.8
8.21
X 0.85
0.8 *1.85
X 7.5m
Y 0.122 X 1.85
Y 0.22(7.5)1.85 5.1m
The curved profile of the downstream portion is determined by the equation Y 0.122 X 1.85 is
confirmed till it meets tangentially, the straight sloping surface at the coordinate x, y i.e.
(7.5, 5.1) - tangent point (x, y).
The coordinates from x=0 to x = 7.51 are listed out in table below:
Table 4 coordinates (x,y) from x=0 to x=7.51
X Y
0.00 0
0.50 0.03
1.00 0.12
1.50 0.26
2.00 0.44
2.50 0.66
3.00 0.93
3.50 1.24
4.00 1.59
4.50 1.97
5.00 2.40
5.50 2.86
6.00 3.36
6.50 3.89
7.00 4.46
7.50 5.07
7.51 5.09
Upstream profile
The upstream profile for an ogee spillway, having downstream and upstream slope can be
determined on the basis of its WES profile in terms of the design head H d .
r1 0.2 * H d 1.05m
r2 0.5 * H d 2.64m
a 0.175 * H d 0.92m
b 0.282 * H d 1.49m
In general the kinetic energy of this super critical flow can be dissipated in two ways:
1. By converting the super critical in to sub critical flow by hydraulic jump.
2. By directing the flow of water in to air and then making it fall away from the toe of
the structure .The energy is dissipated by the aeration of the jet and impact of water
on the river bed.
Though some scour will take place, it is too small or too far away from the dam to endanger it.
Bucket type energy dissipater work on this principles.
y1
y2 1 8F1 1
2
2
v1 2
74.73 y1........(1)
2g
But, Q 5110 m3 sec
Le 192m
Q 5110
q 26.62 m 3 sec/ m
Le 192
q v1 * y1 v2 * y2
q 26.62
v1 ( 2)
y1 y1
26.62
74.73 2
y1
y1
(36.12)
2
y1
74.73 y1
1
36.12 2
y1
74.73 y1
q 26.62
V1 38.03 m sec
y1 0.7
V1 38.03m / sec and
V1 38.03
Fr1 14.51
gy1 9.81 * 0.7
y2
y1
2
1 1 8Fr,2
i.e. y2
0.7
2
1 1 8(14.51) 2
y 2 13.02m
When tail water depth " y 2 " is too great for the formation of hydraulic jump (i.e when " y 2 " too
large is compared to " y1 " ) dissipation of the high energy of flow can be affected by the use of
submerged bracket deflector
y1 0.7m
y 2 13.02m
In general, v1 38.03 m sec
Fr1 14.51
3
q 26.62 m
sec/ m
For desperation of energy, Bucket type energy dissipaters are usually of small size and
more economical than the conventional hydraulic jump stilling basins especially when
the fraud number Fr1 exceeds 10,
In general, the Bucket type of energy dissipater can also be adopted for all tail water
conditions and are commonly used for dissipation of energy below the overflow spillway.
The bucket type energy dissipaters are usually of the following there types.
1. Solid roller bucket
2. Slotted roller bucket
3. Sky jump bucket
For border hydropower project, solid rolled bucket type is selected because the sequent depth, y2
is less than tail water depth…………..Dr. K.R. Arora.
The radius of bucket is taken as:
R 0.6 P * H d
Where P= the height of the fall from the crest of the spillway to the bucket invert=74.73m
H d 5.27m
The bucket lip usually has an exit angle of 45 and the height of the lip is about 0.6 R=0.6*11.91
=7.15m
20500
A 882.64m^ 2
0.82 * 2 * 9.81 * 40.43
.D 2
A 882.64
4
D 33.62m 34m
Therefore, gated bottom outlet with diameter of 34m is provided at the dead storage level.
Chapter 7
7. General layout and conveyance structures
7.1 Intake
The intake structure is situated at the entrance of the canals, tunnels and pipes through which the
flow is diverted from the source such as river or reservoir. It is an essential component of
hydropower schemes and provided as an integral part or in isolation from diversion weir or dam.
The main function of an intake:
Control of the flow of water into the conveyance system. This is achieved by a gate or a
valve.
To provide smooth, easy and vortex or turbulence free entry water into the conveyance
system to minimize head loss. This can be achieved through providing bell ־mouth
shaped entrance.
Stopping coarse river-borne trash matters such as boulder, ice and logs of wood from
entering into the conveyance passage. Trash racks at the bell-mouth achieve this function.
Not allowing heavy sediment loads of the river into the conveyance passage. Special
devices such as silt traps and Silt excluders are used to control and trap the slit.
In order to attain the required discharge capacity the intake must be placed sufficiently below
reservoir operating level and high enough to prevent entry of sediment. It should also be
arranged as high as possible to effect economy in concrete construction and cost of maintenance
of the gate.
For intake on Dam, its arrangement comprises an intake with trash rack, emergence gate at the
entrance for inspection and repair of the conduit, flow regulating gate to regulate the flow
through the turbine and air vent downstream of the flow regulating gate for the following
purpose;
To nullity vacuum effect which could be created when the penstock is drained after control
gate closure.
