Sei sulla pagina 1di 30

Copyright 2013 ISA. All Rights Reserved. www.isa.

org
Presented at ISA Automation Week 2013
Nashville, Tennessee •Renaissance Nashville, USA, 4-7 November 2013

THE HIGH PERFORMANCE HMI:


Proof Testing in a Real World Trial
November 2013 for ISA Automation Week 2013

Authors:
Bill Hollifield (bhollifield@pas.com)
PAS Principal Alarm Management and HMI Consultant
Hector R. Perez (hperez@pas.com)
PAS High Performance HMI Product Manager
PAS (www.pas.com)

Keywords
HMI, Graphics, Operator Effectiveness, Control Room, Process Simulator

Abstract

The human-machine interface (HMI) is the collection of screens, graphic displays, keyboards, switches,
and other technologies used by the operator to monitor and interact with the control system (typically
DCS or SCADA.) The design of the HMI plays a critical role in determining the operator’s ability to
effectively manage the operation, particularly in response to abnormal situations.

For several reasons, the current design and capability of most HMIs are far from optimal for running
complicated operations. Most of these consist simply of schematic-style graphics accompanied by
numbers. Such displays provide large amounts of raw data and almost no real information. They
provide inadequate situation awareness to the operator.

This paper concentrates on proper and effective design of the graphics used in modern control systems.
It also covers a major proof-test of the concepts, conducted by the Electric Power Research Institute at
a large coal-fired power plant in the U.S.

Distributed with permission of author(s) by ISA Automation Week 2013


Presented at ISA Automation Week 2013
Copyright 2013 ISA. All Rights Reserved. www.isa.org
Presented at ISA Automation Week 2013
Nashville, Tennessee •Renaissance Nashville, USA, 4-7 November 2013

HMIs Past and Present

Before the advent of sophisticated digital control systems, the operator’s HMI usually consisted of a
control wall concept.

The control wall (see Figure 1) had the advantages of providing an overview of the entire operation,
many trends, and a limited number of well-defined alarms. A trained operator could see the entire
operation almost at-a-glance. Spatial and pattern recognition played a key role in the operator’s ability
to detect burgeoning abnormal situations.

The disadvantages of these systems were that they were very difficult to modify. The addition of
incremental capability was problematic, and the ability to extract and analyze data from them was
almost non-existent. The modern electronic control systems (DCS/SCADA) replaced them for such
reasons.

Figure 1: Example of a Control Wall

When the modern systems were introduced, they included the capability to create and display graphics
for aiding in the control of the operation. However, there were no guidelines available as to how to
actually create effective graphics. Early adopters created graphics that mimicked schematic drawings,
primarily because they were readily available.

Distributed with permission of author(s) by ISA Automation Week 2013


Presented at ISA Automation Week 2013
Copyright 2013 ISA. All Rights Reserved. www.isa.org
Presented at ISA Automation Week 2013
Nashville, Tennessee •Renaissance Nashville, USA, 4-7 November 2013

Figure 2: An Early Graphic Exhibiting Many Problematic Practices

The limited color palette was used inconsistently and screens began to be little more than crowded
P&ID displays with numbers.

Graphics such as Figures 2 and 3 were developed over 20 years ago and remain common throughout
the industry. Indeed, inertia, not cost, is the primary obstacle to the improvement of HMIs. Engineers
and Operators become accustomed to this style of graphic and are resistant to change.

As a result, industries that use modern control systems are now running multi-million dollar operations
from primitive HMIs created decades ago, at a time that little knowledge of proper practices and
principles was available.

Distributed with permission of author(s) by ISA Automation Week 2013


Presented at ISA Automation Week 2013
Copyright 2013 ISA. All Rights Reserved. www.isa.org
Presented at ISA Automation Week 2013
Nashville, Tennessee •Renaissance Nashville, USA, 4-7 November 2013

Figure 3: A Typical Crowded, P&ID-Style Graphic

As control system hardware progressed, graphics from the manufacturers began to develop very flashy
example graphics which were used for marketing purposes. While good for that, they are quite
ineffective for actually controlling a process. Many companies and projects, however, began to use
those flashy examples. The results were displays that are actually sub-optimal for operators.

Figure 4 is an example of flashy design taken from a power generation facility to illustrate the point.
The graphic dedicates 90% of the screen space to the depiction of 3-D equipment, vibrantly colored
operation lines, cutaway views, and similar elements. However, the information actually used by the
operator consists of poorly depicted numerical data which is scattered around the graphic, and only
makes up 10% of the available screen area.

Distributed with permission of author(s) by ISA Automation Week 2013


Presented at ISA Automation Week 2013
Copyright 2013 ISA. All Rights Reserved. www.isa.org
Presented at ISA Automation Week 2013
Nashville, Tennessee •Renaissance Nashville, USA, 4-7 November 2013

Figure 4: A Flashy Graphic Inappropriate for Actual Operational Control

There are no trends, condition indicators, or key performance elements. You cannot easily tell from this
graphic whether the operation is running well or poorly. That situation is true for more than 90% of the
graphics used throughout the industry because they were not designed to incorporate such information.
Instead, they simply display dozens to hundreds of raw numbers lacking any informative context.

Justification for HMI Improvement


Poorly performing HMIs have been cited time and again as significant contributing factors to major
accidents (see references section for two major examples). Yet our industry has made no significant
change in HMI design. There is another industry that learns from its accidents and has made
phenomenal advancement in HMI design based on new technology. That industry is avionics. Lack of
situation awareness is a common factor cited in aviation and other transportation accident reports. (For
dozens of examples, go to http://www.ntsb.gov/search/search.aspx? and enter “situation awareness.”)

Modern avionics feature fully-integrated electronic displays (See Figure 5). These depict all of the
important information, not just raw data, needed by the operator (i.e., pilot). Position, course, route,
engine diagnostics, communication frequencies, and automated checklists are displayed on moving
maps with built-in terrain proximity awareness. Real-time weather from satellite is overlaid on the
map. Detailed database information on airports is available with just a click. Situation awareness and
abnormal situation detection is far improved by these advances. This capability – impossible even a
dozen years ago in multi-million dollar airliners – is now standard on even the smallest single engine
aircraft.

Distributed with permission of author(s) by ISA Automation Week 2013


Presented at ISA Automation Week 2013
Copyright 2013 ISA. All Rights Reserved. www.isa.org
Presented at ISA Automation Week 2013
Nashville, Tennessee •Renaissance Nashville, USA, 4-7 November 2013

Figure 5: Garmin G2000® Avionics Package in a Small Plane

Since safety is significantly improved with modern HMIs, it is only logical that we would want all
operators to have access to them. Yet most companies have done little to upgrade.

