Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
DESCRIPTION
Disclaimer
The contents of this document are subject to revision without notice due to
continued progress in methodology, design and manufacturing. Ericsson shall
have no liability for any error or damage of any kind resulting from the use
of this document.
Trademark List
All trademarks mentioned herein are the property of their respective owners.
These are shown in the document Trademark Information.
Contents
1 Introduction 1
1 Introduction
Activities on the Operations Support System – Radio and Core (OSS-RC) and
at RBS sites are covered, and there are references to detailed instructions for
procedures. The integration process starts when configuration data is planned
but not defined in OSS-RC, and when the RBS hardware is installed at site
but not configured.
When the integration is completed the cells in the integrated RBS are unlocked
and ready to carry traffic.
• Security
• Licenses
This section describes the overall process for RBS autointegration, including
prerequisites and references to detailed procedures for different stages. For an
overview of the autointegration functions, including parameters and services,
see document RBS Autointegration.
Figure 1 shows stages initiated by users and stages automated with information
exchanged between nodes in the system. Although not shown in the figure,
users are continuously notified about the progress of the process through the
Integrate RBS application and OSS-RC. Continuous lines indicate stages
always part of the process while broken lines indicate optional stages.
1
2
3
4a 4b
4c
4d
4e
4f
4g
4h
4i
4j
4k
5
6
7
8
9
10
11a
11b
12
13
L0000046E
Key to Figure
1 Template Preparations
a Autointegration initiation
e Software upgrade
j Security activation
7 Unlocking of Cells
10 Configuration Backup
11 Testing RBSs
a Performing tests
14 Integration Completed
2.1 Prerequisites
To add an RBS to the network using RBS autointegration, the following
conditions must be met:
• The license for BSIM in OSS-RC is installed and activated, see the
OSS-RC document License Key Administration in OSS-RC.
0 BSIM
0 Common Explorer
• Serving Gateway (SGW) nodes and the Mobility Management Entity (MME)
nodes are installed, enabled, and prepared with S1 termination points; DNS
resolution for MME IP addresses are entered in DNSs.
To prepare templates, see the OSS-RC document OSS Utility Services, User
Guide.
OSS-RC
ONRM
SCS
Template files
1 3
OMSAS
2
BSIM
SMRS
4
DNS DHCP
Integration
Engineer
L0000099C
For each RBS there are also a number of options controlling what is, or is not,
included in the integration scenario:
To add RBSs with BSIM, see the OSS-RC document BSIM, Base Station
Integration Manager, User Guide.
The integration engineer also prepares a DNS server with DNS resolution for
MMEs and eNodeBs, see RBS Autointegration.
• BSIM checks that all mandatory input data and files are present
• BSIM defines the RBSs and cells, and adds the information to the OSS-RC
Network Resource Model (ONRM)
• If configuration over DHCP is used, then BSIM creates and stores RBS
parameters in DHCP servers, or, if third-party products are used for these
servers, compiles configuration files with the parameters
• BSIM creates and stores transport network data and radio network data for
each RBS in a planned area
• BSIM creates and stores configuration data for O&M communication and
RBS equipment on the SMRS, see document Configuration Files
• BSIM prepares the OSS-RC master server with an RBS site installation file
for each RBS; the files must be copied to be available at the RBS sites for
initiation of the autointegration; configuration over DHCP is an alternative to
site installation files
BSIM shows the progress for the operator throughout the process. BSIM also
makes the result of each autointegration available for the operator in a log file.
These OSS-RC preparations can be done at any time before the integration
activities at RBS-sites start.
b The Integrate RBS application configures the RBS with the specified
IP configuration data by creating Managed Objects (MOs) and setting
attributes on MOs.
c If any IP parameter is not supplied by the field technician, then the RBS
retrieves data prepared on a DHCP server.
d The Autointegration RBS Summary file, Site Basic, and Site Equipment
files are obtained from the Software Management Repository Services
(SMRS) server in OSS-RC and stored on the RBS. Also, an ISCF, UP, and
an LKF are obtained if specified in the Autointegration RBS Summary file.
0 Radio units
0 RET Support
0 Support system
0 TMA Support
If activation of the minimum security level fails, then the RBS repeats the
security preparation including retrieving an ISCF from SMRS.
k The RBS notifies OSS-RC that it is up and running. The RBS sends the
notification to different node discovery interfaces in OSS-RC depending
on security level.
The connection of the RBS to the MME is established based on the completed
configuration. No human intervention is required.
This stage runs in parallel with the previous stage and can be completed before
the configuration from OSS-RC is completed.
OSS-RC activates the added RBS by unlocking the cells making them available
for user plane traffic.
When OSS-RC is prepared the integration engineer can choose to have cells
unlocked or locked as a result of the integration.
The RBS may not immediately be ready to carry traffic when the configuration
finished message is received. Cells must be unlocked and to unlock cells is an
option in BSIM. The RBS must also synchronize to the external clock source
before all resources are enabled and ready to carry traffic. In most cases the
RBS is synchronized within 15 min. When using Clock Source over NTP the
IP network must have sufficiently low delay variations. In some IP networks,
the delay variation between the RBS and the time server is low enough to lock
the RBS clock to the time server, but so high that it takes significantly longer
than 15 min to synchronize the RBS.