Intake gates operate under condition of balanced pressure on both side of the gate, thus the
conduit is required to be filled with water through a bypass pipe.
Spacing of bars
Spacing the bars depend on nature and size of debris, types of turbine used in the power house,
its size and speed. For Francis turbine, spacing is equal to the distance between the runner vanes.
But usually spacing ranges from 5cm to 15 cm. Take 10cm for this project.
Cleaning of racks
Manual cleaning can be resorted to when racks are 4 to 5m high. For higher racks with higher
intensity of floating materials, mechanical cleaning is economical. Electrical heating is provided
to prevent formation of ice on the racks. On large project, where much debris is expected,
automatic power-driven racks are used.
The velocity of flow in the entrance flume should be kept within such limits as will not cause
great loss of head and vibration of the rack and will not call for larger intake and trash rack cross
sections. According to Garg permissible velocity of penstock is from o.6 to 1.6. From Zowski’s
point of view if velocity is greater than 0.9m/s, the rack structures undergo a several vibration
and they may collapse. Due to above reasons and also to avoid vortices and minimize eddy loss,
we take 0.8m/s for Border Hydropower project.
Bar thickness
The thickness of bar should be between 0.6cm and 2.5cm. Take bar thickness of 2cm for this
particular project.
Keeping the trash rack inclined is always a better practice. For this particular project, the trash
rack inclination of 200 is taken.
Depth of intake
Designing for a low velocity in to the conduit and increasing submergence of the inlet can help
by preventing the formation of vortices. According to J.B Gordon for the condition of no vortex
at inlets, the necessary-submerged depth will be given by;
1
2
Ys > 0.725V * D
1
2
Ys > 0.725 * 0.8 * 6 Where, Ys is necessary submergence depth
V is velocity of the inlet of the penstock =0.8m/se
D is diameter of the penstock=6m
The minimum required depth of the intake for no formation of vortex is 3m by considering some
factor of safety.
Aeration in intakes
Air vent pipes are provided for the following purposes:
To admit air when the gate is closed and the water in the conduit recedes down.
To exhaust air when the penstock is being filled through bye pass lines to balance the
water on the two sides of the gate prior to its being lifted up.
To control sub pressures downstream of gate at partial opening.
According to G.S. Sarkaria’s formula the diameter of the air vent pipe is given by:
Vb2
hc k t Where kt=0.03, for bell mouth entry
2g
V-velocity at inlet=0.8m/s
g- Acceleration due to gravity
Therefore:
(0.03 * 0.82 )
hc 0.001m
2 * 9.81
Trash rack loss
This loss is due to trash racks and is dependent on cross sectional shape of the rack bars and the
angles at which racks are laid. There are numerous expressions available for predicting head loss
across the trash racks.
The widely used KIRSCHMER’S formula is:
t v2
hr kr ( )4/3 ( a )sin Where kr=trash rack loss coefficient
b 2g
h r 0.009m kr=2.42, for rectangular cross section
T- Bar thickness (2.0cm)
b- Spacing between bars (10cm)
Va-approaching velocity
Φ- Angle of inclination from the horizontal (700)
hr- Trash rack loss
Gate loss: head loss due to gates (at part gate opening) is given by Madan Mohan Das and Mimi
Das Saikia, (2011) as:
2
1 Q
hg Where: Q –flow in the gates (103.68m3/s)
2 g cd * A
Bend loss
The bend loss depends up on the bend radius, conduit diameter and the angle of the bend. The
loss is usually expressed by DR.K.R. Arora 2012 as:
v2
hb kb Where kb-factor varying from 0.2 to 0.1(take 0.2)
2g
h b 0.007m V-velocity at the inlet = 0.8 m/s
7.2 Penstock
The penstock carries water from the pressure shaft to the turbines within the least loss of head
consistent with the overall economy of the project. There may be pressure conduit or shaft. In
underground pressure power development, these penstocks meet the spiral case, which supply
water to the machine.
Factors that must be considered for choice of material, for penstock are head, topography and
discharge. Various material used are steel, R.C, Asbestos, Cement, PVC, etc. but the following
have to also be considered when deciding to use for. These are required pressure, design life etc.
Steel penstock become the most common type of installation in hydropower development due to
simplicity in fabrication, strength, and has long life etc. Hence considering the above steel
penstock is selected for this particular project.
Number of penstock
The number of penstocks used in any particular installation can be single or multiple. The design
should strike for maximum economic solution. If the number of penstock increases the total
weight of steel and the erecting cost also increases. In our project the distance from intake to
power house is short. We use eight penstocks, running to eight units.
Design of penstock
The larger the diameter for a given discharge, smaller will be the head loss and greater will be
the net head available to the turbine, resulting in greater power development. On the other hand,
greater size of penstock would mean less velocity and higher capital investment. We should
choose, therefore, after which would give least cost. According to Madan Mohan Das and Mimi
Das Saikia 2011, the economical velocity of steel penstock falls within 3 to 6m/s.