There have been tests involving actual operators running realistic simulations using traditional graphics
vs. High Performance ones. PAS participated in such a test at a large power plant, sponsored by the
Electric Power Research Institute (EPRI). The results were consistent with a similar test run by the
ASM® (Abnormal Situation Management) Consortium on an ethylene plant. The test showed the high
performance graphics provided significant improvement in the detection of abnormal situations (even
before alarms occurred), and significant improvement in the success rate for handling them. In the real
world, this translates into a savings of hundreds of thousands of dollars per year. Details of the test are
covered later in this paper.

Proper Graphic Principles


Ineffectively designed graphics are very easy to find. Simply search the internet for images under the
category “HMI”. Problems with these graphics include:
 Primarily a schematic representation
 Lots of displayed numbers
 Few trends
 Spinning pumps/compressors, moving conveyors, animated flames, and similar distracting
elements
 Brightly colored 3-D vessels
 Highly detailed equipment depictions
 Attempts to color code piping with contents
 Large measurement unit callouts
 Bright color liquid levels displaying the full width of the vessel

Distributed with permission of author(s) by ISA Automation Week 2013


Presented at ISA Automation Week 2013
Copyright 2013 ISA. All Rights Reserved. www.isa.org
Presented at ISA Automation Week 2013
Nashville, Tennessee •Renaissance Nashville, USA, 4-7 November 2013

 Lots of crossing lines and inconsistent flow direction


 Inconsistent color coding
 Misuse of alarm-related colors
 Limited, haphazard navigation
 A lack of display hierarchy

Ineffective graphics encourage poor operating practices, such as operating by alarm.

By contrast, High Performance graphics have:


 A generally non-schematic depiction except when functionally essential
 Limited use of color, where color is used very specifically and consistently
 Gray backgrounds to minimize glare
 No animation except for specific alarm-related graphic behavior
 Embedded, properly-formatted trends of important parameters
 Analog representation of important measurements, indicating their value relative to normal,
abnormal, and alarm conditions
 A proper hierarchy of display content providing for the progressive exposure of detailed
information as needed
 Low-contrast depictions in 2-D, not 3D
 Logical and consistent navigation methods
 Consistent flow depiction and layout to minimize crossing lines
 Techniques to minimize operator data entry mistakes
 Validation and security measures
 Embedded information in context (via right-click menus or similar methods) such as alarm
documentation and rationalization, standard operating procedures, etc.

Data or Information?
A primary difference of high performance graphics is the underlying principle that, wherever possible,
operational values are shown in an informational context and not simply as raw numbers scattered
around the screen.

“Information is data in context made useful.”

As an example, consider this depiction of a compressor (see Figure 6). Much money has been spent on
the purchase of instrumentation. Yet, unless you are specifically trained and experienced with this
compressor, you cannot tell if it is running at peak efficiency or is about to fail.

Distributed with permission of author(s) by ISA Automation Week 2013


Presented at ISA Automation Week 2013
Copyright 2013 ISA. All Rights Reserved. www.isa.org
Presented at ISA Automation Week 2013
Nashville, Tennessee •Renaissance Nashville, USA, 4-7 November 2013

190.5 psig
55.7 psig 155.2 °F 108.2 °F 166.1 °F
65.1 °F 2.77
135.1 Cooler MSCFH
psig
Oil 155.2 °F
Oil 85.1 psi

West East

W. Vibration: 2.77 E. Vibration: 3.07

Drive: 232.2 amps


Figure 6: All Data, No Information

The mental process of comparing each number to a memorized mental map of what is good is a
difficult cognitive process. Operators have hundreds (or even thousands) of measurements to monitor.
Thus the results vary by the experience and memory of the operator, and how many abnormal situations
they have experienced with this particular compressor. Training new operators is difficult because the
building of these mental maps is a slow process.

Adding more numbers to a screen like this one does not aid in situation awareness; it actually detracts
from it.

By contrast, these numbers can be represented in a bank of analog indicators, as in Figure 7. Analog is
a very powerful tool because humans intuitively understand analog depictions. We are hard-wired for
pattern recognition.

With a single glance at this bank of properly designed analog indicators, the operators can tell if any
values are outside of the normal range, by how much, and the proximity of the reading to both alarm
ranges and the values at which interlock actions occur.

Distributed with permission of author(s) by ISA Automation Week 2013


Presented at ISA Automation Week 2013
Copyright 2013 ISA. All Rights Reserved. www.isa.org
Presented at ISA Automation Week 2013
Nashville, Tennessee •Renaissance Nashville, USA, 4-7 November 2013

RECYCLE COMPRESSOR K43


Cool Suct Inter Dsch Suct Inter Dsch E. Vib N. Vib W. Vib Motor Oil Oil
gpm psig psig psig degF degF degF mil mil mil Amps psig degF
Alarm
2
Indicator

Interlock
Threshold

Alarm
Range

Desirable
Operating
Range

Alarm
Range
42.7 38.7 93.1 185 95 120 170 12 8 9 170 80 290

Figure 7: Analog Depiction of Information

In just a second or two of examination, the operator knows which readings, if any, need further
attention. If none do, the operator can continue to survey the other portions of the operation. In a series
of short scans, the operator can be fully aware of the current performance of their entire span of control.

The knowledge of what is normal is embedded into the HMI itself, making training easier and
facilitating abnormal situation detection – even before alarms occur, which is highly desirable.

Similarly, depiction of PID controllers is accomplished with the addition of easily scanned setpoint,
mode, and output information as in Figure 8.

Distributed with permission of author(s) by ISA Automation Week 2013


Presented at ISA Automation Week 2013
Copyright 2013 ISA. All Rights Reserved. www.isa.org
Presented at ISA Automation Week 2013
Nashville, Tennessee •Renaissance Nashville, USA, 4-7 November 2013

Analog Controller: Add If Final Control


Setpoint, Output, and Mode Element has
to standard analog indicator Position feedback:

2 2
Shows any
mismatch
between
Output bar
32.1 output and
Scaled
actual
0-100%
position
Setpoint
Diamond Actual
562.1 562.1 Position Small
AUTO AUTO
485.0 485.0 Mismatch
AUTO
2%44% 2% 22% Output

Setpoint diamond and PV pointer line up when


controller is working properly

Figure 8: Analog Depiction of PID Controllers

Color
Color must be used consistently. There are several types of common color-detection deficiency in
people (e.g. red-green, white-cyan, green-yellow). For this reason:

Color, by itself, is never used as the sole differentiator of an important condition or status.

Most graphics throughout the world violate this principle. A color palette must be developed, with a
limited number of distinguishable colors used consistently.