The configuration report generated by the RBS shows if the RBS is ready to
carry traffic.
a Checks the hardware status, tests the external alarms, and tests user
plane traffic
b Completes the generated result report and stores it on the client and on an
FTP server
When automated activation of security was not included in the process above,
then the integration engineer manually configures the desired O&M security
level in the RBS, see Security for O&M Node Access and the OSS-RC
document Security System Administration, OSS-RC.
Ericsson recommends:
• Using the push log function to automate the upload of the security log and
the audit trail logs to an FTP server, see Log Service
In this scenario the LKF is not available when the field technician is at the site.
The field technician knows, before starting integration that, no LKF is available
and that the integration includes configuration of licensed resources.
In this scenario the field technician leaves the site before the integration is
completed. The integration continues as described in Section 2.2 on page 7 but
without the activities initiated by the field technician.
This section describes the overall process for integrating RBSs without support
from BSIM in OSS-RC, and with configuration files brought to the RBS site.
Prerequisites and references to detailed procedures for different stages are
included.
Figure 3 shows stages initiated by users and stages automated with information
exchanged between nodes in the system. Although not shown in the figure,
users are continuously notified about the progress of the process through the
Integrate RBS application and OSS-RC. Continuous lines indicate stages
always part of the process while broken lines indicate optional stages.
1
2
3a
3b
3c
3d
3e
3f
3g
3h
4
5
6a
6b
7a 7b
8
9
10
11a
11b
L0000078D
Key to Figure
1 OSS-RC Preparation
a Integration initiation
d Software upgrade
e LKF installation
6 S1 Configuration
8 Unlocking of Cells
10 Configuration Backup
11 Testing RBSs
a Performing tests
12 Integration Completed
3.1 Prerequisites
To add an RBS to the network using the semi-automated process, the following
conditions must be met:
0 SLS
0 ALEX
0 OMSAS
0 ARNE
• The SGW nodes and the MME nodes are installed, enabled, and prepared
with S1 termination points.
• The transport network is available for O&M traffic, control plane traffic,
and user plane traffic.
OSS-RC
ARNE ONRM
OSS Common
Explorer
SMRS
DNS
Integration
Engineer
DHCP
L0000100A
Table 2 shows tools and applications used, type of data, and references to
detailed instructions. The OSS-RC preparation can be done at any time before
the integration activities at RBS-sites start.
a The field technician initiates the integration using the Integrate RBS
application, see document Integrating RBSs On-Site. The prepared
configuration files must be accessible from the Integrate RBS application
as local files. If a software upgrade is planned and if licenses must be
installed, then an UP and a LKF must also be accessible from the Integrate
RBS application.
b The Integrate RBS application configures the RBS with the specified
IP configuration data by creating Managed Objects (MOs) and setting
attributes on MOs.
0 S1 and X2 interface
0 Radio units
0 RET Support
0 Support system
0 TMA Support
h The RBS notifies OSS-RC that it is up and running and OSS-RC starts
synchronizing the MIB with the RBS.
• Integrated IP Security
Ericsson recommends:
• Using the push log function to automate the upload of the security log and
the audit trail logs to an FTP server, see Log Service
3.2.6 S1 Configuration
The S1 interface is configured as follows:
a The integration engineer activates the planned area for the S1 configuration,
see the OSS-RC document PCA, Planned Configuration Administration,
User Guide
b The OSS-RC configures the S1 data in the RBS. The connection of the
RBS to the MME is established based on the completed configuration.
a The integration engineer activates the planned area for the cell network,
see the OSS-RC document PCA, Planned Configuration Administration,
User Guide
The integration engineer activates the added RBS by unlocking the cells
making them available for user plane traffic, see the OSS-RC document CEX,
OSS Common Explorer, User Guide.
The RBS may not immediately be ready to carry traffic after the unlock
procedure. The RBS must synchronize to the external clock source before
all resources are enabled and ready to carry traffic. In most cases the RBS
is synchronized within 15 min. When using Clock Source over NTP the IP
network must have sufficiently low delay variations. In some IP networks, the
delay variation between the RBS and the time server is low enough to lock
the RBS clock to the time server, but so high that it takes significantly longer
than 15 min to synchronize the RBS.
The configuration report generated by the RBS shows if the RBS is ready to
carry traffic.
The OSS-RC informs the OMC technician through the List of Network
Elements, that the RBS is integrated and activated.
a Checks the hardware status, tests the external alarms, and tests user
plane traffic
b Completes the generated result report and stores it on the client and on an
FTP server
When finished, the List of Network Elements in OSS-RC indicates that the
RBS has been integrated, activated, and tested.
In this scenario the LKF is not available when the field technician is at the site.
The field technician knows, before starting integration, that no LKF is available
and that the integration includes configuration of licensed resources.