V 0.125 2gH
1
2 Where; V=optimum velocity in m/s
H=Maximum working head in m
hnet = NPL - (elevation at end of penstock) - (head loss up to the end of penstock)
Where hnet = the rated head
NPL (normal pool level) =574.73a.m.s.l
Elevation at end of penstock=500m
h f h fp h f min or Where, hf- is head loss up to the end of penstock
Conduit loss (hfp): The main loss in the conduit due to friction and this load is estimated by
Darcy Weisback formula:
flv2
hf p VQ Where, f-friction factor for steel lining =0.01
2 gD A
2 2
fl Q fl 4Q
hf p l –length of penstock (120m)
2 gD A 2 gD D 2
h fp 1665.38
D5
Hminor =0.084m (calculated above)
V 0.125 2 * 9.81 64.646 - 1665.38 D
5
1
2
(1)
Q 4Q
V 2
4 * 129.6 2
165.01 2 (2)
A D D D
Equating the above two equation (1) and (2) solving for D by trial and error
0.125(2*9.81(64.646-(1665.38/D5)))1/2 = 165.01/D2
D = 6.02m take 6m commercially available
Check
HT 0.216 0.084
HT 0.3m
H net N .L.P H p H T
H net 74.73m 10m 0.3m
H net 64.43m
Thickness of penstock
Under normal flow, the penstock is subjected to only internal hydrostatic pressure. However,
when the turbine valves or gates at the end are closed suddenly, there is sudden pressure rise,
known as water hammer. The appropriate wall thickness for a penstock is generally a function of
penstock material selected that is steel tensile strength, the diameter of the penstock and the
operating pressure it will experience during its use i.e. the head of water above the penstock and
water hammer pressure during sudden opening and closure of turbine. Thus design head =static
head + water hammer providing a steel penstock, allowable stress (s=150,000KN/m2), joint
efficiency (η=0.95) for weld and assuming thin cylinder thickness.
p*D
t Where, p- total pressure
2 * s *
CV
hw D- inside diameter of penstock
g
1
k 2
C t - Thickness of penstock
1
2.18 * 109 KN m 3 2
C 3
Vo-velocity in the penstock
1000 KN m
C 1476.5 m s C-celerity wave velocity of water
1476.5 * 4.6
hw
9.81 K- Bulk modulus of water (2.18*109KN/m3)
hw 692.34m
ῤ -density of water (1000KN/m3)
p (Hnet + (NPL - elevation of intake at the center) + h w ) * 9.81
p*D
Finally! t
2 * s *
7699 * 6
t 166mm
2 * 150000 * 0.95
Adding 3mm for allowance corrosion the required thickness would be 165mm, which is
commercially available.
Usually, it is not economically feasible to plan on diverting the largest flood that has occurred or
may be expected to occur at the site, and consequently some lesser requirements must be decided
upon.
Therefore, the diversion works is designed for the return period of 20 years and acceptable risk
of 26.5%
The cross-sectional geometry and the layout are designed for their final purpose. Either, the
tunnel can be closed after construction, or it can be connected to a bottom outlet, or withdrawal
structure or a water intake.
A Qd 12663.02
2V 2 30
A 211.05m 2
D 2 4A
A D 16.40m
4
The height at which cofferdam should be constructed may involve an economic study of
cofferdam height versus diversion work capacity, including diversion of design flood. These
small dams are also used to raise the river water level, in order to feed an off- taking tunnel and
some other conveyance system. Therefore, one diversion tunnel having 16.40m diameter is
provided for diversion tunnel. For the design of the coffer dam, the height of the coffer dam is
taken as sum of the diameter of the tunnel and some allowance for free board. i.e.
H 16.40 2.5(Free board)
H 19m
Hence the height of the coffer dam is equal to 19.00 m Therefore, one diversion tunnel having
16.40m diameter is provided for diversion tunnel.
Total height of the coffer dam will be=19.00m
Freeboard: Freeboard or minimum free board is the vertical distance between the maximum
reservoir level and top of the dam. USBR recommendation for freeboard in rock fill dam that are
uncontrolled (free) spillway of any height is between 2 and 3 meter.
.
Width: for small dams, the top width is generally governed by minimum roadway width
requirements.
The top width (T) of the cofferdam for dams longer than 30m
T 0.55 Hto 0.2H Where H-is the height of the dam
. T 0.2 *19 3.8m 4m
U/s and d/s slopes (Recommended side slope by Terzaghi) since the material at the dam site
is composed of 2m sand in depth and generous rock, u/s side slope 1V:3H and d/s side slope
1V:2.5H is taken for the design.
Phreatic line
Phreatic line the line within the dam section below which there are positive hydrostatic in the
dam. The hydrostatic pressure on the phreatic line is equal to the atmospheric pressure and hence
equal to zero.
Essential to determine the position of the phreatic line is the following reasons.
1. It gives us a divide line between the dray and moist or submerged soil. The soil above the
seepage line shall be taken as submerge for computation of shear strength soil.
2. It represents the top steam line and hence helps us in drawing the flow net.
3. The seepage line determination helps us to ensure that it does not cut the downstream
face of the dam. This is extremely necessary for preventing or sloughing of the dam.