Bright colors are primarily used to bring or draw attention to abnormal situations, not normal ones.
Screens depicting the operation running normally should not be covered in brightly saturated colors,
such as red or green pumps, equipment, valves, etc.

When alarm colors are chosen, such as bright red and yellow, they are used solely for the depiction of
an alarm-related condition and functionality and for no other purpose. If color is used inconsistently,
then it ceases to have meaning.

So what about the paradigm of using bright green to depict “on” and bright red for “off”, or vice versa
for the power industry (i.e. red means energized)? This is an improper use of color. The answer is a
depiction such as Figure 9.

Distributed with permission of author(s) by ISA Automation Week 2013


Presented at ISA Automation Week 2013
Copyright 2013 ISA. All Rights Reserved. www.isa.org
Presented at ISA Automation Week 2013
Nashville, Tennessee •Renaissance Nashville, USA, 4-7 November 2013

Wrong Better

Pump Not
Running STOPPED
(Shape is Filled
Darker)

Pump
Running
RUNNING
(Shape is Filled
Wrong Better
Brighter)

Figure 9: Depicting Status with Redundant Coding and Proper Color Usage

The relative brightness of the object shows its status, plus a Process Value WORD next to it.
Equipment items brighter than the background are on (think of a light bulb inside them). Items darker
than the background are off. If equipment has no status that is sensed by the control system, but is
desired to be shown on the graphic anyway, it is shown with a fill the same as the background color.

Alarm Depiction
Proper alarm depiction should also be redundantly coded based upon alarm priority (color / shape /
text). Alarm colors should not be used for non-alarm related functionality.

When a value comes into alarm, the separate alarm indicator appears next to it (See Figure 10). The
indicator flashes while the alarm is unacknowledged (one of the very few proper uses of animation)
and ceases flashing after acknowledgement, but remains as long as the alarm condition is in effect.
People do not detect color change well in peripheral vision, but movement, such as flashing, is readily
detected. Alarms thus readily stand out on a graphic and are detectable at a glance.

Distributed with permission of author(s) by ISA Automation Week 2013


Presented at ISA Automation Week 2013
Copyright 2013 ISA. All Rights Reserved. www.isa.org
Presented at ISA Automation Week 2013
Nashville, Tennessee •Renaissance Nashville, USA, 4-7 November 2013

Figure 10: Depiction of Alarms

It is highly beneficial to include access within the HMI to the alarm rationalization information
contained in the Master Alarm Database (See Figure 11). If these terms are unfamiliar, you are advised
to read the EPRI Guideline on Alarm Management or the ISA 18.2 standard for Alarm Management.

3
122.1 degC TI-468-02 Column
Overhead Temperature
Shape and Size
Alarm: PVHI
Right-click call-up Class: Minor Financial of a standard
Priority: 3
faceplate if
Setting: 320 deg F
Response Time: <15 min possible
Alarm Consequences:
Reveal Alarm Off spec Production
Lowered efficiency
Rationalization
Alarm Causes:
documentation Excess steam
Pressure excursion
on demand! Insufficient reflux
Feed composition variance
Corrective Actions:
Information Adjust base steam rate
Check pressure and feed
recalled from parameters vs. SOP 468-1 Link to
your Master
Adjust reflux per Procedures
Alarm Database computation; check
controller for cascade mode
Check feed composition

Figure 11: Linked Alarm Information

Distributed with permission of author(s) by ISA Automation Week 2013


Presented at ISA Automation Week 2013
Copyright 2013 ISA. All Rights Reserved. www.isa.org
Presented at ISA Automation Week 2013
Nashville, Tennessee •Renaissance Nashville, USA, 4-7 November 2013

Trends
The most glaring deficiency in HMI today is the general lack of properly implemented trends. Every
graphic generally has one or two values on it that would be far better understood if presented as trends.
However, the graphics rarely incorporate them.

Instead, engineers and managers believe claims made by control systems vendors that the operators can
easily trend any value in the control system on demand with just a click. This is incorrect in practice; a
properly scaled and ranged trend may take 10 to 20 clicks/selections to create, and usually disappears
into the void if the screen is used for another purpose!

This deficiency is easily provable; simply walk into the control room and count how many trends are
displayed. Our experience in hundreds of control rooms is that trends are vastly underutilized and
situation awareness suffers due to that.

55.0 West Comp Flow MSCFH 49.1

45.0
-90 -60 -30 2 Hours

50.0 West Comp Discharge Temp °C 44.1

40.0
-90 -60 -30 2 Hours
5000
15
Main
Steam
4150
Feed
Water
3280
Drum
Level
-0.5
0
-10 1 Hr

Figure 12: Trend Depiction of Desirable Ranges

Distributed with permission of author(s) by ISA Automation Week 2013


Presented at ISA Automation Week 2013
Copyright 2013 ISA. All Rights Reserved. www.isa.org
Presented at ISA Automation Week 2013
Nashville, Tennessee •Renaissance Nashville, USA, 4-7 November 2013

Trends should be embedded in the graphics and appear, showing proper history, whenever the graphic
is called up. This is generally possible, but is a capability often not utilized.

Trends should incorporate elements that depict both the normal and abnormal ranges for the trended
value. There are a variety of ways to accomplish this (See Figure 12).

Level Indication
Vessel levels should not be shown as large blobs of saturated color. A simple strip depiction showing
the proximity to alarm limits is better. A combination of trend and analog indicator depictions is even
better (See Figure 13).

2
100
Crude
Feed
TK -21

0
2 Hrs 86.5%

Very Poor Better Trend and


Vessel Vessel Analog
Level Level Level
Indication Indication Indication

Figure 13: Vessel Levels

Bar Charts
Attention to detail is important. It is typical to use bar charts to show relative positions and values.
While this may be better than simply showing numbers, it is inferior to the use of moving pointer
elements since as the bar’s value gets low, the bar disappears. “Zero” may be a very important
condition! The human eye is better at detecting the presence of something than its absence. The
example in Figure 14 is superior in showing relative values, besides the color improvement.

Distributed with permission of author(s) by ISA Automation Week 2013


Presented at ISA Automation Week 2013
Copyright 2013 ISA. All Rights Reserved. www.isa.org
Presented at ISA Automation Week 2013
Nashville, Tennessee •Renaissance Nashville, USA, 4-7 November 2013

Analog Position – Poor Bar Graphs

0% 25% 50% 75% 100%


Valve
V-1 100%
V-2 100%
V-3 95%
X-1 88%
X-2 100%
X-3 100%
X-4 75%
S-1 0%
S-2 55%
K-1 100%
K-2 100%

Analog Position - Better

0% 25% 50% 75% 100%


Valve
V-1 100%
V-2 100%
V-3 95%
X-1 88%
X-2 100%
X-3 100%
X-4 75%
S-1 0%
S-2 55%
K-1 100%
K-2 100%

Figure 14: Bars vs. Pointers

Tables and Checklists


Even tables and checklists can incorporate proper principles (See Figure 15). Consistent colors and
even status indication can be integrated.