Table 7 coordinates of pheratic line for different values x and y (Seepage line)
x Y=(2XS + S2)
0 3.20
5 6.50
10 8.61
15 10.31
20 11.83
25 13.12
30 14.22
35 15.33
40 16.32
41 16.49
Where, h1 is the point at which the vertical line through u/s extremities intersect phreatic line
measured from the base of the dam.
h2 is the point at which the vertical line through d/s extremities intersect phreatic line
measured from the base of the dam.
Approximated values for checking the stability of the rock fill dam-Garg (2001)
Saturated unit weigh, sat 12 KN m 3
Angle of friction 25 0
Unit cohesion C 24 KN m2
2
The area above the seepage line is measured approximately A1= 300m2(from graph)
The area bellow seepage line is
A2 At A1
A2 1073.53m 2 300m 2
A2 773.46m 2
300m 2 * 1 * 18 KN
m3
5400KN
773.53m 2 * 1 * 12 KN
m3
9282.22 KN
WT 5400KN 9282.22 KN
WT 14682.22 KN
Re d 9462.33
Fs 6.67 2......................................safe
Pd 1319.25
16.4 2 25 1
Fhd 12 * tan 450 * 9.81 * 12.8 2
2 2 2
Fhd 1178.68KN
Shear resistance of Reu of upstream slope portion of dam developed at the base of ΔDE
Re u C Wt tan
1
Re u (C * B * 1) sat * * Bu * h tan ........where, Bu 57.23m
2
Re u (24 *1* 57.23) (0.5 *12 *19) tan 25
Re u 4398.07KN
Re u 4398.07
Fs 3.73 2.........................................................safe
Fhu 1178.68
sat * h2 dry (h h2
2
h
12 * 10.8 18(19 10.8
2
19
2 14.59 KN m 3
19 2 25 1
Fhd 14.59 * tan 2 * 9.81 * 10.8 2
2 2 2
Fhd 1640.37 KN
The area of the dry soil with in the ΔBFC above seepage line assume 250m2(from graph)
1
Total area of ABFC * 19 * 47.5 451.25m 2
2
Area of submerged soil A2
A2 451.25m2 250m2 201.25m2
Red=C+Wtanυ
Re d (C * B * 1) ( dry A1 sat A2 ) tan
Chapter 8
8. Preliminary power assessment and power house layout
8.1 General
Hydropower is extracted from the natural potential of usable water resources. The
Transformation of the pressure and kinetic energy of water in to more easily usable form of
electrical energy is takes place in the power house. The plant of hydropower includes different
structures such as dams, intakes, conveyance structure, penstock, power house, surge tank, draft
tube and tail race.
Turbines are machines which convert hydraulic energy to mechanical energy (shaft power).The
shaft power developed is used in running electricity generators which are directly coupled to the
shaft of the turbine, thus producing electrical power.
Load factor: - is the ratio of the average load over a certain period to the peak load during the
same period. A high load factor is indicative of the better utilization of the installed capacity and
consequently the unit generating cost is less and vice versa.
Load factor = average load/maximum load
Installed capacity: refers to the full capacity of the power plant. The installed capacity can be
determined by multiplying the unit weight of water, net head (H), over all efficient and
maximum discharge (Qmax).
P o * * Qmax * H
But Pfirm / Pinst = power factor, according to Sharma load factor can be taken within the range (0.4
– 0.6) for developing countries like Ethiopia, so take 0.48
Pinst= Pfirm/ power factor
= 567.48MW/0.48
Pinst = 1182.25MW
Impulse turbine
Reaction turbine
Impulse turbine
In such type of turbines the potential energy of the flowing water is converted in to kinetic
energy by a means of nozzle through which high impinge on bucket fixed to the number of
turbines and imparts impulse.
Reaction turbine
In this types of turbines the water enters the turbine in circumferential direction into the scroll
case and enter into the through a series of guide vanes called wicket gates. The available energy
partly converted to kinetic energy and substantial magnitude remains in the form of pressure
energy. Examples of reaction turbine are Francis, Kaplan, propeller etc.
6. Overall cost: it includes initial cost and running cost. As much as possible it should be
adopted minimum overall cost turbine unit.
For this project, considering all the above parameters and using the performance curves,
Francis turbine is selected.
N P
Ns Where Ns= specific speed
H 1.25
P= power developed (Kw)
N= rotational speed (rpm)
H= effective head (m)
B. Synchronous speed
It is the speed of the turbine corresponding to generator speed or some multiple of the speed of
the generator. It depends on the way that the generator is coupled with the generator.
120 f
N Where, ƒ=frequency Hz (ƒ=50Hz)
p
Np = number of poles in even number
The speed of a turbine is an important parameter of design. The higher the speed, the smaller the
diameter of the turbine runner and the cheaper the generator coupled to the turbine. High speed;
however, makes a turbine more susceptible to cavitation.
C. Peripheral Velocity
It is the ratio of the peripheral speed of the bucket or vanes at the minimal diameter, D to the
theoretical velocity of water under the effective head H acting on the turbine.