Distributed with permission of author(s) by ISA Automation Week 2013


Presented at ISA Automation Week 2013
Copyright 2013 ISA. All Rights Reserved. www.isa.org
Presented at ISA Automation Week 2013
Nashville, Tennessee •Renaissance Nashville, USA, 4-7 November 2013

Air Status Mode Diag


Comp

C #1 RUNNING AUTO OK

C #2 STOPPED MAN OK
C #3 RUNNING AUTO OK

C #4 STOPPED AUTO FAULT 3

Startup Permissives
Breaker 15 Power OK
Oil Temp 16-33 OK
Oil Pres Status OK
Level in TK-8776 OK
Gen System Status OK
Comp 88 in Auto NOT OK
Lineup Ready OK
Sys Status Checks OK
Bearing Readouts NOT OK
Comm check OK
Outlet Temp < 250 OK
Cooling Flow NOT OK
Internal Circuit Check OK
Bypass Closed OK
AFS Function OK

Figure 15: Tables and Checklists

There are dozens of additional principles like these. See the References section.

Display Hierarchy
Displays should be designed in a hierarchy that provides progressive exposure of detail. Displays
designed from a stack of schematic designs will not have this; they will be “flat” – like a computer hard
disk with one folder for all the files. This does not provide for optimum situation awareness and
control. A four-level hierarchy is desired.

Distributed with permission of author(s) by ISA Automation Week 2013


Presented at ISA Automation Week 2013
Copyright 2013 ISA. All Rights Reserved. www.isa.org
Presented at ISA Automation Week 2013
Nashville, Tennessee •Renaissance Nashville, USA, 4-7 November 2013

Level 1 –Operation Overview


This is a single display showing the operator’s entire span of control, the big picture. It is an overall
indicator as to how the operation is running. It provides clear indication of the current performance of
the operation by tracking the Key Performance Indicators (See Figure 16).

Control interactions are not made from this screen.

5000 7500 1200


Unit 2 5000 1250 1200
Overview 15 5 3000

05-31-10 Steam Air Steam


KLBH KLBH °F
13:22:07 4750 7400 990
Total Fd Wtr Coal Reheat
Alarms KLBH KLBH °F
4580 1000 1005
1 0
Drum Furn Steam
Lvl in. Pres psig
-0.5 -0.5
2 8 2400
1 Hr 1 Hr 1 Hr
0 0 600
3 5 0 0 600
-15 -5 0
Status Alarms Pump Status / Alarms Fan Status / Alarms
PULV A-ON E-ON A B C D PUMPS A2 CWP A2 HWP C2 HWP A2BFPT A2 ECW A2 FD B2 FD A2 PA C-SBAC
B-ON F-ON AND ON ON ON ON ON ON ON ON ON
C-ON G-OFF E F G H FANS B2 CWP B2 HWP SUBFP B2BFPT B2 ECW A2 ID B2 ID B2 PA D-SBAC
D-ON H-ON ON OFF ON ON ON ON ON ON ON

Turbine – Generator LPT-A LPT-B Hydrogen Hydrogen Turb Oil Stator Condenser–Feed Wtr Drum Lvl HW Lvl DA Lvl DA Wide Cond Hdr
Gross MW Net MW MVAR HZ in.hg in.hg psig °F °F GPM A2 BPFT B2 BPFT in.H2O in.H2O in.H2O FT.H2O psig

702.1 640.1 - 5.2 60.00 0.2 0.2 49.1 104 115 351 3.1 3.1 -0.5 20.1 0.0 9.0 400
AUTO AUTO AUTO AUTO
Boiler BBD Econ Econ Gas Aux Stm Fans A2 ID A2 FD B2 ID B2 FD Econ Sec Air CEMS/MISC NOX SO2 Stack CO Inst Air
A/F Ratio pH pH Out °F psig Furn in.H2O Stall Stall Stall Stall % O2 in.H2O % Opac #/MMBTU #/MMBTU ppm psig

7.1 9.4 9.4 775 300 - 0.5 25 25 25 25 6.0 7.0 21.0 0.45 0.9 200 90

Figure 16: Example Level 1 Display

The Figure 16 example is from a large power plant. We often hear “But it doesn’t look like a power
plant?!” Correct! Does your automobile instrument panel look like a diagram of your engine? The
display is designed so that important abnormal conditions and alarms stand out clearly.

Level 2 –Unit Control


Every operation consists of smaller, sectional unit operations. Examples include a single generator or
reactor, a pipeline segment, a distillation train, or a compressor station. A level 2 graphic exists for

Distributed with permission of author(s) by ISA Automation Week 2013


Presented at ISA Automation Week 2013
Copyright 2013 ISA. All Rights Reserved. www.isa.org
Presented at ISA Automation Week 2013
Nashville, Tennessee •Renaissance Nashville, USA, 4-7 November 2013

each separate major unit operation. It is designed to contain all the information and controls required to
perform most operator tasks associated with that section, from a single graphic (See Figure 17).

Feed Composition Coolant: Cat. Purge Conv. Feed ADTV-1 ADTV-2 Temp Pres Product: Thionite State: Mid-Run RTAM: ON-OK
%A %B %C GPM °C Act% MCFH Eff. % MPH MPH MPH °C psig
Reserved
Run Plan: Faceplate Zone
Actual:

I-5A I-5B I-5C Interlock Actions:


I I I When any item
Feed ADTV-1 ADTV-2 Stop Feed OFF
Stop ADTV-1 OFF on the screen is
I-5D I-5E I-5F Stop ADTV-2 OFF selected, the
I Temp I Pres I Level Max Cooling OFF faceplate for
Max Vent OFF
that item
appears in this
SHUT
80.5 15.5 4.0 80.5 15.5 4.0 80.5 15.5 77.5 11.9 4.0 45.0 97.2 VENT FREEZE ISOLATE reserved area.
AUTO AUTO AUTO AUTO AUTO DOWN
M5 M5 M5
76.0
33.1%
12.0
22.3%
4.0
44.3%
45.0 95.0 M5 All control
54.1% 44.3%
manipulation is
accomplished
Material Balance through the
80.0