It is given by:
DN
Where D= diameter of the turbine
60 2 gh
B. Turbine speed
N s (H 5 ) 1.25
N 4 = 219 * (60.43 )
P1 147.78 *103
N = 95.98 rpm, take N=96rpm
C. Synchronous speed
The selection of number of poles is done on the effect of head variation. According to
DONALD if the head is expected to vary less than 10% from the design head, numbers of
poles are taken as lower multiple of 4.
If variation is >10% then the higher multiple of 4 poles is adopted giving lesser speed. The
number of poles should be even number so as to have proper magnetic field. However as per
latest trends the numbers of poles are used as multiple of 4 for a better dispersion of magnetic
flux through some standard generators having multiple of 2 poles only.
120 f
N Frequencies (f) (50-60) take 50Hz
NP
120 * 50
NP = N P =62.5 Take Np= 64 which are divisible by 4 for H<200m=> Np= 64
N
120 * 50
N = 94rpm
64
SO, the new specific speed
N* P
Ns 1634.69/15 = 108.93 MW
H 5/ 4
94 * 147780
Ns 214rpm
60.435 / 4
Threrefore Ns = 214rpm and N=94rpm
2 2
N * H 54 214 * 60.435 4
P s 147.13MW
N 94
1182.25
Therefore Number of unit 8.035 8unit
147.13
Based on the above parameters, operation head of 60.43m, generating coefficient 0.78,
generating power of 147.78Mw and the turbine speed of 94rpm makes Francis turbine suitable
for this project.
The following formula used to determine proportion run away speed as compared to normal
speed.
H max 12
U.S.B.R. Formula Nr K n .N ( )
Hd
Where
K n (0.1475N s 145)in % age
(0.1475 * 275 145)
176.57%
H max H gross 60.73m
H d H net 60.43m
N 94rpm
0.5
60.73
N r (176.57 / 100) * 94 *
60.43
N r 166.38rpm
Hence, the nearest commercially available value is taken.
i.e. N r 180rpm
1
D 7.1Q 2 4.3m
N 100 13 H 14
s
Where H=60.43 (net head)
Ns=214
Q=130.06m3/se
Therefore take commercially available D = 5m
H. Draft tube
The draft tube is a conduit discharging water from the runner to the tailrace, and has two fold
purposes:
To recover as much as possible of the velocity energy of water leaving the runner, thus
increasing the dynamic draft head.
To utilize the vertical distance between the turbine exit and the tail water level, called
static draft head.
The most common draft tube is the elbow type, which minimizes the depth of the sub
structure compared with the vertical type. It also enables the utilization of the static head
between the bottom of the runner and the tail race when runner is placed above the tail
water and, the dynamic head in the water at the turbine exit due to high velocity of flow.
The elbow type draft tube is selected for this project because of the following advantages:
i) Minimize the required depth of excavation.
ii) Direct the flow in the direction of the water flow
iii) Allow the provision of gate at the out let of the tube, which facilitates the dewatering of
the turbine for repairs, if necessary.
3
Wt 0.05 * P 0.05 * 147.78 * 10 950.52tone
H 60.43
P 3 147.78 * 10 3
3
D s 0.111 0.111 1.3m
N 94
i) Generator
ii) Exciter and voltage regulators
iii) Transformer
iv) Control room equipment including switch
Mechanical
i) Shaft, bearings, coup lings, etc for the generator
ii) The oil circuits and pumps
iii) Compressors and pumps
iv) Cranes and other lifting equipment
Besides the above auxiliary equipment, water supply and drainage are also needed for the power
house lighting.
8.4.7.2 Generator
The generator must have vertical configuration, protection against run away speed are to be
provided. This machine should be capable of supplying heavy line charging current the
hydroelectric power plant is located at a considerable distance from the load end.
184725 p( kN ) 147780
= Wg 25 85 K 184725
94 0.8 0.8
= 1023.25 tone
J.H Walker has given elaborate curve and relation to determine the generator diameter. If Dg is
the gap diameter in meter (there is gap between poles and stator and the diameter being at the
end of the gap.
Np 32.5
D' g * K
62 P
64 32.5
D' g * 7 Where; K = constant varies from 5 to 9
62 147780
Taking K = 7,
D’g =7.31m
Diameter of frame in meter
2.1
Df Dg * 1
Np
2.1
Df 13 * 1
64
= 13.42m
The generator pit in diameter
Dp D f 2
D p 13.42 2
D p 15.42m
A. Unit spacing: unit spacing can be determined using the following empirical formulas
1) E.Mosony’s formula
N
5.5 S * D3
Unit spacing= 100 Ns and D3 which is calculated
16.8m
where D3=D when Ns>200rpm…Mosonyi, 1987.
= 4D 3
= 25m
=4.2D 3
=21m
Taking the maximum value, unit spacing=25m
The size of the erector bay is usually governed by the size of the generator. Normally, in the case
of surface power house, the width of the erector bay is equal to the machine hall width and the
length equals that of one operating bay or center to center distance of two adjacent units.
B) Machine hall:-the dimension of the machine hall depends on the number and size of machine
and the type of arrangement.
For Border hydropower project vertical setting is preferable, because this type of setting is better
for multiple units.
Length:-the length of the machine hall depends on the number of units and the size of
machine. Knowing the number of machine, the total length of the machine hall can be
worked out. The additional bay for the erection and loading can be one unit length.
Standard layout indicates a distance of 4.5 to 5.0D, where D is the turbine outlet
diameter.
The dimension between center to center of units is:
L (4.8 * 5) 2.5m (for clearance)
L 26.5m
The total length of the machine hall
8unit * 26.5
212m
Width –the width of the machine hall determined by the size and clearance spacing
between the walls needs as a gangway.
i. For first approximation the width of the power house can be presumed to be at
least equal to the center to center distance of the machine.
Height: - the height of the machine hall is fixed by the head room requirement. The hall
must have a height which will enable the crane to lift the rotor of the generator or the
runner of the turbine clear of the floor without any abstraction.
To this clearance, space is to be added the depth of crane girder, and the head room for
the operating cabin.
H= height of generator + clearance (3m) + allowance for the movement of crane (2m) +
allowance for crane girder (4.5m)
From the previous height of generator
Hg= 4.5m
H = 4.5 + 3 + 2 + 4.5 = 14.0m
Therefore, the site of cavern will be
L=212m, W=25m, H=14m
ERECTION BAY
This space where the heavy vehicles can be loaded and unloaded, the size of the loading
bay should be sufficient to receive the large parts like the rotor and the runner. The
loading bay floor will be having a width at least equal to the distance between the
machine center lines.
CONTROL BAY
Control bay is house of the main control and other equipment. It may be adjacent to the
unit bay as in most of the power houses. It sends instructions to the operations bay from
where the operation control is achieved.
SERVICE CRANES
The cranes should be designed such a capacity as to be able to lift the heaviest parts of
the machine. Usually such heavy components are the generator, rotor and turbine runner.
Chapter 9
9. Environmental impact assessment
9.1 General
Hydropower projects that are intended to produce electric energy, may cause irreversible
environmental changes over a wide geographic area and thus have a potential for significant
impacts. The area of influence of the project extends from the upper limits of the catchments to
far downstream. Therefore hydropower project such as Border hydropower are designed to
enhance economic development and bring a better standard of life to people due consideration
should be given to their adverse environmental and social effects. This can be done through
environmental impact assessment, which is a management tool for officials, and manager who
take decision about important development project.
The EIA not only predicts potential problems but also identifies measures to minimize the
problems and out lines ways to improve the project suitability for its proposed environment.
The aim of environmental impact assessments is:
1. To understand the likely environmental consequences of new developments.
2. To understand the amplification of proposed interventions.
3. To identify measures by which the impacts can be mitigated.
4. To present the results in such a way that they can provide answers needed by
stakeholders.
Generally, EIA can be described in short as an instrument used to identify, predict and assess the
environmental consequences of a proposed major development project. Moreover, EIA is used to
plan appropriate measures to reduce adverse effects.
Chapter 10
10. Cost evaluation and economic analysis
10.1 General
Economic analysis of hydropower project is a technique of analyzing cost expended and benefit
from the project. The benefit includes tangible and intangible benefits those, which cannot be
determined in economic term. Based on accounting analysis, when total benefit acquiring from
project exceeds the total cost expended, the project is believed to be economically viable. (i.e.,
the project has ability to obtain funds for implementation and repay these funds at realistic
interest rate). Therefore economic analysis is used to determine whether the project is worth to
be implemented or not.
Table 21 Waterways
Item no Description Unit Quantity Rate Amount
5.1EXCAVATION AND EARTHWORKES
5.1.1 Excavation
The average energy price according to recent (EEPCO) on hydropower is 0.34 Birr/kW.
Therefore, for evaluation of the project the following data are required.
IRR is calculated through an iterative process, which is done by computer processing and it is
found that at i=6.045% NPV=0 hence IRR=6.045 %.
Conclusion
As far as we progress in the detail of this entire project taxation, we are now about to declare the
initial foot step of implementing a hydropower project with installed capacity of 1645 MW. It
has significant contribution for the developing Ethiopia towards industry lead economy and plays
its own role in pleasing the total power demand. The project site is found 580km downstream of
the renaissance bridge, locally called ‘kessie’ and the construction of the dam will be held on the
ever historic Nile river course just 20km upstream of Ethio-sudan border.
Since there is visible variation in discharge and getting compatible topography with reasonable
geology, we have selected a Roller compacted concrete (Rcc) gravity dam. The dam has a height
of 83m and 42066.8Mm3 capacity of storing water.
Border hydropower project would possibly guarantee to reduce the cost of pumping for irrigation
and cost of removal of sediment from irrigation canal systems. But still it would force few
thousand people to migrate from their village and also till the reservoir gets full there would be
considerable shortage of water at the downstream. Paradoxically we see those constraints as a
stumbling block for achieving our mega project success.
Recommendation
Topographic map should be readily and timely available so as to get the very data to head
the project.
For better accuracy and confident work, periodic site visit should be arranged.