Feed VENT SYS Reset standardized


MPH OPEN faceplates.
OPEN OPEN OPEN OPEN
To Coils Lvl Prod
OP Reactor M5 Agitator % MPH
4
72.0 ON
-90 -60 -30 2 Hrs +10%
Analysis: Purity %
14.0 40.0
Main Menu
Chem
1 0%
L2 M5 Startup
MPH
OP L2 M5 Scram
-10%
10.0
-90 -60 -30 2 Hrs 32.0
-90 -60 -30 2 Hrs L2 Feed System
75.9 92.0
AUTO
6.0
Analysis: Inhibitor Concentration % 75.0 L2 Prod Recovery
54.3% IN OUT %DIFF
Chem 6.0 Tot. In: 19707
2 L2 Compression
Tot Out: 19301
MPH
Calc Diff: 2.1 % L2 RX Summary
OP Hours: 238.1
---- Level 3 ----
2.0 OPEN 5.0 %
-90 -60 -30 2 Hrs Daystrom Pumps
48.0
4.0
-90 -60 -30 2 Hrs M5 Circ
M5 Interlocks
PRODUCT
Temp 74.3 %
°C
75.8 Backup Lvl % M5 Cooling Sys
OPEN
Pump A RUNNING OK
M5 Vent Sys
OP
Pumps Pump B STOPPED FAULT 3
40.0
-90 -30 2 Hrs Needed 1 M5 Agitator
-60

Figure 17: Example Level 2 Display of a Reactor

Level 3 –Unit Detail


Level 3 graphics provide all of the detail about a single piece of equipment. These are used for a
detailed diagnosis of problems. They show all of the instruments, interlock status, and other details. A
schematic type of depiction is often desirable for a Level 3 display (See Figure 18).

Distributed with permission of author(s) by ISA Automation Week 2013


Presented at ISA Automation Week 2013
Copyright 2013 ISA. All Rights Reserved. www.isa.org
Presented at ISA Automation Week 2013
Nashville, Tennessee •Renaissance Nashville, USA, 4-7 November 2013

West Compressor Speed Tot Flow 1 Stg 2 Stg CLR IN CLR OUT Winding MANUAL ACTIONS
% MSCFH psi psi °C °C °C Reserved
20.1 psi Faceplate Zone
OH EAST COMP
IDLE PURGE
WEST WC Speed WEST WEST
P 90.8 % When any item
COMP S 90.0 COMP COMP
OPEN RUNNING O 90.0 % on the screen is
CAS selected, the
faceplate for
111.0 °C
that item
95.1 Oil psi
appears in this
SHUT reserved area.
48.0 psi ISOLATE DOWN
65.0 °C WEST All control
1st 90.8 76.8 48.0 90.0 65.0 32.0 111.0 WEST
CAS AUTO COMP COMP manipulation is
Stage 20.0 °C 90.0 76.0 accomplished
Inter- 90.0 % 88.5 %
cooler CW through the
standardized
28.0 °C faceplates.
44.0 °C 2nd
Stage 32.0 °C Flow Demand
P 76.8 MSCFH FLOW-SPEED
EAST COMP S 76.0 CASCADE
O 88.5 % IN EFFECT
OPEN AUTO
90.0 psi 48.4 MSCFH
RECOVERY
Main Menu

50.0 West Comp Discharge Temp °C 55.0 West Comp Flow MSCFH 95.0 West Comp Speed % L2 Compression

L2 Recovery
---- Level 3 ----
Sequence Overlay

Startup Overlay
40.0 45.0 85.0
-90 -60 -30 2 Hours -90 -60 -30 2 Hours -90 -60 -30 2 Hours West Interlocks

I W-1A I W-1B I W-1C West Cooling


West Compressor Interlock Initiators Mech Flow Pres West Compressor Interlock Actions

Comp in Overspeed 1 Stg Pres is High W. Comp Shutdown Flow Cascade to Manual East Comp
NO NO NO NO
Winding Temp is High 2 Stg Pres is High Inlet Block Valve Maximum Flow Bypass CLOSED ---- Level 4 ----
NO NO OPEN
Vibration is High Suction Pres is Low Outlet Block Valve Maximum Cooling Logic Diagrams
NO NO OPEN NORM
Oil Pres is Low NO Total Flow is Low NO E. Comp Override to 100% NO Winding Purge OFF Procedures

Figure 18: Example Level 3 Display

Level 4 –Support and Diagnostic Displays


Level 4 displays provide the most detail of subsystems, individual sensors, or components. They show
the most detailed possible diagnostic or miscellaneous information. A “Point Detail” display is a
typical example. The dividing line between Level 3 and Level 4 displays can be somewhat gray.

A Real-World Case Study and Test of HP HMI Concepts


The following section is taken from a study conducted by the Electric Power research Institute (EPRI).

Operator HMI Case Study: The Evaluation of Existing “Traditional” Operator Graphics vs. High
Performance Graphics in a Coal Fired Power Plant Simulator , Product ID 1017637

The EPRI study tested these HP HMI concepts at a large, coal-fired power plant. The plant had a full
simulator used for operator training. The existing graphics on the simulator (created in the early 1990s)
operated the same as those on the actual control system. PAS was retained to prepare several high
performance graphics for the simulator. Several operators were then put through several abnormal
situations using both the existing and the new high performance graphics.

Distributed with permission of author(s) by ISA Automation Week 2013


Presented at ISA Automation Week 2013
Copyright 2013 ISA. All Rights Reserved. www.isa.org
Presented at ISA Automation Week 2013
Nashville, Tennessee •Renaissance Nashville, USA, 4-7 November 2013

Four examples of the existing graphics are in Figure 19. They have the following characteristics:
• No graphic hierarchy
• No Overview
• Many controller elements are not shown on any of the existing graphics
• Numbers and digital states are presented inconsistently
• Poor graphic space utilization
• Inconsistent selectability of numbers and elements
• Poor color choices, overuse, and inconsistencies. Bright red and yellow are used for
normal conditions.
• Poor interlock depiction
• No trends are implemented, “trend-on-demand” is not used.
• Alarm conditions are generally not indicated on graphics – even if the value is a
precursor to an automated action.

• Existing Overview

Figure 19: 1990s Graphics from the EPRI HP-HMI Test

The operators used dozens of such graphics to control the process.

Distributed with permission of author(s) by ISA Automation Week 2013


Presented at ISA Automation Week 2013
Copyright 2013 ISA. All Rights Reserved. www.isa.org
Presented at ISA Automation Week 2013
Nashville, Tennessee •Renaissance Nashville, USA, 4-7 November 2013

PAS prepared the following high performance graphics:


 Power Plant Overview (Level 1) – see figure 16.
 Pulverizer Overview Graphic (Level “1.5”) – see Figure 20
 Individual Pulverizer Level 2 Control Graphic – see Figure 21
 Runback 1 and 2: Special Abnormal Situation Graphics – see Figure 22

The Level 1 Overview (see prior Figure 16)


The Overview graphic shows the key performance indicators of the entire system under the operator’s
control. The most important parameters incorporate trends. It is easy to scan these at a glance and
detect any non-normal conditions. Status of major equipment is shown. Alarms are easily detected.