To disregard errors in the time transposing data, a gauging station should be established
near the dam site to record evaporation, temperature, rainfall and other parameters.
It is difficult to comprehend the volume of excavation works as we are in lack of
surveying data.
References
1. P. Novak,A.I.B Moffat, C.Nalluri and R.Narayanan (2006) Hydraulic structure, third edition
2. S.K. Garg (2006), Irrigaton engineering and Hydraulic structures
3. Chow, V.T (1988), Mc Graw-Hill book company,Singapore Applied hydrology
4. M.M Pandeker and K.N Sharma, 1979, water power engineering, vikas publish house PVT
5. J.Giasson,R. Therivel, A. Chadwick (1994), introduction to environmental impact assessment,
UCL press, London
6. R.H.Mccuen, hydraulogic analysis and design, second edition
7. D.R. Maidment, hand book of hydrology
8. R-Suresh, watershed hydrology (principles of hydrology)
9. R.M Hirsch, D.R Heisel, T.A Cohn, and J.Gilroy, statistical treatment of hydrologic data
10. C.S.P Osha, Berndtstone, Bhunya, engineering hydrology
11. J.R Stredinger, R.M Vogel, E.Foufoula Georgiou frequency analysis of extreme event
12. David. R. Maidment, hand book of hydrology
13. Subramanya, K(1987,1988),engineering hydrology, Mc Graw-Hill publisher
14. DR.K.R Arora, water resources and irrigation engineering
ANNEXES
ANNEX-1 FDC Computation Data
Flow Rank p=(m/(n+1))*100 Flow Rank p=(m/(n+1))*100
11103.56 1 0.166389351 5313.36 35 5.823627288
10079.14 2 0.332778702 5219.04 36 5.990016639
9549.90 3 0.499168053 5203.32 37 6.156405990
9107.12 4 0.665557404 5192.84 38 6.322795341
9015.42 5 0.831946755 5166.64 39 6.489184692
8627.66 6 0.998336106 5116.86 40 6.655574043
8609.32 7 1.164725458 5114.24 41 6.821963394
8399.72 8 1.331114809 5088.04 42 6.988352745
8242.52 9 1.497504160 5085.42 43 7.154742097
7998.86 10 1.663893511 5072.32 44 7.321131448
7920.26 11 1.830282862 5001.58 45 7.487520799
7598.00 12 1.996672213 4962.28 46 7.653910150
7338.62 13 2.163061564 4865.34 47 7.820299501
7189.28 14 2.329450915 4826.04 48 7.986688852
7184.04 15 2.495840266 4794.60 49 8.153078203
7008.50 16 2.662229617 4556.18 50 8.319467554
6838.20 17 2.828618968 4548.32 51 8.485856905
6793.66 18 2.995008319 4464.48 52 8.652246256
6746.50 19 3.161397671 4430.42 53 8.818635607
6688.86 20 3.327787022 4401.60 54 8.985024958
6667.90 21 3.494176373 4323.00 55 9.151414309
6492.36 22 3.660565724 4197.24 56 9.317803661
6434.72 23 3.826955075 4192.00 57 9.484193012
6374.46 24 3.993344426 4108.16 58 9.650582363
6319.44 25 4.159733777 4092.44 59 9.816971714
6293.24 26 4.326123128 4068.86 60 9.983361065
6170.10 27 4.492512479 3977.16 61 10.14975042
6031.24 28 4.658901830 3961.44 62 10.31613977
5879.28 29 4.825291181 3869.74 63 10.48252912
5766.62 30 4.991680532 3867.12 64 10.64891847
5688.02 31 5.158069884 3856.64 65 10.81530782
5478.42 32 5.324459235 3854.02 66 10.98169717
5389.34 33 5.490848586 3817.34 67 11.14808652
5352.66 34 5.657237937 3812.10 68 11.31447587
1980 85.9 58.5 43.9 45.6 21.1 44.3 572.7 2028 1691 582.3 315.7 189 473.17
1981 115.7 100 80 70 62.1 30.1 1427 1952 1108 409.4 258.1 168 481.70
1982 120.9 77.6 64.8 56.2 52.4 41.2 261.5 1568 729.6 525.6 220.3 135 321.09
1983 82.9 57.1 50.7 63.5 97.3 86.5 275 1936 851 422.7 219.1 124.2 355.50
1984 75.9 44.2 24.6 16.1 40.8 136.1 601.9 759.2 461.4 152.9 89.8 64.1 205.58
1985 42.5 27.3 19.7 59.4 60.9 55.4 583.6 1942 1381 479.1 266.4 169.1 423.87
1986 108.9 79.4 68.3 90.9 129.2 53.2 1221 1894 1151 492.3 263.7 156.9 475.73