The operators found the overview display to be far more useful than the existing graphics in providing
overall situation awareness and useful in detecting burgeoning abnormal situations.

The Level “1.5” Pulverizer Overview Graphic (Figure 21)


The operator controls eight identical, heavily instrumented, and complex pieces of equipment called
coal pulverizers. At normal rates, seven are in use and one is on standby in case of a problem. The
seven that are running should be showing almost identical performance. It was immediately apparent
that an “Overview” graphic of just these eight items would be very useful to the operators, since much
of their activity is in monitoring and manipulating them. Being mechanical, they are subject to a variety
of problems and abnormal conditions. There were three separate existing graphics needed for
monitoring and controlling each pulverizer, 24 in total for them all. Monitoring using 24 graphics was
difficult for the operators.

The new Pulverizer Overview in Figure 21 depicts more than 160 measurements on a single graphic!
The key to making this understandable is that the devices are supposed to run alike. Instead of blocks
of indicators for each pulverizer being grouped together, the same measurement from each pulverizer
is grouped together. Any individual unit operating differently than the others stands out. The unit that is
in standby service also is easily seen. Air damper positions, a source of problems, are clearly shown.

Note that the trends seemingly violate our recommendation of showing no more than 3 or 4 traces on a
single trend. In this case, what the operator is looking for is any trend line that is not “bunched in” with
the others. For such a condition, having these 8 traces was acceptable. Note that the standby
pulverizer’s trace is normally on the bottom.

Even with such a “dense” information depiction and with so many measurements, the operators found
it easy to monitor all eight devices and easily detect burgeoning abnormal situations. It is easy to scan
your eye across the screen and spot any elements that are inconsistent. Alarm conditions are also easy
to spot.

Note that control actions are not taken on this screen, but rather on the eight individual Level 2
graphics, one for each pulverizer.

Distributed with permission of author(s) by ISA Automation Week 2013


Presented at ISA Automation Week 2013
Copyright 2013 ISA. All Rights Reserved. www.isa.org
Presented at ISA Automation Week 2013
Nashville, Tennessee •Renaissance Nashville, USA, 4-7 November 2013

PULVERIZER OVERVIEW 08-15-2009 14:22:09


Pulverizer Status Coal Flow Trend Mill Amps Trend Diff Pres Trend Pri. Air Flow Trend Primary Damper
A B C D E F G H A B C D E F G H A B C D E F G H A B C D E F G H A B C D E F G H
Burn A A A A M A A A A A A A M A A A A A A A M A A A A A A A M A A A A A A A M A A A
Diag Maint
S S S H H
A ON
B ON
C ON
D ON
E OFF L
F ON
G ON
H ON 113 112 0 112 42 42 0 43 8.0 10.0 0.6 9.5 204 204 0 204 75 78 76 75 51 50 75 55
113 113 113 112 43 44 43 43 9.8 9.5 9.8 9.0 205 205 205 205
74 45 74 74 50 50 65 51
S. Air Flow Trend North Damper South Damper C/A Temp Trend Hot Damper Cold Damper
A B C D E F G H A B C D E F G H A B C D E F G H A B C D E F G H A B C D E F G H A B C D E F G H
A A A A M A A A A A A A M A A A A A A A M A A A A A A A M A A A A A A A M A A A A A A A M A A A
S H

204 204 0 204 75 78 78 75 0 50 75 55 75 78 78 75 30 50 75 55 135 135 277 135 75 78 78 75 40 50 75 55 75 78 78 75 50 50 75 55


205 205 205 205 135 135 135 135
74 77 78 74 0 50 76 51 74 77 78 74 30 50 73 51 74 77 78 74 40 50 65 51 74 77 78 74 50 50 73 51
16 140
Diff Coal
Flame M1 M2 Pres Flow
PSI KLB/HR
Main A A
Flame B B
C C
ON
90 90 D D
ON
8
Igniter
E E
Flame
F F
Fuel Type G G
Gas -1 30 30 H H
OFF OFF

SWG Valves OPEN OPEN

FlmMnt
Flm MntMod
Mod NORM NORM 2 Hrs 2 Hrs
0 1

L1 OVERVIEW RUNBACK 1 RUNBACK 2 PULV A PULV B PULV C PULV D PULV E PULV F PULV G PULV H

Figure 20: The Level “1.5” Pulverizer Overview

The Level 2 Pulverizer Control Graphic (Figure 21)


Rather than using three separate graphics to control each pulverizer (24 graphics total), a single Level 2
graphic for each pulverizer was created with everything needed to accomplish all typical control
manipulations.

Distributed with permission of author(s) by ISA Automation Week 2013


Presented at ISA Automation Week 2013
Copyright 2013 ISA. All Rights Reserved. www.isa.org
Presented at ISA Automation Week 2013
Nashville, Tennessee •Renaissance Nashville, USA, 4-7 November 2013

PULVERIZER A – Level 2 14:22:09


Flow Diff-P Amps “A” Primary Air Flow KLB/HR H. Dmp C.Dmp
“A” Coal Flow KLB/HR Damper “A” C/A Temperature

140 220 200

113.0 10.7 45 205.0 50.0 135 72.1% 31.0%


AUTO AUTO CAS AUTO AUTO AUTO
2 Hrs 115.0 2 Hrs 200.0 49.0% 130 70.0% 30.0%
40 120 2 Hrs
75.0% 65.0% 48.0% 0 71.2% 70.1% 27.8%
Flow Air-N Air-S N Damp S. Damp GAS PSI
“A” Sec. Air Flow (Total) Flame A1 A2 A3 A5 A6 A7
900
Main
Flame
90 88 90 91 91 94
ON ON ON ON ON ON Face
Igniter Plate
Flame Zone
Fuel Type: 30 30 30 30 30 30
Gas OFF OFF OFF OFF OFF OFF
615.2 312 312 50% 50% 5.9
AUTO CAS CAS SWG Valves OPEN OPEN OPEN OPEN OPEN OPEN AUTO
600.0 50% 50% 10.0
400 2 Hrs
60.0% 56% 42% Maint Mode NORM NORM NORM NORM MNT-B NORM 82%

Sequence Blocked By:


“A” PULVERIZER STARTING STOP PULV “A” PULV “A”
Start Sequence All PA f ans stopped or PAH stopped Group Trip TRIP VALVES
LTR oil press low or HDR VLV not open
Status Done Status Done Feeder inlet gate not open Trip Status OK IG HDR VENT CLOSED
Begin Sequence Ready Start Pulv Ready Pulv seal air dif f press low
Reset IG GAS TRIP CLOSED
Sec Air to L.O. Ready Start Feeder HOLD LTR atom air press low
Min boiler A.F. required IG OIL TRIP CLOSED
PTR Status OK
Start Ltrs. Ready Pulv Tmp to Auto X Flame detected
BURNER VENT CLOSED
Reset
Pulv Grp Dmd Ready Rel Sec Air X Flame det clg air press lo

Lube oil press low OK


Start PA Flow Ready Stop Ltrs X Flame Status Open Swg Valves
Any Pulv group trip not reset
Open Swg Vlvs Ready Rel Pul Dmd X Reset
No coal on f eeder belt
Any Seal Air blower stopped

PULV OVERVIEW PULV B PULV C PULV D PULV E PULV F PULV G PULV H L3 Feeder L3 Flame L3 GAS Main Menu

Figure 21: Level 2 Pulverizer Control

While complex in appearance to the layman, the trained operator had no difficulty in understanding and
accessing everything they needed for pulverizer startup, shutdown, and swap situations that arose
during the test. Much of the text on the screen has to do with the status of automated sequences that
sometimes require operator intervention. Everything on the screen is selectable, and when selected the
standard faceplate for the element appears in a reserved “faceplate zone” rather than floating around the
screen obscuring the graphic. Element manipulation is made via the faceplate.

Abnormal Situation Response Graphics


The operator response for many abnormal plant situations is to cut rates by half, from 700MW to
350MW. Called a “Runback,” this is a complicated and stressful procedure that takes about 20 minutes
to accomplish. If done incorrectly or if important parameters are missed, the plant can fall to zero
output, a very undesirable situation. One of the main purposes of the simulator was to regularly train
the operators for this situation. The operators have to use more than a dozen of the existing graphics to
accomplish the task, involving much navigation, screen callups and dismissals, and control
manipulation.

Distributed with permission of author(s) by ISA Automation Week 2013


Presented at ISA Automation Week 2013
Copyright 2013 ISA. All Rights Reserved. www.isa.org
Presented at ISA Automation Week 2013
Nashville, Tennessee •Renaissance Nashville, USA, 4-7 November 2013

However, in more than a decade of such training, it had never occurred to anyone to design special
graphics specifically designed to assist in this task! This demonstrates the power of inertia in dealing
with our HMIs. Specific Abnormal Situation Detection and Response graphics are an important
element of an HP HMI.

PAS created two “Runback” graphics designed specifically to assist in this task. Every element that the
operator needed to effectively monitor and control the runback situation was included on them. In use,
the operators placed them on adjacent physical screens. Figure 22 shows “Runback 1,” Runback 2 was
similar. The reserved faceplate zone is on the lower right.

Figure 22: Abnormal Situation Graphics – Runback 1

As a simple example of providing information rather than data, consider the trend graph at the upper
left of Runback 1. To be successful, the rate of power reduction must not be too slow or too fast. The
existing graphics had no trend of this, simply showing the current power megawatt number. This new
trend graph had the “sloped-line” element placed next to it, indicating the ideal rate of power reduction,
the full load zone, and the target half-rate zone. On the figure, the actual rate of drop is exceeding the
desired rate, and that condition is easily seen. (Note: It would have been more desirable to have the

Distributed with permission of author(s) by ISA Automation Week 2013


Presented at ISA Automation Week 2013
Copyright 2013 ISA. All Rights Reserved. www.isa.org
Presented at ISA Automation Week 2013
Nashville, Tennessee •Renaissance Nashville, USA, 4-7 November 2013

sloped lines on the background of the trend area itself, but the DCS could not accomplish such a
depiction. This is a compromise, but one the operators still found very useful.)

The Testing
Eight Operators, averaging 8 years console operating experience each, were used in the test. They
received only one hour’s familiarity with the new graphics prior to the start of testing. They were
tested on four increasingly complex situations, lasting about 20 minutes each.
 Coal Pulverizer Swap Under Load
 Pulverizer Trip and Load Reduction
 Manual Load Drop with Malfunctions
 Total Plant Load Runback

All operators did all scenarios twice, using the old graphics alone, and the HP HMI graphics. Half used
the old graphics first, and half used the HP HMI graphics first).

Quantitative and qualitative measurements were made on the performance of each scenario (e.g.
detection of the abnormal condition, time to respond, correct and successful response). The full version
of the EPRI report (see References) contains the details.

The Results
The high performance graphics were significantly better in assisting the operator in:
 maintaining situational awareness
 recognizing abnormal situations
 Recognizing equipment malfunctions
 dealing with abnormal situations
 embedding knowledge into the control system

Operators highly rated the Overview screen, agreeing that it provided highly useful “big picture”
situation awareness. Even with only a few hours total with the new graphics, operators had no
difficulties in operating the unit. The High Performance graphics are designed to have intuitive
depictions.

Very positive Operator comments were received on the analog depictions, alarm depictions, and
embedded trends. There were consistent positive comments on how “obvious” the HP HMI made the
various process situations. Values moving towards a unit trip were clearly shown and noticed by the
operators.

The operators commented that HP HMI would enable faster and more effective training of new
operations personnel. The negative operator comments generally had to do with lack of familiarity with
the graphics prior to the test.

Distributed with permission of author(s) by ISA Automation Week 2013


Presented at ISA Automation Week 2013
Copyright 2013 ISA. All Rights Reserved. www.isa.org
Presented at ISA Automation Week 2013
Nashville, Tennessee •Renaissance Nashville, USA, 4-7 November 2013

The best summary quote was this one:

“Once you got used to these new graphics,


going back to the old ones would be hell.”

The effect of inertia being the controlling factor for HMI change was once more confirmed. The
existing HMI had been in use since the early 1990s, with simulator training for more than a decade.
Despite clear deficiencies, almost no change to the existing HMI had been made since inception.

Operators using the existing graphics first in the test were then asked “What improvements would you
make on the existing graphics to help in these situations? In response, there were very few or no
suggestions!

However, operators using the existing graphics after they used the HP HMI graphics had many
suggestions for improvement, namely analog depictions, embedded trends, consistent navigation, etc!

So, people get “used to” what they have – and do not complain or know what they are missing if they
are unfamiliar with these HP HMI concepts.

A lack of complaints does not indicate that you have a good HMI!

The Seven Step Work Process


There is a seven step methodology for the development of a high performance HMI.

Step 1: Adopt a high performance HMI philosophy and style guide. You must have a written set of
principles detailing the proper way to construct and implement a high performance HMI.

Step 2: Assess and benchmark existing graphics against the HMI philosophy. It is necessary to know
your starting point and have a gap analysis.