1987 96.1 64.2 100.4 88.7 108.5 148.5 221.4 1124 490.5 307.8 223.6 118.7 257.70
1988 70.4 56.4 32 26.4 14 33.1 1451 3645 1909 929.5 469.6 281.1 743.13
1989 152.1 91.9 83.2 103.5 45 52.4 590.1 1553 941.5 434.5 243.4 184.5 372.93
1990 92.4 64.7 45.9 43.7 22.7 17.5 513.4 1455 951.5 395.3 187.6 106.9 324.72
1991 63.5 49.6 38.3 56.1 55.4 59.5 1333 2593 1350 572.5 304 180.7 554.63
1992 103.9 73.3 52 34.5 38.4 27.8 414.6 2171 1170 707.2 406.9 225.5 452.09
1993 123.8 73.3 43.9 179.4 156.1 156.5 1313 1600 1704 751.5 388.9 210.2 558.38
1994 116.4 64.8 46.7 23.9 62.9 122 1842 3847 1982 685.1 392.2 147.4 777.70
1995 55.5 37.2 44.3 87.4 68.6 76.2 1077 2478 1123 294.1 185.1 107.7 469.51
1996 65.8 42.1 79.3 107.3 185.6 413.3 1992 3476 1416 641.2 369.5 250.3 753.20
1997 179.7 117.7 185.3 162.1 192.3 341.1 1414 1857 557.2 613.6 494.7 230.6 528.78
1998 180.8 65.1 46.2 33.6 100.4 114.8 1830 4238 1562 922.3 385.1 212.5 807.57
1999 155.6 126.3 72.5 62.2 27.7 75.8 1986 3286 1266 923.1 432.5 244.3 721.50
2000 158.3 112.4 35.5 112.5 54.4 52.7 1158 3053 1133 799.3 487.6 232.6 615.78
2001 88.9 88.4 208.5 214.2 178 282 2402 3293 1057 434.2 265.9 202.6 726.23
2002 237.7 210.5 189.5 196.4 151.8 216.4 846.7 2057 752.7 232.3 164.1 149.4 450.38
2003 129.9 122.7 142 137.3 98 143.4 1457 2553 969.7 275.8 162.4 154.9 528.84
1987 251.78 168.20 263.05 232.39 284.27 389.07 580.07 2944.88 1285.11 806.44 585.83 310.99
1988 184.45 147.77 83.84 69.17 36.68 86.72 3801.62 9549.90 5001.58 2435.29 1230.35 736.48
1989 398.50 240.78 217.98 271.17 117.90 137.29 1546.06 4068.86 2466.73 1138.39 637.71 483.39
1990 242.09 169.51 120.26 114.49 59.47 45.85 1345.11 3812.10 2492.93 1035.69 491.51 280.08
1991 166.37 129.95 100.35 146.98 145.15 155.89 3492.46 6793.66 3537.00 1499.95 796.48 473.43
1992 272.22 192.05 136.24 90.39 100.61 72.84 1086.25 5688.02 3065.40 1852.86 1066.08 590.81
1993 324.36 192.05 115.02 470.03 408.98 410.03 3440.06 4192.00 4464.48 1968.93 1018.92 550.72
1994 304.97 169.78 122.35 62.62 164.80 319.64 4826.04 10079.14 5192.84 1794.96 1027.56 386.19
1995 145.41 97.46 116.07 228.99 179.73 199.64 2821.74 6492.36 2942.26 770.54 484.96 282.17
1996 172.40 110.30 207.77 281.13 486.27 1082.85 5219.04 9107.12 3709.92 1679.94 968.09 655.79
1997 470.81 308.37 485.49 424.70 503.83 893.68 3704.68 4865.34 1459.86 1607.63 1296.11 604.17
1998 473.70 170.56 121.04 88.03 263.05 300.78 4794.60 11103.56 4092.44 2416.43 1008.96 556.75
1999 407.67 330.91 189.95 162.96 72.57 198.60 5203.32 8609.32 3316.92 2418.52 1133.15 640.07
2000 414.75 294.49 93.01 294.75 142.53 138.07 3033.96 7998.86 2968.46 2094.17 1277.51 609.41
2001 232.92 231.61 546.27 561.20 466.36 738.84 6293.24 8627.66 2769.34 1137.60 696.66 530.81
2002 622.77 551.51 496.49 514.57 397.72 566.97 2218.35 5389.34 1972.07 608.63 429.94 391.43
2003 340.34 321.47 372.04 359.73 256.76 375.71 3817.34 6688.86 2540.61 722.60 425.49 405.84
Water pressure at
5 maximum flood level PH 31392 26.67 837224.64
U1 1035.94 69 71479.86
U2 8675.96 44.67 387555.13
Uplift max. flood level
6 with drainage U3 1051.63 69.67 73267.06
Silt pressure Ps 1978.09 11.43 22609.57
70944 10763.5 33370.09 3365556 1392038.2
Σ 60180.47 33370.09 1973517.77
Water pressure at
maximum flood level PH 31392 26.67 837224.64
Extreme load
combination at PU1 9751.14 35.5 346165.47
maximum pool level
7 uplift pressure PU2 22984.83 47.33 1087872.00
8 Silt pressure Ps 1978.09 11.43 22609.57
Ph 961.4 4.67 4489.6446
9 Tail water pressure Pv 812.37 7.89 6409.5993
71756 32736 33370.1 3376455 2296983
Σ 39020.4 -32408.71 1079472.24