Step 3: Determine specific performance and goal objectives for the control of the operation and for all
modes of operation. These are such factors as:
• Safety parameters/limits
• Production rate
• Run length
• Equipment health
• Environmental (i.e. Emission control)
• Production cost
• Quality
• Reliability

It is important to document these, along with their goals and targets. This is rarely done and is one
reason for the current state of most HMIs.

Distributed with permission of author(s) by ISA Automation Week 2013


Presented at ISA Automation Week 2013
Copyright 2013 ISA. All Rights Reserved. www.isa.org
Presented at ISA Automation Week 2013
Nashville, Tennessee •Renaissance Nashville, USA, 4-7 November 2013

Step 4: Perform task analysis to determine the control manipulations needed to achieve the
performance and goal objectives. This is a simple step involving the determination of which specific
controls and measurements are needed to accomplish the operation’s goal objectives. The answer
determines the content of each Level 2, 3, and 4 graphic.

Step 5: Design high performance graphics, using the design principles in the HMI philosophy and
elements from the style guide to address the identified tasks.

Step 6: Install, commission, and provide training on the new HMI.

Step 7: Control, maintain, and periodically reassess the HMI performance.

HP HMI Implementation on a Budget

While desirable, it is not necessary to replace all of your existing graphics to obtain much of the benefit
of HP HMI. A partial implementation can provide most of the benefits. A partial implementation
involves:
 Design new Level 1, Level 2, and Abnormal Situation Management graphics
 Existing graphics can be designated as Level 3 and navigation paths to them altered
 Improvements to those Level 3s (correcting color choices, adding status indications, adding
embedded trends, and providing proper context.) can be made over time

Any facility can afford about twenty new graphics! A High Performance HMI is affordable.

Conclusion
Sophisticated, capable, computer-based control systems are currently operated via ineffective and
problematic HMIs, which were created without adequate knowledge. In many cases, guidelines did not
exist at the time of graphic creation and the resistance to change has kept those graphics in commission
for two or more decades.

The functionality and effectiveness of these systems can be greatly enhanced if redesigned in
accordance with proper principles. A High Performance HMI is practical and achievable.

Distributed with permission of author(s) by ISA Automation Week 2013


Presented at ISA Automation Week 2013
Copyright 2013 ISA. All Rights Reserved. www.isa.org
Presented at ISA Automation Week 2013
Nashville, Tennessee •Renaissance Nashville, USA, 4-7 November 2013

References
Hollifield, B., Oliver, D., Habibi, E., & Nimmo, I. (2008). The High Performance HMI Handbook.

Electric Power Research Institute (EPRI),


Operator HMI Case Study: The Evaluation of Existing “Traditional” Operator Graphics vs. High
Performance Graphics in a Coal Fired Power Plant Simulator , Product ID 1017637

Health and Safety Executive, ‘The explosion and fires at the Texaco Refinery, Milford Haven, 24 July
1994: A report of the investigation by the Health and Safety Executive into the explosion and fires on
the Pembroke Cracking Company Plant at the Texaco Refinery, Milford Haven on 24 July 1994’, ISBN
0 7176 1413 1, 1997. Available at:
http://www.icheme.org/resources/safety_centre/products/~/media/Documents/icheme/Safety%20Centre/HSE%20reports/Ex
plosionAndFireAtTexacoRefinery.pdf

The CSB report on the 2005 Texas City BP Explosion, see


http://www.csb.gov/assets/1/19/CSBFinalReportBP.pdf
and the Baker Panel report at
http://www.bp.com/liveassets/bp_internet/globalbp/globalbp_uk_english/SP/STAGING/local_assets/as
sets/pdfs/Baker_panel_report.pdf

The National Transportation Safety Board, go to


http://www.ntsb.gov/search/search.aspx? enter “situation awareness” for the search term.

Distributed with permission of author(s) by ISA Automation Week 2013


Presented at ISA Automation Week 2013
Copyright 2013 ISA. All Rights Reserved. www.isa.org
Presented at ISA Automation Week 2013
Nashville, Tennessee •Renaissance Nashville, USA, 4-7 November 2013

About the Authors

Bill Hollifield Hector Perez

Bill R. Hollifield, PAS Principal Alarm Management and HMI Consultant


bhollifield@pas.com

Bill is the Principal Consultant responsible for the PAS work processes and intellectual property in the
areas of both Alarm Management and High Performance HMI. He is a member of the American
Petroleum Institute’s API RP-1167 Alarm Management Recommended Practice committee, the ISA
SP-18 Alarm Management committee, the ISA SP101 HMI committee, and the Engineering Equipment
and Materials Users Association (EEMUA) Industry Review Group.

Bill has multi-company, international experience in all aspects of Alarm Management and HMI
development. He has 26 years of experience in the petrochemical industry in engineering and
operations, and an additional 9 years in alarm management and HMI software and services for the
petrochemical, power generation, pipeline, and mining industries.

Bill is co-author of The Alarm Management Handbook, The High Performance HMI Handbook, and
The Electric Power Research Institute (EPRI) guideline on Alarm Management.

Bill has authored several papers on Alarm Management and HMI, and is a regular presenter on such
topics in such venues as API, ISA, and Electric Power symposiums. He has a BSME from Louisiana
Tech University and an MBA from the University of Houston.

Hector R. Perez, PAS High Performance HMI Product Manager


hperez@pas.com

Hector oversees the High Performance HMI business line at PAS. He is a chief designer of high
performance graphics intended to facilitate situation awareness in a variety of industries. At PAS,
Hector oversees PAS software directions to improve product design and capabilities.

Prior to working with PAS, Hector was a senior engineer at Schlumberger. His strength in design
contributed to his success in creating new and improved HMI's for reservoir evaluation services and
interfaces for business Key Performance Indicator tracking.

Distributed with permission of author(s) by ISA Automation Week 2013


Presented at ISA Automation Week 2013
Copyright 2013 ISA. All Rights Reserved. www.isa.org
Presented at ISA Automation Week 2013
Nashville, Tennessee •Renaissance Nashville, USA, 4-7 November 2013

In addition to his expertise in High Performance HMI, Hector has widespread experience in all aspects
of Alarm Management. He has facilitated numerous Alarm Management workshops, conducted alarm
rationalization projects, and developed Alarm Philosophy documents for a wide range of clients in the
petrochemical, power generation, pipeline, and mining industries.

Hector has authored technical articles on High Performance HMI. In 2009, he collaborated with the
Electrical Power Research Institute (EPRI) on a comparative research study evaluating high
performance graphics and operator effectiveness.

Hector holds a Bachelor of Science in Chemical Engineering from Rice University.

Distributed with permission of author(s) by ISA Automation Week 2013


Presented at ISA Automation Week 2013

Potrebbero piacerti anche